Bhel Bearing Erection

Embed Size (px)

Citation preview

  • 7/24/2019 Bhel Bearing Erection

    1/39

    STEAM TURBINE

    500 MW

    ERECTION

    CRITICAL ACTIVITIES

    (ASSEMBLY OF BRG. AT SITE)

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 1of 40

    1. ASSEMBLY OF BEARING AT SITE

    1.1. GENERAL DESCRIPTION

    The KWU design machine are supplied with four bearings out of which three are

    the journal bearing and one is combined thrust and journal bearing on H.P.

    rear end of the shaft. All the turbine bearing are self aligning type and they

    adjust themselves as per the catenary of the machine.

    The function of a journal bearing is to support the turbine shaft , but the

    thrust bearing support the shaft as well as work as a fix point for the turbine

    shaft. The contact arrangements between bearing and bearing supports are of

    two types i.e. sphere to sphere in HP front and HP rear bearing and torus to

    cylindrical in other bearings.

    The bearings are supplied to site after ensuring their contact at works. During

    erection all the bearing are supplied to site in aligned and assemble condition in

    their individual pedestal from the works. After alignment of the bearing in

    their pedestal the seat of the bearing are doweled before dispatch to site.

    In case of Thrust and Journal bearing the seat of the bearing neither doweled

    from the works nor it is recommended to be doweled at site. The bearings

    need preparation before placement of module in position at site. This can be

    done even before the placement of pedestal in position for grouting.

    1.2. ASSEMBLY PROCEDURE

    1.2.1. After opening the pedestal remove and clean the bearing includingits spherical/ cylindrical seat.

    1.2.2. Remove oil guard ring and its duct and keep them in proper placefor their storage at site.

  • 7/24/2019 Bhel Bearing Erection

    2/39

    STEAM TURBINE

    500 MW

    ERECTION

    CRITICAL ACTIVITIES

    (ASSEMBLY OF BRG. AT SITE)

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 2of 40

    1.2.3. Handle bearing carefully to avoid any damage to the babbitand its torus/spherical piece. During storage at site avoid directloading of bearing on its torus. A thick rubber seat may be usedduring handling of bearing at site on its torus.

    1.2.4. Ensure 0.03 feeler tightness on bearing parting plane. In caseof any variation the matter may be referred to designers.

    1.2.5. Measure bore dia of the bearing and journal dia at site and ensurethe oil clearances. If any discrepancy is observed , designer maybe referred.

    1.2.6. Ensure torus/spherical contact with their seats at site. While

    checking the contact the seat may be bolted with theirpedestal. In case variation contact from their specified diagramsare noticed then following may be carried out at site:-

    In case of torus to cylindrical seats the line contact arerecommended by designers. If these lines are not straightand are in angle then the bearing may be rejected straight wayand sent to works for rectification. These line contact may be in awidth of about 20 mm throughout on its seat leaving with areaon both sides. The contact may be wide in Center and thengradually reducing on sides. In case there is no contact is

    achieved in the center and only sides are having contact then afeeler gap may be recorded in bottom. In case if the bottom istight to a feeler of 0.03 mm the bearing may be accepted atsite without doing any rectification.

    In a reverse case the contact are achieved in center only thoughthe 0.03 feeler is not going in the side. The bearing may be stillaccepted at site. In case if the feeler is going in the bottom or insides by 0.03 mm. the bearing are not accepted at site and can besent back for the rectification to the works. Similarly if the contact

    are intermittent on its seat but in a straight line and no feeler isgoing the bearing may be accepted. In case of very wide contactalso the bearing may be sent back for the rectification. Whilechecking these contact very light color may be put on torus of thebearing. Before sending back the bearing to the works the mattermay be referred to designers and their concurrence is to beobtained. No scrapping/lapping is recommended in thesebearing for improvement of the contact.

    In case of spherical to spherical bearing the contacts are called inthe center like a moon shape. In these bearings even full

    contact may be accepted. But in case if there are contact on sides

  • 7/24/2019 Bhel Bearing Erection

    3/39

    STEAM TURBINE

    500 MW

    ERECTION

    CRITICAL ACTIVITIES

    (ASSEMBLY OF BRG. AT SITE)

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 3of 40

    and a feeler gap is noticed on center then the bearing may notbe accepted.

    In such cases if the gap is upto 0.03 mm then thematching/lapping may be carried out at site. But in case of highergap the matter may be referred to designers. In case of reversecase if the feeler gap of 0.03 is noticed on both sides of thebearing the bearing may not accepted at site and matter may bereferred to designers.

    1.2.7. Before checking the contact between torus and its seat ensure thatthe seat is feeler tight to 0.03 mm without tightening of any bolts

    with the pedestal. If necessary this may be corrected withconsultation of designers. Similarly ensure contact between torus\spherical piece with bearing and in case of variation the matter bereferred to designers and no correction is to be carried out at sitewithout the approval of manufacturing unit.

    1.2.8. Before checking the contact between torus/spherical piece withbearing and in case of variation the matter may be referred todesigners and no correction is to be carried out at site withouttheir recommendations.

    1.2.9. The sizes of all the shims may be punched in bearing body and

    spherical/torus piece of the bearing. The number of shims are tobe limited to 3-4 numbers only even after complete alignment ofmachine. A protocol for number of shims may be prepared.

    1.2.10.Torus/spherical should not have any radial movement over itsbearing. This can be seen after opening the torus from thebearing.

    1.2.11. Check jacking oil lines of the bearing and clean them thoroughly.Ensure jacking oil lines fittings also for their male female threadsetc otherwise this may create the oil leakage through these linesduring operation of the machine. The jacking oil pocket in the

    bearing may be checked if necessary they may be corrected atsite as per the drawings.

    1.2.12. When ever JOP is not available, use always thick oil duringrotation of shaft over bearing.The type of oil may be used asservo cylinder 1000 grade of IOC.

    1.2.13.After installation of bearing in position the oil clearances maybe checked after few rotation of the shaft. But the final oilclearances are to be checked after final coupling of the shaft. Incase of variation in side oil clearances no cutting of babbitt metalis permitted at site. Any variation in clearances may be counter

  • 7/24/2019 Bhel Bearing Erection

    4/39

    STEAM TURBINE

    500 MW

    ERECTION

    CRITICAL ACTIVITIES

    (ASSEMBLY OF BRG. AT SITE)

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 4of 40

    checked by measuring journal / bearing bore dia. Bearing bore diais to be measured by assembling and tightening of top & bottomhalves of bearing.

    1.2.14.In case of skew side oil clearances, the investigation may becarried out, if necessary consult manufacturing unit.

    1.2.15.Ensure good contact between journal and babbitt metal of thebearing in the center. Any minor high spot may be removedfrom the babbitt metal while checking with blue color. Ensurefull contact of shaft over the jacking oil pocket also.

    1.2.16.Always cover rotor journal with the upper half bearing to avoid

    entry of any sand particles etc. in the bearing . During pouringof oil the upper bearing may be removed and replaced back afterthe pouring of oil.

    1.2.17.After completing the reaming/honing and final tightening ofcoupling bolts the work of bearing side pad, yoke keys and oilguard fitting may be taken up.

    1.2.18.Before starting the side pad and top keys ensure that the bearingis perfectly level on parting plane. Ensure that the gap for the sidepads are parallel otherwise these are to be made bycutting/scrapping.

    1.2.19.After fitting of the bearing cap if the gap for the radial top keys arein taper a proper correction is to be made here. The bearing capmay also be repositioned to achieve the parallelity of the keyway. The cap may be re-doweled after repositioning it but no taperare to be left on these area. If repositioning of cap is not helpingthen the cutting may be carried out in bearing cap.

    1.2.20.The gap for the top packer of bearing may also be checked. Incase of any taper the same is to be corrected by cutting onbearing cap. Sometime the size of this packer comes to very

    low i.e. even below 5.00 mm. This may be corrected bymatching the cap and size for this packer may be kept around6.00 mm.

    1.2.21.On all these bearing cap key a proper fitting and clearances are tobe maintained during assembly. These key of proper materialare to be only used and no welding deposits are permitted here.The new key may be made at site by EN-24 material if correct keyare not available at site.

    1.2.22.Use of local made shims in bearing may be avoided and shimssupplied from the works with proper cutting of holes are to be

  • 7/24/2019 Bhel Bearing Erection

    5/39

    STEAM TURBINE

    500 MW

    ERECTION

    CRITICAL ACTIVITIES

    (ASSEMBLY OF BRG. AT SITE)

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 5of 40

    used. Ensure drawing requirement of maximum adjustment at siteby + 0.3mm in shim size from manufactured condition.

    1.2.23.A proper care should be given during fitting of bearing oil guardring otherwise it causes the oil leakage during operation of themachine through pedestals. Parting plane joint of oil guard ringand duct should be feeler tight and no elongation of holes on thesearea may be permitted.

    1.2.24.The bearing parting plane bolt are to be tightened to requiredtorque only no other method of tightening of these bolts may beused.

    1.2.25.Adjustment of shims between spherical/torus and bearing body islimited to +0.30 mm in up and down and left, right direction. thismargin may be left for emergency work during overhauling of themachine any adjustment during erection and normal overhaulingmay be done by adjusting shims between spherical/cylindrical seatand pedestal base only. For left and right adjustment thecomplete pedestal of HP front and HP rear may be moved withthe help of their radial keys.

    The above discussed points were common for Journal bearingand combined thrust and journal bearing. Now some specific

    points are detailed here for the assembly of combined Thrustand Journal bearing:

    Remove all the thrust pads before placement of bearing in

    position and store them in a proper place.

    Pressure proper fitting of babbitt metal liner in the bearing body

    including necessary pinch in the fitting of its liner.

    During alignment of rotor along the bearing with respect to the

    shaft by moving spherical seat of the bearing radially and

    axially.

    No elongation of holes are to be carried out in spherical sat of

    the bearing for the purpose of its alignment.

  • 7/24/2019 Bhel Bearing Erection

    6/39

    STEAM TURBINE

    500 MW

    ERECTION

    CRITICAL ACTIVITIES

    (ASSEMBLY OF BRG. AT SITE)

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 6of 40

    Before deciding axial position of the bearing the axial position of the

    rotor is to be determined. If necessary the H.P. rear pedestal as a

    whole may be shifted axially to ensure correct position of the

    thrust bearing.

    Align the thrust bearing in such a way that the thrust pad gap

    achieved are prallel and no difference are noticed in front and rear

    pad thicknesses.

    Movement in the thrust pad should be ensured and a difference in

    thickness of packers including shims should be with in + 0.10 mm

    may be permitted on front and rear pad sizes in exceptional cases.

    After ensuring the perfect alignment of the bearing the axial keys

    are fitted after assembly of upper half bearing. These axial keys

    are to be fitted in perfect parallel slots without any clearances.

    The keys are to be fitted in such a way that there is no movement

    to the bearing during fitting of these axial keys. Necessary dial

    gauges are to be installed on bearing during fitting of these keys.

    After completion of axial key works of the bearing the thrust pads

    may be fitted in the bearing with a clearance of about 0.10/0.15

    mm.

    Before fitting of pads in the bearing ensure that there dimension

    are made parallel to suit the front and rear slot size of the bearing(size between thrust collar and bearing body).

    Ater fitting of pads in the bearing ensure their free movement

    over the bearing.

    Install lower half bearing in position along with their pads and put

    very small quantity of oil on journal then rotate the rotor and put

  • 7/24/2019 Bhel Bearing Erection

    7/39

    STEAM TURBINE

    500 MW

    ERECTION

    CRITICAL ACTIVITIES

    (ASSEMBLY OF BRG. AT SITE)

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 7of 40

    blue color on the thrust collar of the rotor on both front and rear

    side.

    Install upper half bearing along with all pads and fix their axial keys.

    Rotate the rotor and move + direction axially with the help of

    wooden planks. Remove both halves of the bearing and see the

    blue contact on thrust pads. If necessary some cutting may be

    carried out on the pads to achieve the color contact. This

    exercise may be repeated few times to achieve the blue contact

    Ensure a float of 0.30 + 0.10mm during color matching of the

    thrust pads. If necessary the minor adjustment of shims may be

    carried out in the bearing pads.

    Before installation of thrust bearing along with thrust pads in

    position the both halves may be bolted out side and their pads

    may be checked for color contact over a surface plate also infront and rear both sides. This will reduce the time cycle while

    carrying out the color contact of the bearing with the rotor.

    During overhauling of the unit the bearing contact are to be

    rechecked and need correction. In case of torus to cylindrical

    type of bearing if the contact are not satisfactory then the

    bearing and its seat may be remachined at works. In spherical

    to spherical bearing the variation in contact if noticed canbe corrected by matching/lapping at site. Sometimes the

    heavy pitting marks are also noticed on same of the bearing and

    these need correction by machining it.

  • 7/24/2019 Bhel Bearing Erection

    8/39

    STEAM TURBINE

    500 MW

    ERECTION

    CRITICAL ACTIVITIES

    (ASSEMBLY OF BRG. AT SITE)

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 8of 40

  • 7/24/2019 Bhel Bearing Erection

    9/39

    STEAM TURBINE

    500 MW

    ERECTION

    CRITICAL ACTIVITIES

    (ASSEMBLY OF BRG. AT SITE)

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 9of 40

  • 7/24/2019 Bhel Bearing Erection

    10/39

    STEAM TURBINE

    500 MW

    ERECTION

    CRITICAL ACTIVITIES

    (ASSEMBLY OF BRG. AT SITE)

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 10of 40

  • 7/24/2019 Bhel Bearing Erection

    11/39

    STEAM TURBINE

    500 MW

    ERECTION

    CRITICAL ACTIVITIES

    (BUMP CHECK)

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0802GPage No. 11of 40

    2. BUMP TEST

    The axial clearance check is determined after radial clearance

    measurement has been completed.

    In this case the shaft is shifted in the + and - directions from its

    operating position and the dimensions with the shaft in limit position are

    measured using a depth gauge.

    Note: Enter the measured values ( actual dimensions ) on the record sheet

    and compare them with the specified dimensions.

    If the deviations from the specified dimensions is greater then the

    permitted tolerances, the manufacturer must be consulted.

    Note : Based on the readings of bump check, axial position of the shaft wrt

    casing is not to be altered.

  • 7/24/2019 Bhel Bearing Erection

    12/39

    STEAM TURBINE

    500 MW

    ERECTION

    CRITICAL ACTIVITIES

    (ROLL CHECK)

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0803GPage No. 12of 40

    3. ROLL CHECK

    3.1. GENERAL DESCRIPTION

    In KWU machine the minimum radial clearances HP, IP and LP casing are

    measured by actually by moving the casing radially at site while rotor is rotated

    by hand. This is a very accurate and fast method of measuring the minimum

    radial clearance of any of the casing.

    The major variation in these reading may cause vibration in the machine

    and obstruction in barring gear operation etc. Such facilities are not available

    in many other designs of machine and causes longer duration in erection and

    overhauling of the units.

    After completing the alignment of rotors the casing alignments are carried out by

    roll check method but equal importance should also be given to the centering ofHP and IP casing.

    The centering of casing may not be fully sacrificed in comparison of rolling

    test readings and a compromise between these two readings should be made.

    The rolling test should be carried out in cold machine only.

    3.2. PROCEDUREROLL CHECK OF HP AND IP CASING

    3.2.1. Alignment and coupling of HP-IP and LP rotors are to becompleted before starting the rolling test of the casing in normalcase but this can be done without coupling of LP rotor also.

  • 7/24/2019 Bhel Bearing Erection

    13/39

    STEAM TURBINE

    500 MW

    ERECTION

    CRITICAL ACTIVITIES

    (ROLL CHECK)

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0803GPage No. 13of 40

    3.2.2. Centering of the casing on HP front, HP rear IP front and IP rearspigot are also to be completed before starting of the rolling test.These readings can be compared as per the factory protocolalso. Fix temporary radial and axial keys of the casing beforerolling test of casing. During dialing on spigot a proper careshould be taken that the dials are properly mounted over thefixture and the fixture fabricated at site is strong enough to givethe correct readings. The point dial indicator may be used here forthe better results of the dial readings.

    3.2.3. All the four jacking screw of HP and IP casing are to installedalong with dial gauges for monitoring of up and down, and left

    and right movement of the casing.

    3.2.4. One number hydraulic jack on each corner of the casing alongwith a spanner on each corner for jacking screw are also to bemade available.

    3.2.5. During erection of machine the turbine rotor are generally rotatedby hand with the help of periphery holes on coupling. Twopipes of about 1250 mm long along with a pin to suit the dia ofperiphery may be used for rotating the rotor shaft. The initial jerkto the rotor is given by the help of crane and it is further rotatedby these pipes through periphery holes of the coupling. During

    overhauling generally the jacking oil system is available and therotation of rotors are achieved with the hand barring of themachine.

    3.2.6. Before starting the rolling check it should be ensured that the rotorshaft is absolutely free on manual rotation/hand barring asthe case may be. During manual rotation two persons are to beemployed for this work and during hand barring only one personis enough.

    3.2.7. Always use thick oil for rotation of rotor over bearing in absence of

    jacking oil system. The type oil may be servo cylinder 1000 grade(IOC) oil.

    3.2.8. During the rolling test the temporary casing packers are to befitted with about 1.00 mm shims.

    3.2.9. During the rolling test of any one of the casing the same is liftedfirst on all four corners in a step of 0.05 mm with the help ofhydraulic jack and jacking screw. The rotor is also rotatedmanually side by side with the lifting of casing. The rotation of

  • 7/24/2019 Bhel Bearing Erection

    14/39

    STEAM TURBINE

    500 MW

    ERECTION

    CRITICAL ACTIVITIES

    (ROLL CHECK)

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0803GPage No. 14of 40

    rotor and lifting of casing continued till it becomes little bit tighton the seals of the casing

    After this the casing is lowered by about 0.05mm and rotor is

    rotated again if it is completely free. In case the rotor is still tight on

    its manual rotation the casing is further lowered by 0.05 mm on

    all four corners. After ensuring the freeness of rotor it is again

    rotated and casing is lifted simultaneously on front end till the

    rotor rotation becomes tight on seals portion of the casing.

    As soon as the shaft becomes tight the lifting of casing and

    rotation of shaft is stopped and dial readings on front end are

    recorded. The average lift on front end of the casing is the bottom

    clearance on front end of the casing.

    After this the casing on front end is lowered by 0.05 mm and

    freeness of rotor is ensured. In case it is still tight the casing is

    further lowered by 0.05 mm. On front end and the freeness of

    rotor is achieved. Now the rear end of the casing are lifted similar

    to front end and bottom clearance of rear end are recorded . After

    recording the bottom clearance of front and rear end of

    individual casing the casing is lowered with the help of hydraulic

    jacks and jacking screws to its original zero-zero position.

    Repeat similar operation of rotating the rotor and lowering the

    casing on front and rear end for deciding the top clearance in front

    and rear end of the casing. Before starting the rolling test in

    downward direction of the casing remove about 1.00 mm shims

    from each packer of the casing, but kept the casing on

    hydraulic jacks and jacking screws on its original position. The

    casing is again brought back to its original position by

  • 7/24/2019 Bhel Bearing Erection

    15/39

    STEAM TURBINE

    500 MW

    ERECTION

    CRITICAL ACTIVITIES

    (ROLL CHECK)

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0803GPage No. 15of 40

    installation of the shims back to the packers of the casing after

    recording the top clearances of the casing.

    After recording the up and down rolling test values the radial

    keys of the casing are removed and again rolling test for left

    and right direction are done similar to up and down. During this

    process the radial dial on the casing are also installed. After

    this check the casing is brought back to its zero position in radial

    direction also.

    After completing the rolling test readings of one of the HP/IP

    casing in up/downand left/right direction the clearances are

    readjusted as required at site in radial direction by moving the

    casing with the help of temporary radial key or shims on the casing

    packers. The casing is then locked on four corners and final

    dial readings of spigot are recorded on front and rear end.

    Immediately after this the final radial key of the casing are fixedand the locked of the casing are released for fitting of the final

    casing packers. The final spigot dial reading are repeated and

    confirmed with the earlier readings.

    3.2.10.After doing the full rolling test and fixing of a final radial keysand packers of one of the casing the rolling test of another casingis done including the fitting of final keys and packers.

    3.2.11.Necessary offset in the radial clear-ance is also kept before

    fitting of final packers of the casing toward the lift of the shaftduring operation of the unit.

    3.2.12.No inlet and outlet pipes are to be welded with the casing tillcompletion of rolling test and installation of final keys and packerof the casing.

  • 7/24/2019 Bhel Bearing Erection

    16/39

    STEAM TURBINE

    500 MW

    ERECTION

    CRITICAL ACTIVITIES

    (ROLL CHECK)

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0803GPage No. 16of 40

    3.2.13.Radial clearance of the casing are to be ensured with reference tothe factory supplied protocol also.

    3.2.14.After fitting of final keys and packers of the casing the finalspigot dial values of HP front, HP rear, IP front and IP rearcasing are to be recorded for future reference in the protocol.

    3.2.15.The horn drop readings are also to be checked after the fitting offinal packer of the casing.

    3.2.16.In case of IP casing the roll test readings are to be taken withthe IP front end rear shaft scales. The spigot dial readings are alsoto be taken over the spigot of shaft seales.

    3.2.17.During rolling test of the HP and IP casing if the rotor is rotatedover the jacking oil then the adjustment of readings are toadjusted for the lift of the rotor also.

    3.2.18.Four numbers 1.00 mm undersize packers for HP & IP casingmay be made during erection and supplied to customers as T&Pitems for further roll test during overhauling of the unit. If anytaper is left on final packers of the casing then these four packersmay be made to similar taper also.

  • 7/24/2019 Bhel Bearing Erection

    17/39

    STEAM TURBINE

    500 MW

    ERECTION

    CRITICAL ACTIVITIES

    (ROLL CHECK)

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0803GPage No. 17of 40

    3.3. ROLLING TEST OF L.P. INNER CASING

    3.3.1. The rolling test of L.P. inner casing is done similar to the HP or IPcasing but both side joints of L.P. inlet bellows are kept free orbellow itself are not positioned at all, till completion of rolling test.But during overhauling the rolling test is done with already weldedbellows.

    3.3.2. Rolling test of L.P. inner casing is done after the neck welding ofcondenser andstiffener pipes inside the condenser. This includethe welding of stiffener pipes of L.P. casing and gusset platesalso.

    3.3.3. After rolling test of the casing the final radial keys of the Gussetblock and casing packers on all four corners are installed.

    3.3.4. Necessary offset in the radial clearances of the casing is alsokept before fitting of final L.,P. inner casing packers.

    3.3.5. Radial clearances of the casing are to be ensured to the designvalues. In case of any variation the matter may be referred to thedesigners.

    3.3.6. If the rotor is rotated on jacking oil then the rolling test readingsare to be adjuted for the lift of the rotor also.

  • 7/24/2019 Bhel Bearing Erection

    18/39

    STEAM TURBINE

    500 MW

    ERECTION

    CRITICAL ACTIVITIES

    (CATENARY AND ALIGNMENTS)

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0804GPage No. 18of 40

    4. CATENARY AND ALIGNMENTS

    4.1. General Description

    The catenary of the machine is very important for a turbine and Generator

    assembly to achieve proper alignment of various rotors and loading on their

    bearing. Any deviation may lead to various operational problem in the

    machine like high shaft vibration, high bearing vibration, high babbitt metaltemperature of the bearing etc. To avoid these problems it is necessary to

    maintain the catenary of the machine during erection and subsequent

    realignment/overhaul of the unit. Many times it is observed that though the

    alignment of rotors are within limit but the catenary as a whole get deviated

    from the prescribed design value of the machine. In order to avoid such

    derivation a need is felt to devise a procedure which shall ensure rotors

    alignment alongwith proper catenary of the machine.

    During first few years of the operation of the unit the possibility to the

    disturbance of the catenary are much more due to settlement of the foundation

    frame.

    In each overhaul of the unit the catenary of the machine is to be corrected.

    The L.P. front and L.P. rear pedestal are directly grouted here without any

    separate base plate. As such any correction on lifting or lowering. These

    pedestals are not very convenient so if necessary the rotor may be lifted or

    lowered with respect to pedestal seal bore and required catenary may be

    achieved. In extreme cases these pedestals may be even regrouted during

    major overhauls of the unit to correct the catenary of the machine.

  • 7/24/2019 Bhel Bearing Erection

    19/39

    STEAM TURBINE

    500 MW

    ERECTION

    CRITICAL ACTIVITIES

    (CATENARY AND ALIGNMENTS)

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0804GPage No. 19of 40

    4.2. Procedure

    4.2.1. Install a bench mark plate near L.P. rear pedestal as height ofthe machine center line with the consultation of civil Engrs at site.

    A plate of 200 m.m x 300 m.m size with 20 m.m thicknessmachined/ground on top side may be welded over a I Beam or achannel in level condition. This plate is to be installed very carefullyas this will be a future reference for setting up the all elevation ofthe machine.

    4.2.2. Record half bore error of all the four pedestals and confirm thereadings with the factory records also. The half bore error may bechecked in both upper half and lower half of the pedestal andsame may be punched on both halves in left and right side forall future references of the machine.

    4.2.3. During alignment of pedestal at the time of grouting withconbextra cement set the height of the pedestals as per requiredcatenary of the machine considering +value for the half bore errorof the pedestals. While setting the height of the pedestals it shouldbe kept in mind that the height for the center of the pedestal boreare to be kept as per the catenary of the machine not the

    parting plane of the pedestal.

    4.2.4. For better results four water level jar connected to each otherwith a polythene pipe may be installed on each pedestal. TheD.M., water may be used here and leakage through polythenetubes should be avoided fully while making the connections. These

    jars may be fabricated at site by about 125 mm. dia pipe with aplate welded in bottom and then machined for better seating onpedestal base. The height of the jar may be kept as about 175mm. A depth micrometer installed and clamped over a magneticbase is also required for measurement of the water level in the jar.The micrometer point is to be made very sharp by grinding it.Here the magnetic base of the 0-10mm dial gauge may be used.

    4.2.5. .During measurement of water level in the jar the micrometer is tobe kept approximately in center of the jar. The micrometer alongwith the magnetic base to be transferred from one pedestal toanother pedestal very carefully so there is no disturbance to theheight of the micrometer. All the necessary care are to be takenduring this measurement i.e. there should not be any air bubble in

  • 7/24/2019 Bhel Bearing Erection

    20/39

    STEAM TURBINE

    500 MW

    ERECTION

    CRITICAL ACTIVITIES

    (CATENARY AND ALIGNMENTS)

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0804GPage No. 20of 40

    the polythene pipe and the polythene pipe should be kept as

    stationary.

    4.2.6. While finalizing the catenary of the machine these measurementsare to be repeated 3-4 times in a day at different intervals to avoidany possibility of the error.

    4.2.7. The height of the L.P. rear pedestal is the reference point forsetting the height of all other pedestal and L.P. base plates. TheL.P. rear pedestal height is to be first made with the benchmarkplate as per the center line of the machine with the help of waterlevel jar.

    4.2.8. The benchmark plate is to be preserved for all future references.

    4.2.9. The catenary is to be counter checked after grouting all thepedestals as well as after final alignment of the rotors. The finalvalue of the catenary may be worked out as center of the shaft oneach pedestal bore after taking the final seal bore readings. Thefinal catenary should match with the design value of the catenaryotherwise a necessary correction may be carried out.

    4.2.10.After ensuring the required catenary of the machine the couplingalignments are to be made as parallel coupling.

    4.2.11.The value of the catenary given over the drawing are theoreticalvalue calculated by the designers but due to the human error insite measurements some time the correct coupling alignment arenot achieved then an alternate method for checking of catenarymay also be used i.e. optical measurement method or a methodby which direct journal heights are taken on each bearing in placeof pedestal height.

    4.2.12.For measurements of direct journal height a special fixture is tobe fabricated and necessary information about it can be separatelygiven by PS-TS if such necessity arises.

    5. HORN DROP TEST

    5.1. General description

  • 7/24/2019 Bhel Bearing Erection

    21/39

    STEAM TURBINE

    500 MW

    ERECTION

    CRITICAL ACTIVITIES

    (HORN DROP TEST)

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0806GPage No. 21of 40

    By horn drop test the loading of the casing on each corner is determined. The

    horn drop test is repeated at various stages in individual casing i.e. first

    without connection of any pipe lines the horn drop readings are recorded then it

    is compared after welding of inlet, outlet and extraction pipe lines etc. The horn

    drop readings are very important in HP & IP casing. First the proper horn drop

    readings are made without connection of any pipe lines and then the reading

    are taken after welding of all pipe lines on HP & IP casing. As such the

    influence of these major pipe lines are notices on each corner of HP/IP

    casing by comparing the horn drop test readings. The horn drop test will

    indicate the quality of work during assembly/welding of pipe lines with the HP &

    IP casing.

    This is a very important check and may cause serious problem in operation of

    the machine like high vibration in the machine failure of barring gear in hot/cold

    machine, obstruction during expansion of machine etc. In horn drop test a dropis measured on an individual corner of the casing with the help of a dial

    indicator by removing the support of individual corner and then it is compared

    with the opposite corner. As such this gives an indication of indifferent loading

    of the casing. In Russian design machine the value of direct dynoxmetre

    loadings are recorded in place of this horn drop test.

  • 7/24/2019 Bhel Bearing Erection

    22/39

    STEAM TURBINE

    500 MW

    ERECTION

    CRITICAL ACTIVITIES

    (HORN DROP TEST)

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0806GPage No. 22of 40

    5.1.1. Procedure

    5.1.2. After placement of HP and IP casing on four temporary packersensure that the each corner of the casing is loaded on temporarypacker and if necessary the shims may be given on packer forloading of the casing. The load of shaft is also taken on transportdevice during this stage.

    5.1.3. After transferring the load of the rotor on bearing and ensuring thecasing centering with respect to shaft the horn drop check may becarried out.

    5.1.4. Before taking the horn drop reading ensure that the enoughclearance is available on front & rear portion of the shaft with theirseals in the casing inside. After completing the centering of thecasing the some may be lifted by 0. 20 mm on all four corners byproviding shims. This will help in avoiding the touching of sealswith the rotor during the horn drop test readings.

    5.1.5. No adjustment on packer of the HP front and HP rear pedestalsare to be carried out after taking the horn drop test of the casingIn case if any adjustment is carried out on these pedestalpackers then horn drop test are to be repeated again.

    5.1.6. No piping may be connected to HP & IP casing till initial horn dropreadings are over. The piping work should not be postponed forwant of horn drop the only thing the last joint with HP/IP casingmay be left free till completion of horn drop check.

    5.1.7. While recording the horn drop readings the casing must beabsolutely free and even the radial and axial key of front andrear portion of the casing are either to be removed fully or theseare to be made completely free by removing their shims etc.

    Actually during this stage of erection only temporary axial andradial keys are fitted in the casing and even they carry someshims also. Before making the casings free on axial and radial

    key portion the dial gauges are to be installed to monitor themovement of the casing on radial and axial direction.Immediately after the completion of the horn drop test thesekeys/shims may be installed back and centering of casing maybe rechecked before further works.

    5.1.8. In HP casing the initial horn drop test may be done even afterfitting of breach nut assembly and HP exhaust elbow of both sides.

  • 7/24/2019 Bhel Bearing Erection

    23/39

    STEAM TURBINE

    500 MW

    ERECTION

    CRITICAL ACTIVITIES

    (HORN DROP TEST)

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0806GPage No. 23of 40

    5.1.9. In IP casing the initial horn drop test may also be done after fittingof IP inlet pipe lower half assembly but this pipe of upper halfcasing should not be fitted till completion of the horn drop test.

    5.1.10.All the four Jacking screw and hydraulic jack on each corner ofthe casing are to be installed for the horn drop test readings. A dialindicator is also to be installed on each corner of the casing formeasuring the drop of the casing.

    5.1.11.After initial centering of the casing the each corner packer maybe fitted with a shim of about 1 mm. for further adjustment duringthe horn drop test.

    5.1.12.During the horn drop test the individual packer of the casingis removed and the load of that corner is supported over the

    jacking screw of the casing. Now gradually the jacking screw isalso relieved with the help of hydraulic jack on that corner anddrop reading is recorded. This is repeated for each corner of thecasing. In case of variation in left and right side reading thedrop is adjusted by + adjustment of shims from left to right sideor vise-versa. No subtraction / addition in shim sizes from outsideis done here and only the shims are adjusted from left to right orvise versa till equal loading are achieved in left/right side ofindividual casing. The sizes of these casing packers are recorded

    after completion of horn drop to avoid any confusion at a laterdate while fitting the final packers.

    5.1.13.While recording the horn drop readings the drop on eachindividual corner may be controlled with the help of Jackingscrew so that during this test the casing is not touching with theshaft in gland portion of the seals at all and enough clearance isleft there to avoid damage to the seals inside the casing.

    5.1.14.During the initial horn drop the best reading within 0.05/0.06may be achieved by fine adjustment of the packer shims. The

    comparison in horn drop value should always be made in left andright side only of an individual casing.

    5.1.15.In case of HP casing the drop on rear end is so high that unlessthe casing is locked on diagonally opposite end the horn dropcheck is not possible. Therefore while recording drop on HP rearend the front end of the casing diagonally opposite to it shouldbe locked with casing clamp. The pedestal is also required to belocked on all four side with its sole plate with the help of theclamps. In case of IP casing no locking of any corner of the casingis necessary during the horn drop test.

  • 7/24/2019 Bhel Bearing Erection

    24/39

    STEAM TURBINE

    500 MW

    ERECTION

    CRITICAL ACTIVITIES

    (HORN DROP TEST)

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0806GPage No. 24of 40

    5.1.16.The final packers on HP & Ip casing are installed only aftercompleting the rolling test of these casing., The horn drop readingfor an individual casing may be recorded after the fixing of finalpackers also. If necessary a fine adjustment may be carried out atthis stage to achieve correct value of the horn drop reading.

    5.1.17.After completing the welding of all pipe lines with the casing , thehorn drop readings are repeated again for comparison with theearlier readings. These readings are taken along with its radialand axial keys of the casing.

    5.1.18.During this stage exactly this can not be defined that how much

    variation is permitted on these values of horn drop readings., Butthis variation will indicate the influence of the piping load onthe HP/IP casing caused due to welding/connection of various pipelines with the casing. The variation in horn drop readings arepermitted as long as sufficient positive loading is there on eachcorner of the casing. But if any corner of the casing is fullyunloaded/heavily loaded then there is no choice left and pipe linesare to be corrected by dismantling it and making again a free

    joint with the casing.

    5.1.19.During variation of horn drop reading no correction is to bemade on casing packers by adjustment of shims etc. The

    variation at this stage is caused due to the piping pull/push onlyso if any correction is required then the same may be carried outin piping joints and support etc. And any adjustment in pipingsupports can be carried out only after disconnecting the pipe linewith the casing. Even some time it is necessary to cut theindividual or more piping joint for correction of horn drop readings.

    5.1.20.The variation in horn drop reading of left and right side of a casingmay be permitted upto a difference of 50%.

    5.1.21.The horn drop readings are not taken for L.P. inner outer casing

    due to its fabricated structure and the parting plane of thecasing are leveled on four corner with the help of water level jararrangements.

  • 7/24/2019 Bhel Bearing Erection

    25/39

    STEAM TURBINE

    500 MW

    ERECTION

    CRITICAL ACTIVITIES

    (SWING CHECK)

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0806GPage No. 25of 40

    6. SWING CHECK

    6.1. GENERAL DESCRIPTION

    The swing check is the measurement of radial throw caused due to

    coupling face geometric form of the two rotor coupled together. This is

    measured on opposite end of the coupling and at the free end of the rotor. The

    higher swing check value may cause higher shaft vibration, higher bearing

    shell temperature etc. The value of swing check depends on axial runout of

    coupling faces, the diameter of the coupling and the length of the rotor. During

    the machining of rotors in the works some tolerances are permitted by

    Designer's on the coupling faces of the rotor resulting to some swing check

    values. The maximum swing check values permitted caused due to the

    above tolerance for different diameter and length of the rotor can be

    worked out from the enclosed graph. However it is recommended to keep theminimum swing check values for better results during operation of the machine.

    In a multi rotor Turbine-Generator system it is essential to measure the swing

    check value in both extreme end and where the weight of the rotors are light.

    For example 200/210 M.W. KWU machine with Russian Generator and

    static excitation system the swing check values are measured on HP rotor front

    end only. In 500 M.W. machine the swing check values are measured in H.P.

    front end and on exciter rear end. After having general experience of number of

    200 MW & 500 MW units, a necessity is felt to measure swing check value on

    IP rotor front end also for better results during operation of the units. This can

    be done initially during erection with temporary coupling bolts on LP-IP

    coupling before reaming/honing of coupling. Any variation in swing check

  • 7/24/2019 Bhel Bearing Erection

    26/39

    STEAM TURBINE

    500 MW

    ERECTION

    CRITICAL ACTIVITIES

    (SWING CHECK)

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0806GPage No. 26of 40

    values may be corrected without any hesitation during erection of machine.

    Any compromise at erection stage may cause serious problem during

    operation of the unit and any correction becomes much more tedious a later

    stage. The correction may be carried out either by interchanging the

    coupling position or by correcting the coupling faces by

    scrapping/cutting in consultation of Designers.

    6.2. PROCEDURE

    6.2.1. Before placement of Module/Rotor in position the coupling facesof all the rotors are to be measured for concavity/convexity oftheir coupling faces. This can be checked with the help of a thinrectangular light weight straight edge. No convexity is permitted onthese coupling faces however a concavity of about 0.03/0.04 mm ispermitted. In case of any variation the matter may be referredto manufacturing units.

    6.2.2. After placement of individual Module/Rotor the coupling facesare to be measured for axial runout before taking up alignmentof various rotors. The HP rotor rear coupling face can bemeasured after placing it on both of its bearing. The IP rotorfaces are to be measured after placing IP rear end on bearingand front end on lifting tackle. Similarly L.P. rotor, may be placedon bearing on its rear end and front end supported on liftingtackle. Any variation on axial runout on coupling faces for morethen the 0.02 mm. may be referred to Designer's before taking upfurther works.

    6.2.3. After completing final alignment of various rotor they are tobe coupled with temporary bolts, considering their axialrunout/geometric form of the coupling faces.

  • 7/24/2019 Bhel Bearing Erection

    27/39

    STEAM TURBINE

    500 MW

    ERECTION

    CRITICAL ACTIVITIES

    (SWING CHECK)

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0806GPage No. 27of 40

    6.2.4. During coupling with temporary bolts the higher plane of one ofthe rotor face is to be coupled with lower plane of anothercoupling face of the rotor.

    6.2.5. During coupling on temporary bolts the uniform tightening on all thefour temporary bolts are to be ensured otherwise it will disturbthe swing check value of the rotor.

    6.2.6. First IP-LP coupling is to be made with temporary bolts and swingcheck on IP rotor front end is recorded. After this only HP-IP rotoris to be coupled with temporary bolts and the swing check valueon HP front rotor is recorded.

    6.2.7. During swing check of IP rotor its front end is to be supportedon lifting tackle without making any connection between HP-IProtor.

    6.2.8. While recording swing check of HP rotor the front end of the rotoris to be supported on lifting tackle.

    6.2.9. During swing check the lifting tackle are to be fitted properly. Thetie rod of lifting tackle should be ensured for correct fitting of itsspherical bearing and Molykote should be applied on thesespherical bearing for their free movement. These spherical

    bearing should not obstruct the movement of shaft radially duringchecking of its swing check value.

    6.2.10.After taking the load of the rotor on lifting tackle ensure that therotor is not disturb radially due to fitting of lifting tackle.

    6.2.11.During checking of swing check measure radial movement of rotoron parting plane and rotate the rotor either on jacking oil with handbarring or with the help of E.O.T crane with thick oil on bearings.

    Avoid jerk during rotation of rotor while recording the swing checkvalues.

    6.2.12.After ensuring the swing check values as per the graph with ontemporary coupling bolts, the HP-IP and LP-IP coupling may becleared for reaming / honing of the coupling holes. Any variationneed correction of the coupling before reaming/honing of the holes.

    6.2.13.The final swing check value of HP front rotor is to be recordedafter fitting/ elongation of all the coupling bolts of HP-IP & LP-IProtors. Any variation in readings may be referred to the Designer's.For improvement of the swing check values, the indifferenttightening and non-sequential

  • 7/24/2019 Bhel Bearing Erection

    28/39

    STEAM TURBINE

    500 MW

    ERECTION

    CRITICAL ACTIVITIES

    (SWING CHECK)

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0806GPage No. 28of 40

    6.2.14.During checking of swing check readings, the initial few rotationsare to be given to the rotor to avoid initial sag and then only thereadings are to be recorded.

    6.2.15.Similar method is to be adopted while checking the swing checkvalue of the exciter except the rotor is hanged on the suitable sizeof sling in place of the lifting tackle.

    6.2.16.While recording the swing check initially with temporary boltsfor HP & IP rotor, the fitting of eight number temporary bolts arepreferred in place of four bolts on the coupling.

  • 7/24/2019 Bhel Bearing Erection

    29/39

    STEAM TURBINE

    500 MW

    ERECTION

    CRITICAL ACTIVITIES

    (SWING CHECK)

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0806GPage No. 29of 40

  • 7/24/2019 Bhel Bearing Erection

    30/39

    STEAM TURBINE

    500 MW

    ERECTION

    CRITICAL ACTIVITIES

    (COUPLINGS & ALIGNMENTS

    OF ROTORS)

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0807GPage No. 30of 40

    7. COUPLINGS & ALIGNMENTS OF ROTORS

    7.1. GENERAL DESCRIPTION

    The coupling on turbine shaft are generally rigid coupling but in case of L.P.

    rotor sometime the coupling head are shrunk fit and remachined. The basic

    function of any coupling is to connect two or more shaft together to form a

    shaft assembly. The number of shaft mainly depend upon the rating of the

    machine.

    A very high accuracy is required during manufacturing of these rotor shaft

    at works. The axial runout on the coupling face may not exceed 0.02 mm.

    and an additional check is also made at works/site to ensure that the geometry

    of the entire coupling surface does not deviate by more then the 0.02 mm.

    except the concavity on the coupling face which is permitted upto 0.03/0.04

    mm.

    The radial and axial alignment of the various shafts are to be completed

    before their coupling and alignments are to be done in such a way that the

    entire shaft assembly follow the continuous deflection curve given over the

    drgs. for a particular machine. The coupling checks determines both the radial

    and axial position of the two adjacent coupling flanges relative to one another.

    The radial measurement are performed on the circumference of the

    couplings and the axial measurement are performed on outer most diameter

    of the coupling. During coupling of the two shafts it should be ensured that the

    no stresses are exerted as a results of the coupling each other shaft.

    After completion of the alignment and coupling of the shaft the casings are

    aligned radially and axially. Here equal importance is given to the radial & axial

  • 7/24/2019 Bhel Bearing Erection

    31/39

    STEAM TURBINE

    500 MW

    ERECTION

    CRITICAL ACTIVITIES

    (COUPLINGS & ALIGNMENTS

    OF ROTORS)

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0807GPage No. 31of 40

    alignment of stationary parts to avoid any rubbing during operation of the

    machine due to expansion of stationary and rotary parts.

    During the alignment of two coupling both are to be turned in same direction

    and by the same amount when the measurement are taken to avoid the

    influence of the axial & radial runout present in the shaft caused due to the

    machining.

    7.2. PROCEDURE

  • 7/24/2019 Bhel Bearing Erection

    32/39

    STEAM TURBINE

    500 MW

    ERECTION

    CRITICAL ACTIVITIES

    (COUPLINGS & ALIGNMENTS

    OF ROTORS)

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0807GPage No. 32of 40

    7.2.1. Before placement of module/rotor in position check and record thecoupling hole and journal dia of the shaft.

    7.2.2. Check coupling faces for the concavity/convexity withthe help of a thin rectangular straight edge before placement ofmodule/rotor in position.

    7.2.3. Check spigot and recess of the coupling and ensure their fittingbefore placement in position.

    7.2.4. Place the module/rotor in position and check the radial runout ofjournal and axial runout of the coupling faces independently ofeach shaft. During checking of radial and axial runout of the shaftplace H.P. rotor on both of its bearing and IP/LP rotor one endon its bearing and another end on the lifting tackle. The radialand axial face runout on the shaft should be within 0.02 mmaccuracy. Any variation may not be permitted here and matter maybe referred to the designer's.

    7.2.5. The HP,IP & LP rotor are aligned together and then their couplingsare made. After fully completion of HP/IP & IP/LP coupling withtightening of their final bolts the complete shaft is cleared forGenerator rotor alignment.

    7.2.6. During initial alignment of HP/IP & IP/LP rotor the radial checksare generally done with the help of depth micrometer and axialgap are measured with the slip gauges. After completion of theradial alignment the rotor are inserted in their spigot even withsome minor variation in their axial gap values.

    7.2.7. During final alignment only the axial gap values are checked at90o on four places by rotating both the rotor together andaverage of these four reading are taken. The radial alignmentreading along with axial gaps are necessary wherever theeffective spigot are not existing in two couplings i.e. in case of LP -Gen coupling the radial dial reading are also taken.

    7.2.8. Avoid rotation of two shaft in their spigot. If necessary these maybe rotated after taking out from their spigot.

    7.2.9. During alignment of shafts the adjustment of shims in bearingtorus may be fully avoided. The margin of + 0.30 mm. in height &left/right direction may be kept for emergency works only. Anyadjustment during erection and normal overhauling may be doneby adjusting shims between spherical/cylindrical seat andpedestal base only. For left and right adjustment the complete

  • 7/24/2019 Bhel Bearing Erection

    33/39

    STEAM TURBINE

    500 MW

    ERECTION

    CRITICAL ACTIVITIES

    (COUPLINGS & ALIGNMENTS

    OF ROTORS)

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0807GPage No. 33of 40

    H.P. front and HP rear pedestal may be moved with the help oftheir radial keys.

    7.2.10.The final packers of the pedestal and base plates are fitted beforethe grouting of the pedestal itself and here no adjustment isnecessary during erection of the machine. But during overhauling ofthe machine the adjustment may be carried out in these packersfor correction of catenary of the machine.

    7.2.11.During alignment of rotor make HP/IP and IP/LP coupling gapparallel. After completion of final alignment no adjustment ofpackers and keys etc are permitted on pedestals and bearing the

    final alignment of HP/IP & IP/LP rotors should be checked afterfitting of all the final keys and packers of the pedestals.

    7.2.12.After alignment couple the HP-IP & IP-LP rotors on temporarybolts. Record coupled runout of the rotor and ensure that thecoupled runout is not more then 0.03 mm. in any where in the

    journal as well as in coupling area. Before coupling of rotor ontemporary bolts record their spigot clearances by actually movingthe rotor radially.

    7.2.13.During erection IP-LP swing check on IP front and HP-IP swingcheck on HP front are to be recorded on temporary bolts. These

    reading are to be ensured within the design limit.

    7.2.14.Before alignment/coupling position the two shaft adjustment toeach other depending upon the higher and lower point of the shaftwith respect to their axial face measurement values.

    7.2.15.The HP-IP & IP-IP coupling may be cleared for reaming/honingafter ensuring the runout and swing check values of the rotors.In case of variation the cause of the error may be identified andcorrected before further work of reaming and honing of thecoupling.

    7.2.16.During coupling of rotors two taper pins may be used forproper alignment of coupling holes so that there is minimumenlargement of holes are done at site during reaming/honing.Unnecessary enlargement of holes may be fully avoided duringreaming/honing at site as this may cause serious problem at a laterdate during overhauling of the unit.

    7.2.17.As for as possible ream/hone all the coupling bolts holes tosame size. In exceptional cases only the variation in holesizes are permitted. Each hole during honing should be checked

  • 7/24/2019 Bhel Bearing Erection

    34/39

    STEAM TURBINE

    500 MW

    ERECTION

    CRITICAL ACTIVITIES

    (COUPLINGS & ALIGNMENTS

    OF ROTORS)

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0807GPage No. 34of 40

    for bananas shape with the help of a parallel ground straight pinof 0.02/0.03 undersize. No banana shape is permitted in any ofthe hole. The hole should be made to 0.005 mm accuracy.

    7.2.18.All the coupling bolts are to be machined and ground by0.02/0.03 mm undersize then the hole dia. These bolts are tobe fitted with thumb pressure only and no additional force isrecommended while fitting these bolts.

    7.2.19.A very thin layer of molykote may be applied on all thecoupling bolts during their fitting. The molykote should not beapplied on seating face of the coupling bolts. This may cause

    in breaking of their locking pin during elongation of couplingbolts.

    7.2.20.All the coupling bolts are to be balanced before finallyfitting/tightening in position. These are to be balanced within anaccuracy of 5 gms each along with their nuts. In case all thesebolts are of equal size then their weight must be equal. Inexceptional cases the 180o opposite bolts may be made of equalweight.

    7.2.21.During tightening of coupling at any stage first tighten four boltson 90o location. Always tighten bolts in proper sequence

    with 180o opposite bolts. These bolts are to be elongated to thevalue given over drgs.

    7.2.22.During tightening of coupling the radial runout on journal andcoupling may be checked at various stages during tightening ofbolts. The final coupled runout should not be more then 0.03 mm.on coupling and journal of the shaft.

    7.2.23.After final tightening of LP-IP and HP-IP coupling the swingcheck value on HP front rotor is to be rechecked. In case ofvariation in value a proper correction is to be made withconsultation of designer's. The indifferent or unsequential

    tightening for achieving the swing check value or coupled runoutvalue may be fully avoided. this may cause unnecessary stresseson the coupling.

    7.2.24.After completing the coupling work the casing radial and axialalignment may be done.

  • 7/24/2019 Bhel Bearing Erection

    35/39

    STEAM TURBINE

    250 MW

    ERECTION

    CRITICAL ACTIVITIES

    (Welding of steam inlet and exhaust

    pipe lines with HP and IP casing)

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-17-0808GPage No. 35of 40

    Welding of steam inlet and exhaust pipe lines with HP

    and IP casing

    In 210 MW machine the HP Turbine is supplied with two inlet and two exhaust

    flanges for connection of the pipe line.but in case of 500/250 MW HP Turbine

    the casing is supplied with four inlet flanges also. As such in 200 MW machines,

    only two ESV control valves are used in the system. Whereas in 500/250 MW

    machines , It may be either two ESV oontrol valves or four ESV control valves to

    cope with the design of the casing.

    Similarly in 210 MW machines, the I.P. casing is supplied with two inlet flanges

    and eight number exhaust branches or either two exhaust branches only along

    with two inlet flanges. These eight number exhaust branches are distributed four

    on each side of the casing and each four branches are joined together with one

    common pipe while connected to L.P. casing. The 500 MW I.P. casing is similar

    to the 210 MW I.P. casing but some time these are supplied with four numbers

    of I.V. control valves also. The inlet lines from each two control valves are joined

    together and make one connection with the I.P. casing in bottom. As such in

    210 MW machines, only two I.V. control valves are used but in case of 500 MW

    machines, there can be either two I.V. control valves or four I.V. control valves.

    After completion of the rolling test the installation of final keys and packers of the

    H.P. and I.P. casing, the same can be cleared for welding of inlet and outlet

    pipelines. The main steam inlet line from main steam strainer to the control

    valves and then from control valves to the H.P. casing need much more care

    during erection / welding of the pipelines. Similarly the Hot Reheat lines between

    two Hot Reheat strainer to the control valves and from control valves to the I.P.

    casing also need equal care during erection / welding of these pipelines. These

    pipelines are directly affecting the performance of the turbine during operation of

    the machine and a necessity is felt to fully involve the turbine Erection Engineer

  • 7/24/2019 Bhel Bearing Erection

    36/39

    STEAM TURBINE

    250 MW

    ERECTION

    CRITICAL ACTIVITIES

    (Welding of steam inlet and exhaust

    pipe lines with HP and IP casing)

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-17-0808GPage No. 36of 40

    in erection / welding of the pipelines at site along with the Piping Engineers. The

    piping connection between I.P. casing to L.P. casing i.e. cross around piping

    also need proper care but due to its construction with number of bellows in the

    system. Present method of erection / welding much of the problems are not

    faced during operation of the machine. However if proper care is not taken here

    then that may cause the unnecessary loading on the various bellows of the

    piping and reduction in their life. In case, if proper care is not taken during

    erection / welding of MS inlet, CRH & HRH connections with HP & IP casing, a

    load will be transfer from the pipe line to the casing. Which may cause vibration

    in the machine, obstruction in expansion of the machine, obstruction of barring

    gaer operation in hot / cold machine, higher babbit metal temperature and failure

    of brg. babbit etc. during operation of the machine.

    8. PROCEDURE

    8.1. The following points are to be taken care while welding MS, CRH, HRHpipelines with HP & IP casing and control valves / strainers.

    8.1.1. The HP & IP casings are to be cleared in all respects after fitting offinal packers and axial / radial keys of the casing.

    8.1.2. The ESV & IV valves are to be cleared after fitting of theirservomotors and then levelling including the correct elevation etc.

    8.1.3. The equivalent insulation weight is to be given on each controlvalve befor connection of any pipeline with the valve. The changein hanger value of the control valve is to be adjusted back by lifting

    the valve with the help of hangers. The control valve hanger readingshould remain same as before and after installation of equivalentinsulation weight on the valve. After this all the three hangers ofeach valve are to be locked to avoid any movement of the valve inupward direction, in case the equivalent insulation weight isremoved or any of the servomotor is removed. Before starting ofany welding with the control valve the valves are to be locked fortheir movement.

    8.1.4. Erection and welding of MS line upto MS strainer and HRH strainerare to be completed first including either their insulation or

  • 7/24/2019 Bhel Bearing Erection

    37/39

    STEAM TURBINE

    250 MW

    ERECTION

    CRITICAL ACTIVITIES

    (Welding of steam inlet and exhaust

    pipe lines with HP and IP casing)

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-17-0808GPage No. 37of 40

    equivalent weight is to be given for their insulation weight in thelines. These lines should be in perfect floating condition on theirhangers before taking up the further work of MS & HRH lines uptothe ESV & IV control valves.

    8.1.5. Install MS & HRH lines between strainer and control valves andweld all the inbetween joins of the pipelines except the end jointswith the valves and strainers. These lines are to be erected in sucha way that both the end joints remain free and parallel with thestrainer and control valve after taking their load on hangers. Thefreeness of joints are to be ensured after giving the equivalent

    insulation weight of the lines.8.1.6. Weld MS & HRH lines with the strainers and again ensure the

    freeness / paralalllity of MS & HRH lines with the ESV and IVcontrol valves. Any minor variation may be readjusted on hangersto obtain the freeness of the joints with the control valve.

    8.1.7. Install the MS and HRH lines between control valves and HP /IPcasing . Now all the in between joints may be keeping the end jointsfree with the valve and the casing. The erection of these lines areto be done in such a way that freeness and parallelity of end jointsare achieved after fully floating the pipe lines on their hangers. The

    equivalent insulation weights are also to be added during erectionof these pipe lines before welding the end joints.

    8.1.8. After ensuring the freeness and parallelity of the end jointsbetween ESV control valve and HP casing , the same may bewelded together. But the stress relieving of all the in -between jointsof the lines are to be completed before taking up work of the abovelast two end joints . Similar proceedure may be followed for thelines between I V valves and IP casing also.

    8.1.9. Weld left and right MS and HRH joints togethers with the HP andIP casing to avoid any left and right loading on the casing . during

    welding the left and right movements of casing may be monitoredby installing the radial dial gauge on the casing.

    8.1.10. The CRH lines are to be erected on their permanent hangers andthe joint with the HP casing are to be made free /parallel afterfloating the pipe lines. The left and right side casing joints are to bewelded together , similar to MS lines but before weling of these linethe in- between joints are to be completed first . The equvalentinsulation weight is also to be given on these line while checking thefreeness of end joints with the HP casing.

  • 7/24/2019 Bhel Bearing Erection

    38/39

    STEAM TURBINE

    250 MW

    ERECTION

    CRITICAL ACTIVITIES

    (Welding of steam inlet and exhaust

    pipe lines with HP and IP casing)

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-17-0808GPage No. 38of 40

    8.1.11.The horn drop readings are to be recorded for both HP and IPcasing after copletion of the job including insulation of pipe linesand control valve etc.

    8.2. SPECIAL CARE

    8.2.1. If possible keep the insulation weight and servomotors on ESV and

    I V control valves during erection /welding of these MS & HRHlines from strainers to the valve and casing . If the above conditionare fulfilled then there no need of any locking of the valves duringthe welding of any pipe lines.

    8.2.2. The control valves hanger readings are to be measured with theinside micrometer in various stages and changes are to bemonitored properly . The readings are to be measured in thefollowing stages :-

    After complete leveling of ESV and IV control valves with their

    servomotors

    After putting the equivalent insulation weight on the control

    valves.

    After readjustements of control valve height equivalent to

    insulation weight.

    After connection of MS &HRH lines with the strainers .

    After connection of MS & HRH lines with the HP & IP casing .

    After complete insulation of control valve and pipings.

  • 7/24/2019 Bhel Bearing Erection

    39/39

    STEAM TURBINE

    250 MW

    ERECTION

    CRITICAL ACTIVITIES

    (Welding of steam inlet and exhaust

    pipe lines with HP and IP casing)

    8.2.3. Ensure proper clraning of MS and HRH lines between controlsvalve and casing as these lines are not covered in steam blowingoperation . Proper care is to be taken during erection of these linesto avoid entry of foreign material.

    8.2.4. The steam blowing of the MS and HRH pipe line are to be carriedout after fully completing the erection /welding of lines from controlvalve to the HP and IP casing .

    8.2.5. All the four corners of the casing may be locked with the casingclamp during welding of piping joints to avoid movement of casingradially.

    8.2.6. The load of the upper half HRH pipe upto the flange supplied byturbine supplier is taken by the IP casing and by the pipinghangers. This may be taken care while erecting the HRH lines.