Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
AFRICAN DEVELOPMENT BANK
ZAMBIA
LUSAKA SANITATION PROGRAM - CLIMATE RESILIENT SUSTAINABLE INFRASTRUCTURE PROJECT
APPRAISAL REPORT
OWAS DEPARTMENT June 2015
Publi
c D
iscl
osu
re A
uth
ori
zed
P
ubli
c D
iscl
osu
re A
uth
ori
zed
TABLE OF CONTENTS
Currency Equivalents .................................................................................................................. i Fiscal Year .................................................................................................................................. i
Weights and Measures ................................................................................................................ i Program Summary .................................................................................................................... iv
I – STRATEGIC THRUST AND RATIONALE ...................................................................... 1 1.1 Program linkages with country strategy and objectives ............................................. 1
1.2 Rationale for Bank’s involvement .............................................................................. 1 1.3 Donor Coordination .................................................................................................... 2
II – PROJECT DESCRIPTION ................................................................................................. 3 2.1 Project Objective......................................................................................................... 3
2.2 Technical solution retained and other alternatives explored ...................................... 4
2.3 Project Type ................................................................................................................ 5
2.4 Project Cost and Financing Arrangements ................................................................. 5 2.5 Project’s target area and population............................................................................ 7 2.6 Participatory process for project identification, design and implementation ............. 7 2.7 Bank Group experience and lessons reflected in program design .............................. 8
2.8 Program’s performance indicators .............................................................................. 8
III – PROGRAM FEASIBILITY .............................................................................................. 9
3.1 Economic and financial performance ......................................................................... 9 3.2 Environmental and Social Impacts ............................................................................. 9
IV – IMPLEMENTATION ..................................................................................................... 13 4.1 Implementation Arrangements ................................................................................. 13
4.2 Procurement Arrangements ...................................................................................... 13
4.3 Financial Management and Disbursement Arrangements ........................................ 13 4.5 Governance ............................................................................................................... 15 4.6 Sustainability ............................................................................................................ 15
4.7 Risk management ...................................................................................................... 16 4.8 Knowledge building .................................................................................................. 16
V – LEGAL INSTRUMENTS AND AUTHORITY .............................................................. 17 5.1 Legal instrument ....................................................................................................... 17
5.2 Conditions associated with Bank’s intervention ....................................................... 17 5.3 Compliance with Bank Policies ................................................................................ 18
VI – RECOMMENDATION ................................................................................................... 18
i
Currency Equivalents As of April 2015
Currency Unit = US Dollars
1 UA = USD 1.40
1 USD = ZMW 7.40
1 UA = ZMW 9.70
Fiscal Year January 1
st – December 31
st
Weights and Measures
1 metric tonne (t) = 2,205 lbs.
1 kilogramme (kg) = 2.205 lbs.
1 metre (m) = 3.281 ft.
1 kilometre (km) = 0.621 mile
1 square kilometre (km2) = 0.386 square mile
1 hectare (ha) = 0.01 km2
= 2.471 acres
ii
ACRONYMS AND ABBREVIATIONS
AfDB African Development Bank Group MGCD Ministry of Gender and Child Development
ADB African Development Bank NCB National Competitive Bidding
ARAP
Abridged Resettlement Action Plan
NUWSSP
National Urban Water Supply and
Sanitation Program
CCA Climate Change O&M Operation and Maintenance
CLTS
Community Led Total Sanitation
PID Project Implementing Department
CP Cooperating Partner RBCSP Result Based Country Strategy Paper
DFID Department For International
Development R-SNDP Revised Sixth National Development Plan
DHID Department of Housing and
Infrastructure Development SA Sustainability Agreement
EIB European Investment Bank SAG Sector Advisory Group
ESMP Environmental and Social Management
Plan SEA Strategic Environmental Assessment
GIZ German Agency for Technical
Cooperation SESA
Strategic Environmental and Social
Assessment
GRZ Government of Republic of Zambia SOMAP Sustainable Operation and Maintenance
Program
HH House Hold TA Technical Assistance
KfW German Government through the
German Bank for Development UA Unit of Account
ICB
International Competitive Bidding UNICEF United Nations Children's Fund
IMS Information Management System USAID United States Agency for International
Development
IPR Implementation Progress Results USD US dollar
IWRM Integrated Water Resources Management WASHE Water, Sanitation and Hygiene Education
JASZ Joint Assistance Strategy for Zambia WB World Bank
JICA Japan International Cooperation Agency WSS Water Supply and Sanitation
LCC Lusaka City Council Water Sector Cooperating Partner Group
LWSC Lusaka Water and Sewerage Company Zambia Environmental Management
Agency
MCC Millennium Challenge Corporation WSCPG
MCDMCH Ministry of Community Development,
Mother and Child Health ZEMA
MDGs Millennium Development Goals
M&E Monitoring and Evaluation
MLGH Ministry of Local Government and
Housing
MMEWD Ministry of Mines, Energy and Water
Development
MOE
Ministry of Education
MOF Ministry of Finance
MOH Ministry of Health
MOU Memorandum of Understanding
iii
Loan and Grant Information
Client’s Information
BORROWER: Republic of Zambia
EXECUTING AGENCY: Lusaka Water and Sewerage Company
Financing plan
Source Amount (UA) Amount (USD) Instrument
ADB 35.53 million 50 million Loan
WB 46.18 million 65 million Loan
GRZ/ LWSC 9.12 million 12.83 million Counterpart
Contribution
TOTAL COST 90.83 million 127.83 million
ADB’s key financing information
LOAN
Loan currency USD
Interest type Enhanced Variable Rate Spread Loan
Interest rate spread Floating Base Rate + Funding Margin + Lending
Spread
Funding Cost Margin 1
Lending Spread 60 basis points (0.60%)
Commitment fee None
Repayment Semi-Annual
Tenor 20 years
Grace period 5 years
EIRR (base case) 17.01%
Timeframe - Main Milestones (expected)
Project approval June 2015
Effectiveness November 2015
Completion December 2019
Last Disbursement Deadline December 2020
Last repayment December 2040
1 The six-month adjusted average of the difference between: (i) the refinancing rate of the Bank as to the borrowings
linked to 6-month LIBOR and allocated to all its floating interest loans denominated in USD; and (ii) 6-month LIBOR
ending on 30 June and on 31 December. This spread shall apply to 6-month LIBOR which resets on 1 February and on 1
August. The Funding Cost Margin shall be determined twice per year on 1 January for the semester ending on 31 December
and on 1 July for the semester ending on 30 June.
iv
Program Summary
1. Overview: The Lusaka Sanitation Program aims to increase access to sustainable sanitation
services to Lusaka’s residents especially the urban poor and strengthen Lusaka Water and Sewerage
Company’s (LWSC) capacity to manage sanitation services. The program aims to address one of
Zambia’s most binding constraints to economic growth through infrastructure investment in Lusaka,
the rapidly urbanizing capital.
2. The program cost is estimated at US$ 127.83 (equivalent UA 90.83 million), of which AfDB is
financing US$ 50 million (equivalent UA 35.53 million) or 39%, the World Bank 51%, and the
Government of the Republic of Zambia/ LWSC 10%. The program is expected to start in 2015 with a
duration of five years.
3. The program invests in (i) rehabilitated and newly constructed climate resilient sewerage
infrastructure, (ii) decentralized sanitation and hygiene promotion, (iii) support to Lusaka Water and
Sewerage Company, Lusaka City Council (LCC) and the regulator NWASCO for Institutional
Strengthening and Capacity Building including development of faecal sludge management guidelines
and a water and sanitation emergency preparedness disaster risk management plan. The program also
supports the Government of Zambia’s ongoing water sector reform efforts by strengthening sector
institutions. The main beneficiaries in Lusaka are the approximately 600, 000 residents in the project
area who will gain better health from improved environmental and sanitary conditions; especially
those in peri urban areas were most of the urban poor are residing. The beneficiaries will be involved
in the program through customer mobilization and sensitization campaigns and capacity building
initiatives. Indirectly, urban residents in the whole of Lusaka city will benefit from improved
performance of Lusaka Water and Sewerage Company in delivering water and sanitation services.
4. Needs Assessment: The program interventions aim to address a crisis in sanitation that is costing
Zambia 1.3% of GDP per year. Lusaka is worst affected by poor sanitation with annual outbreaks of
cholera, typhoid and dysentery. Rapid urbanization in Lusaka will lead to a doubling of the population
over the next 20 years (from 2.2 million to 4.9 million) exacerbating the problem. 70% of the city’s
population live in peri-urban areas and 90% rely on pit latrines, most of which are poorly constructed.
In addition, 60% of Lusaka’s water supply is from groundwater abstracted within the city, which is
vulnerable to pollution from leaking pit latrines. It is also estimated that at least 75% of the faecal
waste generated in the city is not adequately collected, treated and disposed of and ends up polluting
the environment and water supply sources. Addressing these various faecal waste flows will be the
primary focus of the program.
5. The Banks’ added value in supporting the program is built on its continued focus on (i) poverty
focused components (such as decentralised sanitation in high-density areas); (ii) improved public
health through hardware (investments) and highly cost effective software methodologies (sanitation,
environmental health and hygiene promotion), and (iii) collaborative partnerships and leveraging other
Cooperating Partner funds to increase investments in sanitation.
6. Knowledge management: The Bank will support the development of a monitoring system to
assist LWSC better understand sanitation management and also develop faecal sludge management
guidelines for better management of sludge. These knowledge products will contribute to the
country’s urban sanitation sub-sector in improving its performance as well as help the Bank to
replicate the good practice in other regional member countries. In relation to climate change, with
mounting international concern at the rising frequency and severity of natural hazards and disasters, in
part due to factors related to climate change, a Water and Sanitation Sector Emergency Preparedness
and Disaster Risk Management Plan will be developed to strengthen institutions, mechanisms and
capacities at all levels, in particular at the community level that can systematically contribute to
building resilience to hazards and disasters.
v
Results Based Logical Framework Country and Project Name: Republic of Zambia: Lusaka Sanitation Program
Project Purpose: To increase access to sustainable sanitation services to Lusaka’s residents especially the urban poor.
RESULTS CHAIN PERFORMANCE INDICATORS MEANS OF
VERIFICATION RISKS/MITIGATION MEASURES
Indicator (including CSI) Baseline (2014) Target
IMP
AC
T
Impact: Improved health and poverty alleviation for the urban poor due to sustainable and equitable access to improved sanitation
1. Reduced Under-five mortality rate per 1,000 live births in Zambia 87 in 2013 50 in 2030 National Census, living condition survey
- Stable macroeconomic framework
continued - Consistency in sector reforms
2. Population below poverty line 75% in 2013 20% in 2030
OU
TCO
MES
Outcome 1: Increased access to improved sanitation and hygiene facilities in Lusaka Province
1.1 No. of residents benefiting from improved sanitation facilities 63% (>50% female)
77% in 2020 (>50% female)
National Census, Living Conditions Monitoring Survey and NWASCO Sector Reports
Risk #1. Sewers and WWTPs are expensive and may be unaffordable to many customers. Mitigation. Balance willingness to pay, affordability and technology options. Sustained extensive sensitization campaigns and community participation at the design stage to mitigate such a risk. Tariff and affordability study undertaken
Outcome 2: Improved hygienic and environmental practices among residents of Lusaka city
2.1 Proportion of people practicing hygiene behaviour / sanitation
practices including hand washing (+50% women)
2.2 People served by adequate faecal sludge management systems
39.7% 0
67% in 2020 (>50% female) 360,000 in 2019
Outcome 3: Improved management, institutional capacity and sustainability of WSS services
3.1 Operation and maintenance recovery by LWSC 3.2 Percentage of sewerage blockage complaints addressed satisfactorily 3.3 LWSC sanitation monitoring system established
110% 50% No system
>150% by 2020 95% by 2020 Ready by 2019
NWASCO Sector Reports, quarterly and annual reports
OU
TPU
TS
Component 1- Climate resilient Sewerage Infrastructure Development 1.1 Construction/ Rehabilitation of climate resilient Sewer networks 1.2 Rehabilitation of Sewage Ponds and pump Stations
1.1.1 Length of climate resilient sewer networks rehabilitated/ newly constructed
1.1.2 Number of new connections to sewer in project area 1.2.1 Volume Wastewater treated per year (‘000 M3 cumulative)
0 0 2,018
72 km by 2020 8,000 by 2020 4,789 by 2020
NWASCO sector reports, LWSC quarterly progress reports
Risk #2. Delay in making connections to the rehabilitated and extended sewer network Mitigation. Sustained sanitation marketing and appropriate technology Connection works will be built into overall sewer laying contract, and connection charges recovered from sanitation bills. Revolving fund to be set up Risk #3. Poor coordination between different institutions involved in the implementation of some components at local level. Mitigation. An MOU signed among LWSC and LCC, on the cooperation for implementation of the hygiene and sanitation promotion component, detailing the roles each of the four institutions will play during the implementation of the Project. Risk #4. Delayed ESMP implementation Mitigation. Budgetary allocation for timely implementation and Government to include budgets for this Risk #5: The project may be exposed to future climate risks Mitigation: Development of WSS emergency preparedness and disaster risk management plan and design of climate resilient sewerage infrastructure
Component 2-Decentralised Sanitation and Hygiene Promotion 2.1 WASH strengthened 2.2 Climate resilient demonstration HH sanitation facilities 2.3 Provision of sanitation facilities in public institutions (schools, health centres, and markets) 2.3 Construction of climate resilient Feacal Sludge management systems
2.1.1 No. of people trained to improve hygiene behaviour or sanitation
practices under the project (cumulative) (+50% women) 2.1.2 No. of Trainer of Trainers trained for improved environmental and
sanitation practices
2.2.1 No. of climate resilient demonstration HH facilities 2.2.2 No. of gender sensitive and disabled able friendly sanitation and
hygiene facilities constructed in schools, public places & health centres
2.3.1 No. of Climate resilient Faecal sludge management facilities constructed & used
0 0 0 0 0
150,000 by 2020 250 (>50% female) by 2020 2,000 by 2020 100 double units by 2018 2 facilities by 2020
LCC Team Reports, LWSC quarterly
Component 3- Institutional Strengthening & Capacity Building 3.1 Strengthen LWSC Operation and maintenance of sewers 3.2 Enhanced institutional capacity of
LWSC/LCC Authorities to manage
Sanitation services 3.3 Improved LWSC gender mainstreaming 3.4. Climate Change adaptation plans 3.5 ESMP implemented
3.1.No. of sewage blockages resolved
3.2.1 No. of LWSC/LCC staff trained and supported in sector investment
framework, sanitation and environmental health (% of female staff) 3.3.1 No. of women and youth trained and supported in sanitation related
economic opportunities within the project
3.3.2 Gender Strategy prepared 3.4.1 Guideline for Faecal Sludge Management prepared
3.4.2 Water and Sanitation Sector Emergency Preparedness and Disaster
Risk Management Plan prepared 3.5.1 ESMP implemented
990 0 0 0 0 0 0 0
<100 (annual) by 2018 200 (% female) by 2018 Done by 2017 Done by 2017 Done by 2017 Completed by 2020
Quarterly and Annual Progress Reports
vi
KEY
AC
TIV
ITIE
S Activities INPUTS
1. Climate resilient Sewerage Infrastructure Development: Rehabilitation/ construction new climate resilient sewer networks, rehabilitation of sewage ponds 2.
Decentralised Sanitation and Hygiene Education: Delivery of sanitation, environmental and hygiene education; Construction of climate resilient demonstration institutional/public sanitation facilities and Promotion of Good hygiene practices, Feacal Sludge Management systems constructed, 3. Institutional Strengthening &
Capacity building: Training, development of FSM guidelines, WSS Sector Emergency Preparedness and Disaster Risk Management Plan, support to development of social inclusion and gender framework, ESMP implementation, 4. Program Management: Program Auditing; Technical Assistance; Office Equipment; various goods, procurement of vehicles; and Mid Term Review of the project.
Total Program Cost: USD 127.83 million (Eqv UA 90.83 mil) ADB loan: USD 50 million (equiv. UA 35.53 mil) World Bank: USD 65 million (equiv. UA 46.18 mil) GRZ/LWSC: USD 12.83 million (equiv. UA 9.12 mil)
vii
Program Timeframe
Board Approval
Publication of GPN
Signing
Effectiveness
Launch Mission ◊
Institutional Support
Strategic Environmental Social Assessment
Operationalise LWSC Gender Strategy
Training and Capacity Building ◊ ◊ ◊ ◊ ◊ ◊ ◊ ◊ ◊ ◊ ◊ ◊ ◊ ◊ ◊ ◊ ◊ ◊ ◊ ◊ ◊ ◊ ◊ ◊
HH sanitation surveys
WSS Sector Emergency Preparedness and
Disaster Risk Management Plan
Decen Sanitation & Hygiene Promotion
RfP/bidding & contract award
mobilisation, sensitization, supervison of sanitation works
Engineering Services Consultancy
RfP/bidding & contract award
Design, Tender Doc prep and Tendering
Supervison of Sewerage works
Feacal Sludge Management units
Bidding & contract award
Implementation
Sewerage Works
Bidding & contract award
Implementation
Defect Liability Period
Mid Term Review ◊
Financial Audit (siubmission) ◊ ◊ ◊ ◊ ◊
Program Completion ○
ZAMBIA: LUSAKA SANITATION PROGRAM: CLIMATE RESILIENT INFRASTRUCTURE IMPLEMENTATION SCHEDULE
4 6 8 10 12 6 81012
2015 2016 2017 2018
2 4 126 8 10 10 1222 4 6 8 12Activity
2 4
2020
2 4 6 8 10 122 4 6
2019
8 10
1
REPORT AND RECOMMENDATION OF THE MANAGEMENT TO THE BOARD OF
DIRECTORS ON A PROPOSED LOAN TO ZAMBIA FOR THE LUSAKA SANITATION
PROGRAM
Management submits the following Report and Recommendation for a proposed loan for USD 50
million on ADB terms to the Republic of Zambia to finance the Lusaka Sanitation Program.
I STRATEGIC THRUST AND RATIONALE
1.1 Program linkages with country strategy and objectives
1.1.1. The Government of the Republic of Zambia’s (GRZ’s) development agenda are articulated in the
National Vision 2030 and the Revised Sixth National Development Plan (R-SNDP: 2013-2016). The
National Sector Vision is for clean, safe water supply and sanitation for all by 2030. The R-SNDP has
the goal of increasing “accessibility to reliable safe water by all sectors of the economy in order to
enhance economic growth and improve the quality of life. Thus, the Lusaka Sanitation Program (LSP)
supports the GRZ’s development plan by improving sanitation services of the poor in order to effect
improvements in public health and raise dignity.
1.1.2. In conformity with the thrust of the R-SNDP, the Bank’s Country Strategy Paper (CSP) for
Zambia covering the period 2011-2015 focuses on two pillars: Pillar I - Supporting Economic
Diversification through Infrastructure Development; and Pillar II - Support to Economic and Financial
Governance with Private Sector Development and Capacity Building. The LSP interventions
operationalize both pillars of Zambia’s CSP as the provision and improvement of key infrastructure has
a direct impact on the economic wellbeing of the population (Pillar I). This is part of the national sector
portfolio of activities aimed at improving environmental health and part of GRZ priorities’ to address the
required major investments for rehabilitation and expansion of the infrastructure in the fast growing
urban and peri-urban areas of the major towns through which the private sector would also be involved
(Pillar II). In this way, the LSP is also well-aligned to the Bank’s twin goals of green growth and
promoting inclusive growth. The LSP is also in line with Zambia’s Integrated Water Resources
Management (IWRM) articulated in the National Water Policy of 2010 and the Water Resources
Management Act of 2011.
1.1.3. The LSP is aligned with the Bank’s Ten-year Strategy (2013-2022), IWRM Policy and Urban
Development Framework and seeks to help manage urban growth and develop sustainable climate
resilient urban infrastructure systems, particularly urban water, sanitation and waste management. It is
also in line with the Bank’s Gender Strategy by supporting the Lusaka Water and Sewerage Company
(LWSC) to develop strategies to create economic opportunities for women combined with an operational
document on Faecal Sludge Management (FSM), taking into consideration the gender role-played by
men and women to guide implementation of sanitation and hygiene education in the high density areas
of the capital.
1.2 Rationale for Bank’s involvement
1.2.1 The GRZ has been undertaking water sector reforms since the early 1990’s and considerable
progress has been made in improving access to improved water supply and improved sanitation.
Currently, 63% of Zambians have access to clean drinking water while 49% have access to adequate
sanitation as defined by UNICEF/WHO Joint Monitoring Program. The national long-term vision for
2030 is to reach 80% access to clean water by 2015 and 100% by 2030; 68% access to sanitation by
2015 and 90% by 2030; rehabilitation and reconstruction of sewerage facilities in all major towns and
cities; and 80% of waste collected and treated by 2030. Recent studies show the trend of national water
coverage (in both rural and urban areas) on a slow upward trend while that for sanitation coverage is
even slower. While the national and MDG targets for water supply may be met by 2015, at the current
2
rate, the targets for sanitation will likely be missed. There have not been significant investments
especially in sanitation and capacity constraints both at local and national level have hampered growth
of the sector. This intervention specifically addresses these and hence the need for further investments in
this particular area.
1.2.2 The program interventions aim to address a crisis in sanitation that is costing Zambia 1.3% of
GDP per year according to a recent World Bank (WB) report. Lusaka is worst affected by poor
sanitation with annual outbreaks of cholera, typhoid and dysentery. Rapid urbanization in Lusaka will
lead to a doubling of the population over the next 20 years (from 2.2 million to 4.9 million) exacerbating
the problem. 70% of the city’s population live in peri-urban areas and 90% rely on pit latrines, most of
which are poorly constructed. In addition, 60% of Lusaka’s water supply is from groundwater abstracted
within the city, which is vulnerable to pollution from leaking pit latrines. It is also estimated that at least
75% of the faecal waste generated in the city is not adequately collected, treated, disposed of and ends
up polluting the environment and water supply sources. Addressing these various faecal waste flows will
be the primary challenge of the program.
1.2.3 The Bank’s comparative advantage in financing the LSP is a combination of its comprehensive
experience to sustainable service provision in Zambia and the region. The Bank has continued to focus
on supporting the unserved population to increase access to equitable, sustainable water supply and
improved sanitation, as inadequate access to clean, safe water supply and sanitation in Zambia is a major
contributing factor to poverty. The Bank’s support will complement on-going efforts by GRZ to improve
quality of life and livelihoods of people living in peri urban and high density areas of Lusaka where
women constitute 52% of the population. The Bank has had a long engagement with the LWSC through
the Lusaka Water Supply Rehabilitation Project (1991-2004) assisting in the formation of LWSC from a
municipality department to a private company. Although, it should be noted that at that time, the Bank
support to infrastructure only addressed water supply. GRZ has requested that the Bank this time
reorients its support towards sanitation to complement the substantial investments in urban water in
Lusaka by the Millennium Challenge Corporation (MCC) and investments by WB, European Investment
Bank (EIB) and Kreditanstalt fur Wiederaufbank (KfW). The Bank’s focus will be on (i) poverty
reduction focused components (such as decentralised sanitation in high-density areas); (ii) improved
public health through hardware (investments) and highly cost effective software methodologies
(sanitation and hygiene promotion), and (iii) leveraging other CPs funds to increase investments in
sanitation.
1.3 Donor Coordination
There is a comprehensive donor coordination framework that operates at national and sector level. At
national level, the coordination process is articulated in the Joint Assistance Strategy for Zambia which
involves a Memorandum of Understanding (MOU) that was signed by the GRZ and Cooperating
Partners (CPs). The MOU provides the platform for developing in practice, harmonization of
cooperation by CPs and alignment to Government procedures and processes. A Water Sector CP Group
chaired by the Bank and led by a Troika (AfDB, WB and Germany) has been responsible for enhancing
cooperation, coordination of policies, strategies and approaches in support of WSS development and
effective communication with GRZ. It is also worth-noting, two CPs, MCC and German Development
Corporation (GDC) are supporting the gender mainstreaming in the sector which this program will build
on. This includes policy formulation and development of gender indicators for the sector and technical
support.
3
Table: 1.1: Donor Support to Water (2014)
Sector or subsector*
Size
GDP Exports Labour
Force
Water 2.3 - 0.3%
Players - Public Annual Expenditure (average) : 2014 Budget
Government Donors AfDB 20% UNICEF
6% WB 4%
USD m USD 73 m USD 184 m
% 28% 72% DFID 2.3%
Germany 8.7%
USA 33%
Level of Donor Coordination
Existence of Thematic Working Groups Yes
Existence of SWAps or Integrated Sector Approaches No
ADB's Involvement in Donors Coordination Lead
* The estimate is based on the national budget, past budget performance and donor portfolio information.
*Other donors are not included with contributions less than 1%
II PROJECT DESCRIPTION
2.1 Project Objective
The objectives of the LSP are to increase access to sustainable sanitation services to Lusaka’s residents
especially the urban poor and strengthen LWSC’s capacity to manage sanitation services. The project
components are described in Table 2.1 below, with details provided in Annex B2.
Table 2.1: Project Components and Outputs [cost in million USD]
3 S/No 4 Component
name
*Cost Component description
1 Climate
resilient
Sewerage
Infrastructure
Development
79.86
(39.15)
Rehabilitation, upgrading and expansion of climate resilient sewer
collection networks (using labour intensive
contracts to support local employment) Rehabilitation of Noxious sewage pump station and construction of
Kafue road pump station
Rehabilitation of Matero, Ngwerere and Chelstone sewage ponds and
new climate resilient trunk mains in Kafue road and upgrade of
Western, Matero, Ngwerere interceptors
2 Decentralised
Sanitation and
Hygiene
Education
22.18
(9.05)
Advocacy, sensitization, promotion of decentralised sanitation &
hygiene education, development of gender responsive training and
promotional material
Construction of climate resilient demonstration household sanitation
facilities
Create public awareness to promote connection to the sewer systems,
highlight health and environmental risks associated with inadequate
sanitation.
Pro-poor service provision: develop a mechanism for promoting the
construction of safe sanitation facilities for vulnerable people who are
not able to access or afford a sewerage connection.
Construct Faecal Sludge Management units in selected peri urban
areas and improve FSM, particularly emptying pit-latrines,
transportation, sludge treatment and possible reuse.
Undertake WASH Friendly school campaign (hand washing and
sanitation facilities, responsive to gender and disability)
4
3 S/No 4 Component
name
*Cost Component description
3
Institutional
support and
capacity
building
12.34
(4.22)
Training and capacitating women community based enterprises in
service delivery along the full service delivery chain from collection
of human waste through to its recycle, reuse or disposal. Training of
youth and provision of toolkits to masons, artisans to construct onsite
sanitation facilities to enhance employment opportunities
Training and empowerment of community based enterprises in
production of sanitation products for communities (50% women)
Operationalizing of the LWSC Gender Policy and development of
Gender Strategy (increase women economic opportunities within the
program)
Mainstreaming Gender, Environment, Climate Change, HIV/AIDs &
cross cuttings Issues
Support in development & strengthening of a sanitation monitoring
system at LWSC
Support to National Water and Sanitation Council (NWASCO) to
enhance its capacity for developing sector guidelines and establishing
and enforcing standards in sanitation; Support to Lusaka City Council
to link up with environmental health services as well as a review and
improve relevant bylaws for appropriate design, enforcement of
connections and conforming with design standards and reuse of
wastes
Support to safeguards unit in LWSC to enhance its capacity for
monitoring environmental and social issues during and beyond project
implementation
4 Program
Management
and
coordination
13.50
(3.40)
Provision of technical assistance for design, supervision and program
implementation in accordance with good project management
practices.
Prepare and submit the required reports: (i) undertake annual external
audits; (ii) submit quarterly progress and ESMP reports;
(iii) undertake project mid-term review; and (iv) prepare a program
completion report (v) Program M&E and Reporting (including
baseline and endline), (vi) prepare Program Implementation Manual
* Cost in brackets is the AfDB-funded amount
2.2 Technical solution retained and other alternatives explored
2.2.1 Technical solutions that have been explored and retained are based on options that have been
adopted on similar interventions in Zambia. (i) The performance of gravity sewers is affected by poor
water supply. Therefore, priority has been given to carry out rehabilitation and expansion only in areas
where there is adequate water supply to ensure that cleansing velocities of approximately 0.6m/s are
achieved as per international best practices. This ensures blockages are minimized in the sewer network.
(ii) In terms of climate risks, for flood prone areas of Lusaka, sewers will be designed to be climate
resilient so as to collect, convey and discharge frequently occurring, low-return-period storms to
complement existing drainages in the areas. This minimizes overall capital costs, keeps operations and
maintenance costs low and minimizes pollution. Sustainable Urban Drainage Systems (SUDS) were
considered for Lusaka as a way of managing surface water runoff to prevent sewer flooding and to
improve water quality in streams in case of heavy storms but because of lack of green space in Lusaka,
there are no places to site these. The sewers will be designed to deal with low return period storms.
2.2.2 Construction of Feacal Sludge Management (FSM) facilities coupled with good onsite sanitation
facilities (properly designed and constructed lined pit latrines) are to be adopted in peri urban areas
which were not conducive for a sewer network. The sewer networks would have required good water
supply network, multiple sewage pump stations, large collectors and interceptors to get the wastewater
to treatment plants with a huge capital outlay.
5
Table 2.2: Project alternatives considered and reasons for rejection Alternative Brief Description Reasons for rejection
Sewerage system in some peri
urban areas with bad terrain
Sewer networks with multiple
sewage pump stations, collectors
and interceptors
No piped water, high capital,
operations and maintenance costs
Sustainable Urban Drainage
Systems (SUDS)
Managing surface water runoff to
prevent sewer flooding
No green space
2.2.3 For decentralized sanitation, hygiene promotion, Impact Evaluation and Sanitation Marketing
(SM) will be utilized focusing on community-based approaches (e.g. community decision to stop open
defecation; use of peer pressure to construct their own facilities; collective action to assist vulnerable
people and support public facilities) and support enforcement of bylaws on onsite sanitation The SM
promotes household-centered choice of latrine type. There is significant potential for increasing access
to climate resilient sanitation in flood prone peri-urban areas through introduction of ecological
sanitation technologies for on-site systems and lined latrines. Capacity building activities will be carried
out for ministries/national agencies, sensitization of communities in building sanitation facilities and
supporting Lusaka City Council (LCC) to enforce connections to sewerage systems and that sanitation
facilities built have appropriate design and conform with standards and reuse of wastes.
2.3 Project Type
This project is part of the National Water Supply and Sanitation Program (NUWSSP) which GRZ is
implementing with the aim of providing adequate sanitation facilities to all urban citizens of Lusaka
Province and starting with investments in Lusaka City. The program will implement investments
consistent with the Lusaka Sanitation Master Plan (2011-2030) and develop LWSC’s capacity to
manage all aspects of sanitation from conventional sewerage, on-site systems and FSM. The LSP will be
implemented in two parts, with each part being prepared and implemented concurrently. Part I supported
by the EIB and KfW will focus on the rehabilitation of Manchinchi and Chunga Wastewater Treatment
Plants, plus their associated main collectors, pumping stations and sludge treatment and Part II will
develop a comprehensive approach to sanitation in Lusaka, including on-site and off-site sanitation,
health, hygiene and sanitation promotion and technical assistance supported by the WB, AfDB and EIB.
2.4 Project Cost and Financing Arrangements
2.4.1 The total cost of Part II of the LSP is estimated at USD 127.83 million (UA 90.83 million), net of
taxes and duties, of which USD 82.39 million (64.5%) is foreign costs and USD 45.4 million (35.5%) in
local costs. The cost estimates are derived from the Lusaka Sanitation Master Plan and Pre-Feasibility
Study taking into account rates derived from suppliers and contractors, as well as from experience with
similar ongoing operations in the country and in the region. A physical contingency of 10% and price
contingency of 3% per annum have been taken into consideration in the estimates. A summary of the
program cost estimates by components and expenditure accounts is shown in Tables 2.3 and 2.4 below,
while details are provided in the Annex B.2
2.4.2 The cost of Part II of the program will be financed by ADB, WB and GRZ/LWSC, as
summarized in Table 2.4 below: Financing Plan by Source of Finance. ADB will provide loan of USD
50 million (equivalent UA 35.53 million), which represents 39% of the total costs, WB will provide
USD 65 million (equivalent UA 46.18 million), which represents 51% of the total costs and GRZ/LWSC
will finance the balance of USD 12.83 million (equivalent UA 9.12 million), which represents 10% of
the total program cost. In accordance with the “Policy on Expenditure for Bank Group Financing”, the
GRZ has requested the Bank to consider reducing the requirement for 50% counterpart funding on the
LSP due to the fact that Zambia has only recently transitioned to blend status and is yet to transition to
full ADB only. Zambia is also at the lower end of middle income status and will require substantially
more time to fully transition to a 50% counterpart funding level. A justification is provided in Appendix
V to reduce the requirement for counterpart funding.
6
Table 2.3: Program cost estimates by component
* In addition to the above, EIB and KfW are to provide equivalent of USD$ 137 and USD$ 55 million, respectively to fund the
Lusaka Sanitation Program.
Table 2.4: Sources of financing
Source of Funds (US$ ‘000) (UA ‘000) %
World Bank 65,000 46,185 51%
AfDB 50,000 35,527 39%
GRZ/LWSC 12,829 9,115 10%
Total 127,829 90,827 100%
2.4.3 The summary of the AfDB financed components is provided in Table 2.5(a), while a
summary of the same by category of expenditure is provided in Table 2.5 (b) below.
Table 2.5 (a): Project cost estimates by component
Table 2.5 (b): Project cost by category of expenditure
Table 2.6: Expenditure schedule by component [‘000USD]
Components 2016 2017 2018 2019 Total
A) Sewerage Infrastructure: Rehab and Expansion - 9,768 13,024 9,768 32,561
B) Decentralised Sanitation and Hygiene Promotion 2,440 2,440 1,410 1,410 7,700
C) Institutional Strengthening and Capacity Building 1,625 1,185 755 75 3,640
D) Program Management 1,943 1,454 1,054 1,054 5,505
Total Base Cost 6,008 14,847 16,243 12,307 49,406
Physical Contingencies (10%) 601 1,485 1,624 1,231 4,941
Price Contingencies (3%) 198 995 1,657 1,699 4,549
Total Costs 6,807 17,326 19,524 15,237 58,895
Components FC LC Total FC LC Total F% %
A) Sewerage Infrastructure: Rehab and Expansion 46,868 20,086 66,955 33,302 14,272 47,574 70.0 62.4
B) Decentralised Sanitation and Hygiene Promotion 10,994 7,611 18,605 7,812 5,408 13,220 59.1 17.4
C) Institutional Strengthening and Capacity Building 7,507 2,844 10,351 5,334 2,021 7,355 72.5 9.7
D) Program Management 3,750 7,571 11,322 2,665 5,380 8,044 33.1 10.6
Total Base Costs 69,120 38,113 107,233 49,112 27,081 76,193 64.5 100.0
Physical Contingencies (10%) 6,912 3,811 10,723 4,911 2,708 7,619 64.5 -
Price Contingencies (3%) 6,356 3,517 9,873 4,516 2,499 7,015 64.4 -
Total 82,388 45,441 127,829 58,540 32,288 90,827 64.5 -
(In US$ '000) (in UA '000)
Components FC LC Total FC LC Total F% %
A) Sewerage Infrastructure: Rehab and Expansion 22,793 9,768 32,561 16,195 6,941 23,136 70% 66%
B) Decentralised Sanitation and Hygiene Promotion 4,550 3,150 7,700 3,233 2,238 5,471 59% 16%
C) Institutional Strengthening and Capacity Building 2,640 1,000 3,640 1,876 711 2,586 73% 7%
D) Program Management 1,823 3,681 5,505 1,296 2,616 3,911 33% 11%
Total Base Costs 31,806 17,600 49,406 22,599 12,505 35,105 64% 100%
Physical Contingencies (10%) 3,181 1,760 4,941 2,260 1,251 3,510 64%
Price Contingencies (3%) 2,928 1,620 4,549 2,081 1,151 3,232 64%
Total 37,915 20,980 58,895 26,940 14,907 41,847 64%
(In US$ '000) (in UA '000)
Category of Expenediture FC LC Total FC LC Total %
1) Works 25,793 11,968 37,761 18,320 8,501 26,820 76%
2) Goods 2,240 - 2,240 1,591 - 1,591 5%
3) Services 3,523 2,481 6,005 2,503 1,762 4,265 12%
4) Operating Costs - 1,900 1,900 - 1,349 1,349 4%
5) Miscellaneous 250 1,250 1,500 178 888 1,065 3%
Total Base Cost 31,806 17,600 49,406 22,591 12,500 35,091 100%
Physical Contingency 3,181 1,760 4,941 2,259 1,250 3,509
Price Contingency 2,928 1,620 4,549 2,080 1,151 3,231
Total Cost 37,915 20,980 58,895 26,930 14,901 41,831
64% 36% 100% 64% 36% 100%
(In US$ '000) (in UA '000)
7
2.5 Project’s target area and population
2.5.1 Project Area: The LSP will be implemented in Chunga/ Matero/ Chelstone/ Kaunda Square
sewersheds where the sewerage infrastructure was constructed in the 1960’s. The priority sub-projects
were identified with the aim of covering the peri-urban and low cost areas which are most densely
populated areas in these sewersheds. The main criteria for the selection of interventions included: (i)
aged and dilapidated sewer networks (20% of the 50km network is functional in these areas), (ii)
waterborne disease prevalence, (iii) susceptibility to flooding, (iv) sewage overflows and blockages (994
complaints in 2014) and (v) low access rates of waterborne sewerage. The city’s current population is
expected to double over the next 20 years (from 2.2 million to 4.9 million) exacerbating the problem of
poor sanitation if not addressed.
2.5.2 Project Beneficiaries: The intervention will have direct and indirect benefits to Lusaka City’s
population with improved sanitation to about 600,000 indirect beneficiaries and 473, 000 direct
beneficiaries (52% women). Unlike the sewerage services, onsite sanitation for Lusaka’s urban poor
often depends on landlords and tenants who have few incentives to invest in quality services within
informal settlements, including sanitation facilities. Most of the households in the project areas are
sharing a few on-site latrines or relying on communally managed pay-and-use ablution blocks. Women
and children suffer more when having such arrangements. LCC and LWSC will be supported to engage
with Landlords and plots owners for enforcement of applicable laws bearing in mind balancing between
the need to improve the properties and the ability of the tenants to be able to pay higher rent.
2.5.3 Residents will gain better health from improved environmental and sanitary conditions;
especially those in peri urban areas where most of the urban poor are residing. Special focus will be
given to vulnerable households within the project area. The LSP will target and capacitate women
community based enterprises in service delivery along the full service delivery chain of FSM from
collection of human waste through to its recycle, reuse or disposal. About 615 youths and women, who
presently lack employment opportunities, will be targeted by the program through training in FSM,
business start-up and as masons, artisans and will participate in construction of decentralised sanitation
facilities. The LSP is expected to create at least 250 full-time skilled/semi-skilled and 600 part-time
unskilled jobs in masonry, pipe laying, steel fixing and construction which will benefit both men and
women. This in turn will contribute to reducing poverty and improving the quality of lives of people
from incomes gained. Schools, Markets and health centres lacking adequate sanitation facilities in the
targeted peri urban areas will also benefit from the program. The expected impact of these interventions
are reduction of water related diseases and associate health care cost, reduction of school-dropout rates,
particularly among girls and reduction in environmental pollution. Additional information is provided in
Annex B.8.
2.6 Participatory process for project identification, design and implementation
2.6.1 The program activities were selected through an extensive participatory process which was
initiated during the Bank’s preparation mission, continued throughout appraisal, the environmental and
social impact assessment of the project area which included focused group discussions, workshops and
field visits to understand current applicable technologies, current rates of access and levels of disease
burden.
2.6.2 Extensive consultations were held in a workshop in June 2014 in Lusaka with various
stakeholders including Ministry of Local Government and Housing (MLGH), MoF, MoH, LCC, WB,
other CPs, NGOs such as Water Supply for the Urban Poor and potential beneficiaries. As part of the
ESMF/ESMP preparation, a cross section of affected communities: women, men, youth, local leaders
and people with special needs were consulted in March 2015 in Matero and George peri-urban areas and
their views integrated into the program design. The issues that came out as affecting sanitation included:
(i) fragmented legal and policy framework; (ii) unclear definition of roles, responsibilities and poor
8
institutional arrangements; (iii) lack of enforcement; (iv) inadequate financial resources for
implementing agencies and households to effectively tackle sanitation (vii) lack of sanitary facilities and
poor environmental sanitation; and (ix) concerns on whether works shall affect people’s assets and
associated compensation. All stakeholders acknowledged that poor sanitation is affecting the social
wellbeing and posing serious risks to groundwater contamination and public health.
2.6.3 The LSP will therefore incorporate in its design: (i) development of a comprehensive new WSS
policy; (ii) LCC to review/adapt enforcement bylaws and standards for onsite sanitation; (iii) assist
vulnerable households with a subsidy to construct sanitation facilities; (iv) formal agreements between
LWSC and LCC on roles and responsibilities for decentralised sanitation systems and (v) extensive
sensitization, mobilisation campaigns and community participation during implementation.
2.6.4 Participation of national stakeholders and representatives of beneficiary groups in the LSP will
be through a steering committee that will be established to oversee and guide implementation. In
addition, seconded staff from MLGH, MoH and LCC will also be involved in the Program
Implementation Team. Additional information is provided in Annex B.3.
2.7 Bank Group experience and lessons reflected in program design
2.7.1 The overall performance of the portfolio is satisfactory2; with implementation progress (IP) and
Development Outcomes (DO) of 2.79 and 2.90 respectively in 2014. Ageing operations, as a percentage
of the entire portfolio reduced from 13% since the last CPPR in 2013 to 7% in 2014. The number of
projects at risk has reduced from 17% in 2010 to 7% in 2014. Overall disbursement ratio is 27% for
2014.
2.7.2 The Bank is among the largest and active CPs in the sector financing a total of 12 operations to
date. Recently completed projects include the Central Province Rural Water Supply and Sanitation
Project (Loan of UA 12.41 million) completed in 2009 and the Central Province Eight Centres Water
Supply and Sanitation Project (a blend of Grant and Loan of UA 24.62 million), completed in 2012.
There is no Project Completion Report (PCR) backlog on the two completed projects. The National
Rural Water Supply and Sanitation Program II (USD 15.5 million loan, Euro 3.5 million grant) was
approved in September 2014, with the Nkana Water Supply and Sanitation Project – NWSSP (UA 35
million) and the NRWSSP Phase I (UA 15 million) having closed on a on 31 March 2015. The current
supervision ratings are 2.41 and 2.35 for NWSSP and NRWSSP respectively.
2.7.3 Lessons learned from the Bank’s past and current projects are described in Annex B1. The main
lessons applied to the LSP are: (i) Implementing an integrated approach ensuring that sewerage system
are provided where there is adequate water supply to ensure adequate collection, treatment and disposal
(ii) effective community participation by involving the beneficiaries in project design, project
implementation using existing institutional arrangements for decentralized sanitation facilities, and the
need to strengthen sector institutions at the national and local levels including the LWSC and LCC, (iii)
as happened in Kitwe town on the NWSSP, addressing on-site sanitation through improved facilities and
improved FSM will have a greater impact on environmental pollution and public health than only
improvements to the sewerage system and (v) increasing sustainable demand and commitment for
improved WSS through consistent targeted hygiene behaviour change.
2.8 Program’s performance indicators
2.8.1 Achievement of the expected program results will be demonstrated by the key performance
indicators described in the results-based logical framework and process indicators in annex B9. The
program progress will be tracked through the following outcome indicators : (i) Increase in number of
2 Zambia Combined 2011-2015 Country Strategy Paper Mid Term Review and Country Portfolio Performance Review
9
residents benefiting from improved sanitation facilities , (ii) increase in proportion of people practicing
improved hygiene behaviour/ sanitation practices (+50% women), (iii) percent of sewage blockage
complains addressed satisfactorily. The key output indicators will include: (i) number of people trained
in hygiene behaviours and sanitation practices (ii) climate resilient sewer networks rehabilitated and
extended (kms), (iii) number of new connections to sewer, (iv) number of sewage pump stations and
ponds rehabilitated/ constructed, (v) number of climate resilient FSM facilities constructed, (vi) FSM
guidelines prepared, (vii) preparation of Water and Sanitation Sector Emergency Preparedness and
Disaster Risk Management Plan, (viii) preparation of gender strategy.
2.8.2 Progress towards achieving program outcomes and outputs will be measured and monitored
through bi-annual Bank supervision missions, quarterly progress reports, annual technical and financial
audit reports. The M&E Specialist in the PIT will be responsible for the M&E framework and data
collection, including baseline, impact and other relevant studies to be carried out as required to inform
the program progress. The M&E framework will be implemented in collaboration with stakeholders,
especially LCC, NWASCO and NGOs/CBOs. Internal monitoring systems of the LCC and LWSC will
be strengthened to facilitate post-program implementation monitoring.
III PROGRAM FEASIBILITY
3.1 Economic and financial performance
Table C.1: key economic figures
EIRR 17.01% and NPV ZMK 156.50 million (at 10% base case) NB: detailed calculations are available in Annex B6
3.1.1 The underlying assumptions for the calculation of the EIRR are provided in Annex B6. The main
assumptions are: health benefits from improved sanitation services comprising improved sewerage and
faecal sludge management systems, incremental sanitation revenue, as well as economic value of sludge
produced from the improved facilities. On the cost side, these include investment costs, replacement
costs, and other items as part of operation and maintenance costs comprising of staff costs, energy,
chemicals and repairs and other overhead costs have been taken into account. The incremental O&M
costs are estimated at 3% of investment costs. The economic life of the investment is estimated as 25
years, all the costs and benefits considered are net of duties and taxes. The LSP’s economic rate of
return is estimated at 17.01 %. The value is higher than the opportunity cost of capital of 12% and thus
is considered economically viable. Sensitivity analysis to test the robustness of the EIRR was carried out
to determine the impact of adverse variations. The EIRR changes to 14.64% assuming that investment
cost increases by 20%, and changes to 13.63% assuming that the benefits of the project are decreased by
20%. The analysis shows that the project is economically viable and socially beneficial for Zambia.
3.2 Environmental and Social Impacts
3.2.1 The LSP was classified as Category 2 on 28 November 2014 in line with the Bank’s
Environmental and Social Assessment Procedures (ESAP); mainly because most impacts are site specific
and have no significant and irreversible detrimental effect. Detailed Feasibility studies for the sewer
networks and trunk lines under Component 1 are yet to be completed and the sites for establishment of
FSSM and systems will be identified and selected by LWSC. For these reasons, the type of
Environmental Assessment tool for at this stage is the development of the Environmental and Social
Management Framework (ESMF). The categorization is in alignment with the national environmental
law of Zambia. The ESMF Summary has been prepared, validated by the Bank and disclosed on the
Bank’s website on 20 May 2015.
3.2.2 Potential adverse impacts are anticipated during construction. Direct impacts such as noise, dust,
public safety, disruption of surface water drainage, interruption of utilities, pollution, disposal of waste,
and social impacts will be mitigated and generally eliminated. Excavations to remove old sewer
10
networks and installation of new piping are likely to cause safety hazards to the communities if the
excavations are not protected. The excavation of trenches may also lead to temporary disruption of
businesses that are located along the wayleaves. The environmental impacts resulting from
implementation of civil works are expected to be minor and short-term since the rehabilitation and
expansion works are principally for the laying of buried pipelines.
3.2.3 Construction related impacts will be mitigated by (i) development of a construction ESMP
compliant with the AfDB Integrated Safeguards System; (ii) the contractors’ work practices, especially
those related to maintenance of access, methods of trench excavation, the storage of construction
materials and cleanliness of the work sites; (iii) cooperation by LCC with the contractor in terms of
traffic management and use of public space and utilities; (iv) project management’s strict enforcement of
the correct construction practices and standards; (v) the incorporation of mitigation measures identified
into the bid documents and specifications; (vi) public awareness including liaison at ward level in
advance of work in each work location; and (vii) close monitoring of the contractor’s implementation of
the required mitigation measures. The ESMF implementation and monitoring budget is estimated at
USD 240,000
3.2.4 Potential positive impacts from the program shall include; employment opportunities, for which
the enhancement measures require works contractors to have active employment policy favouring local
workers and women. This will be a requirement of works contracts. After construction, the impacts will
be positive through improved sanitation, reduced pollution incidents on surface and ground water in the
project area, improved health and hygiene among beneficiary communities.
3.2.5 Climate Change: According to the Bank’s Climate Safeguards System, the LSP is classified as
Category II, requiring the implementation of adaptation measures to increase the resilience of
communities and the infrastructure to be rehabilitated to withstand the impacts of climate change. Some
of the adaptation measures considered include (i) development of a Water and Sanitation Sector
Emergency Preparedness and Disaster Risk Management Plan to deal with extreme flooding and drought
scenarios that may affect the infrastructure; (ii) desludging of sewage ponds, strengthening of the
embankments of the ponds and building a wall fence around the facilities to be able to cope with larger
surges of rainfall without impacting the surrounding communities; (iii) improve operational risk
management to ensure preventive and routine maintenance is effectively carried out to reduce blockages
and spillages. For example, sewer manholes to be designed to align to the roads and with properly
designed manhole covers to prevent damage by traffic and stop heavy ingress of storm water to
minimize sewage blockages. as a result of adverse weather, (iv) modify existing sewerage system assets
to increase climate resilience by expanding the capacity of sewerage systems; (v) increasing access to
climate resilient sanitation in flood prone peri-urban centres through promotion of ecological sanitation
technologies for on-site systems and lined latrines; (vi) promotion of clean and hygienic environment,
including handling and disposal of solid wastes, FSM and integrating reuse of wastes to avoid polluting
groundwater sources and (vii) provide information to LWSC, national and municipal institutions and
carry out climate change awareness raising activities. Annex IV provides the adaptation summary.
3.2.6 Gender: The quality of water and especially sanitation services is highly gender sensitive,
therefore, women and men were consulted on their roles, responsibilities, challenges, and opportunities
within the scope of the program’s objectives. Furthermore, consultations with the two CPs supporting
gender mainstreaming of LWSC; MCC and GDC; was conducted. Discussions with LWSC, LCC,
Ministry of Health (MoH), Ministry of Community Development, Mother and Child Health
(MCDMCH) and Ministry of Gender and Child Development (MGCD) to determine the proper
interventions and costing took place. The outcome of these discussions materialized in adopting two
approaches, (i) mainstreaming of gender in program interventions, and (ii) gender focused activities with
total costing of USD 200,000, investing in women’s skill development and economic opportunities
within the sanitation sub-sector.
11
3.2.7 The gender negative impact of the current situation stated by women and men during the
stakeholders consultations were: (i) women workload increase with the rise of water borne diseases as
result of inadequate sanitation facilities and bad hygiene practice by member of the family, (ii)
moreover, women and girls have no sense of privacy because many families sharing one latrine
especially during menstruation. Sometime, women and girls opt to walk a quite a distance to access
other sanitation (communal) seeking privacy; risking their safety In addition, women expressed the need
to be consulted and engaged throughout the project cycle to enable them to share their views and
concerns, (iii) increasing of economic opportunities will help in household improvement.
3.2.8 These pose serious challenges in terms of health, security, and privacy for women and girls.
Vulnerability of household members feature in the way each individual ability tries to address these
challenges. The ability of households to have a decent sanitation facility and practice of good hygiene
is determined by the following: knowledge and attitude, financial ability and the facilitating
environment. To address beneficiaries concerns taking into account the needs of women and vulnerable
households, the LSP aims to support LWSC to address the three determinant factors mentioned above.
3.2.9 In terms of knowledge and attitudes, support will be provided to create demand among the
population on sanitation and good hygiene practice taking into account the gender and social
perspective. Regarding the financial ability of households to connect to the sewer line or to have an
improved on site sanitation facility, the LSP will develop a variety of financial models / support to
facilitate the process. This could be in form of recovering the connection fees through the water bills
over a period of time or through exploring other means of funding (revolving funds) such as use of the
sanitation surcharge which LWSC currently and manages.
3.2.10 While increasing the capacity of the local market to address the envisaged demand on
sanitation, the LSP aims to create an enabling environment for the employment of youth and women.
This will be carried out through training of artisans and masons (women and youth), training of women
and youth in sludge management including biogas in one of the vocational centres in Lusaka, and by
supporting a female engineer internship program, and creating practical attachment opportunities for
Zambia Women in Construction. Women will be trained in start-up business and how to manage public
sanitation and water kiosks. This includes financial literacy and book keeping.
3.2.11 Opportunities: In 2014, LWSC within its Strategic Business Plan (2014 – 2018) has approved
its Gender Policy, which was also guided by the Zambia National Gender Policy. Following that, a
Gender Strategy with detailed activities, costing, and indicators for monitoring was developed. In
addition, LWSC has designated a Gender Focal Point who is situated in the Monitoring and Evaluation
(M&E) Department. A committee to oversee the implementation on gender activities in the utility is
under formation. CP’s including the Bank have been heading the gender mainstreaming of the water
and sanitation national program including mainstreaming of gender for utilities.
3.2.12 Social: Lusaka has a population of about 2.2 million people (336,000 rural and 1,854,000 urban)
showing a high level of urbanization. Lusaka City itself is in size the smallest district in the province and
yet carries a population of 1.7 million meaning it has a high density (4853/ Km²) and is very congested.3
This is the result of many informal settlements in peri-urban areas (27 informal settlements) with a high
level of poverty (75% of the peri-urban population live on less than US$ 1 a day).4 Lusaka is badly
affected by poor sanitation with annual outbreaks of cholera, typhoid and dysentery. Only about 10 – 15
% of the population in Lusaka benefit from access to sewer networks. The remaining population
especially in the peri-urban areas is primarily dependent on pit latrines, which are located within the
household boundaries. The country’s urban system is dominated by Lusaka, which is a host to 32 % of
the total urban population in the country.
3 2010 Living Conditions Monitoring Survey Report
4 Ibid
12
3.2.13 Lusaka is experiencing typical urban development problems associated with population growth,
high levels of urbanization and unemployment, inadequate services and inadequate waste management.
The basic determinants of better health, such as access to water, and sanitation, are still in a critical state
in Lusaka. Limited access to WSS facilities accompanied by poor hygiene is associated with skin
diseases, Acute Respiratory Infections (ARIs), and diarrheal diseases, the leading preventable diseases.
ARI and diarrheal diseases are among the leading causes of child deaths in Zambia5. HIV prevalence
rate for Lusaka district stands at 20.8 per cent, making it the highest district compared to others, in 2013.
The program will continue building on the efforts made by the GRZ on sensitization and awareness
raising. Awareness raising is one of the activities programmed under the gender strategy of the LWSC.
3.2.14 From field visits and discussions with potential beneficiaries, the major findings were as follows:
(i) the state of sanitation in Lusaka has affected the population differently according to their economic
background, gender and their social status. (ii) The effect of the health situation as a result of poor
sanitation facilities is different from high cost areas with sewerage systems to poor-urban areas with
mainly on site sanitation facilities such as pit latrines. While the sewerage system is in a state of
disrepair and experiencing frequent blockages and spillages presenting a very high public health risk for
the population, the majority of residents in the peri-urban areas live in plots shared by a number of
families with one shared sanitation facility, and in some cases also with neighbour’s.
3.2.15 The stakeholders and the host community were positive and there was broad support for the
program as it anticipated that the rehabilitation of the sewer networks and the provision of adequate
sanitation systems and facilities that will result in an improvement in health and hygiene for the
beneficiary population. Most of the respondents in the project area have a positive outlook towards the
Lusaka Sanitation Plan. The youth in particular, are looking forward to employment opportunities during
the construction phase and hence have a positive mind set about the development. There is no negative
impact envisaged.
3.2.16 The LSP therefore will address these issues highlighted above by having proper climate resilient
sewer infrastructure (to reduce spillages and blockages), improved sanitation facilities in public places
(markets, health centers, and the most disadvantage schools in the project peri-urban areas) will reduce
vulnerability to water borne diseases, increase education attainment, and improve health centers
infrastructure. Community Led Total Sanitation (CLTS) and Participatory Hygiene and Sanitation
Transformation (PHAST) will be used to increase awareness among residents with the objective to
create demand for better sanitation. The LSP will also focus on skills development, helping women and
youth to engage in business opportunities to contribute to increasing income for poor households.
Moreover, the LSP will help in sludge management by providing technical knowledge, protection, and
innovative emptying techniques that do not necessarily require manual handling. Annex B.8 provides
more details on the gender and social analysis.
3.2.17 Involuntary resettlement: There will be no involuntary resettlement. Trunk sewer lines and
laterals will be laid along road reserves and existing way leaves to reduce incidences and scale of
compensation. FSM units will be on existing parcels of land requiring minor adjustment within the
defined reserve area to the extent possible. Should the scope of the activities change in such a way that
results in land acquisition, the Bank’s Integrated Safeguards Policy, specifically the Operational Safeguards 2
on Involuntary Resettlement will be followed and implemented accordingly.
5 MoH, 2012a.
13
IV. IMPLEMENTATION
4.1 Implementation Arrangements
4.1.1 The LSP shall be implemented using existing structures of LWSC incorporating lessons and
experience gained from similar operations. The program is expected to start in 2015 with a duration of
five years. The GRZ is the borrower of the ADB loan, while LWSC, under the MLGH, will be the
Executing Agency (EA). LWSC has constituted within its Project Implementation Department (PID), a
Program Implementation Team (PIT), comprising a Program Coordinator, Wastewater Expert,
Environmental Expert, Social/Community Mobilization Expert, Procurement Expert, Onsite Sanitation
Expert, Monitoring & Evaluation Expert, Program Accountant, and seconded staff from MLGH, MoH
and LCC to be in charge of implementation. Gender mainstreaming and gender related activities would
be implementing in consultation with the TA on gender and social equity provided by MCC and the
LWSC Gender Focal Point. The PIT jointly with LCC will be responsible for implementation of
component 2 using NGOs and CBOs within Lusaka’s and especially in the peri-urban areas. The LWSC
shall be responsible for overall coordination of the Program and reporting obligations to the financiers
and GRZ. Technical Assistance to the PIT will be provided by an experienced Engineering Services
consultant for design review, supervision and implementation support for sewerage infrastructure
rehabilitation and development. A program steering committee shall be stablished chaired by MLGH
which will oversee the program implementation. The Bank, WB, EIB and KFW will share the use of the
PIT. See Annex B.3 for implementation details.
4.2 Procurement Arrangements
4.2.1 All procurement of goods and works and acquisition of consulting services financed by the Bank
will be in accordance with the Bank's Rules and Procedures for Procurement of Goods and Works”,
dated May 2008, revised July 2012; and “Rules and Procedures for the Use of Consultants”, dated May
2008, revised July 2012,, using the relevant Bank Standard Bidding Documents. However, all
procurements within the thresholds for National Competitive Bidding (NCB) and Shopping for goods
and works will be procured using the National Procurement Procedures (NPP) as set forth in the Public
Procurement Act, No.12 of 2008, as amended by the Public Procurement (Amendment) Act, 2011
applying the appropriate national standard bidding documents and in conformity with the provisions of
the Financing Agreement. The LWSC as the EA will be responsible for the procurement of goods, works
and service contracts.
4.2.2 Major civil works involving rehabilitation and expansion of sewer networks will be undertaken
through ICB with prequalification, while other sanitation options will be procured under NPP. The
nature, scope and monetary value of the goods, works and consultancy services has determined the
methods of procurement as detailed in the procurement Annex B.5.
4.2.3 The capacity and risk assessment of the EA was done in collaboration with the WB and is rated
as substantial. This rating takes into account that the program is of high value and technically complex
and therefore there is need for high level technical and procurement skills to compliment LWSC
capabilities. A detailed risk assessment with migration measures is in Annex B.5 and the rating is
expected to improve to moderate once most of the recommended measures are undertaken.
4.3 Financial Management and Disbursement Arrangements
4.3.1 Financial Reporting and External Audit: The Bank conducted in collaboration with the WB an
assessment for the LWSC’s Finance Division financial management arrangements for the
implementation of the LSP (that included a review of the budgeting, accounting, internal controls, flow
of funds, financial reporting and auditing arrangements).
14
The assessment indicates that these arrangements meet the Bank’s minimum requirements to ensure that
funds made available for program financing are used economically and efficiently and for the purpose
intended. The overall FM risk rating is Moderate.
4.3.2 The program FM will be handled within the existing structures of the LWSC’s Finance Division.
The program accounting system will be based on an automated accounting package being used by the
LWSC. The EA will produce a single quarterly progress reports, including all sources of financing and
program. The program financial statements (that will include all co-financiers funds and program
expenditures) will be audited annually by the qualified and independent private audit firm, with
involvement of the Office of Auditor General, in accordance with a Bank approved audit ToR. The audit
report together with management letter shall be submitted to Bank within six months after the end of
each fiscal year.
4.3.3 Disbursement Arrangements: Disbursement of the ADB resources will be done in accordance
with Bank’s procedures and the Disbursement Letter will document the disbursement procedures and
methods to be applied for the Loan. The LSP will have access to (i) Direct Payment, (ii) Special Account
(SA) and (iii) Reimbursement as prescribed in the Bank’s Disbursement Handbook. Two separate
Special Account denominated in USD and Kwacha sub-account will be opened at a Commercial Bank
acceptable to the Bank. Disbursement to contractors, suppliers and consultants will be by direct payment
or reimbursement guarantee. Small contracts of values up to UA 20,000, including community
mobilization, sanitation and hygiene, as well as related operational costs may be paid from the Special
Account. Detailed financial management, disbursement and auditing arrangements are included in
Annex B.4.
4.4 Monitoring and Evaluation
4.4.1 M&E of the program will be carried out as a regular management function by LWSC based on
the indicators defined in the result based logical framework. Support will be provided towards
developing a sanitation monitoring system which will capture existing sewer infrastructure, onsite
sanitation areas, operating information on incidences of sewer flooding and relevant public health
information. The M&E Expert PID will be fully responsible for collecting and analyzing data for
reporting.
4.4.2 Joint Bank and co-financiers supervision missions will be undertaken twice per year and the
Bank will undertake desk supervision quarterly, providing feedback and following up on progress
reports. A Mid-Term Review will be undertaken during the third year of implementation. LWSC will
prepare single quarterly Progress Reports, annual technical and financial audits including all activities by
the co-financiers for submission. Upon completion, LWSC will prepare and submit to the Bank a PCR.
Table 4.1: Key Milestones
Timeframe Milestone Monitoring process/feedback loop
June 2015 ADB Board of Directors Loan approval
November 2015 Loan Effectiveness Launching mission; Loan conditions approved by the Bank
February 2016 TA consultant engaged Procurement & contract documents; Bank’s “No objection”
February 2017 Construction works start Bidding & contract documents; Bank’s “No objection”;
Monthly construction supervision reports; Bank’s comments
on the annual and quarterly reports; Supervision missions
January 2016 Hygiene and sanitation
NGOs/consultants engaged
Procurement & contract documents; Bank’s “No objection
June 2018 Mid-Term Review Assessment of progress/performance, restructuring if needed
December 2019 Program completion Commissioning of works
December 2020 Program completion report Project completion mission
15
4.5 Governance
4.5.1 Successful implementation of the program requires good governance at National, Local and
Executing Agency level. The overall governance rating of Zambia is above Africa’s continental average
in many fronts and measures. Zambia ranks 13th
out of 52 countries in the 2014 Ibrahim Index of
African Governance and 83rd
out of 174 in Transparency International’s 2013 Corruption Perception
Index (a relative improvement from 88 compared to 2012). It ranked amongst the top 10 countries
performing reasonably in safety and rule of law. In terms of National Security it stands 6th
on the
Ibrahim Index of African Governance.
4.5.2 The governance of the WSS system goes beyond LWSC. GRZ has shown commitment to reform
the sector for better transparency and accountability. Revision of the WSS policy is ongoing to provide
clear guidance, as planning and implementation of WSS related projects has many socio-economic
aspects. In addition, the LSP is of high value, technically complex and therefore there is need for high
level technical and procurement skills to compliment LWSC capabilities. To mitigate against this, an
Engineering Services consultant will assist LWSC enhance appropriate procurement, technical, contract
management/dispute resolution skills to complement their capability to successfully manage the LSP. To
counter corruption and fraud, tenders shall be evaluated by an appointed evaluation committee whose
recommendations shall be submitted to the LWSC Tender Committee for approval before submission to
the Bank for No Objection and approval of contract award depending on the thresholds. The internal
audit arrangements at the LWSC have been reviewed and found acceptable. There will also be a
program steering committee chaired by MLGH which will oversee the implementation. These shall
reinforce transparency and accountability during tendering and award of contracts.
4.5.3 LWSC management operates under the overall oversight of a non-executive Board of Directors
which provides guidance, monitors executive activities and contributes to development of company
strategies. All board members are appointed by the shareholders who are the LCC, Chongwe, Luangwa
and Kafue District Councils and consists of members from both Government and private sector. The
Bank will support governance enhancement in LWSC through the institutional strengthening and
capacity building component which includes supporting the Sustainability Agreement (SA) entered into
between LWSC and GRZ.
4.6 Sustainability
4.6.1 GRZ’s commitment has been shown by the ongoing water sector reforms since the 1990’s which
culminated in the formation of 11 utilities to provide WSS to the urban town and cities. The LSP is an
integral part of the NUWSSP which Government launched in 2011, a holistic and integrated approach
which aims at improved livelihoods and public health of Zambia’s urban population. Currently, LWSC
has a SA with GRZ, to ensure that the utility moves towards technical, environmental, and financial
sustainability including improved operational performance, financial and corporate governance. In this
regard, renewal of rollover of the SA covering the period 2018-2020 has been made a condition of the
loan.
4.6.2 The tariff for sewerage services is not yet fully reflective of economic cost of service provision.
The current tariff policy is to recover at least O&M costs and in the long run recover full cost through
user charges. Therefore, there is need to review and update the structure to reflect efficient cost of
service so that tariffs are commensurate to the cost of these services. In this regard, LWSC is to finalise
the ongoing tariff and affordability study and implement a program of tariff adjustments for WSS
services in order to ensure sustainability of service provision including investment. These adjustments
should also take into account the social nature of services and the needs of the poor. This is one of the
conditions of the ADB loan.
16
4.6.3 LWSC has capable staff and is already operating its WSS systems in Lusaka. In addition, the
LSP incorporates training and capacity building of LWSC personnel to operate and maintain the
sanitation facilities. As part of the LSP and with the expanding sewerage infrastructure, LWSC is
undertaking institutional assessment study to raise the profile of sanitation services, empower and
strengthen the Sewerage and Peri Urban Departments within LWSC. In this regard, LWSC will
complete the ongoing sanitation institutional assessment study and implement its recommendations by
2016.
4.6.4 Currently, LWSC collects revenue for sanitation services to cover the O&M costs of the existing
sewerage facilities. The refurbishment of dilapidated sewerage infrastructure will reduce the need for
and frequency of repairs, and hence allow for significant savings on O&M costs. At full capacity, the
incremental revenue (more than ZMK 15 million) generated from the LSP will more than offset the
incremental recurrent costs (ZMK 12 million). The incremental revenues as well as cost savings
generated from the program will more than offset the incremental recurrent costs. Consequently, there
will not be any need for budgetary support or subsidies from GRZ to the O&M of the sanitation system
in the project area.
4.7 Risk management
The following risks shall be monitored and mitigated to the extent possible.
RISKS MITIGATION MEASURES (rating) 1. Sewers are expensive and
customers might be unwilling
to pay for services and may
hinder connections to the
sewers and construction of
onsite systems
Carefully balance willingness to pay, affordability and technology options.
A detailed tariff study is currently underway and will be supported by
extensive social marketing and awareness raising. Customers to be
connected as sewers are laid and connection charges recovered from
sanitation bills. Recovered charges will form a revolving fund for LWSC
(Moderate)
2. Poor coordination between
different institutions involved
in the implementation of some
components at local level.
Before loan approval, Borrower to submit an MOU signed between LWSC
and LCC on the cooperation for implementation of the component 2,
detailing the roles each institution will play during the implementation
(Moderate)
3. Unauthorized program
expenditures
Existing internal control systems will be strengthened in the implementation
of the program (Moderate)
4. Program may be exposed to
future climate risks
Development of WSS emergency preparedness and disaster risk
management plan and design of climate resilient sewerage infrastructure
(Moderate)
5. Program is of high value
and technically complex
LWSC to enhance appropriate procurement, technical, contract management
/dispute resolution skills to complement their capability to successfully
manage the program. Engineering services consultant to assist carry out the
design review and prepare tender documents for the civil works.
(Substantial)
4.8 Knowledge building
The Bank will support development of a monitoring system to assist LWSC better understand sanitation
management and also develop guidelines for better management of sludge. The knowledge products will
contribute to improvement of Zambia’s urban sanitation sub-sector as well as assist the Bank replicate
the good practices in other member countries. With mounting international concern at the rising
frequency and severity of natural hazards and disasters, in part due to factors related to climate change,
there is increased impetus in Zambia and other countries to put in place legal, technical, financial and
institutional measures that will reduce the destructive effects on livelihoods of individuals and
communities. Therefore, support will be provided for development of a WSS Sector Emergency
Preparedness and Disaster Risk Management Plan, to strengthen institutions, mechanisms and capacities
at all levels, in particular in communities to systematically contribute to building resilience to hazards
and disasters.
17
V. LEGAL INSTRUMENTS AND AUTHORITY
5.1 Legal instrument
An ADB loan will be used to finance this program.
5.2 Conditions associated with Bank’s intervention
5.2.1 Condition Precedent to Entry into Force of the Loan Agreement
The loan agreement shall enter into force subject to fulfilment by the Borrower of the provisions
of section 12.01 of the General Conditions Applicable to the African Development Bank Loan
Agreements and Guarantee Agreements.
5.2.2 Conditions Precedent to First Disbursement for the Loan
The obligation of the Bank to make the first disbursement of the Loan shall be conditional upon
entry into force of the Loan Agreement in accordance with Section 5.2.1 above and the
fulfilment, in form and substance satisfactory to the Bank, of the following conditions:
Evidence of having opened one (1) foreign currency denominated Special Account and one
(1) local currency denominated Special Account, at a bank acceptable to the Bank into
which the proceeds of the Loan will be deposited; and
Evidence of having signed a Subsidiary Financing Agreement between the Borrower and
the Lusaka Water and Sewage Company in form and substance acceptable to Bank.
5.2.3 Other Conditions
The Borrower/Recipient shall provide evidence, in form and substance satisfactory of the following:
The Borrower shall, by November 2015, submit evidence in form and substance
satisfactory to the Bank, of having established the Program Implementation Team whose
skills and qualifications are acceptable to the Bank;
The Borrower shall report on the sustainability agreement entered into between the Board
of LWSC and the Borrower on an annual basis; and
The Borrower shall renew or rollover the Sustainability Agreement for the period 2018-
2020.
5.2.4 Undertakings
Under the ADB Loan Agreement, the Borrower/ Recipient undertakes the following:
The Borrower undertakes to implement the recommendation of the tariff study and cause
the implementation of a program of tariff adjustments for water supply and sanitation
services in order to ensure sustainability of service provision including investment;
The Borrower undertakes to implement the Program in accordance with national
legislation, and the Environmental and Social Management Plan (ESMP), and report to the
Bank on a quarterly basis in a form acceptable to the Bank and;
The Borrower undertakes to complete the institutional assessment study before end of June
2016, and implement the recommendations by 2017.
18
5.3. Compliance with Bank Policies
The project complies with all applicable Bank policies.
VI RECOMMENDATION
Management recommends that the Board of Directors of the Bank approve the proposal for an
ADB loan of USD 50 million (equivalent UA 35.53 million) to the Republic of Zambia for the
purposes and subject to the conditions stipulated in this report
I
Appendix I. Country’s comparative socio-economic indicators
Year Zambia Africa
Develo-
ping
Countries
Develo-
ped
Countries
Basic Indicators
Area ( '000 Km²) 2011 753 30,323 98,458 35,811Total Population (millions) 2013 14.5 1,109.0 5,909.3 1,252.8Urban Population (% of Total) 2013 40.0 40.2 47.7 78.3Population Density (per Km²) 2013 17.7 46.9 70.7 23.5GNI per Capita (US $) 2012 1 350 1 719 3 815 38 412Labor Force Participation - Total (%) 2012-2013 39.2 37.4 67.9 72.1Labor Force Participation - Female (%) 2012-2013 45.6 42.5 38.6 44.6Gender -Related Dev elopment Index Value 2007-2011 0.473 0.502 0.694 0.911Human Dev elop. Index (Rank among 187 countries) 2012 163 ... ... ...Popul. Liv ing Below $ 1.25 a Day (% of Population)2008-2011 74.5 40.0 20.6 ...
Demographic Indicators
Population Grow th Rate - Total (%) 2013 3.2 2.5 1.3 0.3Population Grow th Rate - Urban (%) 2013 4.3 3.4 2.5 0.6Population < 15 y ears (%) 2013 46.6 40.9 28.3 16.4Population >= 65 y ears (%) 2013 2.6 3.5 6.1 16.8Dependency Ratio (%) 2013 99.6 77.9 52.4 49.9Sex Ratio (per 100 female) 2013 99.5 100.0 103.3 94.4Female Population 15-49 y ears (% of total population) 2013 22.9 24.0 53.1 45.2Life Ex pectancy at Birth - Total (y ears) 2013 58.1 59.2 68.4 77.8Life Ex pectancy at Birth - Female (y ears) 2013 60.0 60.3 70.3 81.2Crude Birth Rate (per 1,000) 2013 42.8 34.8 21.2 11.2Crude Death Rate (per 1,000) 2013 10.2 10.4 7.6 10.4Infant Mortality Rate (per 1,000) 2013 64.4 61.9 39.8 5.5Child Mortality Rate (per 1,000) 2013 99.8 97.4 56.3 6.6Total Fertility Rate (per w oman) 2013 5.7 4.6 2.6 1.7Maternal Mortality Rate (per 100,000) 2010 440.0 415.3 240.0 16.0Women Using Contraception (%) 2013 47.1 34.9 62.6 71.3
Health & Nutrition Indicators
Phy sicians (per 100,000 people) 2004-2011 6.6 47.1 117.8 297.8Nurses (per 100,000 people)* 2004-2011 78.4 132.6 202.7 842.7Births attended by Trained Health Personnel (%) 2006-2011 46.5 52.6 66.3 ...Access to Safe Water (% of Population) 2012 63.3 68.8 87.2 99.2Access to Health Serv ices (% of Population) 2004 90.2 65.2 80.0 100.0Access to Sanitation (% of Population) 2012 42.8 39.4 56.9 96.2Percent. of Adults (aged 15-49) Liv ing w ith HIV/AIDS 2012 12.7 3.9 1.2 ...Incidence of Tuberculosis (per 100,000) 2012 427.0 223.6 144.0 23.0Child Immunization Against Tuberculosis (%) 2012 83.0 83.0 81.5 96.1Child Immunization Against Measles (%) 2012 83.0 74.0 83.0 94.3Underw eight Children (% of children under 5 y ears) 2005-2012 14.9 19.7 17.0 1.4Daily Calorie Supply per Capita 2009 1 879 2 481 2 675 3 285Public Ex penditure on Health (as % of GDP) 2011-2012 3.7 2.9 3.0 7.5
Education Indicators
Gross Enrolment Ratio (%)
Primary School - Total 2012 113.6 101.9 109.4 100.9 Primary School - Female 2012 113.3 97.9 107.6 100.6 Secondary School - Total 2012 20.5 47.4 69.1 100.2 Secondary School - Female 2012 15.2 44.0 67.8 99.7Primary School Female Teaching Staff (% of Total) 2012 53.1 46.6 58.0 84.3Adult literacy Rate - Total (%) 2012 ... 62.0 80.3 99.2Adult literacy Rate - Male (%) 2012 ... 70.7 85.9 99.3Adult literacy Rate - Female (%) 2012 ... 53.7 74.9 99.0Percentage of GDP Spent on Education 2008-2012 1.3 5.3 4.3 5.5
Environmental Indicators
Land Use (Arable Land as % of Total Land Area) 2011 4.6 7.6 10.7 10.8Annual Rate of Deforestation (%) 2000-2009 2.4 0.6 0.4 -0.2Forest (As % of Land Area) 2011 66.3 23.0 28.2 35.0Per Capita CO2 Emissions (metric tons) 2010 0.2 1.2 3.0 11.6
Sources: AfDB Statistics Department Databases; last update :
United Nations Population Division, World Population Prospects: The 2012 Revision;
World Bank: World Development Indicators; UNAIDS; UNSD; WHO, UNICEF, WRI, UNDP; Country Reports.
For any given interval, the value refers to the most recent year available during the period
Note : n.a. : Not Applicable ; … : Data Not Available.
May 2014
0102030405060708090
2005
2006
2007
2008
2009
2010
2011
2012
2013
Infant Mortality Rate( Per 1000 )
Zambia Africa
0
200
400
600
800
1000
1200
1400
1600
1800
2004
2005
2006
2007
2008
2009
2010
2011
2012
GNI Per Capita US $
Zambia Africa
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
2005
2006
2007
2008
2009
2010
2011
2012
2013
Population Growth Rate (%)
Zambia Africa
111213141516171
2005
2006
2007
2008
2009
2010
2011
2012
2013
Life Expectancy at Birth (years)
Zambia Africa
II
Appendix II: Table of AFDB’s portfolio in the Zambia
Division Long name Status of
Project
Finance
project Sector Name Window
Approval
date
Entry into
force
Effective
1st disb
Planned project
completion date Amount App. Amount Dis.
Dis.
Ratio Age
OSAN1
GAFSP-AGRICULTURE
PRODUCTIVITY AND MARKET
ENHANCEMENT PROJEC
OnGo P-ZM-AA0-
019 Agriculture
[OTHERS] 3/26/2014 6/10/2014 10/20/2014 6/30/2020 22,493,675.5 463,050.9 2.1
1.1
OSAN1 LIVESTOCK INFRASTRUCTURE
SUPPORT PROJECT (LISP) OnGo
P-ZM-AAE-
001 Agriculture [ ADF ] 6/19/2013 12/30/2013 3/25/2014 12/31/2018 12,000,000.0 916,122.5 7.6
1.9
OSAN1 PROJECT PREPARATION FACILITY -
ZAMBIA LISP OnGo
P-ZM-AAE-
002 Agriculture [ ADF ] 3/29/2013 8/1/2013 2/26/2014 8/31/2015 300,000.0 196,935.9 65.6
2.1
OSAN3 LAKE TANGANYIKA DEVELOPMENT
SUPPORT PROJ APVD
P-ZM-AA0-
021 Agriculture [ ADB ] 12/18/2014 12/31/2018 16,253,704.4 0.0 0.0
0.4
OSAN3 LAKE TANGANYIKA DEVELOPMENT
SUPPORT PROJ APVD
P-ZM-AA0-
021 Agriculture
[OTHERS] 12/18/2014 12/31/2018 5,059,631.4 0.0 0.0
0.4
Agriculture 56,107,011.2 1,576,109.3 2.8 1.2
OSAN3 STRENGTHENING CLIMATE
RESILIENCE IN THE KAFUE BASIN OnGo
P-ZM-CZ0-
001 Environment
[OTHERS] 10/18/2013 12/18/2013 7/21/2014 6/30/2019 12,649,078.4 0.0 0.0
1.6
OSAN3 STRENGTHENING CLIMATE
RESILIENCE IN THE KAFUE BASIN OnGo
P-ZM-CZ0-
001 Environment
[OTHERS] 10/18/2013 12/18/2013 7/21/2014 6/30/2019 14,817,491.9 608,910.7 4.1
1.6
Environment 27,466,570.3 608,910.7 2.2 1.6
OFSD1
LINE OF CREDIT TO FRB
SUBSIDIARY, FIRST NATIONAL
BANK OF ZAM
APVD P-ZM-HAB-
022 Finance [ ADB ] 12/12/2012 5/21/2022 31,780,267.4 0.0 0.0
2.4
OFSD1
AFRICA SME PROGRAM LOC -
CETZAM FINANCIAL SERVICES
PLC ZA
OnGo P-ZM-HB0-
003 Finance [ ADB ] 10/21/2013 9/4/2014 10/1/2014 3/27/2020 1,084,206.7 1,084,206.7 100.0
1.5
Finance 32,864,474.2 1,084,206.7 3.3 2.0
ONEC2 POWER TRANSMISSION PROJECT OnGo P-ZM-FA0-
003 Power [ ADF ] 6/13/2012 9/24/2013 2/10/2015 12/31/2018 30,000,000.0 0.0 0.0
2.9
ONEC2 POWER TRANSMISSION PROJECT OnGo P-ZM-FA0-
003 Power [ NTF ] 6/13/2012 12/31/2018 6,400,000.0 0.0 0.0
2.9
OPSM3 ITEZHI-TEZHI HYDROPOWER
PROJECT APVD
P-ZM-FAB-
004 Power [ ADB ] 6/13/2012 4/14/2014 12/31/2018 25,298,156.9 0.0 0.0
2.9
Power 61,698,156.9 0.0 0.0 2.9
OSHD2
SUPPORT FOR SCIENCE AND
TECHNOLOGY EDUCATION PROJECT
(SSTEP/
OnGo P-ZM-IA0-005 Social [ ADF ] 11/20/2013 1/7/2015 1/7/2015 12/31/2019 22,220,000.0 767,358.8 3.5
1.5
Social 22,220,000.0 767,358.8 3.5 1.5
OITC2 BOTSWANA/ZAMBIA-KAZUNGULA
BRIDGE PROJECT OnGo P-Z1-DB0-031 Transport [ ADF ] 12/7/2011 9/3/2012 11/16/2012 12/31/2019 51,000,000.0 520,945.4 1.0
3.4
OITC2 MULTI-NACALA CORRIDOR
PROJECT-PHASE II (ZAMBIA) OnGo P-Z1-DB0-063 Transport [ ADF ] 9/27/2010 6/10/2011 10/24/2011 12/1/2016 69,369,000.0 18,971,132.7 27.3
4.6
Transport 120,369,000.0 19,492,078.1 16.2 4.0
AWTF MULTIPURPOSE SMALL DAMS OnGo P-ZM-EAZ-
002 Water Sup/Sanit
[OTHERS] 9/4/2012 8/28/2013 1/31/2014 5/28/2016 744,683.4 223,405.0 30.0
2.7
OWAS2 NATIONAL RURAL WATER SUPPLY
AND SANITATION PROGRAM OnGo P-ZM-E00-009 Water Sup/Sanit [ ADF ] 10/31/2006 11/15/2007 1/29/2008 3/31/2015 15,000,000.0 10,954,689.4 73.0
8.5
OWAS2
TRANSFORMING RURAL
LIVELIHOODS IN WESTERN ZAMBIA
- NATIONAL
APVD P-ZM-E00-028 Water Sup/Sanit [ ADB ] 9/10/2014 12/31/2019 11,203,469.5 0.0 0.0
0.7
OWAS2
TRANSFORMING RURAL
LIVELIHOODS IN WESTERN ZAMBIA
- NATIONAL
APVD P-ZM-E00-028 Water Sup/Sanit
[OTHERS] 9/10/2014 1/7/2015 12/31/2019 2,743,570.3 0.0 0.0
0.7
Water Sup/Sanit 14,691,723.1 223,405.00 37.6 3.1
Grand Total 335,416,935.6 23,752,068.70 7.08 2.2
III
Appendix III. Key related projects financed by the Bank and other development partners in the country Donor
Agency Program Title Project Coverage Total Budget (USD) Implementation Organisation Project Status
AfDB
National Rural Water Supply and
Sanitation Program II Western Province 15,500,000
Ministry of Local Government and
Housing On-going
To develop and field test guidelines for
community driven planning, design
and implementation of multi-purpose
small dams.
Nationwide 1,235,000 Ministry of Mines, Energy and
Water Development On-going
European
Investment
Bank
Zambia water and Sanitation Project
Mufulira,
Chililabombwe,
Chingola,
187,000,000 Mulonga Water and Sewerage
Company On-going
UK DFID/
UNICEF
3 million Sanitation and Hygiene
Project, 44 Districts 32,000,000
Ministry of Local Government and
Housing On-going
Germany
National Rural Water Supply and
Sanitation Programme (Basket
Financing Mechanism)
6 districts in five
provinces 13,000,000
Ministry of Local Government and
Housing On-going
Urban Water Supply and Sanitation
(Basket Financing Mechanism) Nationwide 10,400,000
Ministry of Local Government and
Housing On-going
Devolution Trust Fund - Financial
Support to DTF in 4 phases Nationwide 18,300,000
Ministry of Local Government and
Housing On-going
Urban Water Supply and Sanitation
Eastern Province
Eastern Province-
Nyimba, Chadiza, Katete
and Chipata districts
21,800,000 Eastern Water and Sewerage
Company
On-going
JICA
To establish and roll-out the SOMAP
O&M model
4 Districts in Luapula
Province 6,000,000
Ministry of Local Government and
Housing
On-going
To Construct 216 boreholes with
handpumps
Mansa, Mwense,
Milenge and Nchelenge
in Luapula Province
8,700,000
Ministry of Local Government and
Housing
On-going
US MCC Lusaka Water Supply, Sanitation &
Drainage (LWSSD) Project Lusaka Province 355,000,000
Lusaka Water and Sewerage
Company On-going
US AID
To provide water supply, sanitation
and hygiene facilities in more than 600
schools in 4 districts.
Chadiza, Chipata,
Mambwe and Lundazi of
Eastern Province.
20,000,000
Ministry of Education, Science,
Technology, Vocational Training
and Early Education
(MOESVTEE) and collaborating
with MLGH
On-going
UNICEF
Rural Water, Sanitation, Hygiene
Promotion
Nationawide 22,000,000
Ministry of Local Government and
Housing, Ministry of Chiefs and
Traditional Affairs and Ministry of
Education
On-going
World Bank
Water Resources Management Nationawide 50,000,000 Ministry of Mines, Energy and
Water Development On-going
Irrigation development and Support
project 3 Sites 115,000,000
M Ministry of Agriculture and
Livestock On-going
Livestock Development and Animal
health project Selected provinces 50,000,000 MAL On-going
IV
Appendix IV. Map of Zambia showing Lusaka Water and Sewerage Company and other utilities
Disclaimer
This map was provided by the African Development Bank exclusively for the use of the readers of the report to which it is attached. The names used and the borders shown do
not imply on the part of the Bank and its members any judgment concerning the legal status of a territory nor any approval or acceptance of these borders.
V
APPENDIX V: CLIMATE CHANGE SCREENING
Adaptation Review Summary
Climate change is making sewage treatment plants and sewerage networks more vulnerable to
major failures and overflows due to more intense storms and increasingly heavy precipitation
events. Climate change that is already underway will lead to overwhelmed sewerage systems,
resulting in massive overflows of partially or untreated sewage into residential areas and receiving
waters such as Ngwerere and Chunga steams surrounding Lusaka; water that of the people of
Lusaka and Chongwe town rely on for food and health. The Lusaka Sanitation Program will
support the development of a Water and Sanitation Emergency Preparedness and Disaster Risk
Management plan for Lusaka which will be closely linked with preparation of Climate Change &
Climate Variability adaptation plans.
The plans will respond to climate risks by improving the design of the key sewerage
infrastructure, increase resilience to flooding of communities utilities by building new resilient
sanitation facilities, modify existing assets to be more climate resilience by increasing the
interceptor sizes from 300mm diameter to 750mm, whereas the major sewer collector lines will
be increased from 200mm diameter to 400mm to accommodate both the increase in population
and to cope with more intense rainfall and accommodate low level flooding;, improve master
planning and increase institutional capacity for responding to climate related damage. The plans
would also support increased local community knowledge of risks and responses when disaster
strikes and will contribute to increased resilience of communities.
Selected adaptation component Suggested activities
Improve disaster risk management by
developing a Water and Sanitation Sector
Emergency Preparedness and Disaster Risk
Management Plan to increase LWSC/
National and Municipal agencies and local
community knowledge of risks and
responses
- Provide information to LWSC, National
and Municipal institutions and carry out
awareness raising activities
- Train stakeholders in use of water and
sanitation facilities during climate related
emergencies
- Climate resilient infrastructure better able
to cope with hazards such as flooding and
extreme storms.
- Improve operational risk management to
ensure preventive and routine
maintenance is effectively carried out to
reduce sewage blockages and spillages as
a result of adverse weather
- Modifying existing sewerage system
assets to increase climate resilience by
expanding the capacity of sewerage
systems and ensure protection of local
environment