Upload
buinhi
View
221
Download
3
Embed Size (px)
Citation preview
A Case Study in Hydropower Re-Development
William C. Rodgers
Director of Operations Great Bay Hydro Corporation
West Charleston Hydroelectric Project
A Case Study in Hydropower
Re-Development
William Rodgers
Great Bay Hydro Corporation
October 25, 2012
Case Study Outline
• I. Project Location and History
• II. Site Evaluation & Development
• III. Project Construction
• IV. Key Factors to Success
Project Location
• Town of Charleston, Vermont – Orleans County, NEK
– Clyde River
• West Charleston Dam – constructed circa 1900
– 196 feet long, 28 feet high
– 107 square mile drainage area
– 40 acre impoundment (Lubber Lake)
gawk, goon, lout, lummox, oaf, stumblebum, clod, lump, clumsy person
1. Lubber - an awkward stupid person;
2. Lubber - an inexperienced sailor
landlubber, landsman, beginner, initiate, tyro, novice Source: TheFreeDictionary.com
Project History
• Island Pond Electric – West Charleston began generating in 1903 – One of the early hydroelectric projects in VT
• Citizens Utilities – Owned the project from mid 1930’s thru 2004 – Station ceased operation in 1998 due to poor
condition of penstock
• Great Bay Hydro Corporation – Acquired West Charleston in 2004
Project License
• Clyde River Project, FERC No. 2306 – Newport Development (4,000 kw) – West Charleston Development (800 kw) – Original License 1963; New License 2003
• West Charleston requirements (2003 License) – Replace penstock & generating system – Run-of-river operation – Bypass flow: Oct-May=74 cfs; Jun-Sep=50 cfs – Remove 18 inch flashboards
Development Timeline
• Study & Evaluation 2004-2007
• Design & Permitting 2008-2010
• Construction 2010-2011
• Operational – April 2011
Study & Evaluation 2004-2007
• FERC licensed project – Time constraints – Rehabilitate or retire – Dam maintenance required
• Dam removal considered – Scope/process not well defined – Local opinion
• Re-development options – Penstock rehabilitation – New generating unit at dam
Design & Permitting 2008-2010
• New powerhouse at dam – Use all stream flow – New unit w/ increased efficiency – Reinstallation of flashboards – 25% increase in annual power generation
• Environmental enhancements – Elimination of 1600’ bypass reach – Improved water quality
• Agency Consultation – No fish passage requirement – Help meet State’s renewable energy goals
Key Factors to Development
• American Recovery & Reinvestment Act – Section 1603 Grants
– Incremental hydropower
– Begin construction 2009-10 (extended to 2011)
• Vermont FIT/SOC – VT utilities to procure 50 MW of renewables
– 20 year PPAs
– Technology specific pricing based on construction cost plus ROE
Design & Permitting 2008-2010 (cont.)
• FERC License Amendment
• Vermont WQC Amendment
• Historic & Archaeological (VT SHPO)
• Interconnection Upgrade (Section 248)
• Construction & Operating Plans – Penstock Removal – Trashrack Design – Flow Management & Monitoring – Water Quality Monitoring
Construction 2010-2011
• Remove gatehouse and penstock
• Demolish intake
• Excavate powerhouse footprint and tailrace
• Construct concrete powerhouse
• Install equipment
• Interconnection, start-up, testing
Key Factors to Success
• Creativity in Evaluation and Design
• Pre-consultation with Agencies
• State and Federal Renewable Incentives
• Participate in the Regulatory Process
• Execute the Plan