SCOPE CEA Project Logistics Myanmar was contracted for the transportation and installation of two 18 Tonne vertical storage tanks at a Yangon brewery. The project would prove complex due to two cranes being required to operate in a very narrow location outside the facility. BREWERY TANKS INSTALLATION Locations Yangon, My. Duration 1 Day Cargo Storage tanks x 2 18 Tonne Dimensions (m) W2.5xH15 Equipment Used Mobile crane 100 Tonne Tailing crane 50 Tonne Services Used Project Engineer Project Manager Special Projects Team CASE STUDY CS024 Brewery Tanks Installation 1/2 BREWERY TANKS INSTALLATION PROJECT TEAMS PREPARE THE INSTALLATION SITE

BREWERY TANKS INSTALLATION - ceaprojects.com · BAHAN TOWNSHIP YANGON MYANMAR +959 421 031 286 BREWERY TANKS INSTALLATION Before the arrival of the tanks, CEA teams prepared the installation

Embed Size (px)

Citation preview

SCOPECEA Project Logistics Myanmar was contracted for the transportation and installation of two 18 Tonne vertical storage tanks at a Yangon brewery. The project would prove complex due to two cranes being required to operate in a very narrow location outside the facility.

BREWERY TA

NKS IN

STALLATIO

NLocations Yangon, My.

Duration 1 Day

Cargo Storage tanks x 2 18 Tonne Dimensions (m) W2.5xH15

Equipment Used Mobile crane 100 Tonne Tailing crane 50 Tonne Services Used Project Engineer Project Manager Special Projects Team

CASE STUDY CS024Brewery Tanks Installation 1/2

BREWERY TANKS INSTALLATION

PROJECT TEAMS PREPARE THE INSTALLATION SITE

CEA PROJECT LOGISTICS

G-18 PEARL CONDO

KABAR AYE PAGODA ROAD

BAHAN TOWNSHIP

YANGON

MYANMAR

+959 421 031 286

www.ceaprojects.com

BREW

ERY

TAN

KS IN

STA

LLAT

ION

Before the arrival of the tanks, CEA teams prepared the installation area and affixed anchor bolts to each concrete tank base. After the first tank had arrived both the 100 Tonne mobile crane and 50 Tonne tailing crane positioned themselves either side of the trailer in the narrow alley. All required slings were attached to both ends of the tank and the cranes began the lift.

Due to working in such a confined space each tank had to be lifted above and clear of the adjacent buildings, the crane then turned and lowered each tank onto its concrete base allowing for final alignment and the anchor bolts to be fixed.

CASE STUDY CS024Brewery Tanks Installation 2/2

ON-SITE SAFETY TOOLBOX TALK

CONCRETE BASE LOCATION FOR THE TANKS

FINAL ALIGNMENT

TAILING CRANE BEGINS LIFT

100 TONNE MOBILE CRANE MOVES THE FIRST TANK INTO POSITION

In advance of this operation, CEA Engineering submitted highly detailed lift plans for approval by the client.