Station : NTPC - Simhadri BHEL Ref No. PS-DC-186-500-0015
NTPC Ref No. SIM/1/TS/1/011
Sheet 1 of 14
Plant Area : BOILER
CHEMICAL CLEANING OF AUXILIARY BOILER
SL.NO. LIST OF CONTENTS
PLANT DETAILS
OBJECTIVE
PROPOSAL
SERVICES REQUIRED
SAFETY PRECAUTIONS
EMERGENCY PROCEDURES
STATE OF THE PLANT
METHOD
COMPLETION CRITERIA
APPENDICES
A. TECHNICAL SPECIFICATIONS
B. SAFETY CLEARANCE CERTIFICATE
C. MECHANICAL PLANT ITEM COMPLETION LIST &
ELECTRICAL PLANT AND C&I PLANT ITEM COMPLETION LIST
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
10.0
7/28/2019 ABO AUX
2/16
Station : NTPC - Simhadri BHEL Ref No. PS-DC-186-500-0015
NTPC Ref No. SIM/1/TS/1/011
Sheet 2 of 14
Plant Area : BOILER
CHEMICAL CLEANING OF AUXILIARY BOILER
1.0 PLANT DETAILS STATUS
The Steam generator is of natural circulation. Water tube
design. arranged for pressurized firing. Basically it is a two drum
vertical bent tube arrangement with water cooled furnace walls
combined with the convective boiler bank surface. The complete
steam generator is of the bottom supported design resting on
concrete pedestals.
The upper and lower drums are connected by the bank tubes.
The steam drum is provided with efficient internals for steam
separation. The unheated down comers are located in the rear
half of boiler side wall ensures adequate circulation in the boiler.
The boiler bank tubes are arranged in line for the best heat
absorption. Minimum draft loss and easy tube inspection and
cleaning. Required accessibility is provided at the side of the
boiler bank convective surface. Adequate peep holes are
provided to watch the flame.
Feedwater is fed into the upper drum and circulation is
maintained in the boiler bank through the downcomers. From
the bottom drum water flows through the heat absotbing
furnace tubes and back into the steam drum. After separation of
moisture in the internals, the saturated steam flows through
superheaters and to SH outlet steam collecting header from
where the main steam is tapped off.
The main fuels are Heavy Fuel Oil and Light Diesel Oil. The
firing system consists of one no oil burner with register locatedin the front wall to carry MCR capacity with either of the fuels.
The fuel oil is steam atomized: light oil is air atomized. High
Energy Arc (HEA) ignitor is used for lighting up the burner. A
flame scanning system is provided to monitor the flame
condition in the furnace.
Signatures
NTPC BHEL
Station : NTPC - Simhadri BHEL Ref No. PS-DC-186-500-0015 Sheet 3 of 14
7/28/2019 ABO AUX
3/16
7/28/2019 ABO AUX
4/16
CHEMICAL CLEANING OF AUXILIARY BOILER
2.0 OBJECTIVE STATUS
2.1 The objective of this commissioning schedule is to clean the
internal surface of the steam generating portion and heating
surface (Economiser) using specified chemicals.
Signatures
NTPC BHEL
Station : NTPC - Simhadri BHEL Ref No. PS-DC-186-500-0015
NTPC Ref No. SIM/1/TS/1/011
Sheet 5 of 14
Plant Area : BOILER
CHEMICAL CLEANING OF AUXILIARY BOILER
3.0 PROPOSAL STATUS
7/28/2019 ABO AUX
5/16
The objectives are achieved by carrying out the following
testing proposals.
3.1 By carrying out an effective boil-out, grease, oil and any
protective coatings applied are removed from the interior
pressure parts of the auxiliary boiler
Signatures
NTPC BHEL
Station : NTPC - Simhadri BHEL Ref No. PS-DC-186-500-0015
NTPC Ref No. SIM/1/TS/1/011
Sheet 6 of 14
Plant Area : BOILER
CHEMICAL CLEANING OF AUXILIARY BOILER
4.01 SERVICES REQUIRED STATUS
All the required quantities of chemicals as given below should
be made available prior to the commencement of the process.
7/28/2019 ABO AUX
6/16
SPECIFICATION OF CHEMICALS & QUANTITY
NAME OF CHEMICALS
1. Trisodium Phosphate (Na3PO4. 12H2O) 30 Kg
(IS:573/1992)
2.Disodium Phosphate(Na2 HP O4.12 H2O) 15 Kg
(IS:566/1991)
4.02 Supply of adequate DM water to be ensured
4.03 415 V Supply available
4.04 220 AC/Dc, 110V AC, Control Supply available (Which ever is
applicable).
4.05 Instrument / Service Air Available
4.06 Flood Lights / Telephones / Walkie - Talkie are available
4.07 Ambulance / car for emergency / fire tender available
4.08 Drum level guage glass should be made available with lighting
arrangement and tale-tale switch cum light arrangement
4.09 Sufficient quantity of Raw/Fire water to be ensured for theneutralisation of the alkali boil out effluent in line with A.P.
pollution control Board Norms
Signatures
NTPC BHEL
Station : NTPC - Simhadri BHEL Ref No. PS-DC-186-500-0015
NTPC Ref No. SIM/1/TS/1/011
Sheet 7 of 14
Plant Area : BOILER
CHEMICAL CLEANING OF AUXILIARY BOILER
5.0 SAFETY PRECAUTIONS STATUS
5.1 SAFETY EQUIPMENTS : ENSURE THE AVAILABILITY OF
1. GUM BOOTS (Various Sizes) 6 Pairs
2. Rubber Gloves 6 Pairs
3. Rubber or Polythne Aprons 6 Nos.
7/28/2019 ABO AUX
7/16
4. Helmets 12 Nos.
5. Safety Goggles Plain Glass 6 Nos.
6. Face Mask (Transparent, Plastic) 4 Nos.
7. First aid box (containing dilute ammonium hydroxide, 50%sodium bicarbonate solution, eye loction, bandages,tincture of idodine, cotton, burnol etc.
8. Safety shower.
EMERGENCY PROVISIONS
5.2 Flushing and washing water supplies
5.2.1 Ample supplies of flushing and washing water supplies shallbe provided at all possible points of discharge, spillage orescape of chemicals.
5.2.2 Adequate provisions shall be made for emergency treatmentof the eyes, comprising eye wash bottles, locatedconveniently to places where charging of chemicals areplanned.
5.2.3 Telephone facilities shall be provided within a reasonabledistance of the place where chemicals are being used
Signatures
NTPC BHEL
7/28/2019 ABO AUX
8/16
Station : NTPC - Simhadri BHEL Ref No. PS-DC-186-500-0015
NTPC Ref No. SIM/1/TS/1/011
Sheet 8 of 14
Plant Area : BOILER
CHEMICAL CLEANING OF AUXILIARY BOILER
6.0 EMERGENCY PROCEDURES STATUS
6.1 The testing team should be aware of the operating
procedures of fire extinguishers to be used for quenching
minor or major fires
6.2 The testing team should be aware of the procedure to be
followed in case of accident involving personnel injury.
Signatures
NTPC BHEL
7/28/2019 ABO AUX
9/16
Station : NTPC - Simhadri BHEL Ref No. PS-DC-186-500-0015
NTPC Ref No. SIM/1/TS/1/011
Sheet 9 of 14
Plant Area : BOILER
CHEMICAL CLEANING OF AUXILIARY BOILER
7.0 STATE OF THE PLANT STATUS
7.1 Auxilary Boiler erection must have been completed as per
approved scheme in respect of all ie. machanical, electrical
and C&I area.
7.2 Hydraulic test of boiler should have been completed to the
required parameter. Pl. specify the HYD. Test Pressure.
7.3 Preboiler system circuits should be available for operation.
7.4 For alkali boilout, minimum essential instruments required for
boiler light up are made available
7.5 Boiler should be ready for regular operation as per Q & M
instructions.
7.6 Sampling system should be ready.
7.7 Ensure free access to all equipment.
7.8 Ensure the readiness of fire fighting system as envisaged in
the design.
7.9 Ensure the availability of fire tender near the boiler area.
Signatures
NTPC BHEL
Station : NTPC - Simhadri BHEL Ref No. PS-DC-186-500-0015NTPC Ref No. SIM/1/TS/1/011
Sheet 10 of 14
7/28/2019 ABO AUX
10/16
Plant Area : BOILER
CHEMICAL CLEANING OF AUXILIARY BOILER
8.0 METHOD STATUS
ALKALI BOIL OUT
8.1 The boiler (steam generating surfaces and economiser) is
filled with an alkaline solution containing 500 ppm of
disodium phosphate dodeca hydrate, and 1000 ppm of Tri
sodium phosphate do deca hydrate and then fired to raise
the pressure to 10 kg/ cm2, following the specified
operational procedures.
8.2Procedure
Prepare the boil out chemical solution in demineralised waterin a chemical mixing tank. The solution is formulated bydissolving the following proportionate quantities ofchemicals, depending on the volume of the system to becleaned.
1. 0.05% Na2 HPO4 12 H2O
2. 0.1 % Na3 PO4 12 H2O
8.3 Hold the solution prepared as above in the tank andhomogenise the same by proper mixing the solution.
8.4 Start filling the Aux. boiler with demineralised water, until the
water is seen little above the bottom of the upper drum.
8.5 Pour the chemical solution with the drum through the manhole
by several increments.
8.6 Close the man hole cover and fill up with DM water upto
normal operation level.
Signatures
NTPC BHEL
Station : NTPC - Simhadri BHEL Ref No. PS-DC-186-500-0015
NTPC Ref No. SIM/1/TS/1/011
Sheet 11 of 14
Plant Area : BOILER
CHEMICAL CLEANING OF AUXILIARY BOILER
7/28/2019 ABO AUX
11/16
STATUS
8.7 Light up the boiler as per O & M instructions and gradually
raise the pressure to 10 Kg/CM2 . Hold the pressure for four
hours. Prescribe blow down every 2 Hrs. Once, after killing the
fire; Duration of the blow down shall be for one minute Ensure
that the drum level does not go out of gauge glass vision.
8.8 Repeat the operation of raising the pressure to 10 kg/cm2 and
prescribing blow down every 2 hours (Total 4 Blow downs)
after killing fire.
8.9 The boil out is declared completed when minimum 4 blow
downs are completed.
8.10 Drain the boiler, when it is cooled, as per O & M instructions.
Once the draining is completed, fill the boiler with
demineralised water, through boiler fill pump. Back flush the
superheaters with DM water containing 200 ppm hydrazine
and pH 10.0 with NH3 till it overflows into the drum. Drain the
boiler to the waste disposal system. Inspect the upper drum
and manually clean, if any loose muck and sludge are
present.
8.10 The effluent of alkali boil out shall be neutralised and
disposed in line with A.P. pollution control Board norms.
PH of the solution is lowered to less than 9.0 by sufficient
dilution with raw / fire water.
Signatures
NTPC BHEL
Station : NTPC - Simhadri BHEL Ref No. PS-DC-186-500-0015
NTPC Ref No. SIM/1/TS/1/011
Sheet 12 of 14
Plant Area : BOILER
CHEMICAL CLEANING OF AUXILIARY BOILER
7/28/2019 ABO AUX
12/16
9.0 COMPLETION CRITERIA STATUS
The completion criteria is time based boil out at 10 kg
persg.cm for 10 hrs with intermittent blowdown at once in 2
hours with each blowdown for 1 minute Duration. Drum is
inspected and all the loose muck and other dirts are cleaned( Upper Drum )
Signatures
NTPC BHEL
7/28/2019 ABO AUX
13/16
Station : NTPC - Simhadri BHEL Ref No. PS-DC-186-500-0015
NTPC Ref No. SIM/1/TS/1/011
Sheet 13 of 14
Plant Area : BOILER
CHEMICAL CLEANING OF AUXILIARY BOILER
10.0 APPENDICES
a. TECHNICAL SPECIFICATION
1. Boiler : Natural circulation water tube design, bottomsupported
2. Boiler Drum
Drum ID 1219(S) 762(W)Shell Length 8810 8610Material SA515 Gr 70
3. Furnace
Width 2897 mmDepth 8258 mmHeight 4242 mm
4. Super Heater
Tube O.D 51.0 mmNo.of Assemblies 15Heating Surface 13.75m2
5. Predicted Performance
Flow Tonnnes1. SH Steam 55.02. Combustion Air 61.03. Flue Gas 65.0
Pressure Kg/Cm2 (g)
1. Drum Operating 21.42. Drum Design 25.03. Steam Pressure at
SHO outlet 18.0
5. Temperature
1. At SHO 2150 C
Signatures
NTPC BHEL
7/28/2019 ABO AUX
14/16
Station : NTPC - Simhadri BHEL Ref No. PS-DC-186-500-0015
NTPC Ref No. SIM/1/TS/1/011
Sheet 14 of 14
Plant Area : BOILER
CHEMICAL CLEANING OF AUXILIARY BOILER
STATUS
6. SAFETY VALVES
Sl.No
LOCATIONVALVE
TAG NO
VALVE SETPRESSURE
KSC
%BLOWDOWN
REMARK%
OPEN CLOSE
1) DRUM SV1 25.0 24.0 4.02) DRUM SV2 25.8 24.7 4.3
3) SH SV3 20.5 19.6 4.4
NOTE: Percentage blow down to be within 3% -5% of value lifting pressure
7. Water Valume in m3
1.Upper drum upto normal water level 3.9
Upper drum flooded 11.3
2.Lower drum 4.2
3.water walls including Boiler bank tubes 18.7
4.SH system upto M.S.Stop valve 2.0
b. SAFETY CLEARANCE CERTIFICATE
List of signatories required before running the systemwill be mutually decided at site.
c. MECHANICAL /ELECTRICAL/C & I PLANT ITEM
COMPLETION LIST
The plant item completion list for the above areas willbe mutually prepared at site by BHEL and NTPC.
Signatures
NTPC BHEL
7/28/2019 ABO AUX
15/16
CHEMICAL CLEANING OF AUXILIARY BOILER
7/28/2019 ABO AUX
16/16
PROGRESS REPORT : SG 16
JULY 2001