    Station : NTPC - Simhadri BHEL Ref No. PS-DC-186-500-0015

    NTPC Ref No. SIM/1/TS/1/011

    Sheet 1 of 14

    Plant Area : BOILER

    CHEMICAL CLEANING OF AUXILIARY BOILER

    SL.NO. LIST OF CONTENTS

    PLANT DETAILS

    OBJECTIVE

    PROPOSAL

    SERVICES REQUIRED

    SAFETY PRECAUTIONS

    EMERGENCY PROCEDURES

    STATE OF THE PLANT

    METHOD

    COMPLETION CRITERIA

    APPENDICES

    A. TECHNICAL SPECIFICATIONS

    B. SAFETY CLEARANCE CERTIFICATE

    C. MECHANICAL PLANT ITEM COMPLETION LIST &

    ELECTRICAL PLANT AND C&I PLANT ITEM COMPLETION LIST

    1.0

    2.0

    3.0

    4.0

    5.0

    6.0

    7.0

    8.0

    9.0

    10.0

  • 7/28/2019 ABO AUX

    2/16

    Station : NTPC - Simhadri BHEL Ref No. PS-DC-186-500-0015

    NTPC Ref No. SIM/1/TS/1/011

    Sheet 2 of 14

    Plant Area : BOILER

    CHEMICAL CLEANING OF AUXILIARY BOILER

    1.0 PLANT DETAILS STATUS

    The Steam generator is of natural circulation. Water tube

    design. arranged for pressurized firing. Basically it is a two drum

    vertical bent tube arrangement with water cooled furnace walls

    combined with the convective boiler bank surface. The complete

    steam generator is of the bottom supported design resting on

    concrete pedestals.

    The upper and lower drums are connected by the bank tubes.

    The steam drum is provided with efficient internals for steam

    separation. The unheated down comers are located in the rear

    half of boiler side wall ensures adequate circulation in the boiler.

    The boiler bank tubes are arranged in line for the best heat

    absorption. Minimum draft loss and easy tube inspection and

    cleaning. Required accessibility is provided at the side of the

    boiler bank convective surface. Adequate peep holes are

    provided to watch the flame.

    Feedwater is fed into the upper drum and circulation is

    maintained in the boiler bank through the downcomers. From

    the bottom drum water flows through the heat absotbing

    furnace tubes and back into the steam drum. After separation of

    moisture in the internals, the saturated steam flows through

    superheaters and to SH outlet steam collecting header from

    where the main steam is tapped off.

    The main fuels are Heavy Fuel Oil and Light Diesel Oil. The

    firing system consists of one no oil burner with register locatedin the front wall to carry MCR capacity with either of the fuels.

    The fuel oil is steam atomized: light oil is air atomized. High

    Energy Arc (HEA) ignitor is used for lighting up the burner. A

    flame scanning system is provided to monitor the flame

    condition in the furnace.

    Signatures

    NTPC BHEL

    Station : NTPC - Simhadri BHEL Ref No. PS-DC-186-500-0015 Sheet 3 of 14

  • 7/28/2019 ABO AUX

    3/16

  • 7/28/2019 ABO AUX

    4/16

    CHEMICAL CLEANING OF AUXILIARY BOILER

    2.0 OBJECTIVE STATUS

    2.1 The objective of this commissioning schedule is to clean the

    internal surface of the steam generating portion and heating

    surface (Economiser) using specified chemicals.

    Signatures

    NTPC BHEL

    Station : NTPC - Simhadri BHEL Ref No. PS-DC-186-500-0015

    NTPC Ref No. SIM/1/TS/1/011

    Sheet 5 of 14

    Plant Area : BOILER

    CHEMICAL CLEANING OF AUXILIARY BOILER

    3.0 PROPOSAL STATUS

  • 7/28/2019 ABO AUX

    5/16

    The objectives are achieved by carrying out the following

    testing proposals.

    3.1 By carrying out an effective boil-out, grease, oil and any

    protective coatings applied are removed from the interior

    pressure parts of the auxiliary boiler

    Signatures

    NTPC BHEL

    Station : NTPC - Simhadri BHEL Ref No. PS-DC-186-500-0015

    NTPC Ref No. SIM/1/TS/1/011

    Sheet 6 of 14

    Plant Area : BOILER

    CHEMICAL CLEANING OF AUXILIARY BOILER

    4.01 SERVICES REQUIRED STATUS

    All the required quantities of chemicals as given below should

    be made available prior to the commencement of the process.

  • 7/28/2019 ABO AUX

    6/16

    SPECIFICATION OF CHEMICALS & QUANTITY

    NAME OF CHEMICALS

    1. Trisodium Phosphate (Na3PO4. 12H2O) 30 Kg

    (IS:573/1992)

    2.Disodium Phosphate(Na2 HP O4.12 H2O) 15 Kg

    (IS:566/1991)

    4.02 Supply of adequate DM water to be ensured

    4.03 415 V Supply available

    4.04 220 AC/Dc, 110V AC, Control Supply available (Which ever is

    applicable).

    4.05 Instrument / Service Air Available

    4.06 Flood Lights / Telephones / Walkie - Talkie are available

    4.07 Ambulance / car for emergency / fire tender available

    4.08 Drum level guage glass should be made available with lighting

    arrangement and tale-tale switch cum light arrangement

    4.09 Sufficient quantity of Raw/Fire water to be ensured for theneutralisation of the alkali boil out effluent in line with A.P.

    pollution control Board Norms

    Signatures

    NTPC BHEL

    Station : NTPC - Simhadri BHEL Ref No. PS-DC-186-500-0015

    NTPC Ref No. SIM/1/TS/1/011

    Sheet 7 of 14

    Plant Area : BOILER

    CHEMICAL CLEANING OF AUXILIARY BOILER

    5.0 SAFETY PRECAUTIONS STATUS

    5.1 SAFETY EQUIPMENTS : ENSURE THE AVAILABILITY OF

    1. GUM BOOTS (Various Sizes) 6 Pairs

    2. Rubber Gloves 6 Pairs

    3. Rubber or Polythne Aprons 6 Nos.

  • 7/28/2019 ABO AUX

    7/16

    4. Helmets 12 Nos.

    5. Safety Goggles Plain Glass 6 Nos.

    6. Face Mask (Transparent, Plastic) 4 Nos.

    7. First aid box (containing dilute ammonium hydroxide, 50%sodium bicarbonate solution, eye loction, bandages,tincture of idodine, cotton, burnol etc.

    8. Safety shower.

    EMERGENCY PROVISIONS

    5.2 Flushing and washing water supplies

    5.2.1 Ample supplies of flushing and washing water supplies shallbe provided at all possible points of discharge, spillage orescape of chemicals.

    5.2.2 Adequate provisions shall be made for emergency treatmentof the eyes, comprising eye wash bottles, locatedconveniently to places where charging of chemicals areplanned.

    5.2.3 Telephone facilities shall be provided within a reasonabledistance of the place where chemicals are being used

    Signatures

    NTPC BHEL

  • 7/28/2019 ABO AUX

    8/16

    Station : NTPC - Simhadri BHEL Ref No. PS-DC-186-500-0015

    NTPC Ref No. SIM/1/TS/1/011

    Sheet 8 of 14

    Plant Area : BOILER

    CHEMICAL CLEANING OF AUXILIARY BOILER

    6.0 EMERGENCY PROCEDURES STATUS

    6.1 The testing team should be aware of the operating

    procedures of fire extinguishers to be used for quenching

    minor or major fires

    6.2 The testing team should be aware of the procedure to be

    followed in case of accident involving personnel injury.

    Signatures

    NTPC BHEL

  • 7/28/2019 ABO AUX

    9/16

    Station : NTPC - Simhadri BHEL Ref No. PS-DC-186-500-0015

    NTPC Ref No. SIM/1/TS/1/011

    Sheet 9 of 14

    Plant Area : BOILER

    CHEMICAL CLEANING OF AUXILIARY BOILER

    7.0 STATE OF THE PLANT STATUS

    7.1 Auxilary Boiler erection must have been completed as per

    approved scheme in respect of all ie. machanical, electrical

    and C&I area.

    7.2 Hydraulic test of boiler should have been completed to the

    required parameter. Pl. specify the HYD. Test Pressure.

    7.3 Preboiler system circuits should be available for operation.

    7.4 For alkali boilout, minimum essential instruments required for

    boiler light up are made available

    7.5 Boiler should be ready for regular operation as per Q & M

    instructions.

    7.6 Sampling system should be ready.

    7.7 Ensure free access to all equipment.

    7.8 Ensure the readiness of fire fighting system as envisaged in

    the design.

    7.9 Ensure the availability of fire tender near the boiler area.

    Signatures

    NTPC BHEL

    Station : NTPC - Simhadri BHEL Ref No. PS-DC-186-500-0015NTPC Ref No. SIM/1/TS/1/011

    Sheet 10 of 14

  • 7/28/2019 ABO AUX

    10/16

    Plant Area : BOILER

    CHEMICAL CLEANING OF AUXILIARY BOILER

    8.0 METHOD STATUS

    ALKALI BOIL OUT

    8.1 The boiler (steam generating surfaces and economiser) is

    filled with an alkaline solution containing 500 ppm of

    disodium phosphate dodeca hydrate, and 1000 ppm of Tri

    sodium phosphate do deca hydrate and then fired to raise

    the pressure to 10 kg/ cm2, following the specified

    operational procedures.

    8.2Procedure

    Prepare the boil out chemical solution in demineralised waterin a chemical mixing tank. The solution is formulated bydissolving the following proportionate quantities ofchemicals, depending on the volume of the system to becleaned.

    1. 0.05% Na2 HPO4 12 H2O

    2. 0.1 % Na3 PO4 12 H2O

    8.3 Hold the solution prepared as above in the tank andhomogenise the same by proper mixing the solution.

    8.4 Start filling the Aux. boiler with demineralised water, until the

    water is seen little above the bottom of the upper drum.

    8.5 Pour the chemical solution with the drum through the manhole

    by several increments.

    8.6 Close the man hole cover and fill up with DM water upto

    normal operation level.

    Signatures

    NTPC BHEL

    Station : NTPC - Simhadri BHEL Ref No. PS-DC-186-500-0015

    NTPC Ref No. SIM/1/TS/1/011

    Sheet 11 of 14

    Plant Area : BOILER

    CHEMICAL CLEANING OF AUXILIARY BOILER

  • 7/28/2019 ABO AUX

    11/16

    STATUS

    8.7 Light up the boiler as per O & M instructions and gradually

    raise the pressure to 10 Kg/CM2 . Hold the pressure for four

    hours. Prescribe blow down every 2 Hrs. Once, after killing the

    fire; Duration of the blow down shall be for one minute Ensure

    that the drum level does not go out of gauge glass vision.

    8.8 Repeat the operation of raising the pressure to 10 kg/cm2 and

    prescribing blow down every 2 hours (Total 4 Blow downs)

    after killing fire.

    8.9 The boil out is declared completed when minimum 4 blow

    downs are completed.

    8.10 Drain the boiler, when it is cooled, as per O & M instructions.

    Once the draining is completed, fill the boiler with

    demineralised water, through boiler fill pump. Back flush the

    superheaters with DM water containing 200 ppm hydrazine

    and pH 10.0 with NH3 till it overflows into the drum. Drain the

    boiler to the waste disposal system. Inspect the upper drum

    and manually clean, if any loose muck and sludge are

    present.

    8.10 The effluent of alkali boil out shall be neutralised and

    disposed in line with A.P. pollution control Board norms.

    PH of the solution is lowered to less than 9.0 by sufficient

    dilution with raw / fire water.

    Signatures

    NTPC BHEL

    Station : NTPC - Simhadri BHEL Ref No. PS-DC-186-500-0015

    NTPC Ref No. SIM/1/TS/1/011

    Sheet 12 of 14

    Plant Area : BOILER

    CHEMICAL CLEANING OF AUXILIARY BOILER

  • 7/28/2019 ABO AUX

    12/16

    9.0 COMPLETION CRITERIA STATUS

    The completion criteria is time based boil out at 10 kg

    persg.cm for 10 hrs with intermittent blowdown at once in 2

    hours with each blowdown for 1 minute Duration. Drum is

    inspected and all the loose muck and other dirts are cleaned( Upper Drum )

    Signatures

    NTPC BHEL

  • 7/28/2019 ABO AUX

    13/16

    Station : NTPC - Simhadri BHEL Ref No. PS-DC-186-500-0015

    NTPC Ref No. SIM/1/TS/1/011

    Sheet 13 of 14

    Plant Area : BOILER

    CHEMICAL CLEANING OF AUXILIARY BOILER

    10.0 APPENDICES

    a. TECHNICAL SPECIFICATION

    1. Boiler : Natural circulation water tube design, bottomsupported

    2. Boiler Drum

    Drum ID 1219(S) 762(W)Shell Length 8810 8610Material SA515 Gr 70

    3. Furnace

    Width 2897 mmDepth 8258 mmHeight 4242 mm

    4. Super Heater

    Tube O.D 51.0 mmNo.of Assemblies 15Heating Surface 13.75m2

    5. Predicted Performance

    Flow Tonnnes1. SH Steam 55.02. Combustion Air 61.03. Flue Gas 65.0

    Pressure Kg/Cm2 (g)

    1. Drum Operating 21.42. Drum Design 25.03. Steam Pressure at

    SHO outlet 18.0

    5. Temperature

    1. At SHO 2150 C

    Signatures

    NTPC BHEL

  • 7/28/2019 ABO AUX

    14/16

    Station : NTPC - Simhadri BHEL Ref No. PS-DC-186-500-0015

    NTPC Ref No. SIM/1/TS/1/011

    Sheet 14 of 14

    Plant Area : BOILER

    CHEMICAL CLEANING OF AUXILIARY BOILER

    STATUS

    6. SAFETY VALVES

    Sl.No

    LOCATIONVALVE

    TAG NO

    VALVE SETPRESSURE

    KSC

    %BLOWDOWN

    REMARK%

    OPEN CLOSE

    1) DRUM SV1 25.0 24.0 4.02) DRUM SV2 25.8 24.7 4.3

    3) SH SV3 20.5 19.6 4.4

    NOTE: Percentage blow down to be within 3% -5% of value lifting pressure

    7. Water Valume in m3

    1.Upper drum upto normal water level 3.9

    Upper drum flooded 11.3

    2.Lower drum 4.2

    3.water walls including Boiler bank tubes 18.7

    4.SH system upto M.S.Stop valve 2.0

    b. SAFETY CLEARANCE CERTIFICATE

    List of signatories required before running the systemwill be mutually decided at site.

    c. MECHANICAL /ELECTRICAL/C & I PLANT ITEM

    COMPLETION LIST

    The plant item completion list for the above areas willbe mutually prepared at site by BHEL and NTPC.

    Signatures

    NTPC BHEL

  • 7/28/2019 ABO AUX

    15/16

    CHEMICAL CLEANING OF AUXILIARY BOILER

  • 7/28/2019 ABO AUX

    16/16

    PROGRESS REPORT : SG 16

    JULY 2001