25
Assembly, Integration & Verification 2015 SKA Engineering Meeting Richard Lord 11 November 2015

Assembly, Integration & Verification 2015 SKA Engineering Meeting Richard Lord 11 November 2015

Embed Size (px)

Citation preview

Page 1: Assembly, Integration & Verification 2015 SKA Engineering Meeting Richard Lord 11 November 2015

Assembly, Integration & Verification2015 SKA Engineering Meeting

Richard Lord11 November 2015

Page 2: Assembly, Integration & Verification 2015 SKA Engineering Meeting Richard Lord 11 November 2015

• About the AIV Consortium• Current Status of Major Milestones

• Roll-Out Planning• Integration & Verification Planning• Product Hand-Over Planning• Test Procedure Planning• MeerKAT Precursor Integration Planning

• Risks

Overview

Page 3: Assembly, Integration & Verification 2015 SKA Engineering Meeting Richard Lord 11 November 2015

AIV Consortium Member Organisations

Page 4: Assembly, Integration & Verification 2015 SKA Engineering Meeting Richard Lord 11 November 2015

Element Project Manager: Peter Hekman

Element Systems Engineer: David Bolt

Architecture Group: Gie Han Tan

Project Scientist: Tyler Bourke

Operations Planning Group: Antonio Chrysostomou

SKA Office Contacts

Page 5: Assembly, Integration & Verification 2015 SKA Engineering Meeting Richard Lord 11 November 2015

# Stage 1: Milestone Description Due Date

1 t0 Nov 2013

2 t0 + 12w Jan 2014

3 Verification Requirements Apr 2014

4 Roll-Out Plan (Draft) Jun 2014

5 Input to Re-Baselining Exercise Sep 2014

6 PDR Submission Nov 2014

7 PDR Closure Feb 2015

Major Milestones - Stage 1

PDR Baseline completed in eB.

Page 6: Assembly, Integration & Verification 2015 SKA Engineering Meeting Richard Lord 11 November 2015

Major Milestones - Stage 2

# Stage 2: Milestone Description Due Date1 Kick-off Apr 20152 Telescope Preliminary I&V Plan Jul 20153 SEMP and PMP Alignment Jun 20154 Product Hand-Over Checklist Jul 20155 Updated Cost Model Aug 20156 MeerKAT Precursor ICDs Aug 20157 Telescope Roll-Out Plan (Next Release) Sep 20158 Telescope Test Procedures (Draft) Dec 20159 Precursor Integration Plan and ICDs Mar 2016

10 Telescope Detailed I&V Plan Jun 201611 CDR Data Pack Finalisation (Element CDR) Dec 201612 Telescope AIV Resource Plan Mar 201713 Telescope Test Procedures (Final) Apr 201714 CDR Data Pack Update (for System CDR) May 201715 CDR Submission (for System CDR) Jul 201716 CDR Closure (for System CDR) Oct 2017

Page 7: Assembly, Integration & Verification 2015 SKA Engineering Meeting Richard Lord 11 November 2015

• Forms the basis for the delivery of products and planning of integration & verification activities.

• Considers:– Sequencing of implemented functionality– Scale: How many Dishes / Stations deployed and when– Integration of MeerKAT Precursor into SKA1 MID

• Sequential process – early retirement of risks• Achieved by specifying “Array Releases”

Roll-Out Planning

Page 8: Assembly, Integration & Verification 2015 SKA Engineering Meeting Richard Lord 11 November 2015

How hard can it be?

“Getting to AR1” Session:• Today (Wednesday):

12h30 – 15h00, Breakout 2 (Merlot)

• Friday:8h30 onwards, Breakout 2 (Merlot)

Page 9: Assembly, Integration & Verification 2015 SKA Engineering Meeting Richard Lord 11 November 2015

• Described by:– Date

• When all required products have been installed, i.e. not necessarily integrated into Telescope System

– Number of Dishes / Stations– Array Capability → Determines back-end Element functionality– Key Engineering Goals– Science Capability

• Used by AIV Team and Science Validation Team– Verification of Level-1 (System Level) Requirements– Validation of Science Requirements

Released Array

Page 10: Assembly, Integration & Verification 2015 SKA Engineering Meeting Richard Lord 11 November 2015

V-Diagram

Operational Concept Description

Telescope Requirements Specification

Element Requirements Specification

Component Specification

Design & Manufacture

ComponentAIV

ElementAIV

TelescopeAIV

ScienceValidation

Component Verification

Element Verification

System Verification

User Requirements Validation

Time

Design

Verifi

catio

n

Performed withArray Releases

Page 11: Assembly, Integration & Verification 2015 SKA Engineering Meeting Richard Lord 11 November 2015

• Multiple ITFs– At Element Level or lower

• All over the world. Rely heavily on simulators/emulators. No AIV involvement.

– At System Level• End-to-End line-up of Level-2 products. Possibly one ITF at each Host Country.

– On Site• Conceptually possible to have an on-site ITF, e.g. in the form of an Engineering Array.

• System-Level ITF used for:– System Level Design Qualification– Verification of interfaces between Level-2 products– Debugging, troubleshooting, development work, etc– Testing of hardware/firmware/software upgrades during Constr. Phase– Knowledge transfer (between contractors, engineers, AIV Team, etc)

• Laboratory Verification Event (LVE)– Verification of end-to-end functionality and performance required for Array Release

1

Integration Test Facility (ITF)

Page 12: Assembly, Integration & Verification 2015 SKA Engineering Meeting Richard Lord 11 November 2015

SKA1 MID Roll-Out Plan

Sit

eIn

teg

rati

on

Tes

t F

acili

ty (

ITF

)

LabIntegration Events

Dish Receiver, SaDT,CSP, TM, SDP

T0 + 12 T0 + 24 T0 + 48 T0 + 60T0 + 36

LVE

AR4AR3AR2AR11Dish

2Dishes

4Dishes

LVE2 LVE3 LVE4

DishPRR

Number of SKA1 Dishes deployed

MeerKAT Precursor

Front-End IntegrationINFRA, SaDT, DISH

QualityGate

Page 13: Assembly, Integration & Verification 2015 SKA Engineering Meeting Richard Lord 11 November 2015

SKA1 LOW Roll-Out Plan

Sit

eIn

teg

rati

on

Tes

t F

acili

ty (

ITF

)

LabIntegration Events

Station Beamformer and Digitiser, SaDT,CSP, TM, SDP

T0 + 12 T0 + 24 T0 + 48 T0 + 60T0 + 36

LVE

AR4AR3AR2AR11Station

2Stations

4Stations

LVE2 LVE3 LVE4

LFAAPRR

Number of SKA1 Stations deployed

Front-End IntegrationINFRA, SaDT, LFAA

QualityGate

Page 14: Assembly, Integration & Verification 2015 SKA Engineering Meeting Richard Lord 11 November 2015

SKA1 MID Dish Roll-Out

T0 T0 + 1 T0 + 2 T0 + 3 T0 + 4Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

0

50

100

150

200

250

Start Construction SKA1

Start Early Science

End Construction SKA1

MeerKAT Science Programme

Start Full Science

MeerKAT Integration

New SKA1_MID Dishes

MeerKAT Dishes

1st Dish

DishPRR

T0 + 5

421 3LVE

1

Array Releases

2

3

4

= 8 Dishes

= 64 Dishes

= 128 Dishes

= 133 + 64 Dishes

LVE = Lab Verification Event

Page 15: Assembly, Integration & Verification 2015 SKA Engineering Meeting Richard Lord 11 November 2015

SKA1 LOW Station Roll-Out

T0 T0 + 1 T0 + 2 T0 + 3 T0 + 4Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

0

100

200

300

400

500

Start Construction SKA1

Start Early Science

End Construction SKA1

Start Full Science

1st Station

1

Array Releases

2

3

4

= 16 Stations

= 64 Stations

= 256 Stations

= 512 Stations

T0 + 5

4

2

1

3

LVE

= Laboratory Verification

Event

LVE

Page 16: Assembly, Integration & Verification 2015 SKA Engineering Meeting Richard Lord 11 November 2015

Software Release ManagementS

ite

Inte

gra

tio

n T

est

Fa

cilit

y (I

TF

)

T0 + 12 T0 + 24 T0 + 48 T0 + 60T0 + 36

LVE

AR4AR3AR2AR1

Arb

itra

ry L

oc

atio

n

Laboratory Integration Environment(Software verified against real hardware and firmware)

Development Environment(Software qualified against simulators)

On-Site Environment(Software acceptance tested with production hardware and firmware)

Software Releases

Software Releases

Issues

No Change-Control Under Change-Control

Issues

Page 17: Assembly, Integration & Verification 2015 SKA Engineering Meeting Richard Lord 11 November 2015

Integration & Verification Planning

I&V Plan

Verification Requirements

Roll-Out Plan

Contains:· Integration Events· Verification Events· Resources· ...

· System Requirements

· Hosting Agreements· Telescope Verification Plans· Early-Science Plans· Commissioning Plans· SKAO Input· Consortia Input

1

3

2

· SKAO Input· Consortia Input

Page 18: Assembly, Integration & Verification 2015 SKA Engineering Meeting Richard Lord 11 November 2015

I&V Planning

Integration / Verification Event 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20SaDT.NSDNLab ver - DISH, CSP, TM, SDP I.Lab.1 *TM.TELMGMT - DISH.LMC I.Lab.2 * *TM.TELMGMT - SaDT.SAT.LMC I.Lab.3 *DISH Receiver - SaDT.SAT I.Lab.4 *TM.TELMGMT - CSP.LMC I.Lab.5 *SaDT.DDBHLab ver - CSP - DISH I.Lab.6 *DISH Receiver - CSP.CBF I.Lab.7 *TM.TELMGMT - SDP.LMC I.Lab.8 *CSP.CBF-SDP.Data Proc I.Lab.9 *Lab System Line up C&M I.Lab.10 *Lab System Line up Data I.Lab.11 *Lab System 4 input Verification V.Lab.2.1 * *INFRA - DISH I.D1.1 * * *SaDT.NSDN - TM / DISH I.D1.2 *TM.TELMGMT - SaDT.SAT.LMC I.D1.3 *TM.TELMGMT - DISH.LMC I.D1.4 *DISH Receiver - SaDT.SAT I.D1.5 *SaDT.NSDN - TM / CSP I.D1.6 *TM.TELMGMT - CSP.LMC I.D1.7 *SaDT.DDBH - CSP - DISH I.D1.8 *DISH Receiver - CSP.CBF I.D1.9 *2nd DISH Integration to INFRA, SaDT, CSP 2 Dish Integration * *INFRA Handover V.D1.1.1 *SaDT handover V.D1.1.2 *DISH Handover V.D1.1.3 *TM Handover V.D1.1.4 *CSP Handover V.D2.1.5 *Dish C&M V.D1.2.1 * *Freq range, Sensitivity V.D1.2.2 *RFI Detection V.D1.2.3 *Channelisation V.D2.2.1 *Basic Interferometry V.D2.2.2 * *Correlator Products V.D2.2.3 *Displays V.D2.2.4 *EMI / EMC V.D2.3.1 * * *Environmental V.D1.3.1 *4 DISH Integration to INFRA, SaDT, CSP 4 DISH Integration * * *SaDT.NSDN - TM / SDP I.D4.1 *TM.TELMGMT - SDP.LMC I.D4.2 *SaDT CSP-SDPInitial local link I.D4.3 * *CSP.CBF-SDP.Data Processor I.D4.4 *INFRA Handover V.D4.1.1 *SaDT handover V.D4.1.2 *DISH Handover V.D4.1.3 *TM Handover V.D4.1.4 *CSP Handover V.D4.1.5 *SDP Handover V.D4.1.6 *Channelisation V.D4.2.1 * *Basic Interferometry V.D4.2.2 * *Correlation Products V.D4.2.3 *Imaging V.D4.2.4 * *EMI / EMC V.D4.3.1 * *

Months since T0

Laboratory

Early Site, 1-2 Dishes

Site, 4 Dishes

• Integration Events• Verification Events

• Start date• Duration• Resources• Prerequisites

• Each event is a workpackage that can be project-managed

Page 19: Assembly, Integration & Verification 2015 SKA Engineering Meeting Richard Lord 11 November 2015

Product Hand-Over Planning

Objectives are to ensure that:• A well-defined development process was followed for the

product.• The product meets its technical specifications,

documented by Qualification Test Results (QTRs) and Acceptance Test Results (ATRs).

• The product can be supported and maintained after hand-over.

• The product is successfully installed on-site.• The logistic support development for the product is in

process.

What level of product integration is required from the AIV Contractor?

Page 20: Assembly, Integration & Verification 2015 SKA Engineering Meeting Richard Lord 11 November 2015

Installation, Integration, Verification

ShipmentReadiness

ReviewShip to Site

Responsibility reverts to OEM

Install on SiteIntegrate with

SKA1 Telescope System

System Hand-Over

OperateSKA1 Telescope

System

ProductHand-Over

Review

no

VerifySKA1

Telescope System

Product Hand-Over

no

yes

no

yes yes

Responsibility reverts to OEM

Resolve Issue

ProductHand-Over

Review

noResponsibility

reverts to OEM

ProductHand-Over

Review

noResponsibility

reverts to OEM

yes

yes

AIV Contractor Responsibility

Product Contractor Responsibility Operations Team Responsibility

Page 21: Assembly, Integration & Verification 2015 SKA Engineering Meeting Richard Lord 11 November 2015

Test Procedure Planning

Requirements

Verification Requirements

Verification Events

System

Test Procedures

Test Configurations

specified by

verified by

fulfilled at

employs

employs

formed by

Test EquipmentSystems Engineering Tool

Page 22: Assembly, Integration & Verification 2015 SKA Engineering Meeting Richard Lord 11 November 2015

MeerKAT Integration Planning

Page 23: Assembly, Integration & Verification 2015 SKA Engineering Meeting Richard Lord 11 November 2015

MeerKAT Integration: ECP 150006

• Replace MeerKAT’s Receivers (known as “Digitisers”) with SKA1_MID’s Receivers

• Replace MeerKAT’s TFR distribution to each MeerKAT Dish with SKA1_MID’s STFR distribution

• Does not consider replacement of MeerKAT’s Feeds

Limited space inside SDCL-Band Receiver (“Digitiser”)

25 U rack space

Page 24: Assembly, Integration & Verification 2015 SKA Engineering Meeting Richard Lord 11 November 2015

• Roll-Out Plan not yet mandatory for Design Consortia• Support of the System-Level ITF not yet mandatory for

contractors• Late release of software/firmware functionality (TM, CSP,

SDP) during Construction Phase– Knock-on effect on Array Releases – Integration Test Facility would reduce the risk of on-site issues

• Underestimating scale and complexity of MeerKAT Precursor Integration

• Participating organisations not delivering on their contributions on time, or to an acceptable level of quality

• Staff continuity

Risks

Page 25: Assembly, Integration & Verification 2015 SKA Engineering Meeting Richard Lord 11 November 2015

Thank You