ALLAGASH WILDERNESS WATERWAY

LOCK DAM OUTLET REPLACEMENT PROJECT SEPTEMBER 4TH – OCTOBER 4, 2018

www.maine.gov/allagash

Page 2: Allagash Wilderness WaterwayMATTHEW LAROCHE SUPERINTENDENT, AWW 207-695-3721 x3 matt.laroche@maine.gov

LOCK DAM IN THE EARLY 1900’S

Page 3: Allagash Wilderness WaterwayMATTHEW LAROCHE SUPERINTENDENT, AWW 207-695-3721 x3 matt.laroche@maine.gov

OLD OUTLET CULVERT SHOWING 30 FEET REPLACED IN 2012

Page 4: Allagash Wilderness WaterwayMATTHEW LAROCHE SUPERINTENDENT, AWW 207-695-3721 x3 matt.laroche@maine.gov

EXCAVATION STARTED ON SEPTEMBER 4TH

Page 5: Allagash Wilderness WaterwayMATTHEW LAROCHE SUPERINTENDENT, AWW 207-695-3721 x3 matt.laroche@maine.gov

DIGGING AROUND THE OLD STANDPIPE

Page 6: Allagash Wilderness WaterwayMATTHEW LAROCHE SUPERINTENDENT, AWW 207-695-3721 x3 matt.laroche@maine.gov

OLD CULVERT AND GRATE REMOVED AT INLET

Page 7: Allagash Wilderness WaterwayMATTHEW LAROCHE SUPERINTENDENT, AWW 207-695-3721 x3 matt.laroche@maine.gov

DIGGING THE TRENCH

Page 8: Allagash Wilderness WaterwayMATTHEW LAROCHE SUPERINTENDENT, AWW 207-695-3721 x3 matt.laroche@maine.gov

BYPASS SIPHON TO PROVIDE WATERFLOW DURING CONSTRUCTION

Page 9: Allagash Wilderness WaterwayMATTHEW LAROCHE SUPERINTENDENT, AWW 207-695-3721 x3 matt.laroche@maine.gov

FIRST THREE SECTIONS SET – TALLER SECTION SUPPORTS THE GATES

Page 10: Allagash Wilderness WaterwayMATTHEW LAROCHE SUPERINTENDENT, AWW 207-695-3721 x3 matt.laroche@maine.gov

CRANE USED TO SET PRECAST CONCRETE SECTIONS

Page 11: Allagash Wilderness WaterwayMATTHEW LAROCHE SUPERINTENDENT, AWW 207-695-3721 x3 matt.laroche@maine.gov

PRECAST CONCRETE DOWNSTREAM FROM THE GATES

Page 12: Allagash Wilderness WaterwayMATTHEW LAROCHE SUPERINTENDENT, AWW 207-695-3721 x3 matt.laroche@maine.gov

TOP SIDE OF THE GATES

Page 13: Allagash Wilderness WaterwayMATTHEW LAROCHE SUPERINTENDENT, AWW 207-695-3721 x3 matt.laroche@maine.gov

INSIDE THE PRECAST CULVERT LOOKING UPSTREAM TOWARDS THE GATES

Page 14: Allagash Wilderness WaterwayMATTHEW LAROCHE SUPERINTENDENT, AWW 207-695-3721 x3 matt.laroche@maine.gov

GATES INSTALLED

Page 15: Allagash Wilderness WaterwayMATTHEW LAROCHE SUPERINTENDENT, AWW 207-695-3721 x3 matt.laroche@maine.gov

OUTLET TIMBER SLUICE INSTALLED FOR FISH BARRIER

Page 16: Allagash Wilderness WaterwayMATTHEW LAROCHE SUPERINTENDENT, AWW 207-695-3721 x3 matt.laroche@maine.gov

WATER FLOWING THROUGH THE CULVERT –AHEAD OF SCHEDULEON 9/26/18

Page 17: Allagash Wilderness WaterwayMATTHEW LAROCHE SUPERINTENDENT, AWW 207-695-3721 x3 matt.laroche@maine.gov

INLET WITH JIMMY LEE – OWNER OF EMERY LEE CONSTRUCTION

Page 18: Allagash Wilderness WaterwayMATTHEW LAROCHE SUPERINTENDENT, AWW 207-695-3721 x3 matt.laroche@maine.gov

AERIAL VIEW SHOWING FLOW FROM THE OULET

Page 19: Allagash Wilderness WaterwayMATTHEW LAROCHE SUPERINTENDENT, AWW 207-695-3721 x3 matt.laroche@maine.gov

AERIAL VIEW OF INLET 10/5/18

Page 20: Allagash Wilderness WaterwayMATTHEW LAROCHE SUPERINTENDENT, AWW 207-695-3721 x3 matt.laroche@maine.gov

CONSTRUCTION TEAM

RON HUNT – DIRECTOR OF OPERATIONS AND MAINTENANCE, BUREAU OF PARKS & LANDS

DAVID RODRIGUES – DIRECTOR ENGINEERING & REALTY, BUREAU OF PARKS & LANDS

MATTHEW LAROCHE – SUPERINTENDENT, ALLAGASH WILDERNESS WATERWAY

CONSULTING ENGINEERS – PINNACLE HILL ENGINEERING, CANAAN, MAINE

PRECAST CONCRETE CONTRACTOR – AMERICAN CONCRETE, VEAZIE MAINE

CONSTRUCTION CONTRACTOR – EMERY LEE, MILLINOCKET, MAINE

Page 21: Allagash Wilderness WaterwayMATTHEW LAROCHE SUPERINTENDENT, AWW 207-695-3721 x3 matt.laroche@maine.gov

MATTHEW LAROCHESUPERINTENDENT, AWW

207-695-3721 [email protected]