Upload
buimien
View
219
Download
1
Embed Size (px)
Citation preview
Before the
MAHARASHTRA ELECTRICITY REGULATORY COMMISSION
World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai – 400 005
Tel. 22163964/ 65/ 69 Fax 22163976
Email: [email protected]
Website: www.mercindia.org.in/www.merc.gov.in
CASE NO. 87 of 2015
In the matter of
Petition of Kolhapur Green Energy Pvt. Ltd. for determination of Tariff for supply of
electricity from its 1.8 MW Municipal Solid Waste-based Power Project at Kolhapur to
Distribution Licensees in Maharashtra
Coram
Shri Azeez M. Khan, Member
Shri Deepak Lad, Member
ORDER
Date: 10 October, 2016
M/s Kolhapur Green Energy Pvt. Ltd. (KGEPL), 6th Floor, MET Educational Complex, C- Wing
A.K. Vaidya Marg, Bandra Reclamation, Bandra (West), Mumbai– 400 050 has filed a Petition
on 24 June, 2015 under Section 62(1) of the Electricity Act (EA), 2003 and Regulations 8.1 and
8.2 of the MERC (Terms and Conditions for Determination of Renewable Energy (RE) Tariff)
Regulations (‘RE Tariff Regulations)’, 2015 for determination of Tariff for supply of electricity
from its 1.8 MW capacity Municipal Solid Waste (MSW)-based Power Project at Kolhapur to
Distribution Licensees in Maharashtra.
The Commission, in exercise of its powers under Sections 61, 66, and 86 read with Section 181
of EA, 2003, and all other powers enabling it in this behalf, and after taking into consideration
the submissions made by KGEPL, suggestions and objections from the public and stake-holders
and other relevant material, has determined the tariff for the Project of KGEPL at Kolhapur as
set out in this Order.
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 2 of 44
Table of Contents
1. BACKGROUD AND BRIEF HISTORY ............................................................................................. 7
1.1. Background ............................................................................................................................ 7
1.2. Admission of the Petition and Public Process ........................................................................ 7
1.3. Organisation of the Order ....................................................................................................... 9
2. CONCESSION AGREEMENT BETWEEN KMC AND THE CONCESSIONAIRE .................. 11
2.1. Salient features of the Concession Agreement ..................................................................... 11
2.2. Salient features of the MSW plant ....................................................................................... 12
3. PREMISE FOR DETERMINATION OF PROJECT-SPECIFIC TARIFF .................................. 13
3.1. Regulatory Framework for Tariff Determination ................................................................. 13
3.2. Premise for Development of Tariff Structure ....................................................................... 14
4. PARAMETERES OF TARIFF DETEREMINATION .................................................................... 16
4.1. Background .......................................................................................................................... 16
4.2. Technology of the proposed MSW project .......................................................................... 16
4.3. Seasonal effect on MSW and Output of Power .................................................................... 20
4.4. Installed Plant Capacity ........................................................................................................ 21
4.5. Capacity Utilisation Factor ................................................................................................... 21
4.6. Auxiliary Consumption Factor ............................................................................................. 22
4.7. Capital Cost .......................................................................................................................... 23
4.8. Subsidy ................................................................................................................................. 25
4.9. Debt-equity Ratio ................................................................................................................. 25
4.10. Depreciation ......................................................................................................................... 26
4.11. Accelerated Depreciation ..................................................................................................... 26
4.12. Operation and Maintenance Expenses ................................................................................. 27
4.13. Interest on Term Loan .......................................................................................................... 32
4.14. Interest on Working Capital ................................................................................................. 32
4.15. Return on Equity .................................................................................................................. 33
4.16. Tipping Fee and Other Income ............................................................................................. 33
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 3 of 44
4.17. Discount Rate ....................................................................................................................... 34
4.18. Tariff Rate and Other Conditions ......................................................................................... 37
5. SUMMARY OF COMMISSION’S DIRECTIVES AND RULINGS .............................................. 39
6. APPLICABILITY OF THIS ORDER ............................................................................................... 41
Appendix – 1: List of persons who attended the Technical Validation Session held on 10 September,
2015 ........................................................................................................................................................ 42
Appendix – 1: List of persons who attended the Technical Validation Session held on 9 December,
2015 ........................................................................................................................................................ 42
Appendix – 2: List of persons who attended the Public Hearing held on 10 June, 2016 .................... 43
Annexure-1: Summary of Annual Fixed Charge and Determination of Levelised Tariff ................. 44
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 4 of 44
List of Tables
Table 1: Daily Minimum Waste Quantities .................................................................................. 11
Table 2: Comparison of MSW to Energy Conversion Technologies, as per KGEPL .................. 17
Table 3: Auxiliary Equipment Details, submitted by KGEPL ..................................................... 22
Table 4: Break-up of Capital Cost ................................................................................................ 23
Table 5: Capital Cost of MSW Projects ........................................................................................ 24
Table 6: O&M Expense of different types of Waste to Energy technologies .............................. 27
Table 7: Break-up of O&M Expense as submitted by KGEPL .................................................... 28
Table 8: O&M Expense Escalation applied by Commission........................................................ 30
Table 9: O&M Expense as approved by the Commission (Rs. Lakh) .......................................... 31
Table 10: Computation of Income from Tipping Fee ................................................................... 34
Table 11: Summary of Parameters ................................................................................................ 34
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 5 of 44
Abbreviations
APTEL Appellate Tribunal for Electricity
CEA Central Electricity Authority
CER Certified Emission Reduction
CERC Central Electricity Regulatory Commission
CDM Clean Development Mechanism
CoD Commercial date of Operation
CPCB Central Pollution Control Board
DBFOT Design Build Finance Operate and Transfer
EA Electricity Act
FD Forced Draft
ID Induced Draft
HV High Voltage
KGEPL Kolhapur Green Energy Pvt. Ltd
KMC Kolhapur Municipal Corporation
kVA Kilo Volt Ampere
kW Kilo Watt
kWh Kilo Watt Hour
MEDA Maharashtra Energy Development Agency
MERC Maharashtra Electricity Regulatory Commission
MNRE Ministry of New and Renewable Energy
MoEF Ministry of Environment & Forest
MSEDCL Maharashtra State Electricity Distribution Company Limited
MSETCL Maharashtra State Electricity Transmission Company Limited
MSPGCL Maharashtra State Power Generation Company Limited
MSW Municipal Solid Waste
MU Million Unit
O&M Operation and Maintenance
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 6 of 44
RDF Refuse-Derived Fuel
RSSPL Rochem Separation System Pvt. Ltd
SERC State Electricity Regulatory Commission
SHIIPL Sunil Hi Tech India Infra Pvt. Ltd
SLF Sanitary land filling
SPV Special Purpose Vehicle
TPD Tonnes per Day
WTE Waste to Energy
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 7 of 44
1. BACKGROUD AND BRIEF HISTORY
1.1. Background
1.1.1. Considering the growing need for waste management, the Kolhapur Municipal
Corporation (KMC), with the intention of developing a facility for treatment and disposal
of the waste, had issued Request for Proposal (RfP) in 2013. KMC proposed to deliver
180 TPD of MSW at the Project site to the Developer for setting up of a Municipal Solid
Waste to Energy (WTE) Project.
1.1.2. M/s Rochem Separation System Pvt. Ltd (RSSPL) was selected after the bidding process
and KMC issued it a letter of award dated 17 September, 2013.
1.1.3. A Special Purpose Vehicle (SPV), namely KGEPL, was formed to establish a processing
Plant with a capacity of 180 tonnes per day (TPD) for conversion of MSW into useful
products (Power, Refuse-derived Fuel (RDF) and Compost) at Kasba Bavda Village in
Kolhapur City on a Design, Build, Finance, Operate and Transfer (DBFOT) basis for 30
years. A Concession Agreement was signed between KGEPL and KMC on 7 February,
2014.
1.1.4. KGEPL is promoted by
RSSPL with a shareholding of 51%.
Sunil Hitech Engineers Ltd. (SHEL) and its subsidiary and affiliates, including Sunil
Hitech India Infra Pvt. Ltd., with a shareholding of 49%.
1.1.5. Installed Plant capacity of the proposed MSW Power Project is 1.8 MW.
1.1.6. This Order relates to KGEPL’s Petition for determination of Tariff for supply of
electricity from its 1.8 MW capacity MSW-based Power Project at Kolhapur to
Distribution Licensees in Maharashtra.
1.2. Admission of the Petition and Public Consultation Process
1.2.1. KGEPL filed a Petition on 29 June, 2015 under Sections 62(1) (a) and 86(1) (e) of the
EA, 2003 and Regulations 7.1 and 7.2 of the RE Tariff Regulations, 2010 for
determination of the Tariff for sale of electricity generated from its 1.8 MW MSW-based
Power Project.
1.2.2. Preliminary data gaps were forwarded to KGEPL on 4 September, 2015, to which
KGEPL submitted replies vide letters dated 8 September, 2015.
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 8 of 44
1.2.3. Two Technical Validation Sessions (TVS) were held on 10 September and 9 December,
2015 in the presence of Institutional Consumer Representatives (CRs) authorised under
Section 94(3) of the EA, 2003. KGEPL made a presentation on the salient features of the
Petition. The TVS minutes were forwarded to KGEPL on 23 September and 14
December, 2015. The list of persons who attended the TVS is at Appendix – 1.
1.2.4. The Commission notified the RE Tariff Regulations, 2015 on 10 November, 2015. These
Regulations are applicable to new RE Projects commissioned in Maharashtra for the
generation and sale of electricity to Distribution Licensees in the State. Regulations 8.1(a)
and 8.2 provide for determination of Project-specific tariff for MSW-based power Plants:
“8.1 A Project-specific tariff shall be determined by the Commission on a case-to
case basis for the following types of Projects:
(a) Waste to Energy Projects based on the technologies approved by MNRE such as
Municipal Solid Waste-based Projects;…
8.2 The determination of project-specific tariff for generation of electricity from such
RE sources shall be in accordance with such terms and conditions as may be
stipulated in the relevant Orders of the Commission:
Provided that the financial norms specified in Chapter 2, except with regard to
Capital Cost and O&M expenses, shall be the ceiling norms while determining such
project-specific tariff.”
1.2.5. Following the issue of the RE Tariff Regulations, 2015, on 28 December, 2015 the
Commission asked KGEPL to submit a revised Petition in accordance with the new
Regulations. On 10 February, 2016, KGEPL submitted the revised assumptions and
calculations accordingly. The Commission noted, that in its revised submission, KGEPL
had considered Interest Rate on Term Loan, Interest Rate on Working Capital (IoWC),
Discount Rate and Operation and Maintenance (O&M) escalation percentage based on
the requirement for Projects to be commissioned in FY 2015-16. It asked KGEPL to
submit the expected commissioning date and to revise the assumptions as per the RE
Tariff Regulations for Projects to be commissioned in FY 2016-17, in case its Project was
expected to be commissioned after 31 March, 2016.
1.2.6. KGEPL submitted a revised Petition on 17 March, 2016, with further changes on 3 May,
2016. KGEPL has made the following prayers:
1) “Accept this petition for determination of tariff for supply of electricity from
proposed MSW Power Project at Kolhapur to Distribution licensees in Maharashtra. It is
further requested that the Hon. Commission may specify the levelised tariff for proposed
MSW power plant for 20 year Tariff Period which is Useful Life of the plant. The Hon.
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 9 of 44
Commission may direct the distribution licensee to execute the PPA with KGEPL for the
specified Tariff Period.
2) Approve the final levelised tariff of Rs. 7.44/kWh for sale of electricity generated
from proposed MSW Power Project to distribution licensees in Maharashtra.
3) To grant an opportunity in person before Hon Commission during the hearing on
the above matter.
4) Condone any inadvertent omission/errors/short comings and permit KGEPL to
add/change/modify/alter this filing and make future submissions as may be required at a
future date.”
1.2.7. The Commission admitted the revised Petition on 13 May, 2016. In accordance with
Section 64 of the EA, 2003, it directed KGEPL to publish its Petition in an abridged form
by 16 May, 2016, and to reply expeditiously to all suggestions and objections received
from the public on its Petition.
1.2.8. KGEPL published the Public Notice in the daily newspapers Active Times and Times of
India (English), and Punya Nagari and Mumbai Lakshadeep (Marathi) on 17 May, 2016
inviting public suggestions/objections and intimating the date of Public Hearing. Copies
of the Petition and its Executive Summary were made available at KGEPL’s offices and
on its website. The Public Notice and Executive Summary of the Petition were also made
available on the websites of the Commission (www.mercindia.org.in, www.merc.gov.in)
in downloadable format.
1.2.9. A Public Hearing was held on 10 June, 2016 at the Office of the Commission, 13th
Floor,
Centre No. 1, World Trade Centre, Cuffe Parade, Colaba, Mumbai. The list of persons at
the Public Hearing is at Appendix-2.
1.2.10. The Commission has ensured that the due process contemplated under the law to ensure
transparency and public participation was followed at every stage and adequate
opportunity was given to all concerned to file their say.
1.3. Organisation of Order
1.3.1. This Order is organised in the following 7 Sections:
Section 1 provides a brief history and sets out the quasi-judicial regulatory process
undertaken by the Commission. A list of abbreviations with their expanded forms is
included.
Section 2 describes the salient features of the Concession Agreement between KMC
and the Concessionaire.
Section 3 details the Tariff philosophy underlying the tariff determination.
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 10 of 44
Section 4 comprises the submissions with respect to performance parameters and
financial parameters, the Commission's analysis, and the methodology adopted to
determine the tariff and other parameters.
Section 5 summarises the directives and rulings of the Commission.
Section 6 addresses the applicability of this Tariff Order.
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 11 of 44
2. CONCESSION AGREEMENT BETWEEN KMC AND CONCESSIONAIRE
2.1. Salient features of Concession Agreement
2.1.1. The Project is allotted on DBFOT basis for construction and operation of a MSW
processing facility for 180 TPD for a period of 30 years.
2.1.2. KMC has agreed to deliver the assured waste quantity of 180 TPD at the Project site for
processing. KMC has also agreed to pay a Tipping Fee of Rs 308 per MT of MSW till the
end of the Concession Period.
2.1.3. The MSW processing facility is to be designed for a minimum processing capacity of 180
TPD of MSW as per the schedule shown in the Table below.
Table 1: Daily Minimum Waste Quantities
Sr. No. Financial Year Daily minimum waste
quantity (TPD)
1 2015 140
2 2016 140
3 2017 140
4 2018 150
5 2019 150
6 2020 150
7 2021 150
8 2022 150
9 2023 160
10 2024 160
11 2025 160
12 2026 160
13 2027 170
14 2028 170
15 2029 to End of
Concession Period 180
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 12 of 44
2.1.4. The Concessionaire can market and sell or dispose of all the components/ products of
MSW, including but not limited to electricity, methane, RDF, compost, and retain any
revenues there from.
2.1.5. The Concessionaire shall receive all financial benefits accruing in respect of or on
account of the Project, including Certified Emission Reductions (CERs) under the Clean
Development Mechanism (CDM).
2.1.6. The treatment facility selected for the Project would scientifically process the MSW.
KGEPL is to ensure that not more than 20% of the MSW received at the processing
facility will be sent to a Landfill.
2.1.7. The Concessionaire should transfer the Project facility at the end of the Concession
Period to KMC.
2.2. Salient features of the MSW Plant, as per KGEPL
2.2.1. The proposed MSW Project involves use of mass combustion / incineration technology
for WTE conversion.
2.2.2. The Project will process approximately 180 TPD of MSW and produce around 12.6
million units of green power yearly.
2.2.3. The proposed technology is capable of meeting the emission norms specified by the
Central Pollution Control Board (CPCB) / Ministry of Environment and Forests (MoEF).
2.2.4. The Project proposes a Single Segment Reverse Push Stoker System, capable of
combusting Municipal Waste containing moisture up to 45%.
2.2.5. The special design of the stoker system and grate increases the retention time of the
MSW on the grate and helps in complete combustion of the MSW.
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 13 of 44
3. PREMISES FOR DETERMINATION OF PROJECT-SPECIFIC TARIFF
3.1. Regulatory Framework for Tariff Determination
3.1.1. As per Section 62(1) of the EA, 2003, the Appropriate Commission is empowered to
determine the Tariff for supply of electricity by a Generating Company to a Distribution
Licensee, and for transmission and wheeling of electricity. As per Section 61 (h), the
Commission shall be guided, among others, by the aspect of promotion of electricity
generation from renewable sources of energy.
3.1.2. Section 86(1)(e) of the EA, 2003 stipulates that –
"The State Commission shall discharge following functions, namely
(1)(e) promote cogeneration and generation of electricity from renewable sources of
energy by providing suitable measures for connectivity with grid and sale of electricity to
any person, and also specify, for purchase of electricity from such sources, a percentage
of total consumption of electricity in the area of distribution licensee.”
3.1.3. Regulation 3.1 of the RE Tariff Regulations, 2015 states that:
“3.1 These Regulations shall apply to those new RE Projects which are commissioned in
the State of Maharashtra for the generation and sale of electricity to Distribution
Licensees in the State, are Eligible Projects for the purposes of these Regulations, and
whose tariff is to be determined by the Commission under the provisions of Section 62
read with Section 86 of EA, 2003:”
3.1.4. As per Regulation 8.1, a Project-specific Tariff shall be determined on case to case basis
in case of MSW-based Power Projects.
3.1.5. Regulation 8.2 provides that the financial norms set out in the Regulations, except for
capital cost and O&M expenses, shall be the ceiling norms while determining the Project-
specific Tariff:
“8.2 The determination of project-specific tariff for generation of electricity from such
RE sources shall be in accordance with such terms and conditions as may be stipulated
in the relevant Orders of the Commission:
Provided that the financial norms specified in Chapter 2, except with regard to
Capital Cost and O&M expenses, shall be the ceiling norms while determining such
project-specific tariff.”
3.1.6. The Commission has issued a generic Tariff Order for procurement of power from RE
sources (namely, wind, non-fossil fuel-based co-generation, biomass, small hydro and
solar) for FY 2016-17 in Case No. 45 of 2016, dated 29 April, 2016. While determining
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 14 of 44
the Project-specific Tariff for this MSW Project, it has considered the relevant principles
and methodology adopted in the RE Tariff Order so as to ensure consistency and
certainty in the regulatory approach.
3.2. Premise for Development of Tariff Structure
3.2.1. The Commission has analysed the Detailed Project Report (DPR) and the Petition
submitted by KGEPL taking into consideration the regulatory framework and the
objective of promoting generation from MSW-based Power Projects. The Tariff has been
determined as per Regulation 9.2 of the RE Tariff Regulations, which reads as follows:
“9.2 A Petition for determination of project-specific tariff shall be accompanied by such
fee as may be specified in the applicable Regulations of the Commission, and shall be
accompanied by:
(a) Information in Forms 1.1, 1.2, 2.1 and 2.2, as the case may be, appended as
Annexure-A to these Regulations;
(b) A detailed project report outlining technical and operational details, site-specific
aspects, premises for Capital Cost and financing plan, etc.;
(c) A statement of all applicable terms and conditions and expected expenditure for the
period for which tariff is to be determined;
(d) A statement containing details of any grant, subsidy or incentive received, due or
assumed to be due from the Central Government and/or State Government, which shall
also include the computation of tariff without consideration of such grant, subsidy or
incentive;
(e) Details of financial gain through REC or any other mechanism;
(f) Any other information that the Commission may require KGEPL to submit.”
3.2.2. Useful Life: Regulation 2.1 (mm) stipulates as follows regarding the Useful Life of RE
Projects requiring a Project-specific Tariff.
“Provided that the Useful Life of other RE Projects shall be as stipulated by the
Commission while determining the Project specific tariff, taking into consideration the
norms of the Central Commission.”
3.2.3. The Central Electricity Regulatory Commission (CERC) (Terms and Conditions for
Tariff determination from Renewable Energy Sources) (Fourth Amendment) Regulations,
2015, specifies 20 years as the Useful Life of MSW Projects. Accordingly, the
Commission has taken the Useful Life of the present Project as 20 years from its
commercial date of operation (COD).
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 15 of 44
3.2.4. Levelised Tariff Design: In accordance with Regulations 11.2 and 11.3, the Commission
has determined the levelised tariff for the representative case in respect of MSW-based
Projects. The relevant provisions are given below:
“11.2 For the purpose of computation of levelised tariff, a discount factor equivalent to
the normative post-tax weighted average cost of capital shall be considered.
11.3 Levelisation shall be carried out for the ‘Useful Life’ of the RE Project, while tariff
shall be determined for the period equivalent to the Tariff Period.”
3.2.5. Tariff Period: The Commission has considered a Tariff Period of 20 years for the MSW
Project from the COD.
3.2.6. The assumptions and rationale for input values of Project-specific parameters have been
elaborated in the subsequent Section.
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 16 of 44
4. PARAMETERS OF TARIFF DETEREMINATION
4.1. Background
4.1.1. Under Regulation 10 of the RE Tariff Regulations, 2015, the Tariff for RE Projects shall
be a single-part tariff consisting of the following cost components:
a) Return on Equity (RoE);
b) Interest on Loan Capital;
c) Depreciation;
d) Interest on Working Capital;
e) O&M expenses;
The performance parameters and financial parameters are discussed in this Section.
4.2. Technology of proposed MSW Project
KGEPL’s submission
4.2.1. KGEPL has proposed to use mass combustion technology for the proposed Project, after
having studied the merits and demerits of other technological options and analysis of the
quality of waste and local conditions. Regarding quality of waste, National Environmental
Engineering Research Institute (NEERI) has done a study of the characteristics of waste.
Samples from different Wards, dumping sites and waste bins of Kolhapur city were
collected for physical and chemical analysis. The study revealed that the moisture content of
the waste varied widely from 5.79% to 64% in the 29 samples collected.
4.2.2. KGEPL has referred to the Ministry of New and Renewable Energy (MNRE) document
“Technical Memorandum on Waste to Energy Technologies”, under the National Master
Plan for Development of WTE in India. MNRE has assessed the available technologies
for conversion of MSW to Energy, i.e., bio-methanation, gasification/ pyrolysis,
incineration and land filling. This assessment by MNRE is done on criteria such as
system configuration, system auxiliaries, environmental aspects, resource recovery and
commercial aspects. The advantages of the incineration / combustion technology as per
this assessment are:
a) Mass-combustion systems have larger capacities and higher thermal efficiencies.
b) Mass-combustion systems, as compared to modular systems, generate higher quality
steam, allowing for higher revenues per tonne of waste.
c) The facilities with mass-combustion systems can accept refuse that has undergone
very little pre-processing, like the removal of oversized items.
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 17 of 44
d) Mass-combustion avoids many of the refuse handling problems caused by the
extreme heterogeneity and variability of available waste.
e) If efficient burning is ensured, as in this case, most of the burning occurs on the grate,
less particulate matter enters in the gas stream, and the cost of maintaining air
pollution levels is thus reduced.
f) Even within combustion technology, the net energy conversion in mass combustion
system can be equal to or better than in RDF systems, since minimal energy is used
for front-end processing and no burnable material is removed
g) The units are compact and, therefore, land requirements are less than for RDF.
4.2.3. A comparison of various MSW to Energy conversion technologies is given below:
Table 2: Comparison of MSW to Energy Conversion Technologies, as per KGEPL
Sr.
No
Associated
Factors Composting
Bio-
methanation Incineration Gasification SLF
1 Air Pollution
a Extent Low Low Medium Medium High
b
Requirement of
Air Pollution
Control
Yes Yes
c Dixons/ Furans
Possibility
exists: but
minimized due
to removal of
plastics from
waste by rag
pickers
d
Release of
Green House
Gases
Uncontrolled Controlled and
utilized
Controlled and
utilized
Controlled
and utilized
Mostly
uncontrolle
d
2 Water Pollution
a Exists Yes Yes Yes Yes Yes
b
Requirement of
Waste water
treatment
Yes Yes Yes Yes Yes
c Quality of
treated water
May be
discharged into
water bodies
May be
discharged into
water bodies
Used in the
process
Used in the
process
Discharged
into water
bodies
d Degree of
Pollution High Medium Low Medium High
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 18 of 44
Sr.
No
Associated
Factors Composting
Bio-
methanation Incineration Gasification SLF
3 Rejects
a
Solid Waste
generation due to
rejects/ sludge
formation in the
process
High Low Low Low Low
b
Volume
reduction of
waste
15-30% 45-50% 80-90% 65-75% 70-80%
4.2.4. The important features of the proposed technology are:
a) The technology is based on mass-combustion of the combustible materials present in
MSW.
b) The heat generated is used to produce steam that in turn produces power through
steam turbines.
c) The technology can be used for a very wide range of wastes.
d) The process can reduce the waste volume up to 90% and its capital cost is lower than
other MSW treatment technologies.
e) The entire MSW is converted into energy with higher efficiency as compared to the
other technologies.
f) Complete combustion optimally involves a two stage transformation of fuel, in this
case solid waste into carbon dioxide (C02) and water vapour.
4.2.5. The process flow diagram is shown below:
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 19 of 44
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 20 of 44
Commission’s Analysis and Ruling
4.2.6. The National Master Plan (NMP) for Development of WTE has recognised various
technologies such as bio-methanation, landfill gas recovery, gasification, composting,
incineration, etc. for WTE Projects. Of these, gasification/pyrolysis and
incineration/combustion are suitable for solid waste. The technology adopted by KGEPL
i.e. mass-combustion (incineration) technology for the WTE process, is also recognised
in the NMP. The Commission also verified that the proposed technology is capable of
meeting the emission norms specified by the CPCB and MoEF.
4.2.7. The Commission has considered the technology particulars and specifics for determining
the Project-specific Tariff.
4.3. Seasonal effect on MSW and power output
KGEPL’s submission
4.3.1. KGEPL had not considered the seasonal impact on the receipt of MSW and the output of
power in its Petition.
Commission’s Analysis and Ruling
4.3.2. The Commission asked KGEPL regarding any seasonal impact on receipt or processing
of MSW and consequently on the Tipping Fee and, if so, whether it had been factored
while calculating the annual energy generation. Further, in the rainy season, the moisture
content of the waste may often be above 45%. The Commission asked KGEPL whether
there is any process to handle extremely wet waste and any safeguard to ensure that the
generation is not interrupted due to rain. It also asked whether there is any safeguard to
ensure that the generation is not interrupted if KMC is unable to provide MSW daily as
per the minimum requirement of the Plant.
4.3.3. KGEPL replied that the proposed reverse reciprocating grate incineration/ combustion
route for conversion of MSW to energy is a thermo-chemical conversion of WTE. The
seasonal variations in moisture levels in MSW does not affect the power generation as
may be the case with the bio-chemical conversion of WTE observed in bio-methanation/
gasification technology. Further, the primary air used for supporting burning is pre-
heated by a secondary air heater to raise the temperature to more than 240 ºC to 250 ºC so
as to ensure that the MSW that enters the furnace is dry. The design also allows control
over the amount of primary air in one or several or all air chambers, thereby improving
the regional or whole combustion. The waste holding pit has a capacity to hold waste for
4-5 days, which provides a buffer in case of shortage of waste.
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 21 of 44
4.3.4. Considering the submissions of KGEPL, the Commission has not considered any
seasonal impact on receipt of MSW since it appears that the technology and processes
involved are capable of handling significant variations. The Tipping Fee is also taken as
constant, based on an average yearly MSW receipt of 180 TPD as submitted by KGEPL.
4.4. Installed Plant Capacity
KGEPL’s submission
4.4.1. KGEPL has taken the installed Plant capacity as 1.8 MW.
Commission’s Analysis and Ruling
4.4.2. The Commission referred to the DPR submitted by KGEPL and noted that the proposed
capacity is in line with it. Accordingly, the Commission has taken the installed capacity
of 1.8 MW for the purpose of this Project-specific Tariff determination.
4.5. Capacity Utilisation Factor
KGEPL’s submission
4.5.1. Considering the availability of MSW from KMC and variation in the quality of MSW
across seasons, KGEPL has considered the Capacity Utilization Factor (CUF) as 65%
during the stabilisation period (first year) and 80% for the remaining period.
Commission’s Analysis and Ruling
4.5.2. KGEPL has proposed a higher CUF than considered by CERC and of other similar MSW
Projects. Accordingly, the Commission has considered the CUF of 65% for the first year
and 80% for the remaining life of the Project, as proposed by KGEPL.
4.5.3. The operational risk of the MSW Power Plant operations has to be borne by KGEPL. The
risk of lower generation and consequent lower CUF cannot be passed on to the
Distribution Licensees/consumers at a later stage. Similarly, the benefit of excess
generation beyond the threshold value of CUF will be allowed to be retained by KGEPL.
4.5.4. The MSW Project shall be treated as a “Must Run” Power Plant and shall not be subject
to Merit Order Despatch (MOD) principles till such time as the Commission stipulates or
specifies otherwise as per clause 16.3 of the MERC (Distribution Open Access)
Regulations, 2016.
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 22 of 44
4.6. Auxiliary Energy Consumption Factor
KGEPL’s submission
4.6.1. The overall Plant Auxiliary Consumption has been considered as 20% of gross generation
for tariff computation. Of this 20%, 16% has been considered for the main Plant
equipment Auxiliary Consumption and 4% for Plant lighting, building services and
transformer/other equipment losses.
Commission’s Analysis and Ruling
4.6.2. The Commission had asked KGEPL to explain the higher Auxiliary Consumption
proposed as compared to its Projects at Patna and Surat and other technology-based
MSW Power Projects approved by the Commission. KGEPL stated that the Auxiliary
Consumption of the proposed Plant is higher on account of its smaller capacity (1.8 MW)
as compared to other MSW Projects which have a higher capacity (average of 10 MW).
4.6.3. The Commission also asked for the reasoning/justification for considering 20%
Auxiliary Consumption and sought the equipment-wise break up of Auxiliary
Consumption in terms of equipment ratings. KGEPL submitted that the ID Fan, FD Fan
and boiler feed pumps are required to be operated for 7,008 hours in a year. It submitted
details of the type of auxiliary equipment, their individual load and operating hours as
shown in the Table below:
Table 3: Auxiliary Equipment Details submitted by KGEPL
Sr. No Equipment
Power
Consumption
(kW)
Working
hours in a
year
Annual Energy
Consumption
(kWh)
1 ID Fan 50.0 7,008 350,400
2 FD Fan 30.0 7,008 210,240
3 Boiler Feed Pump 86.0 7,008 602,688
4 Cooling Water System 65.0 6,360 413,400
5 Crane 30.0 4,225 126,750
6 Trommel 35.0 5,618 196,630
7 Fuel Feeding 30.0 4,220 126,600
8 Plant Lighting 35.0 4,225 147,875
9 Building services like air-
conditioning, fire prevention 25.0 8,760 219,000
10 Transformer and other equipment
loss 15.0 8,760 131,400
Total 401
2,524,983
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 23 of 44
4.6.4. The Commission has verified the assumptions made by KGEPL and considered an
Auxiliary Energy Consumption factor of 20%.
4.7. Capital Cost
KGEPL’s submission
4.7.1. The Capital Cost is proposed at Rs. 2482.68 crores, as presented in the Table below:
Table 4: Break-up of Capital Cost
Sr. No Project Cost Amount (Rs. lakh)
1 Civil Work for Plant and Machinery 613.42
2 Plant and Machinery 1,666.68
3 Total of Plant and machinery (EPC cost)(1 +2) 2,280.10
4 Financing cost @ 1.50% of the EPC Cost 34.20
5 Preliminary and pre-operative expenses @ 4% of EPC Cost 91.20
6 Interest during construction 77.18
Total Project Cost (3+4+5+6) 2,482.68
4.7.2. KGEPL has submitted the detailed Techno-Economic Viability (TEV) Report of the
Project giving details of the capital cost.
Commission’s Analysis and Ruling
4.7.3. The Commission had asked KGEPL for the detailed break up of audited capital cost.
KGEPL stated that the major cost of the mass-combustion technology proposed is on
account of the power generation facility, as the fuel treatment and pre-treatment facilities
cost is negligible. There is no compost generation, and hence no compost-related facility
is required. For the fuel treatment, no major equipment/belt conveyor is involved in this
process.
4.7.4. The Commission notes that the capital cost of the Project includes plant and machinery,
civil works, erection and commissioning, financing costs, preliminary and pre-operative
expenses and interest during construction (IDC). As per the proviso to Regulation 13 of
the RE Tariff Regulations, 2015, KGEPL has submitted the detailed break-up of the
capital cost items as specified in Regulation 9.2.
4.7.5. While the entire technology risk entailing selection of capacity, configuration,
technology, etc., is borne by KGEPL, the Commission has to ensure that the capital cost
is optimal and reasonable so that no undue cost burden is passed on to consumers through
the Project-specific Tariff determination.
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 24 of 44
4.7.6. In response to a query, KGEPL confirmed that, as submitted in the TEV Report, it has
considered the cost of evacuation arrangement up to the HV side of the generator
transformer which is the inter-connection point. This cost is included in the total capital
cost.
4.7.7. The Commission has considered the documents furnished, such as the TEV Report of an
independent agency, details of bids quoted by the technology providers, and the
submissions made by KGEPL. In its proposed norms for determination of Generic Tariff
for MSW/WTE Projects for 2015-16, CERC has considered a capital cost of Rs 1500
lakh/MW, excluding land cost. In its recent Order dated 4 August, 2015, the Gujarat
Electricity Regulatory Commission (GERC) has determined the Project-specific Tariff
for the 11.5 MW MSW Plant of RGE Surat Pvt. Ltd. considering Rs 1778 lakh/MW
based on mass-burn combustion technology. A comparative Table of recently approved
capital costs for WTE Projects by several Regulatory Commissions in India with the
capital cost approved in the present case is presented below:
Table 5: Comparative Capital Cost of MSW Projects
Sr. No
Waste to Energy Project
Capital Cost
(in Rs.
Lakh) MW
Capital Cost /
MW (In Rs.
Lakh) Technology
1 MERC, Case No. 87 of 2015
(KGEPL) (present Case) 2482.7 1.8 1379.3
Mass
Combustion
2 MERC, Case No. 65 of 2009
(Solapur Bioenergy) 3614.6 2.8 1277.2 Gasification
3 MERC, Case No. 77 of 2014
(Rochem Pune, RGEPL) 12949.9 9.0 1443.7 Gasification
4 GERC, Case No. 1433 of 2014
(RGE Surat Pvt. Ltd.) 20448.0 11.5 1778.1
Mass
Combustion
5 CERC (Generic, SM/03/2015) 1500.0 Combustion
6 BERC, Case No. 22 of 2015
(PGEPL, Patna) 20542.8 11.5 1786.3 Combustion
4.7.8. Considering the above comparison of capital costs for WTE projects, the Commission
finds the capital cost claimed by KGEPL to be within reasonable limits, especially when
compared to similar combustion technology-based projects. Accordingly, for tariff
determination for the 1.8 MSW Power Project of KGEPL, the Commission has taken a
capital cost of Rs 2,482.68 lakh (1379.27 lakh/MW), as submitted by KGEPL.
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 25 of 44
4.8. Subsidy
KGEPL’s submission
4.8.1. KGEPL has not considered any MNRE subsidy for determination of tariff for the Project.
It would inform the Commission as and when any MNRE subsidy is sanctioned.
Commission’s Analysis and Ruling
4.8.2. The Commission asked KGEPL to confirm the nature and extent of grant or capital
subsidy available for such MSW Projects, whether it has been availed or is proposed to
be availed, with justification. KGEPL stated that, as per the MNRE Administrative
Approval dated 12 September, 2013, the capital subsidy is to the extent of Rs 2
crore/MW. A total outlay of Rs 38 crore was allocated for the programme on energy from
Urban, Industrial and Agriculture Waste for 2013-14. However, MNRE has not
announced any capital subsidy for FY 2015-16 and, therefore, KGEPL has not applied
for it.
4.8.3. The Commission noted from the documents submitted by KGEPL that it is yet to receive
any MNRE subsidy as it has not been announced yet.
4.8.4. In view of the above, the Commission has not taken any MNRE subsidy for tariff
determination. KGEPL is directed to submit the details of such subsidy as and when
sanctioned by MNRE. The Commission also directs the Maharashtra Energy
Development Agency (MEDA), which is the State Nodal Agency, to inform the
Commission and the concerned Distribution Licensee of any such grant or subsidy if and
when it is provided to KGEPL. The treatment of any such grant or subsidy received in
future shall be in accordance with Regulation 24 of the RE Tariff Regulations. Further,
specific provisions for recovery of any such grant or subsidy by the Distribution Licensee
(if availed by KGEPL), reflecting the relevant provisions of Regulation 24, shall be
incorporated in the Energy Purchase Agreement (EPA) between KGEPL and the
concerned Distribution Licensee.
4.9. Debt-Equity Ratio
KGEPL’s submission
4.9.1. The Project’s actual debt: equity ratio is 65:35. However, KGEPL has proposed a debt:
equity ratio of 70:30, in line with the RE Tariff Regulations, for determination of tariff.
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 26 of 44
Commission’s Analysis and Ruling
4.9.2. The Commission has taken the debt-equity ratio of 70:30 as specified in Regulation 14 of
the RE Tariff Regulations, 2015, which states as follows:
“14.2 For project-specific tariff determination, if the equity actually deployed is
more than 30% of the Capital Cost, the equity in excess of 30% shall be treated as
normative loan:
Provided that, where the equity actually deployed is less than 30% of the
Capital Cost, the actual equity shall be considered for determination of tariff;…”
4.9.3. Since the equity actually deployed is more than 30% of the capital cost, the equity in
excess of 30% has been considered as normative loan, and a debt:equity ratio of 70:30
has been applied for tariff determination.
4.10. Depreciation
KGEPL’s submission
4.10.1. KGEPL has computed depreciation at the rate of 5.83% per annum for the first 12 years
of the Tariff Period. The remaining depreciation amount (up to 90% of capital cost) has
been spread over the remaining Useful Life of the Project (8 years), in line with the RE
Tariff Regulations, 2015.
Commission’s Analysis and Ruling
4.10.2. The Commission has accepted the computation of depreciation proposed by KGEPL,
which is in accordance with Regulation 16 of the RE Tariff Regulations, 2015.
4.11. Accelerated Depreciation
KGEPL’s submission
4.11.1. KGEPL has not claimed any Accelerated Depreciation benefit.
Commission’s Analysis and Ruling
4.11.2. Regulation 24 of the RE Tariff Regulations, 2015 requires that the accelerated
depreciation benefit be taken into account while determining the tariff if it has been
availed. In its Petition, KGEPL did not consider any Income Tax benefit on account of
accelerated depreciation. In response to a query, KGEPL clarified that the benefit of
accelerated depreciation has not been availed by it. Hence, the Commission has not
considered accelerated depreciation while determining the tariff. However, the
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 27 of 44
Distribution Licensee entering into an EPA with KGEPL shall verify this claim of not
having availed accelerated depreciation benefit after the accounts of KGEPL for the 1st
year of operation are audited. The Distribution Licensee shall pass on the benefit to
consumers if accelerated depreciation is actually availed by KGEPL. Further, provisions
reflecting the Regulations in this regard for passing on the benefit of accelerated
depreciation (if availed by KGEPL) shall be incorporated in the EPA.
4.12. Operation and Maintenance Expenses
KGEPL’s submission
4.12.1. KGEPL has estimated the O&M cost at 6.6% of the Project cost (Rs. 165 lakh in the first
year). The projection of O&M expenses is based on the Technical Memorandum on
Investment and Funding Strategies prepared under the NMP for the development of
WTE, under which a comparison of the available technological options in terms of capital
cost, O&M cost, and Project life was done. The summary of O&M expenses for different
types of WTE technologies as given in the Technical Memorandum is set out below:
Table 6: O&M Expenses of different Waste to Energy Technologies
Particulars Units Capacity (1000 TPD) Capacity (500 TPD) Capacity (150 TPD)
Bio-
methanati
on
Gasificat
ion
RDF –
INC
Bio-
methanati
on
Gasificat
ion
RDF
INC
Bio-
methanati
on
Gasificat
ion
RDF
INC
Project Life Years 15 15 15 15 15 15 15 15 15
Capital Cost Rs. lakh 10000 21904 6483 6000 13000 3890 1800 4600 1400
O&M % of CC 8.5 7.43 13.54 8.33 6.5 13.55 9.44 6.5 13.57
4.12.2. The above benchmarks are based on 2002-03 data. For a typical 150 TPD capacity MSW
Plant using RDF-based incineration technology, the capital cost is Rs 14 crore, and O&M
cost is around 13.57% of the capital cost.
4.12.3. Due to the pre-treatment (screening, shredding and segregation of waste) requirement, the
KGEPL Project’s O&M cost is slightly higher than that of other WTE Power Projects.
KGEPL has applied an annual escalation of 5.72% per annum in O&M cost, and
considered Rs. 100 lakh as periodic maintenance cost (included in the O&M cost) every
three years.
Commission’s Analysis and Ruling
4.12.4. The Commission asked KGEPL for the detailed break up of proposed O&M expenses,
comprising repairs and maintenance (R&M), establishment (including employee
expenses), and administrative and general (A&G) expenses including insurance. KGEPL
submitted the break-up as below:
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 28 of 44
Table 7: Break-up of O&M Expenses as submitted by KGEPL
Description Rs. (In lakh)
Administrative Expenditure and Labor Cost (Incl. Insurance) 50
R&M including Plant Spares and Consumables 115
Total O&M Cost 165
4.12.5. The Commission also asked KGEPL for justification for the additional capital
expenditure of Rs 100 lakh after every three years of operation, over and above the
regular O&M expenses. KGEPL stated that this periodic additional capital expenditure is
envisaged for major overall maintenance work required for the entire process plant after
every 3 years. In this major maintenance schedule, major and critical equipment like
boiler tube, reciprocating grates and ducting will be replaced/ repaired, for which a
provision of Rs. 100 lakh has been made. KGEPL has submitted the details of machinery
requiring replacement along with the associated cost. Some of the machinery / parts
require replacement / overhaul every year from the 5th
year onwards. Therefore, KGEPL
has considered the additional Rs 100 lakh O&M in the 4th
year, and thereafter escalated
the amount at a normative escalation factor of 5.72% in subsequent years.
4.12.6. The Commission notes that the O&M expenses projected by KGEPL are within the
norms provided in the Technical Memorandum on Investment and Funding Strategies
prepared under the NMP for the development of WTE.
4.12.7. The O&M expense projected by KGEPL has three components:
Regular O&M expense of Rs. 165 lakh in the first year, escalated every year
based on the inflation factor
Additional O&M expense of Rs. 100 lakh after every three years for machinery
requiring replacement every three years (Heat exchanger, Grab crane feeding
system, Feed hoppers with bridge breakers, Hydraulic ram feeder and Reciprocating
grate)
Additional O&M expense on machinery / parts requiring replacement / overhaul
every year from the 5th
year onwards.
4.12.8. The Commission notes that the O&M escalation of 5.72% applied by KGEPL is as per
the RE Tariff Regulation, 2010 and not as per the latest RE Tariff Regulations, 2015
which are applicable to its Project.
4.12.9. The RE Tariff Regulations, 2015 provide that the Base Year O&M expense is to be
escalated at the rate specified in the Commission’s Multi-Year Tariff (MYT)
Regulations over the Tariff Period for determination of the levelised Tariff. Regulations
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 29 of 44
45.1(d), 47.1(c) and 47.2(b) of the current MYT Regulations, 2015 specify the norms
for escalation of O&M expenses in subsequent years beyond the Base Year:
“The O&M expenses for each subsequent year shall be determined by escalating
the base expenses determined above for FY 2015-16, at the inflation factor
considering 60% weightage for EA, 2003ual point to point inflation over
Wholesale Price Index numbers as per Office of Economic Advisor of
Government of India in the previous year and 40% weightage for EA, 2003ual
Consumer Price Index for Industrial Workers (all India) as per Labour Bureau,
Government of India in the previous year, as reduced by an efficiency factor of
1%, to arrive at permissible O and M expenses for each year of the Control
Period.”
4.12.10. Thus as per the MYT Regulations, 2015, the escalation factor for O&M expenses from
FY 2016-17 is to be worked out based on the inflation factor considering 60% and 40%
weightage for actual point to point Wholesale Price Index (WPI) and Consumer Price
Index (CI), respectively, in the previous year, reduced by an efficiency factor of 1%.
4.12.11. The Commission has analysed the WPI and CPI data for the previous year, i.e., FY
2015-16. Based on the analysis, the Commission notes that, by applying 60% weightage
to WPI and 40% weightage to CPI for FY 2015-16, the inflation factor works out to
0.74%. When the efficiency factor of 1% is applied, the escalation factor to be
considered for projecting O&M expenses from FY 2016-17 works out to (-) 0.26%
(negative).
4.12.12. The Commission recognises that the escalation rates worked out based on actual WPI
and CPI have reduced significantly during the last 2 years as compared to previous
years. The Commission is of the view that it may not be appropriate to apply a negative
inflation factor for projecting O&M Expenses from FY 2016-17 onwards for the entire
Useful Life of the Project as a certain portion of O&M expenses are likely to increase
from year to year.
4.12.13. In this context, the Commission also analysed the approach adopted by the CERC for
fixing the O&M expenses while framing its Tariff Regulations, 2014. It is observed that
CERC has considered the escalation rate based on 5-year average WPI and CPI from
FY 2008-09 to FY 2012-13, with 60% and 40% weightage to CPI and WPI,
respectively, and compared it with the actual increase in O&M expenses.
4.12.14. The inflation factor based on the provisions of the MYT Regulations, 2015 works out to
be negative due to the reduction in WPI in FY 2015-16 over FY 2014-15. The
Commission is of the view that, at this stage, it will be more appropriate to consider the
WPI and CPI variation over a longer period so that wide fluctuations in any one
particular year are smoothened, for arriving at the inflation factor to be applied. Hence,
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 30 of 44
the Commission has considered the 3-year average variation in WPI and CPI to arrive at
the inflation factor to be applied for projecting the O&M Expenses from FY 2016-17
onwards. Based on this approach, the inflation factor, considering 60% weightage to
WPI and 40% weightage to CPI, works out to 3.97%. After applying the efficiency
factor of 1%, the escalation factor to be applied for projecting O&M expenses from FY
2016-17 to FY 2019-20 works out to 2.97%.
4.12.15. In this background, in its Generic RE Tariff Order for FY 2016-17 dated 29 April, 2016
in Case No. 45 of 2016 also, the Commission had invoked its power to remove
difficulties under Regulation 82 of the RE Tariff Regulations and revised the O&M
escalation percentage to be applied to RE Projects. In that Order also, the Commission
has applied the escalation factor considering 60% and 40% weightage to the WPI and
CPI numbers, respectively, for the average of the previous three years (upto FY 2015-
16), as reduced by the efficiency factor of 1%.
4.12.16. In view of the above, the Commission, in exercise of its powers under Regulation 82 of
the RE Tariff Regulations, 2015, has computed the O&M expenses for the period
beyond FY 2016-17 applying the escalation factor of 2.97% considering the 3 year
average variation in WPI and CPI instead of one year.
4.12.17. Accordingly, the computation of O&M escalation percentage adopted in this Order is as
presented in Table below:
Table 8: O&M Expense Escalation applied by Commission
Month
WPI CPI
FY
2012-13
FY
2013-14
FY
2014-15
FY
2015-16
FY 2012-
13
FY 2013-
14
FY 2014-
15
FY
2015-
16
April 163.5 171.3 180.8 176.4 205 226 242 256
May 163.9 171.4 182 178 206 228 244 258
June 164.7 173.2 183 179.1 208 231 246 261
July 165.8 175.5 185 177.6 212 235 252 263
August 167.3 179 185.9 176.5 214 237 253 264
September 168.8 180.7 185 176.5 215 238 253 266
October 168.5 180.7 183.7 176.9 217 241 253 269
November 168.8 181.5 181.2 177.5 218 243 253 270
December 168.8 179.6 178.7 176.8 219 239 253 269
January 170.3 179 177.3 175.4 221 237 254 269
February 170.9 179.5 175.6 174.1 223 238 253 267
March 170.1 180.3 176.1 174.6 224 239 254 268
Average 168 178 181 177 215 236 251 265
YoY Increase %
5.98% 2.00% -2.52%
9.68% 6.29% 5.65%
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 31 of 44
Average of 3-year
CPI Growth %
Average of 3-year
WPI Growth %
Inflation Factor with
60% WPI and 40% CPI
Escalation rate considering
1% Efficiency Factor
7.21% 1.82% 3.97% 2.97%
4.12.18. Based on the above, the Commission has approved the following O&M expenses for the
Project.
Table 9: O&M Expenses as approved by Commission (Rs. Lakh)
Sr.No. Particulars/Year 1 2 3 4 5 6 7 8 9 10
1 Basic O&M
Expenses 165.09 170.00 175.05 180.26 185.62 191.13 196.82 202.67 208.69 214.90
2
Additional O&M of
Rs. 100 lakh
(escalated for
inflation) after every
three years for
machineries
requiring
replacement every
three years
100.00
109.19
119.22
3
Additional O&M for
the machineries /
parts required
replacement /
overhaul every year
from 5th year
onwards.
102.97 106.03 109.19 112.43 115.78 119.22
4 Total O&M 165.09 170.00 175.05 280.26 288.59 297.17 415.19 315.10 324.47 453.33
Sr.No. Particulars/Year 11 12 13 14 15 16 17 18 19 20
1 Basic O&M
Expenses 221.29 227.86 234.64 241.61 248.80 256.19 263.81 271.65 279.73 288.05
2
Additional O&M
Expenses after every
3 years
130.17
142.13
155.18
3
Additional O&M for
replacement /
overhaul every year
from 5th year
onwards
122.76 126.41 130.17 134.04 138.02 142.13 146.35 150.70 155.18 159.80
4 Total O&M 344.05 354.27 494.98 375.65 386.82 540.45 410.16 422.36 590.10 344.05
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 32 of 44
4.13. Interest on Term Loan
KGEPL’s submission
4.13.1. A loan repayment period of 12 years is taken, in line with Regulation 15.1 of the RE
Tariff Regulations, 2015.
4.13.2. KGEPL has taken the interest on long term debt at 300 basis points above the State Bank
of India (SBI) Base Rate of the previous year. Accordingly as given in the Draft RE
Generic Tariff Order for FY 2016-17, the Base Rate (9.56%) plus 300 basis points has
been applied, and interest on debt computed as 12.56% per annum.
Commission’s Analysis and Ruling
4.13.3. The Commission has taken a loan tenure of 12 years, in line with Regulation 15.1 of the
RE Tariff Regulations, 2015. It has considered the weighted average of the SBI Base
Rate from April, 2015 to March, 2016 to arrive at the effective SBI Base Rate of 9.54%.
Accordingly, it has applied interest on term loan at 12.54% (9.54% + 300 basis points) in
accordance with Regulation 15.2.
4.14. Interest on Working Capital
KGEPL’s submission
4.14.1. KGEPL has computed the working capital in accordance with the Regulations
comprising (a) O&M cost for one month, (b) receivables equivalent to 2 months of net
energy charges for the sale of electricity calculated on the normative CUF and (c)
maintenance spares @15% of O&M expenses. IoWC is taken as the SBI Base Rate plus
350 basis points, which works out to 13.06 %.
Commission’s Analysis and Ruling
4.14.2. Regulation 18.1 of the RE Tariff Regulations, 2015 specifies the components of working
capital for Wind, Small Hydro, Solar PV and Solar Thermal Power Projects (projects
with no fuel cost component). Regulation 18.2 specifies the components of working
capital for Biomass and non-fossil fuel-based Co-Generation Projects (Projects having
fuel cost component). Since there is no fuel cost component in the proposed MSW
Project of KGEPL, the Commission has considered the components of working capital in
accordance with Regulation 18.1, which is the same as submitted by KGEPL. It has
computed the interest rate on working capital in accordance with Regulation 18.3 and the
SBI Base Rate as elaborated in para. 4.13.3 above, and applied an interest rate on
working capital of 13.04%.
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 33 of 44
4.15. Return on Equity
KGEPL’s submission
4.15.1. The RE Tariff Regulations, 2015 allow RoE at the Base Rate of 16%, to be grossed up as
per the applicable Income Tax rate. The Regulations also provide for the rate of RoE to
be computed by grossing up the Base Rate with the Tax rate equivalent to Minimum
Alternate Tax (MAT) for the first 10 years from COD, and at the normal Tax rate for the
remaining years of Project life. Accordingly, as per the prevailing Tax rate, the Base Rate
of 16% has been grossed up with MAT (@21.34% for the first 10 years, and with
Income Tax (@ 34.61%) for the remaining 10 years of Plant operation.
Commission’s Analysis and Ruling
4.15.2. The Commission accepts KGEPL’s submission since it has considered the RoE in
accordance with the RE Tariff Regulations, 2015.
4.16. Tipping Fee and Other Income
KGEPL’s submission
4.16.1. As per the Concession Agreement, a Tipping Fee of 180 TPD @ Rs 308/tonne, without
any escalation, has been taken as income. The yearly income has been calculated as
follows:
Yearly Income from Tipping Fee = TPD of MSW received (180 TPD) X Tipping
Fee rate X CUF of the Project (65% for first year and 80% for remaining period).
4.16.2. The income from sale of bottom ash (30 TPD) which will be generated in the process will
be sold in the open market @ Rs 150/tonne. The yearly income has been calculated as
Yearly Income from sale of bottom ash = TPD of by-product (30 TPD) X rate of
by-product X CUF of the Project (65% for first year and 80% for the remaining
period).
4.16.3. KGEPL has envisaged the income from by-product sale as Rs.10.68 lakh in the first year
and Rs. 13.14 lakh from the second year onwards.
Commission’s Analysis and Ruling
4.16.4. KGEPL receives income for collection of MSW from KMC. The income from Tipping
Fee has been computed after taking into account the CUF of the Plant, as summarized
below:
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 34 of 44
Table 10: Computation of Income from Tipping Fee
Sr.
No Particular Unit First Year
Remaining
period
1 Waste Received Tonne per day (TPD) 180 180
2 CUF % 65% 80%
3 Rate Rs. Per tonne 308 308
Tipping Fee Receipt Rs. lakh 131.53 161.88
4.16.5. Based on the submissions of KGEPL, the Commission has also considered the income
from sale of by-products like bottom ash which will be produced during the process as
Rs.10.68 lakh in the first year and Rs. 13.14 lakh from the second year onwards.
4.17. Discount Rate
KGEPL’s submission
4.17.1. KGEPL has applied a discount rate of 10.55% for determination of levelised tariff.
Commission’s Analysis and Ruling
4.17.2. In accordance with Regulation 11.2 of the RE Tariff Regulations, 2015, for levelised
tariff computation the Commission has taken the discount rate as equivalent to the
weighted average cost of capital, which works out to 10.54% considering the approved
interest rate and rate of RoE in this Order.
4.17.3. In accordance with Regulation 11.3, the Commission has undertaken levelisation for the
entire Useful Life of 20 years.
4.17.4. The summary of various parameters and assumptions covering capital cost, financial
parameters, operating parameters and performance parameters, as considered for the
Project-specific Tariff determination in this Order, is shown in the following Table:
Table 11: Summary of Parameters
Sl.
No.
Assumption
Head Sub-Head Sub-Head (2) Unit
Assumptions
of KGEPL
Assumptions
as approved
in this Order
1 Power
Generation
Capacity
Installed Power
Generation
Capacity
MW 1.8 1.8
Auxiliary
Consumption % 20% 20%
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 35 of 44
Sl.
No.
Assumption
Head Sub-Head Sub-Head (2) Unit
Assumptions
of KGEPL
Assumptions
as approved
in this Order
CUF(first six
months) % 65% 65%
CUF(remaining
period) % 80% 80%
Useful Life Years 20 20
Tariff Period Years 13 13
2 Project Cost
Capital
Cost/MW Power Plant Cost
Rs
lakh/MW 2482.68 2482.68
3 Financial
Assumptions
Debt: Equity
Debt % 70% 70%
Equity % 30% 30%
Total Debt
Amount Rs lakh 1737.88 1737.88
Total Equity
Amount Rs lakh 744.80 744.80
Debt
Component
Loan Amount Rs lakh 1737.88 1737.88
Moratorium
Period years 0.00 0.00
Repayment Period
(incld.
Moratorium)
years 12.00 12.00
Interest Rate % 12.56% 12.54%
Equity
Component
Equity amount Rs lakh 744.80 744.80
Return on Equity
for first 10 years
(16% gross up
with MAT rate)
% p.a. 20.34% 20.34%
RoE Period Year 10.00 10.00
Return on Equity
11th year onwards
(16% gross up
with Income tax
rate)
24.47% 24.47%
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 36 of 44
Sl.
No.
Assumption
Head Sub-Head Sub-Head (2) Unit
Assumptions
of KGEPL
Assumptions
as approved
in this Order
Weighted average
of ROE 22.40% 22.40%
Discount Rate
(equiv. to WACC) 10.55% 10.54%
4 Financial
Assumptions
Fiscal
Assumptions
Income Tax % 34.61% 34.61%
MAT Rate (for
first 10 years) % 21.34% 21.34%
80 IA benefits Yes/No Yes Yes
Depreciation
Depreciation
Rate(power plant) % 5.83% 5.83%
Depreciation Rate
13th year onwards % 2.50% 2.50%
Years for 5.83%
depreciation rate 12 12
5 Working
Capital
O&M Charges O&M Charges Months 1 1
Maintenance
Spare
(% of O&M
expenses) 15.00% 15.00%
Receivables for
Debtors
Receivables for
Debtors Months 2 2
Interest On
Working
Capital
Interest On
Working Capital % 13.06% 13.04%
6 Operation and
Maintenance
Opening Opening 165.09 165.09
Total O and M
Expenses
Escalation
Total O and M
Expenses
Escalation
% 5.72% 2.97%
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 37 of 44
Sl.
No.
Assumption
Head Sub-Head Sub-Head (2) Unit
Assumptions
of KGEPL
Assumptions
as approved
in this Order
7 Others
Amount of Waste
to be delivered
per day
Tonne 180.00 180.00
Tipping Fees to
be received by
Developer from
Corporation
Rs./Tonne 308.00 308.00
Annual Tipping
Fees Collection in
first year
Rs. lakh 131.53 131.53
Annual Tipping
Fees Collection
Second year
onwards
Rs. lakh 161.88 161.88
Tipping Fees
escalation over 20
years
% - -
Revenue from
sale of by-
products first year
Rs. lakh 10.68 10.68
Revenue from
sale of by-
products second
year
Rs. lakh 13.14 13.14
4.18. Tariff Rate and Other Conditions
4.18.1. Based on the parameters, assumptions and methodology outlined in earlier paragraphs,
the Commission has determined the tariff over the Useful Life of the Project as Rs 5.49
per kWh, which shall be applicable over a period of 20 years. The computations are
shown in Annexure-1 of this Order.
4.18.2. The above tariff shall be applicable for supply of electricity from the MSW Power Project
of KGEPL for supply to any Distribution Licensee in Maharashtra, subject to the
conditions set out below:
a) The tariff and structure shall be firm, and will not vary with exchange rate variations
or on account of changes in performance parameters.
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 38 of 44
b) The tariff determined in this Order shall be exclusive of taxes and duties on
generation and sale of electricity from the Project as may be levied by the appropriate
Government, which shall be allowed as pass-through on actually incurred basis.
c) In case any capital subsidy or grant from the Central or State Government or their
agencies is available or availed by the Project in future, its benefit will have to be
passed on in accordance with Regulation 24 of the RE Tariff Regulations, 2015.
d) The technology risk and MSW fuel supply availability risk will be borne by KGEPL.
4.18.3. Accordingly, the risk of sub-optimal syngas generation and consequent lower electricity
generation cannot be passed on to the Distribution Licensee(s) at a later stage. Similarly,
the benefit of excess generation over and above the normative CUF of 80% considered
for the tariff determination in this Order shall be available to KGEPL. The tariff for such
excess generation shall be the same as determined in this Order.
4.18.4. The performance parameters of this MSW Project shall be monitored by MEDA on a
quarterly basis, and be compiled and submitted to the Commission in an annual report for
each year.
4.18.5. The Commission notes that KGEPL has already made a request to the Maharashtra State
Electricity Distribution Co. Ltd (MSEDCL) for entering into an EPA with it. MSEDCL
has sought additional documents from KGEPL along with details of the Project-specific
Tariff approved by the Commission.
4.18.6. KGEPL may enter into an EPA with any Distribution Licensee in Maharashtra for the
Tariff Period of 20 years applicable to its MSW Project for the sale of power, in
accordance with Clause 6.4(1)(ii) of Tariff the Policy, 2016 (under which procurement of
all power produced by WTE Plants in the State by Distribution Licensee(s) is
mandatory). KGEPL shall submit a copy of the EPA to the Commission as soon as it is
entered into. The other terms and conditions of EPA such as rebate, late payment
surcharge, taxes and duties, etc. shall be in accordance with the RE Tariff Regulations,
2015.
4.18.7. In accordance with Regulations 4.1 and 4.2 of the MERC (Renewable Purchase
Obligation, its Compliance and Implementation of REC framework) Regulations, 2016,
the energy procurement from this MSW Power Project at the tariff determined in this
Order will be eligible for meeting the Renewable Purchase Obligation target of the
Distribution Licensee.
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 39 of 44
5. SUMMARY OF COMMISSION’S DIRECTIVES AND RULINGS
5.1.1. The Commission hereby determines the levelised Tariff for the said MSW-based power
Plant of KGEPL as Rs 5.49 per kWh, which shall be applicable over a period of 20
years.
5.1.2. KGEPL is directed to submit the details of such subsidy as and when sanctioned by
MNRE. The Commission also directs the Maharashtra Energy Development Agency
(MEDA), which is the State Nodal Agency, to inform the Commission and the concerned
Distribution Licensee of any such grant or subsidy if and when it is provided to KGEPL.
The treatment of any such grant or subsidy received in future shall be in accordance with
Regulation 24 of the RE Tariff Regulations. Further, specific provisions for recovery of
any such grant or subsidy by the Distribution Licensee (if availed by KGEPL), reflecting
the relevant provisions of Regulation 24, shall be incorporated in the Energy Purchase
Agreement (EPA) between KGEPL and the concerned Distribution Licensee.
5.1.3. Distribution Licensee entering into an EPA with KGEPL shall verify this claim of not
having availed accelerated depreciation benefit after the accounts of KGEPL for the 1st
year of operation are audited. The Distribution Licensee shall pass on the benefit to
consumers if accelerated depreciation is actually availed by KGEPL. Further, provisions
reflecting the Regulations in this regard for passing on the benefit of accelerated
depreciation (if availed by KGEPL) shall be incorporated in the EPA.
5.1.4. The Commission directs that performance parameters of this MSW Project shall be
monitored by MEDA on a quarterly basis and to be compiled and submitted to the
Commission on an annual basis in form of an annual report.
5.1.5. KGEPL may enter into an EPA with any Distribution Licensee in Maharashtra for the
Tariff Period of 20 years applicable to its MSW Project for the sale of power, in
accordance with Clause 6.4(1)(ii) of Tariff the Policy, 2016 (under which procurement of
all power produced by WTE Plants in the State by Distribution Licensee(s) is
mandatory). KGEPL shall submit a copy of the EPA to the Commission as soon as it is
entered into. The other terms and conditions of EPA such as rebate, late payment
surcharge, taxes and duties, etc. shall be in accordance with the RE Tariff Regulations,
2015.
5.1.6. The MSW Project shall be treated as a “Must Run” Power Plant and shall not be subject
to Merit Order Despatch (MOD) principles till such time as the Commission stipulates or
specifies otherwise as per clause 16.3 of the MERC (Distribution Open Access)
Regulations, 2016.
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 40 of 44
5.1.7. In accordance with Regulations 4.1 and 4.2 of the MERC (Renewable Purchase
Obligation, its Compliance and Implementation of REC framework) Regulations, 2016,
the energy procurement from this MSW Power Project at the tariff determined in this
Order will be eligible for meeting the Renewable Purchase Obligation target of the
Distribution Licensee.
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 41 of 44
6. APPLICABILITY OF ORDER
The Project-specific Tariff determined in this Order for KEGPL’s MSW-based Project at
Kolhapur shall be applicable for 20 years from the COD of the Project.
The Petition of M/s Kolhapur Green Energy Pvt. Ltd in Case No. 87 of 2015 stands disposed of
accordingly.
Sd/- Sd/-
(Deepak Lad) (Azeez M. Khan)
Member Member
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 42 of 44
Appendix – 1
List of persons at the Technical Validation Session held on 10 September, 2015
Sr. No. Name Organisation
1. Shri Rohit Sharma KGEPL
2. Shri Paramvir singh KGEPL
3. Shri Ashok Mahendrakar KGEPL
4. Shri Harshad Patil KGEPL
5. Shri Surendra Pimparkhedkar World Institute for Sustainable Energy (WISE)
6. Shri M.M.Davare BEST Undertaking
7. Shri Mangesh Kharote BEST Undertaking
8. Shri V. K.Rokadpe BEST Undertaking
9. Shri A. W.Mahajan Maharashtra State Electricity Distribution Co.
10. Ms. Ambica Gupta Tata Power Co. Ltd. (TPC)
List of persons at the Technical Validation Session held on 9 December, 2015
Sr. No. Name Organisation
1. Shri Rohit Sharma KGEPL
2. Shri Ashok Mahendrakar KGEPL
3. Shri Surendra Pimparkhedkar WISE
4. Shri M.M.Davare BEST
5. Smt. Swati Mehendale TPC
6. Shri Ghanashyam Thakkar Reliance Infrastructure Ltd.
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 43 of 44
Appendix – 2
List of persons at the Public Hearing held on 10 June, 2016
Sr. No. Name Organisation
1. Shri Rohit Sharma KGEPL
2. Shri Balaji Iyer KGEPL
3. Shri Ashok Mahendrakar KGEPL
4. Shri Surendra Pimparkhedkar WISE
5. Shri Satadru Charkraborty WISE
6. Smt. Jitesh Nair Shapoorji Pallonji & Co. Ltd(SPCL)
MERC Order for determination of Tariff for 1.8 MW MSW project of KGEPL
MERC Order- Case No. 87 of 2015 Page 44 of 44
Annexure-1: Summary of Annual Fixed Charge and Determination of Levelised Tariff
Particulars Unit 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
FIXED COST
O&M Expenses Rs lakh
165.09
170.00
175.05
280.26
288.59
297.17
415.19
315.10
324.47
453.33
344.05
354.27
494.98
375.65
386.82
540.45
410.16
422.36
590.10
447.84
Depreciation Rs lakh 144.82 144.82 144.82 144.82 144.82 144.82 144.82 144.82 144.82 144.82 144.82 144.82 62.07 62.07 62.07 62.07 62.07 62.07 62.07 62.07
Interest on term loan Rs lakh
208.78
190.63
172.47
154.32
136.16
118.01
99.85
81.70
63.54
45.39
27.23
9.08 - - - - - - - -
Interest on working
Capital Rs lakh
16.86
15.99
15.86
17.95
17.90
17.86
20.25
17.81
17.80
20.45
18.50
18.53
19.83
17.39
17.87
21.51
18.85
19.37
23.34
20.44
Return on Equity Rs lakh
151.50
151.50
151.50
151.50
151.50
151.50
151.50
151.50
151.50
151.50
182.24
182.24
182.24
182.24
182.24
182.24
182.24
182.24
182.24
182.24
Total Fixed Cost Rs lakh
687.06
672.94
659.70
748.85
738.97
729.36
831.62
710.93
702.13
815.49
716.84
708.94
759.11
637.35
648.99
806.26
673.32
686.03
857.74
712.59
Net Energy
generation MU
9.15
10.09
10.09
10.09
10.09
10.09
10.09
10.09
10.09
10.09
10.09
10.09
10.09
10.09
10.09
10.09
10.09
10.09
10.09
10.09
Per unit Fixed Cost Rs/kWh
7.51
6.67
6.54
7.42
7.32
7.23
8.24
7.04
6.96
8.08
7.10
7.03
7.52
6.32
6.43
7.99
6.67
6.80
8.50
7.06
OTHER INCOME
Income from Tipping
Fee Rs lakh 131.53 161.88 161.88 161.88 161.88 161.88 161.88 161.88 161.88 161.88 161.88 161.88 161.88 161.88 161.88 161.88 161.88 161.88 161.88 161.88
Income from sale of
byproducts Rs lakh 10.68 13.14 13.14 13.14 13.14 13.14 13.14 13.14 13.14 13.14 13.14 13.14 13.14 13.14 13.14 13.14 13.14 13.14 13.14 13.14
Total Other Income Rs lakh 142.21 175.02 175.02 175.02 175.02 175.02 175.02 175.02 175.02 175.02 175.02 175.02 175.02 175.02 175.02 175.02 175.02 175.02 175.02 175.02
Per Unit Other
Income Rs/kWh 1.55 1.73 1.73 1.73 1.73 1.73 1.73 1.73 1.73 1.73 1.73 1.73 1.73 1.73 1.73 1.73 1.73 1.73 1.73 1.73
Per unit Tariff Rs/kWh
5.96
4.93
4.80
5.69
5.59
5.49
6.51
5.31
5.22
6.35
5.37
5.29
5.79
4.58
4.70
6.26
4.94
5.06
6.77
5.33
Levelised Tariff Rs/kWh 5.49
ADD Levellised
benefit Rs/kWh 0.52
Tariff net of ADD
Benefit Rs/kWh
4.97