Upload
isukuru
View
219
Download
0
Embed Size (px)
Citation preview
7/30/2019 Bos2 Chain Units Pipelines
1/10
Master course on CCS,University of Zagreb
6-7 May, 20
Chain units: pipelines
Assessing CarbonCapture and Storage(CCS) value chains
May 6th, 2011
Chain units: pipelines
Slide 26-7 May 2011, CCS master course University of Zagreb
CO2 value chain
Slide 36-7 May 2011, CCS master course University of Zagreb
Ref: www.sintef.no/ecco
Slide 46-7 May 2011, CCS master course University of Zagreb
Transport
Pipe line Sh ip
Source
Industry PowerPlant
Storage / Sinks
Buffer Geology
Pipeline
1
Pipeline 4
Pipelin
e5
Pipeline
3
Define Network / Components / Contracts
PowerPlant w/
Capture
EOR Field
Pipeline
2
Steel Mill
w/ Capture
DGF1-n
The Network can build-out with time as components are added
ECCO tool: integrated technical/economical CCS evaluation tool
Contracts
C1-nTSO1-n SO1-n
Tool output:
Tech KPIs
DCF-KPIs
Planning charts
EUA price
Cost indices
Govt matchingfunds reqd
Initially LTcontracts?Later, moreST?
Slide 56-7 May 2011, CCS master course University of Zagreb
Pipelines(general)
6-7 May 2011, CCS master course University of Zagreb
Offshore gatheringsystem and ControlRoom in Den Helder
7/30/2019 Bos2 Chain Units Pipelines
2/10
Master course on CCS,University of Zagreb
6-7 May, 20
Chain units: pipelines
Slide 76-7 May 2011, CCS master course University of Zagreb
Classification of pipelines
Fluid content (gas, oil, water, or mixturesof all three)
Offshore or onshore
Buried or on surface (both offshore oronshore)
Construction material
Type of corrosion protection
Insulated or non-insulated
Slide 86-7 May 2011, CCS master course University of Zagreb
Pipeline construction Saudi Aramco
Slide 96-7 May 2011, CCS master course University of Zagreb
Pipeline construction EuropeSlide 106-7 May 2011, CCS master course University of Zagreb
Alaskan pipeline
Slide 116-7 May 2011, CCS master course University of Zagreb
Pipeline
through theMexicanmountains
Slide 126-7 May 2011, CCS master course University of Zagreb
Procedure for sizing a pipeline
Four principal considerations:
1. maximum pressures the pipeline will have towithstand at any point along its length
2. maximum throughput
3. pressure drop that can be allowed
4. upside throughput potential needs to beallowed for
7/30/2019 Bos2 Chain Units Pipelines
3/10
Master course on CCS,University of Zagreb
6-7 May, 20
Chain units: pipelines
Slide 136-7 May 2011, CCS master course University of Zagreb
Necessary to calculate the relationship betweengas throughput, inlet and outlet pressures and
pipeline diameter and length.
Not a simple matter, since the flow ismultiphase (liquid and gas) and the pipeline isnot horizontal.
Generally a multiphase flow computer simulatorwill be used.
Calculating the required pipeline size
Slide 146-7 May 2011, CCS master course University of Zagreb
Slugcatcher,
Den Helder NL
Slide 156-7 May 2011, CCS master course University of Zagreb
In simple situations, analytical correlations may beuseful. For example, for a level gas pipelinecontaining no liquids, the AGA equation can beused
pin2 - pout
2 = C L f z T q2/ d5
Reynolds number is usually high, for a gas we cannearly always use the Colebrook-White equation:
f = { 2 log10 [3.71d/]}-2
is the roughness of the pipe
Calculating the required pipeline size
Slide 166-7 May 2011, CCS master course University of Zagreb
Factors in pipeline design - 1
Type of material
Type and grade of steel
Linepipe manufacture
Weldability
Selection of the pipeline route
Burial
Stresses and loads
Slide 176-7 May 2011, CCS master course University of Zagreb
Pipelineburial
onshore
Slide 186-7 May 2011, CCS master course University of Zagreb
Factors in pipeline design - 2
Corrosion
Temperature control
Hydrate formation
Inspection
Cleaning
Valves and other components
7/30/2019 Bos2 Chain Units Pipelines
4/10
Master course on CCS,University of Zagreb
6-7 May, 20
Chain units: pipelines
Slide 196-7 May 2011, CCS master course University of Zagreb
Insulatedpipeline
Slide 206-7 May 2011, CCS master course University of Zagreb
Weighted pipes to prevent buoyancy
Slide 216-7 May 2011, CCS master course University of Zagreb
Pipeline pigSlide 226-7 May 2011, CCS master course University of Zagreb
Pipelinepig
Slide 236-7 May 2011, CCS master course University of Zagreb
Pipeline laying methods
laybarge or layship
towing
Slide 246-7 May 2011, CCS master course University of Zagreb
Pipelinetowout
GullfaksSouth
Norway
7/30/2019 Bos2 Chain Units Pipelines
5/10
Master course on CCS,University of Zagreb
6-7 May, 20
Chain units: pipelines
Slide 256-7 May 2011, CCS master course University of Zagreb
Layout of a pipe-laying vessel
Slide 266-7 May 2011, CCS master course University of Zagreb
Pipelineentering the
water from apipe-layingvessel
Slide 276-7 May 2011, CCS master course University of Zagreb
Methods of laying offshore pipelinesfrom ship or barge
S-lay
J-lay
Extended S-lay
Reeled method
Slide 286-7 May 2011, CCS master course University of Zagreb
Pipelayingoffshore
S-lay
Slide 296-7 May 2011, CCS master course University of Zagreb
AllSeas Lorelay pipe-laying vesselSlide 306-7 May 2011, CCS master course University of Zagreb
AllSeas Solitaire pipe-laying vessel
Length 300m = largest in the world. Dynamic Positioning using 10screws. Main advantage of Solitaire is preparatory welding work of 2 pipes @12m in
preparatory welding lanes. Only thereafter do the 24 m sections come onto the main welding lane: fa ster
welding (double speed). There are 9 welding stations in main lane. Speed is 24m each 5-7 min = 5-6 km /
day non-stop.
7/30/2019 Bos2 Chain Units Pipelines
6/10
Master course on CCS,University of Zagreb
6-7 May, 20
Chain units: pipelines
Slide 316-7 May 2011, CCS master course University of Zagreb Slide 326-7 May 2011, CCS master course University of Zagreb
Solitaire: combating weld fatigue
Challenge
Fatigue Enhancement in the Cantilever of the StingerHandling System
Solution Treat existing and repaired welds with UIT
Post-weld fatigue improvement technique using UltrasonicImpact Treatment = optimising shape of weld
Fatigue tests preceding treatment
Benefits Reduction of Down Time
Enhanced Fatigue Life
Slide 336-7 May 2011, CCS master course University of Zagreb
Inside AllSeas SolitaireSlide 346-7 May 2011, CCS master course University of Zagreb
Welding device
Slide 356-7 May 2011, CCS master course University of Zagreb
Solitaire test-welding stationSlide 366-7 May 2011, CCS master course University of Zagreb
EPTM
LB 2000laybarge
7/30/2019 Bos2 Chain Units Pipelines
7/10
Master course on CCS,University of Zagreb
6-7 May, 20
Chain units: pipelines
Slide 376-7 May 2011, CCS master course University of Zagreb
Saipem vessel with a 135m J-lay tower
Pipe stalks with a length upto 6 joints are upended andwelded to the seagoing pipe in a near vertical ramp.
Pipe leaves the lay system in an almost vertical position
Slide 386-7 May 2011, CCS master course University of Zagreb
J-lay pros and cons
Pipeline is only bent once during installation (at theseabed) advantageous for installing pipelines that are sensitive to fatigue.
Reduced stress on the pipe allows J-lay to work indeeper water depths.
Can withstand more motion and underwater currentsthan pipe being installed in the S-lay fashion.
Relatively low production rate due to the singlewelding station.
Less suitable for shallow waters as this requires asteep departure angle.
Slide 396-7 May 2011, CCS master course University of Zagreb
Extended
S-lay indeep water
max 1800 m
Slide 406-7 May 2011, CCS master course University of Zagreb
Allseas Solitairelaying 24'' pipelinein deep water for
Shells Malampaya
project in ThePhillipines
504 km of pipe
5-6 km/day
Slide 416-7 May 2011, CCS master course University of Zagreb
Pipelinelaying for
Gullveigsatellite inNorway(reeled method)
Slide 426-7 May 2011, CCS master course University of Zagreb
Pipeline trenching methods
ploughing
jetting
mechanical excavation
fluidisation
dredging
7/30/2019 Bos2 Chain Units Pipelines
8/10
Master course on CCS,University of Zagreb
6-7 May, 20
Chain units: pipelines
Slide 436-7 May 2011, CCS master course University of Zagreb
Trenchingtechniques
Slide 446-7 May 2011, CCS master course University of Zagreb
Rock -dumping
Slide 456-7 May 2011, CCS master course University of Zagreb
Solitaire: own supply of rocks
Slide 466-7 May 2011, CCS master course University of Zagreb
These procedures give a first approximation fora screening study.
Capital cost, pipe diameter and required designpressure must be verified as soon as firm datais available on fluid properties and tie-inpressures
Value of simple costing methods
Slide 476-7 May 2011, CCS master course University of Zagreb
Offshore pipeline cost parameters
Direct costs Pipe diameter D in inches, weight in kgEngineering 0.4 million $ + 6$/m
Line pipe 1.3 $/kg
Corrosion coating 9D$/mWeight coating 7D $/m
Other material cost 1.2D $/mTie-in or riser cost (each) 0.26D million $Installation cost 0.6D million $ + 60D $/mTrenching and dumping cost 0.4D million $ + 16D $/m/passMiscellaneous Factor 1.1 to 1.3
S ho re appr oach/landfall 2 - 10 million $ ( ver y var iable )
Indirect costsManagement & supervision 5% of direct costs
Insurance 2% of direct and indirect cost
Pipeline costing rules of thumb
Note: obsolete figures!
Slide 486-7 May 2011, CCS master course University of Zagreb
Weight of line pipe for costing
Pipe Diameter Wall Thickness Weight
inch mm inch mm kg/m
12 324 0.312 7.9 61.7
14 356 0.375 9.5 81.5
16 406 0.406 10.3 100.718 457 0.469 11.9 130.8
20 508 0.500 12.7 155.1
22 559 0.562 14.3 191.6
24 610 0.625 15.9 232.4
26 660 0.688 17.5 277.0
28 711 0.750 19.0 325.1
30 762 0.750 19.0 349.0
7/30/2019 Bos2 Chain Units Pipelines
9/10
Master course on CCS,University of Zagreb
6-7 May, 20
Chain units: pipelines
Slide 496-7 May 2011, CCS master course University of Zagreb
02468
101214161820222426
2830323436
0 2 4 6 8 10 12 14 16
Gas million cubic meter/day
THROUGHPUT
Pipediameter(inche
s)
Oil thousand bbl/day
10 20 30 40 50 60 70
GAS
OIL
Quick sizing procedure
Slide 506-7 May 2011, CCS master course University of Zagreb
Pipelines and CO2
Slide 516-7 May 2011, CCS master course University of Zagreb
CO2 transport & injection Complex due to phase changes
supercriticalLiquid
Gas
Solid
Pipeline
Reservoir (LD)
Reservoir (HD)
Injection(LD)
Slide 526-7 May 2011, CCS master course University of Zagreb
CO2 phase diagram
Critical point at 31.1C, 73 atm.
Supercritical state requires much less compression power for transport
But seabed water 4-10C.
Slide 536-7 May 2011, CCS master course University of Zagreb
Useful reference (2006)
Techno-Economic Models for Carbon DioxideCompression, Transport, and Storage &Correlations for Estimating Carbon Dioxide
Density and Viscosity
By David L. McCollum, Joan M. Ogden
Institute of Transportation Studies, University ofCalifornia
Slide 546-7 May 2011, CCS master course University of Zagreb
CO2 transport: Pump & compressor
power requirement (gas vs. supercritical)
7/30/2019 Bos2 Chain Units Pipelines
10/10
Master course on CCS,University of Zagreb
6-7 May, 20
Chain units: pipelines
Slide 556-7 May 2011, CCS master course University of Zagreb
Pump & compressor capital costs
Slide 566-7 May 2011, CCS master course University of Zagreb
Pipeline capital cost vs. mass flow rate
Slide 576-7 May 2011, CCS master course University of Zagreb
Pipeline capital cost vs. length
Slide 586-7 May 2011, CCS master course University of Zagreb
Pipelines in ECCOtoolUserInputShee t
Pipeline Module 1 from Hamburg IGCCto Ekofisk EOR
Pipeline Type Pipeline Parameters Values Pipeline Name Routing points
Mild steel 100% U ni t s D ef au l t U se r G IS E as t G IS N or th
Stainl ess steel Design Max imum Pressure bar 190 9.97 53.87
D es ig n M ax im um Fl ow ra te M t/ a 5 Location points (Deg 2dp)
Terrain D es ig n M in S af e O ut pu t P re s su re b ar 8 0 Start module
Default User Ambient Temperature C 4 Hamburg IGCC
Onshore - Flat rural Leakage % 0% 10.00 53.50
Onshore - Urban Constructi on Employment FTE No. 2 End moduleOnshore - Hills Permanent Employment FTE No. 0 Ekofisk EOR
Onshore - Mountai ns 3.20 56.50
Onshore - average 5% Derived Values Units Value UserOffshore - Sandy seabed Pipeline length km 559
Offshore -Trenched Pipeline Diameter mm 457 610 Pressure Drop OK
Offshore - Diff icult Pipeline wall thickness mm 18 24 Hoop Stress OK
O ff sh or e - A ve ra ge 9 5% D es ig n P re ss ur e D ro p( Ma x) b ar 1 0. 6
TOTAL 100% 0% A dd i ti o na l C om pr e ss io n b ar 0
Crossings Costings Values (2010 basis) Index Cost summaryDefault User Units Default User Default User Value Units
Onshore - Road 0 Materials - steel pipe only m/km 0.16 RPI Pipeline capi tal cost (base) 746 m
Onshore - Pipel ine 0 Labour m/km 0.24 RPI
Onshore - O ther 0 Othe rcosts f or al l pi pe li nes m/km 0. 20 RP I P ipel ine capi tal cost ( scal ed for te rrai n 8 95 m
Of fs hore - P ipel ine 0 Offshore
Offshore - Other 0 Platform tie in m 48.0 EAndPCosts Opex cost fixed 18.8 m/a
Shallow Installation m/km 0.35 EAndPCosts Opex cost variable m/a
Heavy Lift m/km 0.02 EAndPCosts
Remote Control Dredging m/km 0.02 EAndPCosts
Default User Marine Survey m/km 0.02 EAndPCosts
Umbi lical 0 Transportation m/km 0.02 EAndPCosts
Umbilicals m/km 0.06 EAndPCosts
Trenching to beach m 22.0 EAndPCosts
Materials- coating/concrete m/km 0.17 RPI
Timing U n i ts D e f au l t U s erC on str uc ti on du ra ti on y ea rs 3
Operational year 2015Cease ope rati ons y ear
Pipeline Module 1
% of total length
Number
Number