Upload
shawn-harrington
View
223
Download
0
Tags:
Embed Size (px)
Citation preview
April 6, 2012 1
CEQAEnergy Division First Friday Forum
April 6, 2012 2
What Does the CEQA Team Do?• Environmental review pursuant to the
California Environmental Quality Act Transmission | Telco | Water/Sewer |Natural Gas Storage | Section 851 Divestitures
• Construction monitoring after projects are approved
• Interagency initiatives– Desert Renewable Energy Conservation Plan– Renewable Energy Transmission Initiative– Solar Programmatic Environmental Impact Statement– Renewable Energy Policy Group
April 6, 2012 3
What is CEQA?• CEQA requires state and local agencies to:
– evaluate and disclose to decision makers and the public the environmental impacts of their actions; and
– avoid or mitigate those impacts, if feasible• CEQA is triggered when a public agency
must take discretionary action when reviewing a proposed project
• CPUC CEQA cases are challenged at the CA Supreme Court
April 6, 2012 4
CEQA Objectives
• Make public and disclose environmental impacts of projects
• Mitigate or avoid environmental damage• Encourage public participation• Disclose reasons for project approval if the
project creates unavoidable impacts
April 6, 2012 5
CEQA Impact Areas
• Aesthetics• Agricultural Resources• Air Quality (GHG)• Biological Resources• Cultural Resources• Geology/Soils• Hazards & Hazardous Materials• Hydrology/Water Quality
• Land Use/Planning• Mineral Resources• Noise• Population/Housing• Public Services• Recreation• Transportation/Traffic• Utilities/Service Systems
Social and Economic
April 6, 2012 6
El Casco Fossil Find
April 6, 2012 7
Impacts of the “Whole of the Action”
• Environmental review must consider impacts of related or connected actions that could result from approval of the proposed project
• For example: If a utility proposes a substation that could result in additional power plants, the Commission must assess the impacts from the power plants at the level of detail available
• Although the Commission may assess impacts from connected actions, it does not permit the power plants
April 6, 2012 8
Mitigation Measures
BIO – California Tiger Salamander Exclusion Fencing• Work sites are surveyed for CTS• Exclusion fencing is installed to prevent CTS from entering
and provides an exit if trapped within the fencing
April 6, 2012 9
Mitigation Measures
AIR – Fugitive Dust Control• Rumble strips prevent work trucks from tracking dirt onto
roadways and spreading noxious weeds into other areas• Other measures include wash stations between the working
area and the road and spraying the roads with a water truck
April 6, 2012 10
Environmental Documents
• Findings from the Initial Study of environmental impacts determines the type of document
• Negative Declaration (ND) – The project creates no significant impacts
• Mitigated Negative Declaration (MND)– The project creates significant impacts, but the
impacts can be avoided or mitigated
April 6, 2012 11
Environmental Documents
• Environmental Impact Report (EIR)– The project may cause significant impacts that
cannot be avoided or mitigated to a level that is less than significant
– Includes alternatives analysis– The environmentally superior alternative must be
chosen if feasible– Cost is not a factor unless economically infeasible
April 6, 2012 12
Joint Federal/State Documents
• The National Environmental Policy Act (NEPA) applies to Federal agencies
• The CPUC frequently produces joint CEQA/NEPA documents with federal agencies
• Memorandums of Understanding define each agency’s duties
• Agencies together produce a joint EIR/EIS but only make decisions for projects within their respective jurisdiction
April 6, 2012 13
Public Participation
• Scoping meetings allow the public to raise issues before environmental review begins
• Public notice is required when an application is filed and at important milestones
• The public has the opportunity to comment• CPUC responds to all public comments
April 6, 2012 14
Agency Coordination
• CA Dept. of Fish and Game
• US Fish and Wildlife Service
• US Forest Service• Bureau of Land
Management• Caltrans• Air Quality
Management Districts• CA Coastal Commission
• Army Corps Of Engineers
• Department of Water Resources
• State Historic Preservation Office
• Native American Heritage Commission
• State Water Resources Control Board
• State Lands Commission
April 6, 2012 15
CEQA at the CPUC
Two stages:• Project review and approval
– 6-12 months for Mitigated Negative Declaration– 1-2 years for Environmental Impact Report– Sunrise and Tehachapi: 2.5 years (both joint
CEQA/NEPA documents)
• Construction Monitoring– 1-5 years – Sunrise 6 years, Tehachapi 5+ years
April 6, 2012 16
Section 851 Divestures
• Sales, leasing, and transfer of utility assets• Divestiture of power plants; ownership
interest in shared facilities; watershed conservation lands; surplus property
• Entering into leases and granting easements -residential and commercial
• Streamlined Advice Letter pilot program for certain types of transactions
April 6, 2012 17
Transmission Project Review and Approval
Types of Applications• Certificate of Public Convenience and Necessity
(CPCN)– Transmission lines greater than or equal to 200 kV– Requires a review of need and cost
• Permit to Construct (PTC)– Power lines greater than 50kV and less than 200 kV– Substations greater than 50kV and less than 200 kV – Does not require a review of need and cost
• Need may become an issue if there are overriding considerations
April 6, 2012 18
Two Parallel Review Processes
• Completeness review• Agency Consultation• Notice of Preparation• Public Scoping Meeting• Draft EIR• Public Meeting • Public Comments• Final EIR
CEQA Review
Proponent’s Environmental Assessment
• Protest/Responses Filed• Prehearing Conference• Public Participation Hearing• Scoping memo• Evidentiary hearings
CPUC Proceeding
Application (PTC or CPCN)
April 6, 2012 19
One Final Approval Process
• Proposed and Alternate Decisions • Public Comment on PD and APD• CPUC vote to certify the environmental
document and approve the project• The document certification and project
approval can be done separately, but this is rare at the CPUC and common at other agencies
April 6, 2012 20
Mitigation Monitoring
• After project approval, staff manages construction monitoring through Environmental Monitors
• Mitigation Monitoring, Reporting and Compliance Program – Mitigation measures– Applicant proposed measures– Communication protocols
April 6, 2012 21
Mitigation Monitoring
• Staff grants a Notice to Proceed for each stage of construction
• Staff first ensures compliance with all permits, plans, mitigation measures, and applicant proposed measures
• Staff can issue a stop work order if a utility is out of compliance
April 6, 2012 22
Worker Environmental Awareness Program
• Anyone on the project site must first attend a WEAP training.
• Once trained, personnel place stickers on their hard hats to show compliance with WEAP.
April 6, 2012 23
Atascadero• PG&E project in San Luis Obispo County
– Replaces existing 70kV line with new conductor– Replaces light duty steel poles and lattice steel
towers – 15.5 miles
April 6, 2012 24
Atascadero
• Draft Environmental Review - 7 Months – PG&E filed application and Proponent’s
Environmental Assessment (PEA)– Application and PEA deemed complete– Initial Study to determine MND or EIR
• Public Review, Final Document - 6 Months – CPUC released Draft IS/MND and Notice of Intent
to adopt MND – Public review and comment– Final IS/MND
April 6, 2012 25
Atascadero
• Construction – Approximately 2.5 years– Notice to Proceed with approved work plans– Monitoring implementation of mitigation
measures
April 6, 2012 26
Atascadero
April 6, 2012 27
Atascadero
April 6, 2012 28
Atascadero
April 6, 2012 29
Lockhart (Water Valley) Substation NTPs
• SCE Project• San Bernardino County• Interconnects the 250 MW Abengoa Mojave Solar
Project • 220kV switching station
April 6, 2012 30April 6, 2012 CEQA Team First Friday Forum
Lockhart (Water Valley) Substation NTPs
April 6, 2012 31
Major Projects
April 6, 2012 32
Tehachapi Renewable Transmission Project
(TRTP)
April 6, 2012 33
Tehachapi Renewable Transmission Project
• Connects Tehachapi Wind Resource Area (TWRA) in Kern County to Los Angeles Basin
• Most of project is an upgrade of the 220 kV system to 500kV– Only 1 new right of way (ROW)
• Potential - 4500 MW, maybe more• 173 miles• 3 new substations and upgrades/work at 6 other
substations• 3 counties, 21 cities, multiple jurisdictions
April 6, 2012 34
April 6, 2012 35
Project Objectives
• Connect renewable energy (mostly wind) to the grid.• Kern County has applications for 1,000 MW of solar
in the western Mojave.
April 6, 2012 36
Application and Environmental Review
• SCE filed application in June 2007• Joint EIR (CEQA)/EIS (NEPA) with US Forest
Service– Line goes through Angeles Forest triggering NEPA
• Draft EIR/EIS released February 2009• Over 2,000 comments and 15 public meetings• Final EIR/EIS released October 2009
– 2 years, 4 months after application was filed
April 6, 2012 37
Alternative Analysis
• EIR/EIS considered 29 alternatives– Various routes– Different technologies– Different construction technologies
• While the proposed project went through the City of Chino Hills, at the request of the City, an alternative route was designed to avoid the city by going through Chino Hills State Park
April 6, 2012 38
CPCN DECISION
• CPUC Decision December 2009– 2.5 years after application was filed
• Decision did not approve the Chino Hills State Park alternative, but chose the proposed route along the existing Right of Way through the City of Chino Hills
• There was considerable opposition from the City of Chino Hills which filed an Application for Rehearing (appeal) to the decision– No resolution yet
April 6, 2012 39
Chino Hills
• City of Chino Hills filed suit against SCE stating the ROW was “overburdened”
• Suit failed in Superior Court and was rejected by Court of Appeals and State Supreme Court
April 6, 2012 40
Construction
• Construction started in April 2010 and is about 50% complete at this time, mostly in the north– Estimated completion Summer 2015– Originally 2013
• Wind generators are starting to connect to northern section of project
• SCE began building towers through Chino Hills, until the CPUC stopped construction in Chino Hills in November 2011 in response to community concerns
April 6, 2012 41
Tehachapi Wind Project
April 6, 2012 42
Chino Hills
• SCE and Chino Hills entered into an unsuccessful Alternative Dispute Resolution (ADR) process February 2012
• The Commission stay on construction in Chino Hills remains in effect while the Commission considers other possibilities
• Completion date may suffer more delay based on possible new alternatives for Chino Hills
April 6, 2012 43
Sunrise Powerlink
April 6, 2012 44
Sunrise
• In 2006, SDG&E proposed the Sunrise Powerlink– 150 miles from Imperial County to San Diego County
through Anza Borrego Desert State Park– 500/230 kV line– 500/230 kV substation
• Controversial project with 52 unmitigable significant impacts
• Required an extensive public engagement process
April 6, 2012 45
Existing Conditions Through Anza Borrego
• Existing view along SR78 towards Narrows Substation. Wood poles from an existing 69 kV line are also visible.
April 6, 2012 46
Simulation of Proposed Route Through ABDSP
• Visual simulation along SR78 towards Narrows Substation in ABDSP. The project would be located north of SR78 and the existing 69 kV line would be relocated underground.
April 6, 2012 47
Sunrise
• The CPUC prepared an 11,000 page joint EIR/EIS with BLM
• 27 fully analyzed alternatives, including non-park routes and non-wires
• In December 2008 the CPUC approved Environmentally Superior Southern Alternative– 123 miles– 127 mitigation measures– Route avoids Anza Borrego Desert State Park– Overall, less impactful than original proposal
• Project costs – $19 million environmental review, $1.9 billion to construct by June 2012
April 6, 2012 48
Approved Project Route
April 6, 2012 49
Construction
• 77 notices to proceed• 67 variances • SDG&E cited 11 times for non-Compliance• 2 Stop Work Orders Issued – 1 by CPUC and 1
by USFS
April 6, 2012 50
Construction Challenges
• Construction around cultural sites• Eagle nesting• Bighorn sheep lambing season
April 6, 2012 51
Construction Challenges• Construction in steep terrain• Helicopter construction for 237 out of 443 towers• 15-33 helicopters operating daily
Dropped tower outside of Plaster City Construction Yard during tower erection activities in Imperial County
April 6, 2012 52
Construction Challenges• Dropped air compressor near Kruetzkamp Construction
Yard. Hook system on the helicopter was found to be the cause of the incident and was removed from operation for evaluation
• Helicopter was fitted with an alternative hook system and continued operation the next day
April 6, 2012 53
Construction Challenges• 6 miles of 230 kV undergrounding in Alpine Blvd.
Business District
Vault excavation on Alpine Boulevard
April 6, 2012 54
Skycrane Tower Lift
April 6, 2012 55
Wire Installation Construction Activities
April 6, 2012 56
Conventional Tower Assembly in the Desert
April 6, 2012 57
Mountain Springs Grade (MSG) Construction
• MSG micropile drilling (left) and tower staging access pads (right) with barefoot banded gecko exclusionary fencing surrounding the temporary and permanent disturbance areas
April 6, 2012 58
Nighttime Construction at the S-2 Yard
April 6, 2012 59
Sunrise
Expected completion date: June 2012
April 6, 2012 60
For More Information on CEQA at the CPUC
• Public Utilities Code Section 1001• General Orders 131-D, 95-A, 96-B, 159-A, 69-C, 163-A• California Code of Regulations Title 14 section
15000 et seq.