Queens April/May
2015
Bill de Blasio DDC Website
Mayor www.nyc.gov/buildnyc
Dr. Feniosky Peña-Mora DDC Video
Commissioner www.nyc.gov/webuild
Installation of New Bulkheads, Water Main, Sanitary and Storm
Sewers, Roadway Reconstruction, Sidewalks, Traffic and Street
Lighting (West 11th, West 12th and West 13th Roads between Cross Bay Boulevard and the shoreline of Jamaica Bay) Project # HWQ1182A
The New York City Department of Design and Construction (NYC
DDC) is managing a construction project to install new
bulkheads, water main, sanitary and storm sewers, roadway
reconstruction, new streets and sidewalks, traffic and street
lighting on West 11th, West 12th and West 13th Roads in the
Broad Channel section of Queens. This project has an
anticipated completion date of June, 2017.
Proposed Work Schedule April/May 2015
Continue installation of bulkhead at West 11th Road.
Continue installation of bulkhead at West 12th Road.
Continue installation of bulkhead at West 13th Road.
Work Completed to Date
Cofferdam construction completed on West 11th, West
12th and West 13th Roads.
Installation of new valves at Cross Bay Boulevard and
West 11th, West 12th, and West 13th Roads.
Located underground water and sewer service to
homes on West 11th, West 12th and West 13th Roads.
Construction of Cofferdam at West 12 t h Road
Water Service Interruption
During the course of this project, there wil l be
temporary water service interruptions. To allow water
mains replacement, the existing water service must
be shut off by closing the valves at either end of the
section. Advance notice will be given for all planned
interruptions. Water service will be restored everyday
by the end of the work shift. If additional shut downs
are required you will receive a new notice daily unti l
work is completed.
Community Impacts
During construction hours, you can expect the following:
Increased levels of dust, noise and heavy equipment
Vehicular travel lane closures will be required
Detours (Warning signs will be posted in advance)
Parking and driveway restrictions
Signs will be posted within the affected areas
Pedestrian access to buildings will be maintained
Property Damage
You are advised to inform the Resident Engineer (RE) or the
Contractor of any property damage that you may have; if the
contractor fails to respond within 10 days, you should inform the
DDC Borough Director in writing. If you intend to file a claim you
must do so within 90 days of the occurrence with the New York
City Comptroller’s Office.
Community Construction Liaison (CCL)
The DDC has assigned Ms. Fern Weinreich of LiRo
Group, as the Community Construction Liaison (CCL)
for this project. Please contact Ms. Weinreich for
any project related inquiries/concerns you may have:
Phone: (646)300-4351 Email: [email protected] Field Office: 59 West 12th Road, Broad Channel, Queens, NY 11693
Newsletter Distribution Newsletters for this project are distributed regularly within the project area and to the Broad Channel Civic Association.