Awarded Physical Development Projects - Prime & Sub - 2011 (Rev. 11/22/11)
Project Contractor
Date
of
Award
AwardAmount
MWBE
Amount
Sub
Contractor
Sub Award
Amount
Sub MWBE
AmountProjected Bpt
Workers %
Projected
Minority
Workers %
ONR FencingQuality FencingPeekskill, NY 01/03/11 $13,510.00
Engineers
Welding (AA
MBE)
Bridgeport, Ct. $4,500.00 $4,500.00 100.00% 100.00%
Columbus
School HVAC
Phase II
DiRienzoMechanical(WBE) NewHaven, Ct. 01/20/11 $397,440.00 $397,440.00 0.00% 20.00%
A.B. Electric (AAMBE) Windsor,Ct. $24,000.00 $24,000.00 0.00% 100.00%
MNB14611C -
Boiler
Replacement
at Producto
Southport
Contracting
(WBE)
Bridgeport, Ct. 01/25/11 $149,900.00 $149,900.00 33.00% 33.00%
CPMEnvironmental(AA MBE)
Seymour, Ct. $23,900.00 $23,900.00 50.00% 50.00%
A & R Electric
(Hispanic MBE)
Bridgeport, Ct. $4,200.00 $4,200.00 0.00% 0.00%
Edgerton Inc.Monroe, Ct. $7,200.00 0.00% 0.00%Davis & Davis
Const.
Bridgeport, Ct. $5,000.00 100.00% 100.00%
8/3/2019 Awarded Physical Development Projects for 2011 Only - Prime Sub Rev 11-22-11 (2)
2/24
Awarded Physical Development Projects - Prime & Sub - 2011 (Rev. 11/22/11)
Project Contractor
Date
of
Award
AwardAmount
MWBE
Amount
Sub
Contractor
Sub Award
Amount
Sub MWBE
AmountProjected Bpt
Workers %
Projected
Minority
Workers %
COB168111 -Pleasure
Beach Water
Taxi
BTT MarineEast Boston,Mass. 03/02/11 $518,000.00 0.00% 0.00%
Resource
Services (AA
MBE) $63,516.00 $63,516.00 100.00% 100.00%
KTM Electrical(WBE) Orange,Ct. $53,950.00 $53,950.00 0.00% 33.00%
COB169111 -
New Vaults
City Hall Annex
Merritt
Contractors
Bridgeport, Ct. 03/23/11 $523,000.00 33.00% 33.00%
Engineers
Welding (AA
MBE)
Bridgeport, Ct $85,700.00 $85,700.00 75.00% 100.00%
DeRienzoMechanical
(WBE) NewHaven, Ct. $43,140.00 $43,140.00 33.00% 33.00%
MacKenziePainting (WBE)Stratford, Ct. $27,400.00 $27,400.00 tba tba
East CoastMasonrySeymour, Ct $59,800.00 0.00% 0.00%
8/3/2019 Awarded Physical Development Projects for 2011 Only - Prime Sub Rev 11-22-11 (2)
3/24
Awarded Physical Development Projects - Prime & Sub - 2011 (Rev. 11/22/11)
Project Contractor
Date
of
Award
AwardAmount
MWBE
Amount
Sub
Contractor
Sub Award
Amount
Sub MWBE
AmountProjected Bpt
Workers %
Projected
Minority
Workers %
County Electric
Bridgeport, Ct. $18,600.00 0.00% 0.00%
RJB ContractingTorrington, Ct. $67,970.00 0.00% 20.00%
COB170113 -
Columbus
School Phase3 Abatement
Oscar'sAbatement
(Hispanic MBE)Hartford, Ct. 03/24/11 $1,117,496.00 $1,117,496.00 50.00% 100.00%
DedicatedIndustries (AAMBE)New Haven, Ct. $95,000.00 $95,000.00 0.00% 80.00%
MNB149112 -
Exhaust Fan
Police
Headquarters
Carl TechMilford, Ct. 04/07/11 $8,600.00 50.00% 0.00%
Jordan Electric(AA MBE)
Bridgeport, Ct $1,290.00 $1,290.00 n/a n/a
COB170113 -
Columbus
School Phase
3 - General
Trades
Merritt
Contractors
Bridgeport, Ct. 04/19/11 $687,000.00 33.00% 33.00%
8/3/2019 Awarded Physical Development Projects for 2011 Only - Prime Sub Rev 11-22-11 (2)
4/24
Awarded Physical Development Projects - Prime & Sub - 2011 (Rev. 11/22/11)
Project Contractor
Date
of
Award
AwardAmount
MWBE
Amount
Sub
Contractor
Sub Award
Amount
Sub MWBE
AmountProjected Bpt
Workers %
Projected
Minority
Workers %
Engineers
Welding (AA
MBE)
Bridgeport, Ct. $21,200.00 $21,200.00 100.00% 100.00%
Jordan Electric
(AA MBE)
Bridgeport, Ct $20,500.00 $20,500.00 100.00% 100.00%
ADE Const. (AA
MBE)Bridgeport, Ct. $25,500.00 $25,500.00 0.00% 50.00%
Unity Prevention
(AA MBE)
Bridgeport, Ct. $29,205.00 $29,205.00 0.00% 100.00%
Phoenix Builders(WBE) Oxford,Ct. $110,500.00 $110,500.00 n/a n/a
COB170113 -Columbus
School Phase
3 Painting
C & G PaintingNew York, NewYork 04/20/11 $224,922.00 n/a n/a
JHP IndustrialSupply (AA MBE)Syracuse, NY $24,760.00 $24,760.00 n/a n/a
AbracadabraPainting (WBE)
Mamaroneck, NY $97,736.00 $97,736.00 0.00% 100.00%
8/3/2019 Awarded Physical Development Projects for 2011 Only - Prime Sub Rev 11-22-11 (2)
5/24
Awarded Physical Development Projects - Prime & Sub - 2011 (Rev. 11/22/11)
Project Contractor
Date
of
Award
AwardAmount
MWBE
Amount
Sub
Contractor
Sub Award
Amount
Sub MWBE
AmountProjected Bpt
Workers %
Projected
Minority
Workers %
COB143101 -
Citywide
Streetscape -
Madison Ave.
(North to
Harral)
G. Pic
Bridgeport, Ct 05/16/11 $447,366.00 75.00% 30.00%
ADE Ladscaping
& Construction
(AA MBE)
Bridgeport, Ct $142,050.00 $142,050.00 33.00% 66.00%
COB16611C -Roof
Replacement -
Engine 12
AlliedRestoration EastHartford, Ct. 05/23/11 $94,460.00 30.00% 67.00%
Jordan Electric
(AA MBE)
Bridgeport, Ct. $16,000.00 $16,000.00 n/a n/a
ASAEnvironmentalProducts (WBE)
Stonington, Ct. $18,000.00 $18,000.00 n/a n/aCOB172115 -
Burroughs
Library Boiler &
Chiller
Southport
Contracting
(WBE) Bpt., Ct. 05/11/11 $469,900.00 $469,900.00 33.00% 33.00%
EES (AA MBE)Trumbull, Ct. $28,194.00 $28,194.00 0.00% 100.00%
8/3/2019 Awarded Physical Development Projects for 2011 Only - Prime Sub Rev 11-22-11 (2)
6/24
Awarded Physical Development Projects - Prime & Sub - 2011 (Rev. 11/22/11)
Project Contractor
Date
of
Award
AwardAmount
MWBE
Amount
Sub
Contractor
Sub Award
Amount
Sub MWBE
AmountProjected Bpt
Workers %
Projected
Minority
Workers %
MNB14211CR -
Siding &
Gutters -
Fairchild
Wheeler
Ground's
Keeper's
House
Leake BuildersOxford, Ct 06/03/11 $16,510.00 0.00% 0.00%
YumblaConstruction(MBE)Wallingford, Ct $2,500.00 $2,500.00 0.00% 100.00%
Hartford LumberCompany (WBE)Hartford, Ct. $5,302.00 $5,302.00 n/a n/a
111 -
Cardinal
Sheehan
Center -
Overhead
Door
Willco SalesFairfield, Ct. 06/07/11 $6,500.00
Wallco Sales(WBE)Fairfield, Ct. $2,800.00 $2,800.00 0.00% 0.00%
CDB250114 -
Cardinal
Sheehan
Center
Joe R. Masonry(Hispanic MBE)Monroe, Ct. 06/14/11 $11,320.00 $11,320.00 60.00% 60.00%
8/3/2019 Awarded Physical Development Projects for 2011 Only - Prime Sub Rev 11-22-11 (2)
7/24
Awarded Physical Development Projects - Prime & Sub - 2011 (Rev. 11/22/11)
Project Contractor
Date
of
Award
AwardAmount
MWBE
Amount
Sub
Contractor
Sub Award
Amount
Sub MWBE
AmountProjected Bpt
Workers %
Projected
Minority
Workers %
Advanced
CleaningConcepts (AA
MBE)
Bridgeport, Ct. $680.00 $680.00 75.00% 100.00%
CDB256114 -
Cardinal
Sheehan
Center -
Shower Heads
Joe R. Masonry(Hispanic MBE)Monroe, Ct. 06/14/11 $8,700.00 $8,700.00 50.00% 100.00%
Advanced
CleaningConcepts (AA
MBE)
Bridgeport, Ct. $525.00 $525.00 75.00% 100.00%
COB175115 -
Wilbur
CrossPkg. 02 -
Abatement &
Demo
Enviroguard,LLCSeymour, Ct. 06/30/11 $650,000.00 15.00% 50.00%
CPMEnvironmental(AA MBE)Trumbull, Ct. $97,500.00 $97,500.00 50.00% 60.00%
R.E.D.Technologies(WBE)Bloomfield, Ct. $30,000.00 $30,000.00 n/a n/a
8/3/2019 Awarded Physical Development Projects for 2011 Only - Prime Sub Rev 11-22-11 (2)
8/24
Awarded Physical Development Projects - Prime & Sub - 2011 (Rev. 11/22/11)
Project Contractor
Date
of
Award
AwardAmount
MWBE
Amount
Sub
Contractor
Sub Award
Amount
Sub MWBE
AmountProjected Bpt
Workers %
Projected
Minority
Workers %
Supreme Safety,Inc. (WBE)Warminster, PA $70,000.00 $70,000.00 n/a n/a
COB143101 -
Unit Prices -
Sidewalks in
Front of
Volleyball
Court in
Seaside park
G. Pic & Sons
(WBE)
Bridgeport, Ct. 07/01/11 $73,620.00 $73,620.00 80.00% 50.00%
NyborConstruction
(AA MBE)
Bridgeport, Ct. $4,425.00 $4,425.00 n/a n/a
COB143101 -
Unit Prices -
Corner of
Coleman &
Pequonnock
G. Pic & Sons
(WBE)
Bridgeport, Ct. 07/01/11 $27,660.00 $27,660.00 80.00% 50.00%
Nybor
Construction
(AA MBE)Bridgeport, Ct. $1,700.00 $1,700.00 n/a n/a
COB143101 -
Unit Prices -
ADA Ramps
G. Pic & Sons
(WBE)
Bridgeport, Ct. 07/01/11 $218,855.00 $218,855.00 80.00% 50.00%
Nybor
Construction
(AA MBE)
Bridgeport, Ct. $13,115.00 $13,115.00 n/a n/a
8/3/2019 Awarded Physical Development Projects for 2011 Only - Prime Sub Rev 11-22-11 (2)
9/24
Awarded Physical Development Projects - Prime & Sub - 2011 (Rev. 11/22/11)
Project Contractor
Date
of
Award
AwardAmount
MWBE
Amount
Sub
Contractor
Sub Award
Amount
Sub MWBE
AmountProjected Bpt
Workers %
Projected
Minority
Workers %
COB143101 -Unit Prices -
Park Ave.
Sidewalks
G. Pic & Sons
(WBE)
Bridgeport, Ct. 07/01/11 $463,824.00 $463,824.00 80.00% 50.00%
Nybor
Construction
(AA MBE)
Bridgeport, Ct. $27,850.00 $27,850.00 n/a n/a
CDB249113 -
Demolitions -
291 HarriettSt., 131
Caroline St. &
578
Beechwood
Ocean TraceWatertown, ct 07/06/11 $134,579.00 25.00% 25.00%
CPMEnvironmental(AA MBE)Seymour, Ct. $28,066.00 $28,066.00 15.00% 80.00%
Balestrieri & Sons(WBE) Trumbull,Ct. $27,000.00 $27,000.00 0.00% 0.00%
COB175115 -
Wilbur Cross
ADA Pkg.
16Electrical
Conn. ElectricalNew Haven, Ct. 07/18/11 $775,624.00 40.00% 60.00%
TF Electric (AAMBE) New
Haven, Ct. $199,500.00 $199,500.00 0.00% 100.00%
8/3/2019 Awarded Physical Development Projects for 2011 Only - Prime Sub Rev 11-22-11 (2)
10/24
Awarded Physical Development Projects - Prime & Sub - 2011 (Rev. 11/22/11)
Project Contractor
Date
of
Award
AwardAmount
MWBE
Amount
Sub
Contractor
Sub Award
Amount
Sub MWBE
AmountProjected Bpt
Workers %
Projected
Minority
Workers %
Leo
Construction
(AA MBE)
Bridgeport, Ct. $33,210.00 $33,210.00 n/a n/a
COB174115
Discovery
Magnet
Playscape
Pat CorsettiContractingMamoroneck,NY 07/19/11 $133,000.00 0.00% 75.00%
Peggy Payne &Assos. (WBE)Hawthorne, NY $31,837.00 $31,837.00 0.00% 0.00%
COB143101 -
Citywide
Streetscape
Unit Prices-
Esplanades on
Commerce Dr.
G.Pic & Sons
(WBE)
Bridgeport, Ct. 07/21/11 $86,018.00 $86,018.00 80.00% 50.00%
Nybor
Construction
(AA MBE)Bridgeport, Ct. $5,650.00 $5,650.00 n/a n/a
CDB249113 -
Demo 45
Revere,1563
East Main,
Deforest Ave.
Cherry Hill NorthBranford, Ct. 07/22/11 $91,700.00 0.00% 33.00%
TLC Services (AAMBE) Monroe, Ct. $29,300.00 $29,300.00 0.00% 80.00%
8/3/2019 Awarded Physical Development Projects for 2011 Only - Prime Sub Rev 11-22-11 (2)
11/24
Awarded Physical Development Projects - Prime & Sub - 2011 (Rev. 11/22/11)
Project Contractor
Date
of
Award
AwardAmount
MWBE
Amount
Sub
Contractor
Sub Award
Amount
Sub MWBE
AmountProjected Bpt
Workers %
Projected
Minority
Workers %
CDB 253114 -
Toilet
Renovation -
392 Prospect
St.
SouthportContracting
(WBE)
Bridgeport, Ct. 07/27/11 $19,160.00 $19,160.00 0.00% 0.00%
Davis & Davis
Construction
(AA MBE)
Bridgeport, Ct. $1,900.00 $1,900.00 100.00% 100.00%
CDB252114 -
Hall
NeighborhoodRoof
DME
ConstructionOldfield, NY 08/01/11 $7,910.00 0.00% 100.00%
Logan & Logan(AA MBE)Ansonia, Ct. $1,200.00 $1,200.00 n/a n/a
Hartford LumberCompany (WBE)Hartford, Ct. $1,100.00 $1,100.00 n/a n/a
COB143101 -Citywide
Streetscapes -
Unit Prices -
South Main St.
& Whiting
G. Pic & Sons
(WBE)
Bridgeport, Ct. 08/01/11 $93,556.00 $93,556.00 80.00% 50.00%
Nybor
Construction
(AA MBE)
Bridgeport, Ct. $6,110.00 $6,110.00 n/a n/a
8/3/2019 Awarded Physical Development Projects for 2011 Only - Prime Sub Rev 11-22-11 (2)
12/24
Awarded Physical Development Projects - Prime & Sub - 2011 (Rev. 11/22/11)
Project Contractor
Date
of
Award
AwardAmount
MWBE
Amount
Sub
Contractor
Sub Award
Amount
Sub MWBE
AmountProjected Bpt
Workers %
Projected
Minority
Workers %
COB143101 -Citywide
Streetscape -
Unit Prices -
Gilman St.
Sidewalks
G. Pic & Sons
(WBE)
Bridgeport, Ct. 08/01/11 $99,013.00 $99,013.00 80.00% 50.00%
Nybor
Construction
(AA MBE)
Bridgeport, Ct. $6,000.00 $6,000.00 n/a n/a
COB175115 -
Cross School
ADA Alteration -
Sitework Pkg.
DallingConstructionStratford, Ct. 08/02/11 $563,323.00 30.00% 30.00%
A & JConstruction(Hispanic MBE)Brookfield, Ct. $54,089.00 $54,089.00 0.00% 85.00%
Resource
Services (AAMBE)
Bridgeport, Ct. $4,625.00 $4,625.00 100.00% 100.00%
Engineers
Welding (AA
MBE)
Bridgeport, Ct. $21,867.00 $21,867.00 100.00% 100.00%
Logan & Logan(AA MBE)Ansonia, Ct. $8,241.00 $8,241.00 n/a n/a
8/3/2019 Awarded Physical Development Projects for 2011 Only - Prime Sub Rev 11-22-11 (2)
13/24
Awarded Physical Development Projects - Prime & Sub - 2011 (Rev. 11/22/11)
Project Contractor
Date
of
Award
AwardAmount
MWBE
Amount
Sub
Contractor
Sub Award
Amount
Sub MWBE
AmountProjected Bpt
Workers %
Projected
Minority
Workers %
COB175115 -Wilbur Cross -
Painting Pkg.
ProfessionalPainting (WBE)New Haven, Ct 08/04/11 $61,700.00 $61,700.00 0.00% 50.00%
Valentine Repairs(AA MBE) NewHaven, Ct $9,500.00 $9,500.00 n/a n/a
COB175115 -
Wilbur Cross -
Fire Protection
Davis-UlmerEastLongmeadow,Mass 08/10/11 $259,000.00 tbd tbd
JHP Supply (AAMBE) Syracuse,NY $38,850.00 $38,850.00 n/a n/a
JC Smith (WBE)Syracuse, NY $38,850.00 $38,850.00 n/a n/a
CDB249113 -
Additional
Demos
PrimroseConstruction
(Hispanic MBE)
Bridgeport, Ct. 08/17/11 $91,825.00 $91,825.00 0.00% 50.00%
EES (AA MBE)Trumbull, Ct. $32,300.00 $32,300.00 100.00% 100.00%
CDB255114R -
Hall
NeighborhoodHouse - HVAC
Jordan Electric
(AA MBE)Bridgeport, Ct. 08/18/11 $26,050.00 $26,050.00 50.00% 50.00%
8/3/2019 Awarded Physical Development Projects for 2011 Only - Prime Sub Rev 11-22-11 (2)
14/24
Awarded Physical Development Projects - Prime & Sub - 2011 (Rev. 11/22/11)
Project Contractor
Date
of
Award
AwardAmount
MWBE
Amount
Sub
Contractor
Sub Award
Amount
Sub MWBE
AmountProjected Bpt
Workers %
Projected
Minority
Workers %
Celco Inc.
Bridgeport, Ct $18,675.00 0.00% 25.00%
COB180127 -
Knowlton Park
Phase One
Anthony Julain
R.R.
Bridgeport, Ct. 08/18/11 $1,089,110.00 25.00% 25.00%
ADE
Landscaping
(AA MBE)Bridgeport, Ct. $170,000.00 $170,000.00 50.00% 75.00%
T. Arduini (WBE)
Bridgeport, Ct. $251,000.00 $251,000.00 75.00% 50.00%
COB175115 -
Wilbur Cross -
Drywall Pkg.
Epifano BuldersMilford, Ct. 08/30/11 $430,000.00 0.00% 0.00%
Aries
Contracting (AA
MBE)
Bridgeport, Ct $70,000.00 $70,000.00 25.00% 25.00%
MCM Acoustics(AA MBE)Hartford, Ct. $152,000.00 $152,000.00 0.00% 0.00%
8/3/2019 Awarded Physical Development Projects for 2011 Only - Prime Sub Rev 11-22-11 (2)
15/24
Awarded Physical Development Projects - Prime & Sub - 2011 (Rev. 11/22/11)
Project Contractor
Date
of
Award
AwardAmount
MWBE
Amount
Sub
Contractor
Sub Award
Amount
Sub MWBE
AmountProjected Bpt
Workers %
Projected
Minority
Workers %
COB143101 -Citywide
Streetscape
Unit Prices -
Central Ave.
G. Pic & Sons
(WBE)
Bridgeport, Ct. 08/31/11 $16,105.00 $16,108.00 80.00% 50.00%
Nybor
Construction
(AA MBE)
Bridgeport, Ct. $1,100.00 $1,100.00 n/a n/a
COB143101 -
CitywideStreetscape
Unit Prices -
Alanson St.
G. Pic & Sons
(WBE)
Bridgeport, Ct. 08/31/11 $93,558.50 $93,558.50 80.00% 50.00%
Nybor
Construction
(AA MBE)
Bridgeport, Ct. $6,250.00 $6,250.00 n/a n/a
COB143101 -
Citywide
Streetscape
Unit Prices -
333 State St.
G. Pic & Sons
(WBE)
Bridgeport, Ct. 08/31/11 $72,297.50 $72,297.50 80.00% 50.00%
Nybor
Construction
(AA MBE)
Bridgeport, Ct. $4,750.00 $4,750.00 n/a n/a
CDB249113 -
Additional
Demos
Ct. Dismantling
Bridgeport, Ct. 08/31/11 $52,466.00
8/3/2019 Awarded Physical Development Projects for 2011 Only - Prime Sub Rev 11-22-11 (2)
16/24
Awarded Physical Development Projects - Prime & Sub - 2011 (Rev. 11/22/11)
Project Contractor
Date
of
Award
AwardAmount
MWBE
Amount
Sub
Contractor
Sub Award
Amount
Sub MWBE
AmountProjected Bpt
Workers %
Projected
Minority
Workers %
EES, Inc. (AAMBE)Trumbull, Ct. $15,000.00 $15,000.00 75.00% 75.00%
COB143101 -
Citywide
Streetscape
Unit Prices -
Remington &
Dover
G. Pic & Sons
(WBE)
Bridgeport, Ct. 08/31/11 $389,555.50 $389,555.50 80.00% 50.00%
NyborConstruction
(AA MBE)
Bridgeport, Ct. $24,780.00 $24,780.00 n/a n/a
COB143101 -
Citywide
Streetscape
Unit Prices -
Fishing Pier
G. Pic & Sons
(WBE)
Bridgeport, Ct. 09/02/11 $90,430.00 $90,430.00 80.00% 50.00%
Nybor
Construction(AA MBE)
Bridgeport, Ct. $5,925.00 $5,925.00 n/a n/a
COB143101 -
Citywide
Streetscape
Unit Prices -
Carroll &
Ordinance
G. Pic & Sons
(WBE)
Bridgeport, Ct. 09/02/11 $59,930.00 $59,930.00 80.00% 50.00%
8/3/2019 Awarded Physical Development Projects for 2011 Only - Prime Sub Rev 11-22-11 (2)
17/24
Awarded Physical Development Projects - Prime & Sub - 2011 (Rev. 11/22/11)
Project Contractor
Date
of
Award
AwardAmount
MWBE
Amount
Sub
Contractor
Sub Award
Amount
Sub MWBE
AmountProjected Bpt
Workers %
Projected
Minority
Workers %
Nybor
Construction
(AA MBE)
Bridgeport, Ct. $3,920.00 $3,920.00 n/a n/a
COB179116 -
Longfellow
Asbestos
Abatement &
Demo
AAIS, Inc. WestHaven, Ct 09/07/11 $418,425.00 25.00% 50.00%
Premier
Construction
(AA MBE)
Bridgeport, Ct. $63,800.00 $63,800.00 80.00% 80.00%
Premier
Enterprises (AA
WBE)
Bridgeport, Ct. $64,000.00 $64,000.00 100.00% 100.00%
CDB249113 -
Demo -
Additional
Quotes
******(partial waive)
StamfordWrecking
Trumbull, Ct 09/07/11 $30,400.00 50.00% 50.00%
Midway Trucking(WBE) NorthBranford, Ct $7,900.00 $7,900.00 0.00% 0.00%
Total Fence(WBE) NewHaven, Ct. $1,925.00 $1,925.00 0.00% 0.00%
8/3/2019 Awarded Physical Development Projects for 2011 Only - Prime Sub Rev 11-22-11 (2)
18/24
Awarded Physical Development Projects - Prime & Sub - 2011 (Rev. 11/22/11)
Project Contractor
Date
of
Award
AwardAmount
MWBE
Amount
Sub
Contractor
Sub Award
Amount
Sub MWBE
AmountProjected Bpt
Workers %
Projected
Minority
Workers %
COB075115 -Wilbur Cross
School -
Plumbing &
HVAC
SuperiorMechanicalWallingford, Ct 09/15/11 $910,000.00 25.00% 25.00%
R.K. Insulation(AA MBE)Hartford, Ct $136,500.00 $136,500.00 0.00% 50.00%
Superior ServiceGroup (WBE)Cheshire, Ct $140,000.00 $140,000.00 n/a n/a
COB175115 -
Wilbur Cross
School -
Windows
Massey Plate &GlassBranford, Ct 09/16/11 $528,000.00 0.00% 10.00%
Nybor
Constructio (AA
MBE)
Bridgeport, Ct $79,200.00 $79,200.00 n/a n/a
MasseyArchitecturalSystems (WBE)Branford, Ct $135,404.00 $135,404.00
COB175115 -
Wilbur Cross
School -
Flooring
Spectrum FloorsCheshire, Ct 09/25/11 $223,865.00 20.00% 20.00%
8/3/2019 Awarded Physical Development Projects for 2011 Only - Prime Sub Rev 11-22-11 (2)
19/24
Awarded Physical Development Projects - Prime & Sub - 2011 (Rev. 11/22/11)
Project Contractor
Date
of
Award
AwardAmount
MWBE
Amount
Sub
Contractor
Sub Award
Amount
Sub MWBE
AmountProjected Bpt
Workers %
Projected
Minority
Workers %
Nybor
Construction
(AA MBE)
Bridgeport, Ct. $33,000.00 $33,000.00 n/a n/a
Garsan Corp(WBE)Watertown, Ct $25,000.00 $25,000.00 n/a n/a
JJ Curran & Sons(WBE) Albany,NY $7,894.00 $7,894.00 0.00% 0.00%
COB201128 -
Washington
Park Splash
Pad
ConcreteCreations newHaven, Ct 10/05/11 $118,000.00
Nybor
Construction
(AA MBE)
Bridgeport, Ct $19,470.00 $19,470.00 n/a n/a
M.E. O'Brien(WBE)Medfield, Mass $28,355.00 $28,355.00 n/a n/a
COB16611C -
Engine 7/11
Roof
Replacement
AlliedRestoration EastHartford, Ct. 10/19/11 $134,400.00 20.00% 65.00%
8/3/2019 Awarded Physical Development Projects for 2011 Only - Prime Sub Rev 11-22-11 (2)
20/24
Awarded Physical Development Projects - Prime & Sub - 2011 (Rev. 11/22/11)
Project Contractor
Date
of
Award
AwardAmount
MWBE
Amount
Sub
Contractor
Sub Award
Amount
Sub MWBE
AmountProjected Bpt
Workers %
Projected
Minority
Workers %
Jordan Electric
(AA MBE)
Bridgeport, Ct $20,160.00 $20,160.00 100.00% 100.00%
ASAEnvironmentalProducts(Hispanic WBE)Stonington, Ct. $20,160.00 $20,160.00 n/a n/a
CDB249113 -
Demos -Additional
Quotes
Ocean TraceDemolitionWatertown, Ct. 10/31/11 $54,422.00 0.00% 33.00%
CPMEnvironmental(AA MBE)Seymour, Ct $8,162.00 $8,162.00 100.00% 100.00%
Balestrieri & Sons(WBE) Trumbull,Ct $8,004.00 $8,004.00 33.00% 66.00%
COB20912A -
Washington
Park
Improvements
ConcreteCreations NewHaven, Ct. 11/08/11 $182,900.00 0.00% 0.00%
8/3/2019 Awarded Physical Development Projects for 2011 Only - Prime Sub Rev 11-22-11 (2)
21/24
Awarded Physical Development Projects - Prime & Sub - 2011 (Rev. 11/22/11)
Project Contractor
Date
of
Award
AwardAmount
MWBE
Amount
Sub
Contractor
Sub Award
Amount
Sub MWBE
AmountProjected Bpt
Workers %
Projected
Minority
Workers %
NyborConstruction
(AA MBE)
Bridgeport, Ct $40,178.00 $40,178.00 n/a n/a
M.E. O'Brien(WBE)Medfield, Mass $15,000.00 $15,000.00 n/a n/a
COB178116R -
BurroughLibrary Roof
Replacement -
Rebid
GreenwoodIndustries, Inc.Worcester,Mass. 11/22/11 $1,013,000.00
Costar Metal &Iron Services (AAMBE) Bethel,Ct. $75,500.00 $75,500.00 0.00% 0.00%
Imperial RubbishRemoval (AA
MBE)Yalesville, Ct. $105,642.00 $105,642.00 0.00% 100.00%
Ace Mechanical(AA MBE)Waterbury, Ct. $27,645.00 $27,645.00 0.00% 100.00%
PremierEnterprises KM,LLC (AA WBE)Bridgeport, Ct. $46,320.00 $46,320.00
8/3/2019 Awarded Physical Development Projects for 2011 Only - Prime Sub Rev 11-22-11 (2)
22/24
Awarded Physical Development Projects - Prime & Sub - 2011 (Rev. 11/22/11)
Project Contractor
Date
of
Award
AwardAmount
MWBE
Amount
Sub
Contractor
Sub Award
Amount
Sub MWBE
AmountProjected Bpt
Workers %
Projected
Minority
Workers %
NyborConstruction (AAWBE) Bridgeport,Ct. $89,430.00 $89,430.00 n/a n/a
8/3/2019 Awarded Physical Development Projects for 2011 Only - Prime Sub Rev 11-22-11 (2)
23/24
Awarded Physical Development Projects - Prime & Sub - 2011 (Rev. 11/22/11)
Project Contractor
Date
of
Award
AwardAmount
MWBE
Amount
Sub
Contractor
Sub Award
Amount
Sub MWBE
AmountProjected Bpt
Workers %
Projected
Minority
Workers %
Award
Total $14,477,905.50 Sub Contractor Total $3,876,452.00Prime MWBE
Award Totals $4,137,916.50 Sub MWBE Totals $3,699,207.00
Calculated on
11/22/11 Prime MWBE % 28.58%
Sub MWBE % of
the Total Sub
Contracts 95.43%
(15) WBE Amount $2,882,552.00
Sub MWBE % of
the Total Prime
Awards 25.55%
(5) MBE Amount $1,255,391.00
Sub WBE Total
Amounts $1,262,257.00
(1) AA MBE Amount $26,050.00
Sub WBE % of the
Total Sub
Contracts 32.56%
Sub WBE % of the
Total Prime
Awards 8.72%
Sub MBE Totals
Amounts $2,500,950.00
Sub MBE % of the
Total Sub
Contracts 64.52%
Sub MBE % of the
Total Prime
Awards 17.28%
Sub AA MBE Total
Amounts $2,440,161.00
Sub AA MBE % of
the Total Sub
Contracts 62.95%
Sub AA MBE % of
the Total Prime
Awards 16.86%
8/3/2019 Awarded Physical Development Projects for 2011 Only - Prime Sub Rev 11-22-11 (2)
24/24
Awarded Physical Development Projects - Prime & Sub - 2011 (Rev. 11/22/11)
Project Contractor
Date
of
Award
AwardAmount
MWBE
Amount
Sub
Contractor
Sub Award
Amount
Sub MWBE
AmountProjected Bpt
Workers %
Projected
Minority
Workers %
keys:
Not awarded to low
bidder, because they
failed to comply with
the City's MBE
Ordinance
*****Grantedwaiver throughGood FaithEfforts
WBE = CertifiedWoman OwnedBusiness
MBE = CertifiedMinority OwnedBusiness
AA MBE =Certified AfricanAmericanOwned Business
MBV = MinorityBusinessViolation
DBV = DavisBacon Violation
Bold Type=Bpt
Based
Businesses