    E R E C T I O NM A N U A L

    STEAM TURBINE500 MW

    (KWU DESIGN)

    DOCUMENT NO. TS-T1-08

    Bharat Heavy Electricals Limited

    POWER SECTORTECHNICAL SERVICES (HQ)

    NOIDA

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 1

  • 8/12/2019 BHEL Erection Manual

    2/127

    FOREWORD

    I am glad that Power Sector - Technical Services ( Head Quarters),

    Noida has brought out this erection manual of 500 MW steam

    turbine (KWU design) being produced by BHEL. This manual lays

    emphasis on site optimisation techniques which aims at uniform

    erection practices, improvement in quality, reduction in time cycle

    and saving in cost.

    I am sure, this manual will form the basis for site erection activities

    so that the organisation can derive full benefit out of this. It is

    needless to emphasize that upgrading of technology is a continuous

    process and we have to review our methods of working and make

    suitable changes, wherever required.

    (K P Mathur)New Delhi Executive Director

    (PEM & TS)

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 2

  • 8/12/2019 BHEL Erection Manual

    3/127

    PREFACEThe Erection Manual for 500 MW Steam Turbine (KWU design)

    manufactured by BHEL for Thermal Power Stations has been

    prepared by a team of BHEL engineers having long experience in

    Erection & Commissioning, Design, Quality control of steam turbines.This dedicated team has been drawn from regional erection group,

    designed department of manufacturing units, PS-Q & TS-HQ,

    Noida.

    The manual carries general description of steam turbine, erection

    procedure, special instruction, general instructions, and various other

    technical instructions with an intention to establish an uniform

    approach for erection of steam turbine.

    The Erection Manual provides broad based guide line for erection of

    steam turbine. Product standard, technical circulars & BHEL

    drawings for the specific project will precede the instructions and

    guidelines furnished in this manual. Project specific document will be

    generated by region concerned. This document is generated as a

    standard Erection Manual for 500 MW fixed pedestal type steam

    turbine with spring loaded foundation.

    The work done by TASK FORCE is commendable. Feed-back and

    suggestions are welcome for the improvement of this Erection

    Manual to bringing down the cycle time with quality.

    BHEL reserves the right to suggest alternative procedure if

    necessity arises at site due to local site conditions .

    (BABOO RAM)

    NOIDA GENERAL MANAGER(TS&Q)

    SNO DESCRIPTION INSTRUCTION NO

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 3

  • 8/12/2019 BHEL Erection Manual

    4/127

    1 TECHNICAL DATA T 1- 08-0101G

    2 INSTRUCTION FOR HANDLING ANDSTORAGE OF TURBINE

    T 1-08-0202G

    3 ERECTION SEQUENCE T 1-08-0303G

    4 ERECTION PROCEDURE T 1-08-0404G

    5 GROUTING PROCEDURE T 1- 08-0505G

    6 ASSEMBLY OF IP MODULE AT SITE T 1-08-0606G

    7 SEALING AND ANTISEIZING COMPOUNDS T 1-08-0707G

    8 CRITICAL ACTIVITIES T 1-08-0808G

    9 SPRING LOADED FOUNDATION T 1- 08-0909G

    10 ERECTION OF PIPING T 1-08-1010G

    11 SPECIFICATION FOR GAS HEATING DEVICE T 1-08-1111G

    12 SPECIFICATION FOR BREECH NUT HEATINGDEVICE

    T 1-08-1212G

    13 SPECIFICATION FOR THERMAL INSULATION T1-08-1313 G

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 4

  • 8/12/2019 BHEL Erection Manual

    5/127

    The following codification system is used for numbering of instructions and thecodification of Log Sheets is as per FQA document.

    XX X - XX XX XX XAlpha Numeric Numeric Numeric Numeric Alpha

    Type ofInstruction

    System Instruction No

    System Designation

    Rating of Main Equipment

    Type of Manual

    Product Code

    1.1 PRODUCT CODE

    B Boiler

    BA Boiler Aux.

    T Turbine

    TA Turbine Aux.

    G Generator

    GA Generator Aux

    P Power Plant Piping

    CI C&I1.2 TYPE OF MANUAL

    1 Erection

    2 Commissioning

    3 Service

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 5

  • 8/12/2019 BHEL Erection Manual

    6/127

    1.3 RATING OF MAIN EQUIPMENT

    01 200/210 MW

    02 120 MW

    03 110 MW

    04 60 MW

    05 30 MW

    06 100 MW

    07 235 MW

    08 500 MW KWU Design

    09 210 MW KWU Design

    10 120 MW KWU Design

    11 60 MW KWU Design

    12 70 MW KWU Design

    13 Industrial Units

    14 210 MW Tower Type Concrete Pylem

    15 210 MW Tower Type Steel Structure

    16 500 MW Tower Type Once through

    17 250 MW

    18 CCP

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 6

  • 8/12/2019 BHEL Erection Manual

    7/127

    1.4 SYSTEM DESIGNATION

    SNO DESCRIPTION

    1. TECHNICAL DATA

    2. INSTRUCTION FOR HANDLING AND STORAGEOF TURBINE

    3. ERECTION SEQUENCE

    4. ERECTION PROCEDURE

    5. GROUTING PROCEDURE

    6. ASSEMBLY OF IP MODULE AT SITE

    7. SEALING AND ANTISEIZING COMPOUNDS

    8. CRITICAL ACTIVITIES

    9. SPRING LOADED FOUNDATION

    10. ERECTION OF PIPING

    11. SPECIFICATION FOR GAS HEATING DEVICE

    12. SPECIFICATION FOR BREECH NUT HEATINGDEVICE

    13. SPECIFICATION FOR THERMAL INSULATION

    1.5 TYPE OF INSTRUCTION

    G General

    T Technical

    L Log Sheet

    C Check List

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 7

  • 8/12/2019 BHEL Erection Manual

    8/127

    LOAD

    RATED 500 MW

    MAX. UNDER VALVE WIDE OPEN (VWO) CONDITION 524.2

    CONSTRUCTION

    THREE CYLINDER REHEAT CONDENSING TURBINE 500 MW

    SINGLE FLOW HP TURBINE WITH 17 REACTION STAGES TYPE H30-100-2

    DOUBLE FLOW IP TURBINE WITH 12 REACTION STAGES PERFLOW

    TYPE M30-63

    DOUBLE FLOW LP TURBINE WITH 6 REACTION STAGES PERFLOW

    TYPE N30-2X10

    2 MAIN STOP AND CONTROL VALVES TYPE EV320-1

    2 REHEAT STOP AND CONTROL VALVES TYPE IV560

    1 SWING CHECK VALVE IN COLD REHEAT LINEMAKE

    DN-800BHEL,TIRUCHY

    2 BYPASS STOP AND CONTROL VALVES DN-320

    EXTRACTION SWING CHECK VALVES :

    EXTRACTION-1 : NO VALVE -

    EXTRACTION-2 : 1 SWING CHECK VALVE WITH ACTUATORMAKE

    DN-800BHEL,TIRUCHY

    EXTRACTION-3 : 1 SWING CHECK VALVE WITH ACTUATOR&1 SWING CHECK VALVE WITHOUTACTUATOR

    MAKEDN-500

    BHEL,TIRUCHY

    EXTRACTION-4.1 : 2 SWING CHECK VALVE WITH ACTUATORMAKE

    DN-500BHEL,TIRUCHY

    EXTRACTION-4.2 : 2 SWING CHECK VALVE WITH ACTUATORMAKE

    DN-500BHEL,TIRUCHY

    EXTRACTION-5 : 1 SWING CHECK VALVE WITH ACTUATOR&1 SWING CHECK VALVE WITHOUT ACTUATOR

    MAKEDN-400

    BHEL,TIRUCHY

    EXTRACTION-6 : NO VALVE

    SPEED

    RATED SPEED 50.0 /S

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 8

  • 8/12/2019 BHEL Erection Manual

    9/127

    SPEED LIMITATION IN LOAD & STATION AUX. LOADOPERATION

    MAX. SPEED, NO TIME LIMITATIONMIN. SPEED, NO TIME LIMITATION

    PERMISSIBLE FOR A MAXIMUM OF 2 HRS. DURING THE LIFE OFLP BLADING SPEEDBELOW

    SPEEDABOVE

    ::

    ::

    524.251.5 /S47.5 /S

    47.5 /S51.5 TO 60 /S

    SPEED EXECUTION RANGE AT OPERATION WITHOUT LOAD* : 6.7 TO 47.5 /S

    STANDARD OVER SPEED TRIP SETTING : MAX. 55.5 /s

    * THIS SPEED RANGE SHOULD BE PASSED THROUGH IN ONE

    SMOOTH OPERATION TO AVOID ENDANGERING THEBLADES DUE TO RESONANCE

    STEAM PRESSURESRATED* LONG TIME

    OPERATIONSHORT TIMEOPERATION

    INITIAL STEAM 166.7 166.7 20.7 BAR

    BEFORE 1st HP DRUM STAGE 154.4 163.4 169.9 BAR

    HP CYLINDER EXHAUST 44.9 52.0 57.4** BAR

    IP CYLINDER STOP VALVE INLET 40.3 46.7 55.2** BAR

    EXTRACTION 6 44.9 52.0 57.4 BAR

    EXTRACTION 5 17.5 22.2 22.2 BAR

    EXTRACTION 4 7.2 8.7 8.7 BAR

    EXTRACTION 3 2.58 3.2 3.2 BAR

    EXTRACTION 2 1.329 1.66 1.66 BAR

    EXTRACTION 1 0.257 0.41 0.41 BAR

    LP CYLINDER EXHAUST 0.1013 0.3 0.3 BAR

    * THESE VALUES CORRESPOND TO 500 MW LOAD WITH 3% MAKE-UP AND 0.1013 BAR BACKPRESSURE WITH ALL HEATERS IN SERVICE AND RATED STEAM CONDITIONS.

    ** THE SAFETY VALVES MUST BE SET SO THAT THESE SHORT TIME VALUES ARE NOT EXCEEDED.

    LONG TIME OPERATION : UPPER LIMIT VALUE, PERMISSIBLE WITHOUT TIME LIMIT.

    SHORT TIME OPERATION : PERMISSIBLE MOMENTARY VALUE. THE AGGREGATE DURATION OFSUCH SWINGS MUST NOT EXCEED 12 HOURS IN ANY ONE YEAR.

    ALL PRESSURES ARE ABSOLUTE PRESSURES

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 9

  • 8/12/2019 BHEL Erection Manual

    10/127

    LOW VACUUM TRIP, STANDARD SETTING

    HYDRAULIC LOW VACUUM TRIP : 0.3 BAR

    ELECTRICAL LOW VACUUM TRIP : 0.3 BAR

    HYDRAULIC LOW VACUUM TRIP BYPASS OPERATION : 0.6 BAR

    SEAL STEAM SUPPLY SYSTEM

    PRESSURE IN SEAL STEAM HEADER (ABOVE ATMOSPHERIC) : 35 MBAR

    AXIAL SHIFT

    ALARM TRIP

    * 0.5 mm * 1 mm

    * DIRECTION OF ROTATIONANTI CLOCK WISE WHEN VIEWED FROM FRONT PEDESTAL TOWARDS THEGENERATOR

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 10

  • 8/12/2019 BHEL Erection Manual

    11/127

    STEAM TEMPERATURES

    RATEDVAL.

    ANNUAL

    MEANVALUE

    LONG TIMEVALUE

    (WITHIN

    ANNUALMEANVAL.)

    400 hPER

    ANNUM

    80 h PERANNUM

    MAX. 15

    MIN ININDIVIDUA

    L CASE

    INITIAL STEAM 536.0 546.O 552.O 566.0OC

    IP CYLINDER STOP VALVE INLET 536.0 546.3 552.0 566.0OC

    RATEDVALVE *

    LONGTIME

    OPERATION

    80 h PERANNUM

    MAX. 15MIN IN

    INDIVIDUAL CASE

    INSPECIAL

    CASESAT NO

    LOAD

    HP CYLINDER EXHAUST 340.0 360.0 440.0 500.0**OC

    EXTRACTION 6 340.0 360.0 440.0 500.0**OC

    EXTRACTION 5 413.9 421.9 459.9OC

    EXTRACTION 4 292.1 304.1 346.4OC

    EXTRACTION 3 187.3 195.3 242.3OC

    EXTRACTION 2 128.3 139.3 184.3OC

    EXTRACTION 1 66.5 86.5 136.5OC

    LP CYLINDER EXHAUST 46.1 70.0 70.0OC

    LONG TIME OPERATION : UPPER LIMIT VALUE, PERMISSIBLE WITHOUT TIMELIMIT.

    * THESE VALUES CORRESPOND TO 500 MW LOAD WITH 3% MAKE-UP AND 0.1013 BARBACK PRESSURE WITH ALL HEATERS IN SERVICE AND RATED STEAMCONDITIONS.

    ** ONLY VALID FOR THE NO LOAD PERIOD WITH HIGH REHEAT PRESSURE AFTER

    TRIP-OUT FROM FULL LOAD OPERATION. FOR INDIVIDUAL CASE APPROX. 15MINUTES

    THE TURBINE IS IMMEDIATELY RE-LOADED OR THE BOILER IMMEDIATELYREDUCED TO MINIMUM LOAD IF NO LOAD OPERATION IS MAINTAINED.

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 11

  • 8/12/2019 BHEL Erection Manual

    12/127

    CASING TEMPERATURES

    WALL TEMPERATURES ALARMAT

    MACHINE MUST BESHUT DOWN AT

    HP TURBINE CASING EXHAUST 480 500OC

    OUTER CASING OF LP CYLINDER 90 110 OC

    PERMISSIBLE DIFFERENTIAL TEMP. BETWEEN PARALLEL STEAM SUPPLY LINES :

    NO TIME LIMITATION : 17OC

    SHORT TIME PERIOD (15 MIN.) : 28OC

    IN THE HOTTEST LINE THE LIMITATIONS INDICATED FOR INITIAL STEAM & REHEAT TEMP. MUST NOT BE EXCEEDED.

    SPRAY WATER TO LP TURBINE MUST BE SWITCHED ON AT 90OC.

    TEMPERATURES DIFFERENCE ALARMAT

    MACHINE MUST BESHUT DOWN AT

    DIFFERENCE BETWEEN UPPER & LOWER

    CASING HALVES HP TURBINE. MIDDLE

    * 90 * 100OC

    LP TURBINE. FRONT * 30 * 45OC

    LP TURBINE. REAR * 30 * 45OC

    FEEDWATER HEATER OUT OF SERVICE

    OPERATION WITH FEEDWATER HEATER OUT OF SERVICE MAIN STEAM

    FLOW Kg/s

    LOAD

    MW

    EXTRACTION A6 = 0 395 500

    EXTRACTION A5 = 0 421 500

    EXTRACTION A3 = 0 423 500

    EXTRACTION A2 = 0 425 500

    EXTRACTION A1 = 0 423 500

    EXTRACTION A6, A5 = 0 400 525

    OUTPUT LIMIT DURING TESTING WITH AUTOMATIC TURBINE TESTER

    TESTING OF MAIN STEAM STOP & CONTROL VALVE 400 M W

    TESTING OF HRH STEAM STOP & CONTROL VALVE 200 - 500 M W

    MOTORING :

    MOTORING IS THE CONDITION IN WHICH THE TURBINE IS DRIVEN BY THE GENERATOR ATRATED SPEED WITH THE STOP & CONTROL VALVES CLOSED. IN THIS OPERATING MODE,CERTAIN TURBINE COMPONENTS ARE HEATED UP BY WINDAGE POWER IN THE BLADING.TO PREVENT HEAT-UP BEYOND PERMISSIBLE TEMPERATURES, MOTORING MUST NOT BEALLOWED TO CONTINUE FOR LONGER THAN ONE MINUTE. IF THE CONDENSER LOWVACUUM LIMIT OF 0.3 BAR IS EXCEEDED, MOTORING MUST NOT BE ALLOWED TO CONTINUEFOR MORE THAN 4 SECONDS.

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 12

  • 8/12/2019 BHEL Erection Manual

    13/127

    BEARING TEMPERATURES

    ALARMAT

    MACHINE MUST BESHUT DOWN AT

    OPERATION TEMPERATURE BELOW 75O

    C 90 120OC

    OPERATION TEMPERATURE 75 TO 85 OC 100 120 OC

    OPERATION TEMPERATURE 85 TO 90OC 110 120

    OC

    OPERATION TEMPERATURE ABOVE 90OC 115 120

    OC

    VIBRATION

    ABSOLUTE BEARINGHOUSING VIBRATION

    ABSOLUTE SHAFTVIBRATION

    STANDARD ALARM SETTING 30 m ABOVENORMAL LEVEL*

    m

    MAXIMUM ALARM SETTING 35 120 m

    LIMIT VALUE FOR TRIPPING 45 200 m

    * THE NORMAL LEVEL IS REPRODUCIBLE VIBRATIONAL BEHAVIOUR TYPICAL FOR THE MACHINE ANDDEPENDENT ON THE OPERATING CONDITIONS, VIBRATION READINGS INDICATED IN CONTROLROOM ARE HALF PEAK. THE ABOVE VALUES ARE ALSO GIVEN IN HALF PEAK.

    WEIGHTS

    HP TURBINE, COMPLETELY ASSEMBLED : 94.6 T

    IP TURBINE. TOP HALF OUTER CASING : 25.7 T

    IP TURBINE, TOP HALF INNER CASING, COMPLETE WITH BLADING : 15.5 T

    LP TURBINE. TOP HALF OUTER CASING COMPLETE : 42.6 T

    LP CYLINDER, TOP HALF OUTER SHELL OF INNER CASING, COMPLETEWITH BLADING, STATIONARY BLADE CARRIERS & DIFFUSER

    : 38.5 T

    HP TURBINE ROTOR, COMPLETE WITH BLADING : 16.3 T

    IP TURBINE ROTOR, COMPLETE WITH BLADING : 23.1 T

    LP TURBINE ROTOR, COMPLETE WITH BLADING : 85.8 T

    MAIN STOP & CONTROL VALVE, COMPLETE WITH SERVO MOTORS,WITHOUT BEND & PIPE SECTION

    : 20.9 T

    REHEAT STOP & CONTROL VALVE, COMPLETE WITH SERVOMOTORS, WITHOUT BEND & PIPE SECTION : 32.2 T

    ALL WEIGHTS HAVE BEEN CALCULATED WITH SAFETY ALLOWANCES. SLINGS

    CHOSEN MUST PROVIDE SUFFICIENT SECURITY.

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 13

  • 8/12/2019 BHEL Erection Manual

    14/127

    OIL SUPPLY

    MAIN OIL TANK, RATED CAPACITY : 25/40 Cu . M

    Ist OIL FILLING (ESTIMATED) : 47.5 Cu . M

    FLUSHING OIL QUANTITY (ESTIMATED) : 28.5 Cu . M

    OIL COOLER FOR OPERATION, NUMBER : 1 NO.

    OIL COOLER FOR RESERVE, NUMBER : I NO.

    OIL TEMP. AT COOLER OUTLET, UNIT IN OPERATION

    MIN.NORMALMAX.

    :::

    384547

    OC

    OIL TEMP. AT COOLER OUTLET, UNIT SHUT DOWN

    MAX. : 75OC

    TEMP. RISE OF OIL IN BEARINGSNORMALMAX.

    :

    :

    20

    25

    OC

    ESTIMATED OIL REQUIREMENTS OF BEARINGS :

    BEARING 1(HP TURBINE, FRONT PEDESTAL) : 0.8 dm3/S

    BEARING 2 : 15.4 dm3/S

    BEARING 3 : 4.1 dm3/S

    BEARING 4 : 8.6 dm3/S

    GENERATOR FRONT BEARING : 7.92 dm3/S

    GENERATOR REAR BEARING : 7.92 dm3/S

    EXCITER BEARING : 0.70 dm3/S

    1 DUPLEX OIL FILTER FOR BEARING OIL (FULL FLOW) : 200 mm

    DUPLEX OIL FILTER . TYPE - 2.62.9. SIZE 355/750. MAKE : BOLL & KIRCH

    FILTRATION PARTICLE SIZE OF DUPLEX FILTER ELEMENT : 37 m

    FILTRATION PARTICLE SIZE OF MAIN OIL TANK FILTER

    ELEMENT

    : 250 m

    SAFETY VALVE IN JACKING OIL SYSTEM, SETTINGMAX.

    : 200 BAR

    PRESSURE LIMITING VALVE IN JACKING OIL SYSTEM,SETTING

    : 100 BAR

    1 DUPLEX OIL FILTER FOR JACKING OIL : 25 mm

    FILTRATION PARTICLE SIZE OF JACKING OIL FILTER : 37 m

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 14

  • 8/12/2019 BHEL Erection Manual

    15/127

    OIL PUMPS

    MAIN OILPUMP

    AUXILIARYOIL PUMP

    DCEMERGENCY

    OIL PUMP

    JACKINGOIL PUMP

    QUANTITY 1 2 1 AC : 2 DC : 1

    MAKER BHEL KSB KSB TUSHAKO

    TYPE 97.22 dm3/S ETA-150-

    50VVLETA-100-

    33VVLSDF80

    CAPACITY(RATED)

    75 89.25 30 1.53 dm3/s

    DISCHARGEPRESSURE

    (GAUGE)

    8.6 6.2 2.3 178 BAR

    SPEED 50 24.75 24.3 49.42 /s

    DRIVE TURBINE AC MOTOR DC MOTOR ACMOTOR

    DCMOTOR

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 15

  • 8/12/2019 BHEL Erection Manual

    16/127

    CONTROL FLUID SUPPLY

    CONTROL FLUID TANK, RATED CAPACITY : 10/16 Cu . M

    Ist FLUID FILLING (ESTIMATED) : 15 Cu . M

    FLUSHING FLUID QUANTITY (ESTIMATED) : 10 Cu . M

    CONTROL FLUID COOLER FOR OPERATION, NUMBER : 1 NO.

    CONTROL FLUID COOLER FOR RESERVE, NUMBER : I NO.

    CONTROL FLUID MAINTENANCE EQUIPMENT :

    GEAR PUMP

    MANUFACTURERTYPE

    ::

    STEIMELBGK 2-24R

    FLUID FLOW : 0.28 dm3

    /S

    GAUGE PRESSURE : 3.06 at

    SPEED : 25 S-1

    MOTOR POWER : 0.75 KW

    2 EARTH FILTERS

    MANUFACTURERTYPE

    ::

    ROTRINGPYG5-350

    EARTH FILLING MESH : 140 Kg

    1 FINE MESH FILTERMANUFACTURER

    TYPE

    ::

    ROTRINGS-1800-14-TUY

    FILTRATION PARTICLE SIZE : 3-5 m

    FILTER MATERIAL : COTTON

    CONTROL FLUID SUPPLY SYSTEM

    A FIRE RESISTANT FLUID IS USED FOR THE CONTROL SYSTEM

    SCOPE

    The document covers all steam turbine components and provides the handling,inspection and storage instructions for large steam turbine components at site.A strict adherence to these instructions is necessary to avoid damages duringhandling and storage at site.

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 16

  • 8/12/2019 BHEL Erection Manual

    17/127

  • 8/12/2019 BHEL Erection Manual

    18/127

    While the load is being conveyed, the rigger must accompany it and seethat it is not moved above any person. Prior to lowering the load the riggershould examine the ground on which the load will be, lowered and make surethat these is no risk of falling or slipping of the load.

    If any one of the personnel present during lifting or lowering of the load detects some

    defect of the crane or sling of notices some conditions jeopardizing the lifting orlowering operation, he must give a signal for emergency grounding of thepackage or components.

    Smooth lifting and transportation of equipment must be ensured. Shocks and jerksshould be avoided.

    All lifting devices, slings must be properly conserved after use and periodicallyinspected and tested.

    In the turbines having diaphragms, it is prohibited to handle diaphragms by puttingslings in between the blades. For handling the welded diaphragms, speciallifting devices is supplied by BHEL and the cast diaphragms are handled

    by putting the eye bolts, for which the provision of threads holes have beenmade in the diaphragms.

    While handling the bearings, it is prohibited to put the sling across the rabbit surface ofthe bearings. Threaded holes have been provided; in which the eye bolts haveto be put for handling of the bearings.

    While handling the cylinders, it must be ensured that the slings or any other materialdoes not get rubbed at their horizontal and vertical parting planes or at anyother machined surface.

    The handling of the long components such as longitudinal girder, endwall etc. shouldbe done with extra care. When they are placed on the floor, in addition to theend supports, few extra supports at the intermediate positions must be provided.

    While handling LP rotor with free standing blades, care must be taken to ensure that noforce is exerted on the free standing blades to avoid collapsing of clampingpieces under blade root.

    MARKINGS ON PACKING CASES

    Various symbols are marked on the packing cases as per 0456.001 to facilitatestorage and handling of the crates and protection of equipment inside.

    INSPECTION

    Before storing the equipment it should be opened for visual examination or theinternal packing, protective coating and condition of the equipment. Anydamage to packing and conservation should be immediately rectified.

    It is necessary to carryout first inspection within three weeks of arrival of theconsignment. Thereafter, all the equipment should be inspected once in everythree months to insure that the conservation is intact. During rainy season, theinspection should be done once in a month. At any time, if any original

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 18

  • 8/12/2019 BHEL Erection Manual

    19/127

    conservation is found damaged, it should be reconserved as per relevantconservation instructions No. ST 33004.

    While inspecting the packages containing rotors, special care should be taken to checkthe journals. In case of slightest sign of pitting on the journals and thrustcollar, immediate steps for rectification should be taken and equipment

    reconserved as per relevant conservation instructions.

    STORAGE

    All steam turbine equipment should be accommodated in the designated place ofstorage immediately after arrival at destination. This is very essential particularlyduring the rainy season.

    Store houses fall into the following categories

    TYPE OF CONDITIONSSTOREHOUSE

    TEMP. RELATIVEHUMIDITY

    ARRANGEMENT

    'P' +50 Cto

    500 C

    < 70 % Totally enclosed, rain proof, ventilatedand dry with cemented floor.

    'Q' upto500 C

    - Roofed area with walls (of brick /asbestos/ GI sheet ) around andcemented / pucca hard floor.

    'R' - - Raised platform with shed of asbestos /GI sheet / water proof tarapaulin.

    'S' - - Raised Platform.

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 19

  • 8/12/2019 BHEL Erection Manual

    20/127

    The platforms and store-houses should be built up in conformity with the fireprevention rules and standards. Complete storage area especially the R& Scatagory must be adequately fenced & protected against theft & pilferage.

    These store houses and areas around them should have proper drainage facility forthe sub-soil, surface and rain water. The water should not be allowed to stand

    or get accumulated in these areas, especially where the material has beenstored.

    Store house should be provided with proper ventilation facilities.

    Level should be maintained for all the packages and equipment and should beuniformly supported to avoid distortion. The long packages should besupported at intermediate places also, so as to avoid sagging during storage.

    Store houses should preferably be equipped with proper lifting devices to ensurenormal handling of equipment.

    Small and medium size parts can be kept on shelves with proper identification tags.

    Packages upto 5 tones can be placed on upon the other upto 2.5m in height usingrequired number of wooden spacers 50 mm thick. In doing so, lighterpackages would be laid upon heavier once to avoid any damage to lowerpackages.

    Articles weighing more than 5 tones should be laid in a single tier.

    For heavier components under Q, the roof/walls may be constructed/fabricated afterplacement of the component on cemented/pucca hard floor.

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 20

  • 8/12/2019 BHEL Erection Manual

    21/127

    STORAGE OF STEAM TURBINE COMPONENTS

    SNO. DESCRIPTION OF THE COMPONENT TYPE OFSTORAGE

    1. FOUNDATION BOLT Q

    2. EMBEDDED PARTS (ADDITIONAL) R

    3. COMPONENTS OF BASE PLATE ASSLY. Q

    4. BASE PLATE LP CASING R

    5. LP OUTER CASIONG R

    6. LONGITUDINAL GIRDER (LEFT & RIGHT) R

    7. LP FRONT WALL (TS&GS) R

    8. LP SHAFT SEALING (FRONT & REAR) Q

    9. AUXILIARIES OF TURBINE Q

    10. HP/IP BEARING PEDESTAL Q

    11. HP/IP BEARING PEDESTAL ASSEMBLY PARTS Q

    12. IP/LP PEDESTAL ASSEMBLY Q

    13. LP/GEN. PEDESTAL Q

    14. BEARING PEDESTAL PARTS Q

    15. FRONT BEARING PEDESTAL Q

    16. LIFTING BEAM R

    17. LP CASING EXTRACTION A1 R

    18. LP EXTRACTION A2 R

    19. LP EXTRACTION A3 R

    20. LP EXTRACTION PIPE SHEATHING R

    21. INNER GUIDE PLATE DIFFUSER R

    22. DIFFUSER (UPPER & LOWER HALVES) R

    23. LP INNER-OUTER CASING (VH) Q

    24. LP INNER CASING ASSEMBLY (LH & VH) Q

    25. HEATING DEVICE Q26. LP CASING ASSEMBLY Q

    27. LP INNER CASING ASSEMBLY (FASTENER) Q

    28. INNER GUIDE PLATE DIFFUSER (GS) R

    29. LP ROTOR Q

    30. IP TURBINE Q

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 21

  • 8/12/2019 BHEL Erection Manual

    22/127

    31. IP TURBINE PARTS Q

    32. IP INLET PIPES Q

    33. HP TURBINE Q

    34. HP INLET ASSEMBLY Q

    35. HP EXHAUST ELBOW Q

    36. HPT RELATED PARTS Q

    37. FRAME FOR SUSPENSION (ESV) R

    38. SUSPENSION OF VALVE (ESV) Q

    39. ESV & CV CASING WITH VALVE Q

    40. ESV SERVOMOTORS WITH LIMIT SWITCH Q

    41. HP CONTROL VALVE SERVOMOTORS Q

    42. SUSPENSION OF VALVE (IV) Q

    43. IV & CV CASING WITH VALVE Q

    44. IV SERVOMOTORS WITH LIMIT SWITCH Q

    45. IP CONTROL VALVE SERVOMOTORS Q

    46. FRAME FOR SUSPENSION (IV) R

    47. IV SERVOMOTORS WITH LIMIT SWITCH Q

    48. STEAM BLOWING & HYD. TEST DEVICE Q

    49. TOOLS FOR GOVERNING SYSTEM Q

    50. SUSPENSION OF LPB VALVE Q

    51. WATER INJECTION VALVES Q

    52. CHEST LPB WITH STOP & CONTROL VALVE q

    53. LPB STOP VALVE SERVOMOTOR Q

    54. LPB CONTROL VALVES SERVOMOTORS Q

    55. INJR. FOR SUCTION PIPE NB 350 R

    56. INJR. FOR SUCTION PIPE NB 300 R

    57. MAIN OIL TANK R

    58. MAIN OIL TANK & NOZZLE ASSEMBLY R59. OIL STRAINER Q

    60. LEVEL MONITOR INSTALLATION Q

    61. INSTRUMENTS Q

    62. LEAKAGE / DIRTY FLUID TANK R

    63. VARIABLE ORIFICES & THROTTLE Q

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 22

  • 8/12/2019 BHEL Erection Manual

    23/127

    64. CONTROL FLUID TANK R

    65. CONTROL FLUID TANK NOZZLE ARRANGEMENT R

    66. EXPANSION TANK R

    67. FILTER & PR. DAMPING DEVICES Q

    68. CROSS AROUND PIPE R

    69. SUPPORT FOR CAP R

    70. CHANGE OVER VALVE R

    71. RATING & MONOGRAM PLATES Q

    72. OIL STRIPER R

    73. HOUSING FOR HRH STEAM STRAINER R

    74. HOUSING FOR MAIN STEAM STRAINER R

    75. MS & HRH STR.HSG GASKET Q

    76. STEAM STRAINER MS Q

    77. STEAM STRAINER HRH Q

    78. COMPENSATOR Q

    79. TURBINE CONTROL LPB / SUPPLY RACK Q

    80. TEMPERATURE & PRESSURE CONNECTIONS Q

    81. PR. TRANSMITTERS BAR. PROBES THERMOCOUPLES Q

    82. TRANSMITTERS & JUNCTION BOXES Q

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 23

  • 8/12/2019 BHEL Erection Manual

    24/127

    STORAGE & PRESERVATION OF COMPONENTS OFTURBOGENERATOR, EXCITER AND SYSTEMS

    SNO. DESCRIPTION OF THE COMPONENT TYPE OFSTORAGE

    1. EMBEDDED PARTS R

    2. FOUNDATION PARTS R3. WOUND STATOR WITH GAS COOLERS Q

    4. TURNION FOOT PLATES Q

    5. ROTOR Q

    6. ASSEMBLY OF PIPE CONTROL FOR GAS COOLERS R

    7. END SHIELDS Q

    8. FAN SHIELD, GEN VVIEW HEADER ASSEMBLY R

    9. TERMINAL BUSHING AND HEADER ASSEMBLY Q

    10. BEARING WITH BRUSH GEAR Q

    11. SEAL BODY Q

    12. TEMP. CONNECTION Q13. CASING FOR TURNIONS R

    14. ERECTION MATERIALS Q

    15. ERECTION DEVICES R

    16. SHAFT SEALS Q

    17. SEAL RINGS Q

    18. ADOPTING RING Q

    19. AUXILIARY BEARING Q

    20. CENTRIFUGAL FAN Q

    21. CARBON DIOXIDE VAPOURISER Q

    22. FILTER O.C.P. Q23. EXPANSION TANK R

    24. OIL SEPARATOR R

    25. PRE CHAMBER R

    26. S.O.S.T. R

    27. SEAL OIL UNIT Q

    28. HYDROGEN DISTRIBUTION R

    29. CARBON DIOXIDE DISTRIBUTION R

    30. VALVES FOR AUXILIARY SYSTEMS P

    31. GAS UNITS Q

    32. FLEXIBLE LEADS QSTORAGE & PRESERVATION OF COMPONENTS OF

    HEAT EXCHANGERS

    SNO. DESCRIPTION OF THE COMPONENT TYPE OFSTORAGE

    PRODUCT : CONDENSER

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 24

  • 8/12/2019 BHEL Erection Manual

    25/127

    1. BOTTOM PLATE S

    2. LOWER DOM WALL S

    3. SIDE WALL S

    4. WATER CHAMBER Q

    5. UPPER DOM WALL S

    6. STIFFENING PIPES S

    7. STIFFENING RODS S8. TUBE SUPPORT PLATE R

    9. WATER BOX R

    10. AIR EXTRACTION PIPING R

    11. HOTWELL S

    12. SPRING ELEMENTS R

    13. LOOSE ITEMS Q

    14. INSTRUMENTS Q

    15. CONDENSER TUBES (STAINLESS STEEL) R

    16. CONDENSER TUBES (NON-FERROUS) Q

    17. VACUUM PUMP Q

    18. EJECTOR R19. AIR MEASURING DEVICE Q

    PRODUCT : HEATER

    1. GLAND STEAM CONDENSER R

    2. STAND PIPE Q

    3. INSTRUMENTS Q

    4. DRAIN COOLER R

    5. L.P.HEATERS R

    PRODUCT : COOLER1. OIL COOLER R

    2. CONTROL FLUID COOLER R3. STATOR WATER COOLER R

    4. HYDROGEN COOLER Q

    5. EXCITER AIR COOLER Q

    6. INSTRUMENTS / LOOSE ITEM Q

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 25

  • 8/12/2019 BHEL Erection Manual

    26/127

    MAXIMUM PERMISSIBLE LOADING FOR WIRE ROPES IN KG.

    NOMINAL SINGLE DOUBLE CORD WITH INCLUDED ANGLE OF

    DIA (d) OF

    ROPES mm

    CORD0

    o 45o 90o 120o

    9 522 1044 965 738 522

    12 1170 2340 2070 1580 1170

    18 2150 4300 4000 3060 2150

    24 3850 7700 2100 5400 3850

    30 6200 12400 11500 8800 6200

    36 9000 18000 16600 12700 9000

    42 12200 24400 22600 17300 12200

    48 16000 32000 29500 22600 16000

    54 20200 40400 37300 28500 20200

    60 24900 49800 46000 35200 24900

    66 30100 60200 55700 42600 30100

    72 35800 71600 66200 50700 35800

    78 42100 84200 77700 59500 42100

    84 48800 97600 90200 69000 48800

    90 56000 112000 103500 79200 56000

    96 63700 127400 117700 90000 63700

    102 71900 143800 132900 101700 71900

    108 81000 162000 149700 114500 81000

    114 89900 179800 166100 127100 89900

    120 99700 199400 184300 141100 99700

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 26

  • 8/12/2019 BHEL Erection Manual

    27/127

    ERECTION SEQUENCE

    (For 500 MW Fixed pedestal type Turbine with spring loaded foundation)

    1. Cleaning and checking of Turbine and Generator foundations as per the transverse

    and longitudinal axis including their elevation.

    2. Prepare and install LP base plates, HP front pedestal, HP rear pedestal, LP front

    pedestal, LP rear pedestal along with their anchor bolts and anchor plates.

    3. Provisionally align and level all the pedestal and LP base plates as per the

    transverse and longitudinal axis including their elevation.

    4. Matching of anchor plates of pedestal and LP base plates to ensure their perfect

    seating.

    5. Finally align and level HP front, HP rear, LP front and LP rear pedestals along with

    LP base plates as per the transverse and longitudinal axis including their elevation

    and catenary as per the design.

    6. Prepare and install steel bars for LP casing centralising keys in foundation slab as

    per the required center line .

    7. Weld locating ring of LP front pedestal and steel bars of LP front and LP rear

    centralising keys.

    8. Prepare shuttering and grouting of the pedestals and LP base plates including

    anchor plates of HP rear pedestal.

    9. Prepare, install, align/ level both the LP girder along with their carrier plates.

    10. Prepare , install and assemble LP front and rear end walls with the LP girders.

    11. Level / align LP outer casing lower half as per the transverse and longitudinal axis

    of the machine.

    12. Install permanent packers of LP outer casing including their radial and axial keys.

    13. Prepare and install LP inner outer casing along with gusset plates in position

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 27

  • 8/12/2019 BHEL Erection Manual

    28/127

    14. Align LP inner outer casing lower half and level it. Install LP casing parting plane

    platform .

    15. Prepare and install LP front and LP rear lower half shaft seals housing and align it

    provisionally.

    16. Prepare and install LP rotor along with their bellows in position.

    17. Align LP rotor radially and axially in position and record free run out of rotor.

    18. Record/ Ensure radial and axial clearances of the LP casing including rotor float

    including fitting of final axial keys of the LP inner casing .

    19. Box up LP inner inner casing and heat tighten the parting plane bolts.

    20. Box up LP inner outer casing .

    21. Prepare and place HP module in position on temporary packers.

    22. Transfer the load of HP rotor on bearings from the transport device and align it

    radially and axially.

    23. Check free run out of HP rotor on journal and coupling face including its float.

    24. Prepare and place IP module in position on temporary packers. (In case IP module

    is sent to site in disassembled condition, refer Instruction T1-08-0606G.

    25. Loading of IP rear end of the shaft on bearing and removal of transport device.

    26. Provisionally align HP , IP and LP rotor .

    27. Couple HP / IP rotor on temporary Bolts and align rotor / casing radially and axially.

    28. Record/ Ensure IP rotor float by shifting HP casing axially.

    29. Conduct Horn drop test of HP casing without any radial and axial keys and pipe

    lines.

    30. Conduct Horn drop test of IP casing without IP inlet upper half pipe lines.

    31. Assembly of breech nut of HP casing and Main Steam Stop & Control valve

    assembly.

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 28

  • 8/12/2019 BHEL Erection Manual

    29/127

    32. Erection of Reheat Stop & Control valve assembly.

    33. Weld IP inlet upper half pipe and record Horn drop values without radial-axial keys.

    34. Alignment of HP/IP/LP rotors and their coupling on temporary bolts including its

    couple runout.

    35. Swing check of HP rotor on its front end with temporary alternate bolt tightened on

    HP/IP coupling .

    36. MOP alignment and its doweling.

    37. Reaming/honing of HP/IP and LP/IP coupling including fitting of final coupling bolts.

    38. Fixing of axial position of shaft and assembly of thrust bearing including its colour

    matching.

    39. Roll check of HP/IP casing and fixing of radial and axial keys of the casing (Casing

    final packers need not to be put at this stage).

    40. Assembly of bearings and checking of all clearances including fittings of side pads

    of bearing, yoke keys etc.

    41. Turbovisory works in all the pedestal i.e. assembly and calibration of thrust bearing

    axial shift, LP rotor expansions pick up, Hall generator and thermocouples of

    bearing .

    42. Preparations of the bearing for oil flushing.

    43. Oil flushing of the machine and normalizing the bearing after oil flushing.

    44. Preparation and floating of TG deck as per Instruction No. T1-08-0909G.

    45. Decoupling of HP / IP, LP/IP, LP/Gen., Gen./Exciter coupling and rechecking of

    alignment/catenary after floating of TG deck spring.

    46. Final tightening of HP/IP, IP/LP , LP/Generator and Generator / Exciter coupling

    after correcting the alignment including their couple run out and swing check of rotor

    on HP Front and exciter rotor.

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 29

  • 8/12/2019 BHEL Erection Manual

    30/127

  • 8/12/2019 BHEL Erection Manual

    31/127

    CHECKING OF FOUNDATION BEFORE CASTING

    Customer to provide, center line and elevation point.

    Check positioning of all the inserts and fixed points with respect to center line

    in transverse and longitudinal direction as per BHEL Hardwar drawings.

    Check elevation of all points.

    Check verticality of all the pipe sleeves with the help of plumb.

    Ensure proper locking of all the insert and fixed points before grouting.

    Ensure leveling on the fixed points of LP girder and LP rear pedestal.

    Preserve machined surfaces of all the fixed points against any damages due toImproper handling.

    Ensure proper flatness of the bottom seating plate of all the inserts.

    Ensure proper stiffeners in all the vertical and horizontal embedment providedfor various purposes like hangers and supports etc.

    Ensure proper cleaning of the area before casting.

    Remove all unwanted material.

    NOTE: In case of spring loaded TG deck refer Installation InstructionNo. T1-08-0909G prior to positioning of inserts etc.

    CHECKS DURING CASTING/POURING OF CONCRETE

    Casting of foundation\TG deck should be carried out immediately afterinspection of the foundation\TG deck i.e. within 3-4 days after finalinspection to avoid any disturbance to the inserts and fixed point.

    Ensure no disturbance to the insert etc. during pouring of concrete while

    vibrators are used.

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 31

  • 8/12/2019 BHEL Erection Manual

    32/127

    About 15-20 mm extra concrete may be left on top on all the pedestals and LP

    base plate area for chipping/cleaning purpose at a later date.

    Close all the pipe sleeve from top to avoid entry of concrete inside. Alternatelythe pipe sleeve should be filled with sand.

    CHECKING OF FOUNDATION AFTER CASTINGClean complete foundation and remove all shuttering etc.

    Ensure there is no loose concrete layer in the region where the pedestal andbase plates are to be laid. No repair should be done in this region withoutconsulting the turbine erection engineer.

    Cover all the opening before checking any dimensional measurement to

    avoid any accident.

    Establish a suitable longitudinal axis considering the fixed point of the LP rearpedestal and various pipe sleeves / inserts.

    Establish a transverse axis as 90 degree with the help of the odolite.

    Measure pitching/elevation of all the inserts and fixed points.

    Measure elevation of all foundation on different pedestal and LP base plate area.

    Check level of LP rear pedestal fixed points and if required correction may

    be carried out.

    PREPARATION OF FOUNDATION FOR PLACEMENT OFPEDESTALS AND BASE PLATES:

    Foundation are to be cleaned and loose concrete are to be chipped off.

    Maintain elevation of foundation to ensure correct thickness of non-shrink

    grout.

    A reference point for elevation in respect of machine center line (equivalent to LPrear pedestal) is to be maintained at a proper place. This point is to bepreserved with proper protection. For making reference point a one side

    ground plate of about 200 x300 x20 mm may be used. This may bewelded on a I-beam near Generator. The ground position of the plate isto be kept on top side and all elevation are to be transferred from thispoint with the help of water level jar. A correct elevation reading is to

    be punched on this plate. This reference point is to be used only during theturbine erection period.

    Clean and deburr piping sleeves of the foundation on ID/OD of the pipe.

    Ensure all corners of the foundation remains perfect during chipping of extraconcrete of foundation.

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 32

  • 8/12/2019 BHEL Erection Manual

    33/127

    PLACEMENT OF PEDESTALS

    Open and clean the pedestal.

    Ensure there is no paint/oil on bottom face of the pedestal sole plate.

    Ensure there is no paint on inside surface or the pedestal and if required sand

    blasting may be carried out at site.

    Ensure correct fitting/clearance of locating rings of LP rear pedestal.

    The half bore error of pedestals is punched by manufacturing unit however in

    case it is not there, measure and punch half bore error of pedestal inleft/right side of the pedestal. If the error is nil then this may bepunched as zero-zero.

    Ensure that the pedestal parting plane is feeler tight after tightening all the

    parting plane bolts. If required, colour matching may be carried out butscraping/cutting is to be done on upper half cover only.

    Check proper colour contact of spherical/cylindrical supports of the bearingwith the pedestal.

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 33

  • 8/12/2019 BHEL Erection Manual

    34/127

    Check contact between spherical Torus piece of bearing and

    spherical/cylindrical seat. In case of any variation in contact noscraping/cutting to be carried out at site and this may be referred tomanufacturing unit. Also refer T1-08-0808G. Check centering of individualbearing w.r.t. pedestal seal bores by fixing pianowire on individual

    pedestal.

    Ensure cleanliness of all pedestal oil lines. Close opening of oil lines ofpedestal to avoid any foreign material entering in these pipe lines during

    erection at site.

    Weld MOP suction and discharge pipe lines in HP front pedestal as per thedrawing before placement.

    Assemble protection sheet in the foundation bolt holes of pedestals.

    Assemble anchor bolts along with anchor plate of the pedestals. Ensure thatthere is good contact available to the backing plate with the

    foundation. If required colour matching/grinding may be carried out toachieve the contact.

    Assemble protection sheet in the anchor bolt hole from bottom side of HP rearpedestal foundation to avoid entry of grout metal.

    Ensure level of both anchor plate of H.P. rear pedestal with 70-90 mm gap for

    filling of grouting concrete.

    Adjust height of the Anchor Bolts as specified in the drawing.

    PLACEMENT OF LP BASE PLATE, OVER THE FOUNDATION :

    Clean all the four base plates.

    Mark/punch center line on the base plate as per drawing.

    Ensure proper cleaning of base plate on bottom side.

    Put identification marks on each base plate to avoid any mistake in positioning ofthe same.

    Do colour matching of all the eight nos. carrier plate on both the faces.

    Match LP base plate with the individual carrier plate.

    Place all the four base plates in position along with their leveling screws andfoundation bolts.

    Provisionally align and level all the four base plates.

    Assemble protection sheet in the foundation bolt holes.

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 34

  • 8/12/2019 BHEL Erection Manual

    35/127

    ALIGNMENT OF PEDESTALS AND LP BASE PLATES

    Provisionally align and level all the four pedestals including LP base plates withreference to the earlier marked longitudinal and transverse axis. Theelevation reference is to be taken from the already positioned plate for

    this purpose.

    Align and level LP rear pedestal and set the elevation as per machine center line.

    Use piano wire arrangement with micrometer for centering of pedestal bore anduse water level jar for setting of elevation. Use measuring tape to

    maintain pitching of the bearing from one pedestal to another. Pedestalsare to be set in level condition on both longitudinal and transversedirection. Align and level HP front, HP rear and LP front pedestals.

    Elevation of the pedestals are to be set as per catenary of the machineconsidering the half bore error of the pedestal if any.

    Align and level, LP base plates. Elevation of LP base plate is to be kept higherthan the rear pair of LP base plate in line with catenary of rotor.

    After alignment of LP rear pedestal weld the locating rings as mentioned in thedrawing.

    During welding of locating ring, ensure that there is no movement in thepedestal in any of the direction.

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 35

  • 8/12/2019 BHEL Erection Manual

    36/127

    GROUTING OF PEDESTALS AND LP BASE PLATES

    Fill 3 to 8 mm washed Pea-gravel in all the anchor bolts sleeves. These gravelare necessary to give damping effect to the anchor bolts during operationof the machine.

    Seal anchor bolts holes after filling of gravel to avoid any entry of grout metal.Medical tape may be used for sealing of these anchor bolt holes.

    Clean foundation with compressed air.

    Make shuttering of all the pedestal and LP base plates. Use thick polythene

    sheet inside the shuttering to give better finish and avoid moistureabsorption by shuttering.

    Shuttering should be made with maximum care to avoid any leakage of grout

    concrete. All sides of the shuttering are to be sealed either with somesealing compound or with thick mixture of grout material to avoid leakageof grout material.

    Foundation are to be kept wet for about 6 hrs. before grouting.

    Non shrinkage cement duly approved by BHEL is to be used for grouting of thepedestals and base plate.

    Use fresh stock of the grouting material only and check the strength of the

    material before use.

    During grouting, the mixture has to be poured from one end only and it has toflow to opposite end to avoid any blockage of air pocket.

    Water curing is to be carried out for about 10 days duration.

    All anchor bolts are to be stretched minimum after 21 days of grouting.

    HP, IP & LP module placement work can be taken up after 24 hours of groutingof the pedestal and base plates.

    For individual pedestal and base plate, grout mixture should be poured in one lotonly.

    PLACEMENT OF HP MODULE IN POSITION

    Ensure matching of all the four palms of the module where it is resting on thepedestals.

    Ensure matching and parallelity of front and rear key block of the HP casing.

    Assemble all four jacking screw of HPC and ensure their free movement.

    Clean journals and coupling of the HP rotor.

    Record journal dia, coupling hole sizes and spigot dia of HP rotor.

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 36

  • 8/12/2019 BHEL Erection Manual

    37/127

    Lift module in level condition and place it in position by keeping it 3 to 5 mmtoward front pedestal side.

    During placement of module use temporary packers similar to permanent and

    additionally support it by four jacking screws.

    Ensure load on all four packers with the help of some additional shims ifrequired.

    Install temporary radial and axial keys of the casing.

    Prepare HP rotor for alignment (Ref. section 20 before placing the IP module.

    PLACEMENT OF IP MODULE IN POSITION

    Ensure matching of all the four palms of the module where it is resting on thepedestals.

    Ensure matching and parallelity of front and rear key block of IP casing.

    Assemble all four jacking screws of IP casing and ensure their freemovement. If these jacking screw holes are provided with the boltsfrom factory then same are to be removed before placement of module.

    Clean IP rotor on both sides including coupling and journal.

    Record spigot /recess, journal dia, and coupling hole sizes.

    Lift the module in level condition and place the module in position by movingabout 7 to 8 mm towards generator end. Use temporary packers for

    placement of module in position and additionally support the module withjacking screws.

    Ensure load on all four packers with the help of some additional shims ifrequired.

    Provisionally align the casing on front and rear pedestal bore. Install temporaryradial and axial keys of the casing with some shims.

    Prepare IP rotor for alignment (Ref. section 20).

    NOTE: In case IP module is sent to site in disassembled condition, referInstruction T1-08-0606G.

    ASSEMBLY OF LP MODULE

    This assembly can be divided in following sub assemblies:

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 37

  • 8/12/2019 BHEL Erection Manual

    38/127

    Assembly of girder and end walls.

    Assembly of LP inner inner and LP inner outer casing lower half.

    Assembly / welding of LP outer casing.

    Before starting assembly of LP casing in position, following works arealso to be completed :

    - Positioning and welding of LP casing centering pin of front and rearside.

    - Positioning of key block of LP casing axial keys.

    - Positioning of all internal of condenser.

    POSITIONING AND WELDING OF LP CASING CENTERING

    PIN

    Two nos. centering pins are to be located below LP front and LP rear pedestal.Necessary pipe along with two sq. end plates are already provided in thefoundation to take the radial load of the LP casing:

    Plumb the center line from LP front and LP rear pedestal bore on both side

    over the square plate of the foundation.

    Establish accurate position of the pin and put a punch mark at a required heightand mark a circle and a controlling circle over all the four sq. Plates.

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 38

  • 8/12/2019 BHEL Erection Manual

    39/127

    Dia of the circle must be equal to pin dia. A template equivalent to pin dia hasto be made for this purpose with about 20 mm thick plate and a weldedpipe for using as an handle. The template dia must be very accurate and

    same may be made on machine.

    Make precise hole with gas cutting/grinding to match template on all four

    embedded plate. Ensure that the template is fitted with minimumclearance and hole center are perfect as per marking.

    Drill hole of about 10 mm dia on one of square plate of LP front and on oneplate of LP rear for air venting to avoid cracks during welding.

    Insert both the pins and carry out the welding as per laid down procedure.

    Before welding set correct axial position of the pins.

    Insert key block on both the pins and weld their locking ring also. Ensureproper clearances in key block before welding of its locking ring.

    Preheating of 200 degree Celsius or more to be achieved before any welding.

    Dye penetrate test on root run and after final welding is to be carried out.

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 39

  • 8/12/2019 BHEL Erection Manual

    40/127

    ASSEMBLY OF GIRDER AND END WALL

    Colour match side matching flange of girder with the surface plate.

    Colour match seating flange of girder where it rests over the LP base plate.

    Match and ensure parallality of axial key ways of girder.

    Colour match side flanges of end wall.

    Match and ensure parallality of key block of end wall.

    Place left and right girder with carrier plate, spacer and lubrite packer on LP

    base plate.

    Provisionally align and level the girders. Set height of the girder equivalent tomachine center line maintaining catenary of the machine with the help ofwater level jar arrangement.

    Assemble locking plate of the front and rear end wall to facilitate its assembly

    with the girders.

    Assemble front and rear end wall with the girders and ensure perfect parting

    plane level during tightening.

    Align, level LP outer casing and ensure contact of packers by colourmatching/machining of spacer height.

    Install LP casing radial and axial keys.

    Assemble inner outer casing axial key blocks on left and right side of girderand dowel them.

    Lock with tack welding all the vertical joint bolts.

    Put a seal weld run between girder and end wall joint all around except on topface.

    Weld girder and end wall parting plane joint with argon welding. Beforewelding make a V groove with the help of a chisel and allow the projection

    of material on surface. Do not make the groove by grinding.

    Do colour matching with a surface plate on all four corner where argon weldinghave been carried out.

    ASSEMBLY OF LP INNER INNER AND LP INNER OUTERCASING LOWER HALF

    The LP inner inner casing lower half is received from factory in assembledcondition with LP inner outer casing lower half.

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 40

  • 8/12/2019 BHEL Erection Manual

    41/127

    Clean the casing and check all the threaded holes.

    Do colour matching on all four corners of the casing where it rest over thegirder.

    Colour match all eight carrier plates of inner casing on both side.

    Assemble all carrier plates on girder and do the colour matching withindividual carrier plate.

    Prepare Gusset plate of front and rear side with temporary radial keys for fittingin LP inner casing.

    Level and lift LP inner outer casing and assemble/weld both the gusset plateswith the help of some temporary support.

    Lower the casing in position over the carrier plates fitted with spacer and lubritepacker.

    Provisionally align the casing radially and axially.

    Support the gusset plate with the help of screw jack (about 10-15 tons) on frontand rear side by taking support from condenser stiffeners. Screw jack is tobe unscrewed after box-up.

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 41

  • 8/12/2019 BHEL Erection Manual

    42/127

    Adjust the height of the LP inner outer casing as per center line of the machine

    and then level it with the help of water level jar arrangement.

    Ensure that all the eight packers have good contact. Loading of each packer isto be ensured.

    Lower the casing by about 2 mm on all the eight packers with the help of shimsfor placement of LP rotor to avoid any fauling during placement of rotor.

    Fit and weld all gusset plate stiffener pipes except pipe between LP inner outercasing and condenser. Do not make any weld connection between

    condenser and any of these stiffeners till neck welding of the condenseris over.

    PLACEMENT OF LP ROTOR

    Measure journal dia, spigot dia and coupling hole sizes.

    Ensure centering of temporary bearing support in the LP front pedestal for

    placement of LP rotor.

    Place LP rear bearing in position.

    Prepare shaft seal compensator along with gaskets (Gasket to be installed in

    fully ring shape only ) and position them on LP rotor with the help ofsupplied supports of compensator.

    Lift LP rotor with the supplied lifting beam in perfectly level condition and placeit in position. During lowering of rotor ensure radial clearance with the

    help of long feeler gauges in the LP casing.

    WELDING OF LP OUTER CASING

    The welding of LP outer cover is to be carried out before placement of LPRotor in position to avoid damage to the rotor.

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 42

  • 8/12/2019 BHEL Erection Manual

    43/127

    Colour match and remove all high spots of the matching flange of the LPouter casing.

    Ensure good contact between parted diffuser of LP front and LP rear cover.

    Colour match and remove all the high spots of the parted diffuser/vertical face

    to ensure good contact with the compensator at a later stage.Colour match and remove all burrs and high spots from parting plane of LP outer

    casing.

    Side flange of LP front and rear cover are to be ensured in right angle toachieve good contact with their matching flanges.

    Place LP front LP rear cover along with parted diffuser and ensure feeler tight

    joint after tightening the parting plane bolts. The joint must be feelertight just after normal tightening of bolts. Do not over tighten partingplane bolts.

    Ensure matching of parted diffuser face on both side of LP casing. If necessarycolour matching may be carried out to achieve a feeler tight joint.

    Drill/ream all the parting plane holes as per drawings and install all dowel pins.

    After fixing of LP front and rear cover measure the dimension for

    positioning of both the center flanges. The dimension are to be recordedin such a way that there is no clearance after fitting of center flanges inposition on both side with the LP front and rear cover. The centerflanges are supplied in extra length on both sides from the factory and

    final length are to be maintained at site only.

    Drill/ream dowel pin holes in center flanges and install all dowel pins in position.Ensure drilling and reaming of all dowel pin holes to equal depth.

    Fit both the center pieces of the cover in position.

    Achieve the fitting clearances for welding as per laid down procedure.

    Weld/lock LP upper half flange with respect to lower half casing with the helpof metal cleats to minimise the distortion during welding of LP cover.

    The cleats may be welded at an interval of about one meter distance.

    Carry out the welding as per the following welding procedure.

    WELDING PROCEDURETack weld the crowned seam joint. permanently welding approx. 100 mm at the

    generator end of the joint.

    Opposite tack welded radial joint 2, permanently weld approx. 100 mm of the

    crowned seam joint, pos. 1, staggering the two weld ends to ensure aperfect transition when the crowned seam joint is finish welded.

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 43

  • 8/12/2019 BHEL Erection Manual

    44/127

    Tack weld the crowned seam joint at regular intervals with a tack of 5T and pitchof 25T.

    When welding radial joint 2, shell plates 1 & 2, tacked together, rest on but are

    not tacked to the retaining strip in the region of joint 1, so that anyshrinkage occurring during welding of seam 2 is not obstructed.

    The tacking & welding sequence applies for all shells courses.

    Weld radial seam at TE according to welding sequence plan.

    Align, adjust and tack weld radial seam at GE.

    Weld radial seam at GE according to welding sequence plan.

    Weld crowned seam joint.

    Align shell courses on joint strips and tack weld,

    Weld on joint strips from center & ends of shell plate.

    Insert pins in top half casing, release top half casing and lift to insert and tack

    filler piece between joint strips.

    Unbolt top half casing and lift in order to weld and finish - machine filler pieces inthe region of the joint surface.

    Check welds according to specifications.

    ALIGNMENT AND COUPLING OF LP-IP & HP ROTORLP rotor is to be aligned on pedestal seal bore and LP inner outer casing is to be

    centralised in such a way that enough clearances are available to LP rotor,during alignment. Now this alignment activity of all the three rotor can bedivided as below :

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 44

  • 8/12/2019 BHEL Erection Manual

    45/127

    Preparation of HP rotor for alignment.

    Preparation of IP rotor for alignment.

    Preparation of LP rotor for alignment.

    Alignment of LP-IP & HP rotors.

    Reaming, honing of the coupling holes.

    Balancing of coupling bolts weight.

    PREPARATION OF HP ROTOR FOR ALIGNMENT

    Align HP rotor with reference to front and rear pedestal seal bore reading. If

    required move complete HP module along with the rotor.

    Fix temporary radial and axial key of the casing on both front and rear side ofthe casing. Remove HP front upper half transportation device.

    Lift module by 0.20 mm on front side by putting additional shims in frontpackers.

    Insert HP front bearing in position.

    Reduce 0.20 mm shims gradually and ensure about 0.10 mm load on the rotor. If

    required further lower the front side of the module to achieve the loadingon bearing by about 0.10 mm.

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 45

  • 8/12/2019 BHEL Erection Manual

    46/127

    Remove HP front lower half transport device gradually and ensure no

    movement between HP casing and rotor. If necessary adjust shims ofHP casing front packers.

    During loading of bearing always ensure that the rotor is not fouling inside thecasing with the shaft seals. This may be ensured by checking with feeler

    gauge also.

    Check axial position of HP rotor in front side on left; right and top positionfrom the rotor reference point to the HPC as given in the shop protocol.

    Insert and load the bearing in HP rear end in similar way as carried out incase of HP front end and record axial position of rotor as per shopprotocol.

    Lock axially HP rotor with some fixture along with the arrangement of

    jacking screw for movement of rotor. This fixture may be mounted on rearpedestal. Before locking of rotor ensure axial position of the shaft.

    Center HP shaft with reference to HP casing front and rear spigot. If necessary,move the casing readily to achieve the centering. A fixture can be

    fabricated at site for mounting the dial gauge on both the end of the rotorto check the centering of the shaft.

    Use thick oil during rotation of shaft on the bearing.

    Protect bearing from any of the dust particles. It is recommended to placeupper half of bearing in position to avoid dust and any other damage tothe shaft journal.

    Realign the rotor shaft with respect to pedestal seal bore and if necessary

    adjust the shims below spherical support of the bearing.

    Care should be taken during alignment that radial and axial clearancesbetween rotor and casings does not get bridged.

    Check HP rotor radial run out on journal and coupling.

    Check axial run out on thrust collar and both the coupling faces of HP rotor.

    Check axial float of the rotor. Compare values with shop protocol values. (Ref. T1-08-0802G). Deviations to be reported to Manufacturing Unit.

    PREPARATION OF IP ROTOR FOR ALIGNMENT

    The IP module is also to be prepared in line with the HP module. Howeveras IP rotor is provided with one side bearing and opposite side is coupledwith the HP rotor without a bearing, extra care is necessary duringalignment of rotor in IP casing. The additional point which are to be taken careare explained below :

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 46

  • 8/12/2019 BHEL Erection Manual

    47/127

    Place IP rotor rear end on bearing similar to the HP rotor and removetransportation device.

    Provisionally align HP/IP rotors and couple on temporary bolts by moving both

    the modules. During coupling of the rotors, the transportation device of IPfront end is also to be taken out.

    Check axial position of rotor w.r.t. IP casing and adjust as per shop protocol.

    Check centering of IP rotor front and rear end w.r.t. IP casing (similar to the HProtor centering check).

    Check float of the IP rotor. Compare values with the shop protocol values. (Ref.T1-08-0802G). During checking of float ensure HP casing is not fouling

    with HP rotor. If required HP casing may be moved axially for this purpose.

    Check facial runout on IP rear coupling face and radial runout on journals andcouplings.

    PREPARATION OF LP ROTOR FOR ALIGNMENTProvisionally align LP rotor in pedestal seal bore placing the front end of shaft

    on auxiliary bearing and rear end on bearing.

    Align LP inner outer casing radially with the help of long feeler gauges andinstall temporary radial keys in the gusset plate.

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 47

  • 8/12/2019 BHEL Erection Manual

    48/127

    Record all the radial and axial clearances of the LP casing without coupling

    the LP-IP rotor. Variation if any in radial or axial clearances are to becorrected/approved at this stage.

    Remove shims from the front end of auxiliary bearing and keep rotor on liftingtackle.

    Record radial run out of LP rotor coupling and journal and axial run out of thecoupling faces of the both end.

    Record float of the LP rotor by moving the LP inner outer casing lower half.

    After ensuring the radial and axial run out of the LP rotor the LP inner outercasing can be boxed up. Parting plane bolts of LP inner-inner casing are tobe heat tightened.

    ALIGNMENT OF HP, IP AND LP ROTORS

    Ensure radial and axial runout of all the three rotors are individually in order. Ifnecessary individual rotor module can be taken out for correction of

    coupling face runout. Any variation on radial runout of rotor is to bereferred to the factory.

    Match coupling faces of two rotor as per the axial face reading of the rotor.Ensure that the higher point of the rotor coupling face and lower point of

    another rotor coupling face are matched together. This is to be comparedwith shop protocol also.

    Preliminary align radially and axially all the three rotors and shift them in spigot

    along with the casing to avoid fouling of rotor inside the casing.

    During alignment achieve left and right movement of the rotor with the help ofshims in spherical / torus piece of the bearing. The up and downmovement of the rotor is to be achieved with the help of shims in the

    cylindrical/spherical support of the bearing . The adjustment of shims inthe bearing should be within the permissible limits only.

    Ensure during alignment that the catenary of the shaft is maintained.

    Check/record spigot clearance of HP-IP and LP-IP rotors by actually moving themin spigot.

    Install four nos. supplied bolts along with one/two pins in HP-IP and LP-IP

    coupling. Hand tighten the coupling bolts by keeping a gap of > 1.00 mmin coupling faces for alignment.

    Rotate the rotor system and record the coupling gap at 90 Deg. interval onleft, right and top position. Ensure that the coupling, bolts and pinsremain free while recording the gap of the coupling for the alignment

    purposes.

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 48

  • 8/12/2019 BHEL Erection Manual

    49/127

    Check swing check value of the HP rotor with alternate bolts in position. Theabove value must be within the prescribed limit only otherwise acorrection must be carried out at site in consultation with designer.

    Ensure free movement of rotor on their bearing. Do not rotate the rotor if itis tight during its rotation.

    Ensue that the coupling holes are properly aligned to avoid unnecessary

    enlargement of holes.

    Ensure HP-IP-LP rotor radial run out after tightening with alternate clearancebolts. Release the couplings for reaming / honing of couplings.

    In case of spring loaded TG decks, refer alignment procedure T1-08-

    0909G

    REAMING / HONING OF COUPLING

    Ensure that there is no disturbance on coupling during reaming/honing

    operation.

    First ream/hone two opposite holes of the coupling and install two pins/boltswith sliding fit and then take up all other holes.

    Enlarge coupling holes to the minimum possible diameter and try to make all theholes to same dia.

    Ensure that the finished holes are straight and there is no banana shape. This

    can be ensured by checking hole with a straight ground finish pin having0.02/0.03 mm clearance.

    The length of the pin should be equal to the bolt length. In case, few holes havegone considerably over size during reaming/honing at site/works, do notenlarge all the holes. As a special case in such cases these few holesmay be left as oversize.

    Ensure that the holes during reaming/honing are perfectly finished as groundbore and size obtained should be within 0.005 mm. Ensure all the coupling

    bolts are fitted within 0.02/0.03 mm clearance with sliding fit and bolts areto be ground within an accuracy of 0.005 mm.

    Coupling bolts are not to be hammered in the holes and these are to be fitted with

    thumb pressure only.

    Do not decouple the coupling in any case without ensuring the fitting of all thecoupling bolts.

    BALANCING OF COUPLING BOLTS

    After fitting the coupling bolts in all the holes these are to be balanced within 5gms accuracy and an accurate balance which can take a load of about 20 kg.

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 49

  • 8/12/2019 BHEL Erection Manual

    50/127

    may be used. During balancing of coupling bolts following points are to be takencare.

    Final balancing of the coupling bolts are to be done along with the couplingnut of individual bolt.

    If all the coupling bolt hole sizes are same before/after reaming and honing

    then all the bolts can be kept of equal weight.

    If necessary adjust the weight of the bolts by machining the metal from the bolthead.

    When the holes of the coupling are of different sizes then it must be seen that

    whether excess enlargement have been done at site or works. In suchcases if excess cutting have been done at site in a particular hole thencoupling bolt with excess weight are to be used. The amount of excessweight must be equivalent to the excess enlargement of hole at site. If a

    particular hole of excess dia. is noticed from factory then it is assured thatthe particular rotor is balanced with excess dia hole and there is no

    need of providing excess weight bolt at site.

    COLOUR MATCHING OF THRUST BEARING

    After completion of reaming/honing and preliminary tightening of the couplingbolts, the colour matching of the thrust bearing pad have to be carried out withrespect to the thrust collar of the HP Rotor. During colour matching a goodcontact on all the pads of front and rear side are to be ensured with respect torotor collar by moving the rotor in +/- direction during its hand rotation. Followingpoints are to be taken care during colour matching.

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 50

  • 8/12/2019 BHEL Erection Manual

    51/127

    Thrust bearing must be axially locked with the help of axial keys during thecolour matching of the pads. Axial keys to be fitted while finalising thealignment of thrust bearing with rotor collar without pads.

    Few drops of oil is to be put on journal portion of the thrust bearing duringrotation of rotor to ensure that the oil is not entering in pad portion of the

    bearing.

    Colour is to be applied on the thrust collar of the rotor.

    If necessary move the spherical support of the bearing pedestal to ensure theequal thickness of the pads before fittment of axial keys of the bearing.

    During moving of the spherical support in front or rear direction ensure that

    there is no left - right movement to the support otherwise that maycause misalignment of the bearing.

    After colour matching of the thrust pad the axial zero position of the rotor isachieved and this can be taken for all other future reference for setting of

    axial position of HP, IP & LP casing.

    HP, IP and LP lower casing are to be set axially after fixing the axial positionof the rotor and their final axial keys can be installed at this stage.

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 51

  • 8/12/2019 BHEL Erection Manual

    52/127

    ALIGNMENT OF HP, IP & LP CASING

    After completion of colour matching of the thrust bearing pads the casingalignment work can be taken up. The following points are to be taken carewhile aligning HP, IP and LP casing.

    The roll check have to be carried out in HP, IP and LP casing to ensure thecorrect radial clearances of the casing.

    TG deck springs are to be kept in floating condition while recording the rollcheck of LP casing. However the roll check of HP/IP casing may be carried

    out before floating of TG deck for fitting of their radial keys but up anddown roll check of HP/IP casings are to be done with TG deck in floatingcondition as per the procedure TS/ST/ 01/0008/00/96.

    Ensure that there is no obstruction in the movement of LP inner casing due to

    welding of any of extraction piping. The one of the joint of extractionpiping may be left free till completion of roll check of the casing.

    The welding of steam inlet pipes between LP inner casing and LP girders are tobe taken up after completion of roll check of the casing.

    HP, IP and LP casing are to be fitted with final packers and axial key immediatelyafter the roll check. During fitting of casing axial keys and palm packersensure proper contact on lubrite coating of the keys/packers to avoid any

    damage of these coating during operation of the machine,

    After completion of fitting of final keys and packers only the casing are to becleared for further works of welding of various pipe lines.

    The gland steam, balancing leak of lines, steam inlet and exhaust pipes are to

    be welded with HP casing after fitting of final axial keys and packers of thecasing.

    Center HP rotor w.r.t. casing front and rear spigots. Compare the readings withshop protocol and record the readings.

    Offset center line of the HP, IP & LP casing w.r.t. respective rotor center line asper recommended logsheet.

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 52

  • 8/12/2019 BHEL Erection Manual

    53/127

    Check/record LP diffusers centering readings after roll check of the casing.

    Before roll check of LP casing all the stiffener pipe welding work must becompleted. Refer T1-08-0909G.

    FINAL TIGHTENING OF COUPLINGSIn case of spring loaded foundation after completing all other works the HP / IP ,IP/LP , LP/GEN , GEN/EXCITER couplings are to be reopened and realignedafter completing the reaming /honing . The rotors alignment are to be checkedwith TG deck in floating condition as per the laid down procedure. Afterchecking of alignment /catenary the final couplings are to be tightened includingtheir coupled run out and swing check of rotors on HP front and Exciter end ofthe shaft.

    BOXING UP OF LP INNER INNER AND LP INNER OUTERCASING

    The boxing up of LP inner inner and LP inner outer casing can be taken upbefore starting the alignment of HP-IP & LP rotor for coupling work. Thefollowing points are to be taken care before/during boxing up of these twocasings.

    Ensure matching of all the parting plane holes, fitting of cap nuts and

    accessibility of spanner .

    Ensure feeler tightness of the parting plane joint of both the casing.

    Check/record all the radial and axial clearances of the casing.

    Ensure proper cleanliness of the LP inner inner and LP inner outer casing.

    Ensure adequate clearance between LP inner inner casing and LP inner outercasing to avoid any obstruction during expansion of the LP inner casinginside the LP inner outer casing during operation of machines.

    BOXING UP OF LP OUTER CASING

    During the boxing up of the LP outer casing following points are to be taken care.

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 53

  • 8/12/2019 BHEL Erection Manual

    54/127

    Roll check of LP inner casing including the fitting of key, packers etc. must befinished.

    All the works must be finished inside the LP casing before boxing up of LP

    casing including LP extraction pipe line works.

    Ensure matching of all parting plane holes and feeler tightness of the jointbefore boxing up of the casing.

    Ensure feeler tightness of bursting diaphragm flange joint before boxing up ofthe casing.

    Ensure proper assembly of parting plane rubber cord.

    FINAL HORN DROP CHECK

    After completing the welding of HP inlet, HP exhaust, IP inlet, IP exhaustand other piping of HP/IP casing the final horn drop readings are recorded

    as per the laid down procedure mentioned in the manual for horn dropcheck. However the IP casing horn drop is also to be recorded with IPinlet upper half pipe welded with casing alone.

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 54

  • 8/12/2019 BHEL Erection Manual

    55/127

    Grouting of turbine base plates, bearing pedestals, foundation frame with shrink-free

    grouting compound is intended to ensure uniform transmission of the force and vibration

    of the TG unit to the foundation.

    Caution:

    Preparations for grouting, and grouting must be carried out with great care as it is no

    longer possible to check and rectify the parts once they have been grouted.

    CONBEXTRA GP-II or equivalent should be used as grouting compound. Further

    details on the grouting depths, mixing time, quantity of water to be mixed, should be

    refereed from the manufacturers brochures.

    PROCEDURE

    The foundation should be thoroughly cleaned. All foundation bolt holes should be filled

    with pea-gravels and covered at the top to avoid entry and sticking of grouting materials

    with the bolts.

    NOTE:- Remove all rust preventive paints, grease etc. from surfaces by wire brushesto ensure proper adhesion of the grouting compound.

    SETTING UP OF SHUTTERING

    Set up shuttering from suitable material in box like manner around the foundation plates

    and secure it firmly.

    NOTE:- Shuttering must be sealed well to prevent the liquid grouting compound from

    running out. This can be done by using paste of grout materials and allowing it sets.

    As the grouting compound remains workable for a limited time, to prevent air bubbles, it

    must be poured from one side only. For this, a large size filling heaped should be used.

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 55

  • 8/12/2019 BHEL Erection Manual

    56/127

    PREPARATION OF GROUT MIX

    Following measure must be taken before commencing mixing and grouting due to

    limited time that the grouting compound remains workable.

    Keep the foundation moist for at least 6 hours before the grouting.

    -Set up mixers in the immediate vicinity of the foundation plates. The capacity of the

    mixers, should be adequate to cope with the quantity of mixed cement required at a

    time. Two or more mixers are required for grouting of bearing pedestal foundation

    frame.

    -Store the grouting compound next to mixer.

    - Ensure that the compound is well within its expiry date.

    -Provide the water hose and measuring pans near the mixers.

    -Ensure uninterrupted power supply to the mixers and EOT Crane for handling the

    ready mix.

    -Provide adequate workmen for grouting.

    -Ensure six empty cubes for filling the grout for strength testing. This is to be done as

    per recommended FQP

    -Take 80 % of the required water quantity first in the mixture. Then add gradually thegrout, ensuring that no lumps are found. It is desirable to add five or six large sizes

    stones to break any lumps. Finally add the balance quantity of water and mix for at-

    least another five minutes

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 56

  • 8/12/2019 BHEL Erection Manual

    57/127

    This mixture is then taken into through heaped mesh. The hopper must be big enough

    to make the full quantity of grout.

    Than pour the grout with a hose through the filling hopper until the desired height is

    achieved on the opposite side. (Flow may be accelerated by moving the grout in the

    filling nozzles underneath the plates with chains or material strips.) This should be done

    only if it is permitted by the grout supplier.

    CAUTIONS

    1. Do not use concrete vibrator.

    2. Pour grout from one side only so that no air bubbles remains entrapped in the

    grouting compound.

    3. Due to short workability times, never mix more grouting compound at one time than

    is required for one plate or volume to be grouted.

    4. Pour in one continuous operation, without interruption.

    5. Do not install any woven steel fabric reinforcing mats beneath the foundation plates.

    6. It is desirable that in hot weather the grouting is done in the evening so that ambient

    temperature is low during the initial setting time.

    7. Water should be clean and free from dissolved chlorides, as these weaken the grout.

    8. In case during the grouting operations heavy leakage is observed from the shuttering

    that cannot be plugged during the grouting operation, and the level of grout has

    fallen below the base plate level, it is desirable to wash out the complete grout. The

    operation should be repeated after the shuttering has been rectified.

    NOTE:- After at-least 72 hours setting time, work may be commenced on pre-

    tensioning of the foundation both.

    After the grouting compound has set (approximately. 24 hours after grouting), remove

    all shuttering and smooth off the excess grout. The grouting compound is subjected to

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 57

  • 8/12/2019 BHEL Erection Manual

    58/127

    compressive forces only. Resultant hair cracks are insignificant with regard to TG

    stability. These can be avoided by covering the exposed areas of grout by polythene

    sheets to avoid excess loss of moisture during initial setting.

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 58

  • 8/12/2019 BHEL Erection Manual

    59/127

    ASSEMBLY PROCEDURE OF IP MODULEDue to oversize dimension of the IP module (M30 - 63) and its limitation intransportation from Hardwar to site, the same will be dispatched to site in dismantledcondition in various packages after completing the shop assembly at Hardwar. Firstthe complete assembly of IP module will be done at works except the heat tightening of

    parting plane bolts of IP inner and IP outer casing. Afterward complete casing will bedismantled and dispatched to site.

    The above machines are equipped with the spring loaded foundation deck. As a

    general requirement initially all the turbine and generator rotors will be aligned/coupled

    without floating the TG deck. The coupling will be opened and again re-aligned after

    floating of the TG deck which is generally done after erecting all the components of

    Turbine -Generator including their piping etc.

    ASSEMBLY PROCEDURE AT SITE :Place IP outer casing lower half in position after its cleaning over the pedestals bysupporting it on the Jacking screws at four corners of casing. Additionallysupport the casing on temporary packers with the pedestals also.

    Align IP outer casing radially with the help of piano wire keeping the HP rear and IPfront pedestals seal as reference. Install temporary radial keys of the IP outercasing with the pedestal.

    Clean and install IP inner casing lower half along with its radial keys (Drg. No. 0-106-01-27500 item No. 25) of front and rear end. During placement

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 59

  • 8/12/2019 BHEL Erection Manual

    60/127

    of inner casing support it on its four nos. Jacking screws. (Drg no. 0-106-01-27500# 18). After placement of inner casing install its axial keys (drg N. 0-106-01-27500 # 20). Before placement of inner casing install its thermocouple,parting plane studs (drg N. 0-106-01-27500 # 33 & 34 ). Seal ring of inlet insert& extraction line (drg N. 0-106-01-27500 # 3,4,9,10,13,14 ).

    Place IP inner casing upper half in position and tighten alternate parting plane bolts.During this process the heat tightening the bolts are not necessary as this isrequired for ensuring the feeler tight parting plane joints of the IP inner casing.The IP inner casing packers are also to be installed during tightening of the P/Pbolts and load of the inner casing is to be transferred on these casing packers(drg N0-106-01-27500 # 17) fter taking the load on the packers release thejacking screws of the IP casing.

    Loosen IP inner casing parting plane bolts and remove IP inner casing upper half.Before loosening the IP inner casing parting plane bolts support inner casingagain on its four jacking screws and ensure that the parting plane level of lowerhalf inner casing is not disturbed and remain same as it was kept after tightening

    of parting plane bolts with load on its four packers.Place IP rotor in position after its cleaning. The front end of the rotor is to be placed

    over segment (drg N. 0-106-01-27500 # 21) and rear end of the rotor on itsbearing. During placement of IP rotor ensure that the rotor is free on its seal finsof IP inner casing and necessary the IP outer casing may be lowered on its rearend.

    Provisionally align and couple HP/IP/LP/ Generator rotors and complete reaming/honing of the coupling including swing check etc. Before rotation of IP rotorremove segment (drg N. 0-106-01-27500 # 21).

    Set axial position of the IP rotor as per the zero position of the thrust bearing and set

    axial position of the IP outer casing as per Hardwar protocol on front and rearend of the IP outer casing.

    Align radially IP outer casing with reference to the IP rotor on front and rear glands.Recheck/correct axial position of the IP casing.

    Assemble IP inner casing upper half end tighten the alternate parting plane bolts toensure feeler tight joint.

    Do roll check of IP inner casing by moving the IP outer casing in left/right direction andIP inner casing itself in up/down direction with the help of inner casing jackingscrews by removing the inner casing packers. Ensure / compare roll checkvalues with shop records.

    Check IP rotor axial float in IP inner casing and compare with shop protocol.

    Loosen IP inner casing bolts and remove IP inner casing upper half.

    Decouple and lift IP rotor for assembly of rear end shaft seals of IP casing. The frontend of the seals may also be assembled now of afterward with the IP rotor inposition.

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 60

  • 8/12/2019 BHEL Erection Manual

    61/127

    Place IP rotor in position and provisionally couple it with HP rotor on temporary bolts.The IP rotor may not be coupled at its rear end with the LP rotor at this stage.

    Assemble and heat tighten IP inner casing upper half as per required elongation ofparting plane bolts. Install seal rings of inlet insert and extraction pipe on IPinnercasing upper half (drg N. 0-106-01-27500 # 1,2,7,8,11,12). The taper pins

    of IP inner casing parting planes are to be removed before placement of IP outercasing upper half after the heat tightening of IP inner casing bolts.

    Assemble IP outer casing upper half and tighten the parting plane bolts to ensure feelertight joints. The heat tightening of the bolts are not to be done now. Beforeplacement of IP outer casing upper half assemble casing shaft seals of front &rear end also.

    Do roll check & float of completely assemble IP turbine and compare it with factoryprotocol.

    Heat tighten IP outer casing parting plane bolts to required values, and carry out finalroll check and float of completely assembled turbine.

    NOTE : These are general instructions for the assembly of IPmodule M 30 - 63 at site. However, depending on the site

    conditions the same may be suitably reviewed, if necessary.

    Bharat Heavy Electricals LimitedRev 00, 7-98

    T1-08-0801GPage No. 61

  • 8/12/2019 BHEL Erection Manual

    62/127

    SEALING & ANTISIEZING COMPOUNDS

    SNO LOCATION FEATURES RECOMMENDEDCOMPOUND

    01 JOINT PLANE OF HPT IPT

    & VALVE CASINGS,GLAND BOXES &STRAINER HOUSINGS,BREECH NUT MATINGFACE.

    METAL TO METAL

    JOINT IN HIGHTEMPERATUREZONE

    BIRKOSIT

    STAG B

    MAGNESITECOMPOUND OFBHEL BHOPAL

    JOINT PLANE OF LPOUTER CASING(WITHOUT RUBBERSEALING CHORD).

    METAL TO METALJOINT IN LOWTEMPERATUREZONE

    HOLDITE

    LOCTITE 574

    03 JOINT PLANE OFBEARING PEDESTALS,

    MOP CASING, VALVESERVOMOTOR.

    METAL TO METALJOINT IN OIL

    ENVIRONMENT

    HYLOMER

    GOLDENHERMETITE

    VICTORSHELLAC

    04 THREADED FASTNERSINCLUD