Bos2 Chain Units Pipelines

  • Upload
    isukuru

  • View
    219

  • Download
    0

Embed Size (px)

Citation preview

  • 7/30/2019 Bos2 Chain Units Pipelines

    1/10

    Master course on CCS,University of Zagreb

    6-7 May, 20

    Chain units: pipelines

    Assessing CarbonCapture and Storage(CCS) value chains

    May 6th, 2011

    Chain units: pipelines

    Slide 26-7 May 2011, CCS master course University of Zagreb

    CO2 value chain

    Slide 36-7 May 2011, CCS master course University of Zagreb

    Ref: www.sintef.no/ecco

    Slide 46-7 May 2011, CCS master course University of Zagreb

    Transport

    Pipe line Sh ip

    Source

    Industry PowerPlant

    Storage / Sinks

    Buffer Geology

    Pipeline

    1

    Pipeline 4

    Pipelin

    e5

    Pipeline

    3

    Define Network / Components / Contracts

    PowerPlant w/

    Capture

    EOR Field

    Pipeline

    2

    Steel Mill

    w/ Capture

    DGF1-n

    The Network can build-out with time as components are added

    ECCO tool: integrated technical/economical CCS evaluation tool

    Contracts

    C1-nTSO1-n SO1-n

    Tool output:

    Tech KPIs

    DCF-KPIs

    Planning charts

    EUA price

    Cost indices

    Govt matchingfunds reqd

    Initially LTcontracts?Later, moreST?

    Slide 56-7 May 2011, CCS master course University of Zagreb

    Pipelines(general)

    6-7 May 2011, CCS master course University of Zagreb

    Offshore gatheringsystem and ControlRoom in Den Helder

  • 7/30/2019 Bos2 Chain Units Pipelines

    2/10

    Master course on CCS,University of Zagreb

    6-7 May, 20

    Chain units: pipelines

    Slide 76-7 May 2011, CCS master course University of Zagreb

    Classification of pipelines

    Fluid content (gas, oil, water, or mixturesof all three)

    Offshore or onshore

    Buried or on surface (both offshore oronshore)

    Construction material

    Type of corrosion protection

    Insulated or non-insulated

    Slide 86-7 May 2011, CCS master course University of Zagreb

    Pipeline construction Saudi Aramco

    Slide 96-7 May 2011, CCS master course University of Zagreb

    Pipeline construction EuropeSlide 106-7 May 2011, CCS master course University of Zagreb

    Alaskan pipeline

    Slide 116-7 May 2011, CCS master course University of Zagreb

    Pipeline

    through theMexicanmountains

    Slide 126-7 May 2011, CCS master course University of Zagreb

    Procedure for sizing a pipeline

    Four principal considerations:

    1. maximum pressures the pipeline will have towithstand at any point along its length

    2. maximum throughput

    3. pressure drop that can be allowed

    4. upside throughput potential needs to beallowed for

  • 7/30/2019 Bos2 Chain Units Pipelines

    3/10

    Master course on CCS,University of Zagreb

    6-7 May, 20

    Chain units: pipelines

    Slide 136-7 May 2011, CCS master course University of Zagreb

    Necessary to calculate the relationship betweengas throughput, inlet and outlet pressures and

    pipeline diameter and length.

    Not a simple matter, since the flow ismultiphase (liquid and gas) and the pipeline isnot horizontal.

    Generally a multiphase flow computer simulatorwill be used.

    Calculating the required pipeline size

    Slide 146-7 May 2011, CCS master course University of Zagreb

    Slugcatcher,

    Den Helder NL

    Slide 156-7 May 2011, CCS master course University of Zagreb

    In simple situations, analytical correlations may beuseful. For example, for a level gas pipelinecontaining no liquids, the AGA equation can beused

    pin2 - pout

    2 = C L f z T q2/ d5

    Reynolds number is usually high, for a gas we cannearly always use the Colebrook-White equation:

    f = { 2 log10 [3.71d/]}-2

    is the roughness of the pipe

    Calculating the required pipeline size

    Slide 166-7 May 2011, CCS master course University of Zagreb

    Factors in pipeline design - 1

    Type of material

    Type and grade of steel

    Linepipe manufacture

    Weldability

    Selection of the pipeline route

    Burial

    Stresses and loads

    Slide 176-7 May 2011, CCS master course University of Zagreb

    Pipelineburial

    onshore

    Slide 186-7 May 2011, CCS master course University of Zagreb

    Factors in pipeline design - 2

    Corrosion

    Temperature control

    Hydrate formation

    Inspection

    Cleaning

    Valves and other components

  • 7/30/2019 Bos2 Chain Units Pipelines

    4/10

    Master course on CCS,University of Zagreb

    6-7 May, 20

    Chain units: pipelines

    Slide 196-7 May 2011, CCS master course University of Zagreb

    Insulatedpipeline

    Slide 206-7 May 2011, CCS master course University of Zagreb

    Weighted pipes to prevent buoyancy

    Slide 216-7 May 2011, CCS master course University of Zagreb

    Pipeline pigSlide 226-7 May 2011, CCS master course University of Zagreb

    Pipelinepig

    Slide 236-7 May 2011, CCS master course University of Zagreb

    Pipeline laying methods

    laybarge or layship

    towing

    Slide 246-7 May 2011, CCS master course University of Zagreb

    Pipelinetowout

    GullfaksSouth

    Norway

  • 7/30/2019 Bos2 Chain Units Pipelines

    5/10

    Master course on CCS,University of Zagreb

    6-7 May, 20

    Chain units: pipelines

    Slide 256-7 May 2011, CCS master course University of Zagreb

    Layout of a pipe-laying vessel

    Slide 266-7 May 2011, CCS master course University of Zagreb

    Pipelineentering the

    water from apipe-layingvessel

    Slide 276-7 May 2011, CCS master course University of Zagreb

    Methods of laying offshore pipelinesfrom ship or barge

    S-lay

    J-lay

    Extended S-lay

    Reeled method

    Slide 286-7 May 2011, CCS master course University of Zagreb

    Pipelayingoffshore

    S-lay

    Slide 296-7 May 2011, CCS master course University of Zagreb

    AllSeas Lorelay pipe-laying vesselSlide 306-7 May 2011, CCS master course University of Zagreb

    AllSeas Solitaire pipe-laying vessel

    Length 300m = largest in the world. Dynamic Positioning using 10screws. Main advantage of Solitaire is preparatory welding work of 2 pipes @12m in

    preparatory welding lanes. Only thereafter do the 24 m sections come onto the main welding lane: fa ster

    welding (double speed). There are 9 welding stations in main lane. Speed is 24m each 5-7 min = 5-6 km /

    day non-stop.

  • 7/30/2019 Bos2 Chain Units Pipelines

    6/10

    Master course on CCS,University of Zagreb

    6-7 May, 20

    Chain units: pipelines

    Slide 316-7 May 2011, CCS master course University of Zagreb Slide 326-7 May 2011, CCS master course University of Zagreb

    Solitaire: combating weld fatigue

    Challenge

    Fatigue Enhancement in the Cantilever of the StingerHandling System

    Solution Treat existing and repaired welds with UIT

    Post-weld fatigue improvement technique using UltrasonicImpact Treatment = optimising shape of weld

    Fatigue tests preceding treatment

    Benefits Reduction of Down Time

    Enhanced Fatigue Life

    Slide 336-7 May 2011, CCS master course University of Zagreb

    Inside AllSeas SolitaireSlide 346-7 May 2011, CCS master course University of Zagreb

    Welding device

    Slide 356-7 May 2011, CCS master course University of Zagreb

    Solitaire test-welding stationSlide 366-7 May 2011, CCS master course University of Zagreb

    EPTM

    LB 2000laybarge

  • 7/30/2019 Bos2 Chain Units Pipelines

    7/10

    Master course on CCS,University of Zagreb

    6-7 May, 20

    Chain units: pipelines

    Slide 376-7 May 2011, CCS master course University of Zagreb

    Saipem vessel with a 135m J-lay tower

    Pipe stalks with a length upto 6 joints are upended andwelded to the seagoing pipe in a near vertical ramp.

    Pipe leaves the lay system in an almost vertical position

    Slide 386-7 May 2011, CCS master course University of Zagreb

    J-lay pros and cons

    Pipeline is only bent once during installation (at theseabed) advantageous for installing pipelines that are sensitive to fatigue.

    Reduced stress on the pipe allows J-lay to work indeeper water depths.

    Can withstand more motion and underwater currentsthan pipe being installed in the S-lay fashion.

    Relatively low production rate due to the singlewelding station.

    Less suitable for shallow waters as this requires asteep departure angle.

    Slide 396-7 May 2011, CCS master course University of Zagreb

    Extended

    S-lay indeep water

    max 1800 m

    Slide 406-7 May 2011, CCS master course University of Zagreb

    Allseas Solitairelaying 24'' pipelinein deep water for

    Shells Malampaya

    project in ThePhillipines

    504 km of pipe

    5-6 km/day

    Slide 416-7 May 2011, CCS master course University of Zagreb

    Pipelinelaying for

    Gullveigsatellite inNorway(reeled method)

    Slide 426-7 May 2011, CCS master course University of Zagreb

    Pipeline trenching methods

    ploughing

    jetting

    mechanical excavation

    fluidisation

    dredging

  • 7/30/2019 Bos2 Chain Units Pipelines

    8/10

    Master course on CCS,University of Zagreb

    6-7 May, 20

    Chain units: pipelines

    Slide 436-7 May 2011, CCS master course University of Zagreb

    Trenchingtechniques

    Slide 446-7 May 2011, CCS master course University of Zagreb

    Rock -dumping

    Slide 456-7 May 2011, CCS master course University of Zagreb

    Solitaire: own supply of rocks

    Slide 466-7 May 2011, CCS master course University of Zagreb

    These procedures give a first approximation fora screening study.

    Capital cost, pipe diameter and required designpressure must be verified as soon as firm datais available on fluid properties and tie-inpressures

    Value of simple costing methods

    Slide 476-7 May 2011, CCS master course University of Zagreb

    Offshore pipeline cost parameters

    Direct costs Pipe diameter D in inches, weight in kgEngineering 0.4 million $ + 6$/m

    Line pipe 1.3 $/kg

    Corrosion coating 9D$/mWeight coating 7D $/m

    Other material cost 1.2D $/mTie-in or riser cost (each) 0.26D million $Installation cost 0.6D million $ + 60D $/mTrenching and dumping cost 0.4D million $ + 16D $/m/passMiscellaneous Factor 1.1 to 1.3

    S ho re appr oach/landfall 2 - 10 million $ ( ver y var iable )

    Indirect costsManagement & supervision 5% of direct costs

    Insurance 2% of direct and indirect cost

    Pipeline costing rules of thumb

    Note: obsolete figures!

    Slide 486-7 May 2011, CCS master course University of Zagreb

    Weight of line pipe for costing

    Pipe Diameter Wall Thickness Weight

    inch mm inch mm kg/m

    12 324 0.312 7.9 61.7

    14 356 0.375 9.5 81.5

    16 406 0.406 10.3 100.718 457 0.469 11.9 130.8

    20 508 0.500 12.7 155.1

    22 559 0.562 14.3 191.6

    24 610 0.625 15.9 232.4

    26 660 0.688 17.5 277.0

    28 711 0.750 19.0 325.1

    30 762 0.750 19.0 349.0

  • 7/30/2019 Bos2 Chain Units Pipelines

    9/10

    Master course on CCS,University of Zagreb

    6-7 May, 20

    Chain units: pipelines

    Slide 496-7 May 2011, CCS master course University of Zagreb

    02468

    101214161820222426

    2830323436

    0 2 4 6 8 10 12 14 16

    Gas million cubic meter/day

    THROUGHPUT

    Pipediameter(inche

    s)

    Oil thousand bbl/day

    10 20 30 40 50 60 70

    GAS

    OIL

    Quick sizing procedure

    Slide 506-7 May 2011, CCS master course University of Zagreb

    Pipelines and CO2

    Slide 516-7 May 2011, CCS master course University of Zagreb

    CO2 transport & injection Complex due to phase changes

    supercriticalLiquid

    Gas

    Solid

    Pipeline

    Reservoir (LD)

    Reservoir (HD)

    Injection(LD)

    Slide 526-7 May 2011, CCS master course University of Zagreb

    CO2 phase diagram

    Critical point at 31.1C, 73 atm.

    Supercritical state requires much less compression power for transport

    But seabed water 4-10C.

    Slide 536-7 May 2011, CCS master course University of Zagreb

    Useful reference (2006)

    Techno-Economic Models for Carbon DioxideCompression, Transport, and Storage &Correlations for Estimating Carbon Dioxide

    Density and Viscosity

    By David L. McCollum, Joan M. Ogden

    Institute of Transportation Studies, University ofCalifornia

    Slide 546-7 May 2011, CCS master course University of Zagreb

    CO2 transport: Pump & compressor

    power requirement (gas vs. supercritical)

  • 7/30/2019 Bos2 Chain Units Pipelines

    10/10

    Master course on CCS,University of Zagreb

    6-7 May, 20

    Chain units: pipelines

    Slide 556-7 May 2011, CCS master course University of Zagreb

    Pump & compressor capital costs

    Slide 566-7 May 2011, CCS master course University of Zagreb

    Pipeline capital cost vs. mass flow rate

    Slide 576-7 May 2011, CCS master course University of Zagreb

    Pipeline capital cost vs. length

    Slide 586-7 May 2011, CCS master course University of Zagreb

    Pipelines in ECCOtoolUserInputShee t

    Pipeline Module 1 from Hamburg IGCCto Ekofisk EOR

    Pipeline Type Pipeline Parameters Values Pipeline Name Routing points

    Mild steel 100% U ni t s D ef au l t U se r G IS E as t G IS N or th

    Stainl ess steel Design Max imum Pressure bar 190 9.97 53.87

    D es ig n M ax im um Fl ow ra te M t/ a 5 Location points (Deg 2dp)

    Terrain D es ig n M in S af e O ut pu t P re s su re b ar 8 0 Start module

    Default User Ambient Temperature C 4 Hamburg IGCC

    Onshore - Flat rural Leakage % 0% 10.00 53.50

    Onshore - Urban Constructi on Employment FTE No. 2 End moduleOnshore - Hills Permanent Employment FTE No. 0 Ekofisk EOR

    Onshore - Mountai ns 3.20 56.50

    Onshore - average 5% Derived Values Units Value UserOffshore - Sandy seabed Pipeline length km 559

    Offshore -Trenched Pipeline Diameter mm 457 610 Pressure Drop OK

    Offshore - Diff icult Pipeline wall thickness mm 18 24 Hoop Stress OK

    O ff sh or e - A ve ra ge 9 5% D es ig n P re ss ur e D ro p( Ma x) b ar 1 0. 6

    TOTAL 100% 0% A dd i ti o na l C om pr e ss io n b ar 0

    Crossings Costings Values (2010 basis) Index Cost summaryDefault User Units Default User Default User Value Units

    Onshore - Road 0 Materials - steel pipe only m/km 0.16 RPI Pipeline capi tal cost (base) 746 m

    Onshore - Pipel ine 0 Labour m/km 0.24 RPI

    Onshore - O ther 0 Othe rcosts f or al l pi pe li nes m/km 0. 20 RP I P ipel ine capi tal cost ( scal ed for te rrai n 8 95 m

    Of fs hore - P ipel ine 0 Offshore

    Offshore - Other 0 Platform tie in m 48.0 EAndPCosts Opex cost fixed 18.8 m/a

    Shallow Installation m/km 0.35 EAndPCosts Opex cost variable m/a

    Heavy Lift m/km 0.02 EAndPCosts

    Remote Control Dredging m/km 0.02 EAndPCosts

    Default User Marine Survey m/km 0.02 EAndPCosts

    Umbi lical 0 Transportation m/km 0.02 EAndPCosts

    Umbilicals m/km 0.06 EAndPCosts

    Trenching to beach m 22.0 EAndPCosts

    Materials- coating/concrete m/km 0.17 RPI

    Timing U n i ts D e f au l t U s erC on str uc ti on du ra ti on y ea rs 3

    Operational year 2015Cease ope rati ons y ear

    Pipeline Module 1

    % of total length

    Number

    Number