WORKFLOW MATURITY LEVELS LEVEL 2 LEVEL 3 LEVEL 1 LEVEL 0 NUMBER OF DATA DOMAINS: TASKS QUANTITIES AUTO-MATCHING ATTRIBUTES SMART COST ITEMS METHODOLOGIES RELATIONS RESOURCES ACTIVITY QUANTITIES SUBCONTRACTORS PROCUREMENT DATA-DRIVEN ADVANCED ANALYTICS ZONES TASKS & RELATIONS WORKFLOW SPEED 4D/5D BIM PLANNING

4D/5D BIM PLANNING - bexelmanager.com

  • Upload
    others

  • View
    13

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 4D/5D BIM PLANNING - bexelmanager.com

WORKFLOW MATURITY LEVELS

LEVEL 2

LEVEL 3

LEVEL 1

LEVEL 0

NUMBER OF DATA DOMAINS:

• TASKS • QUANTITIES • AUTO-MATCHING ATTRIBUTES

• SMART COST ITEMS • METHODOLOGIES • RELATIONS

• RESOURCES • ACTIVITY QUANTITIES • SUBCONTRACTORS

• PROCUREMENT • DATA-DRIVEN ADVANCED ANALYTICS • ZONES

TASK

S &

REL

ATI

ON

S

WORKFLOW SPEED

4D/5D BIM PLANNING

Page 2: 4D/5D BIM PLANNING - bexelmanager.com

TRADITIONALLY CREATED SCHEDULE

WITHOUT BIMBIM MODEL

CHALLENGING LINKING OF SCHEDULE TASKS WITH

MODEL ELEMENTS

4D SIMULATION DEVELOPMENT

CHALLENGES:

MANUALLY CREATING THOUSANDS OF TASKS AND RELATIONS

TASKS USUALLY DO NOT CONTAIN QUANTITIES, RESOURCES AND COSTS, OR TOP-DOWN COSTS ARE ADDED AS A ROUGH ESTIMATE

MANUAL CREATION OF SELECTION SETS OR ADDITIONAL NECESSARY PROPERTIES IN THE BIM MODEL

NOT ALIGNED SCHEDULE WITH THE BIM MODEL, MAKING VERY CHALLENGING LINKING OF SCHEDULE TASKS WITH MODEL ELEMENTS

MANUAL UPDATES OF ALL ANALYSES THAT CANNOT COPE WITH PROGRESS AND DESIGN UPDATES

SCHEDULES CONTAIN LIMITED NUMBER OF TASKS

PRIMARILY USED FOR MARKETING AND PRESENTATION PURPOSES

BENEFITS:

UNDERSTANDING OF CONSTRUCTION PROCESS

IDENTIFICATION OF CONSTRUCTION CONFLICTS AND SAFETY ISSUES

! !

4D/5D BIM PLANNING - LEVEL 0

Page 3: 4D/5D BIM PLANNING - bexelmanager.com

CHALLENGES:

MANUALLY CREATING THOUSANDS OF TASKS AND RELATIONS

TASKS USUALLY DO NOT CONTAIN QUANTITIES, RESOURCES AND COSTS, OR TOP-DOWN COSTS ARE ADDED AS A ROUGH ESTIMATE

MANUAL CREATION OF SELECTION SETS OR ADDITIONAL NECESSARY PROPERTIES IN THE BIM MODEL

NOT ALIGNED SCHEDULE WITH THE BIM MODEL, MAKING VERY CHALLENGING LINKING OF SCHEDULE TASKS WITH MODEL ELEMENTS

MANUAL UPDATES OF ALL ANALYSES THAT CANNOT COPE WITH PROGRESS AND DESIGN UPDATES

SCHEDULES CONTAIN LIMITED NUMBER OF TASKS

PRIMARILY USED FOR MARKETING AND PRESENTATION PURPOSES

BENEFITS:

3X FASTER THAN 4D/5D BIM PLANNING LEVEL 0

UNDERSTANDING OF CONSTRUCTION PROCESS

IDENTIFICATION OF CONSTRUCTION CONFLICTS AND SAFETY ISSUES

AUTO-MATCHING TASKS-ELEMENTS BASED ON PROPERTIES AND NAMING

TRADITIONALLY CREATED SCHEDULE

WITHOUT BIM

BIM MODEL

DEVELOPED FOLLOWING BEP (ATTRIBUTES, NAMING CONVENTION)

4D SIMULATION

DEVELOPMENT

4D/5D BIM PLANNING - LEVEL 1

Page 4: 4D/5D BIM PLANNING - bexelmanager.com

CHALLENGES:

MANUAL DEFINING ZONES AS ATTRIBUTES DURING MODEL DEVELOPMENT

BENEFITS:

10X-15X FASTER THAN 4D/5D BIM PLANNING LEVEL 1

REUSABILITY

CAPTURING EXPERTS LOGIC

DETAILED SCHEDULE

AUTOMATED UPDATES

SAFETY MEASURES DEFINED IN METHODOLOGIES

FLEXIBLE APPROACH

MANAGE TEMPLATES - EXCHANGE (IMPORT/FINE-TUNE/EXPORT)

ZONES

CREATION TEMPLATE

IfcEntity IfcObjectTypeIfcMaterialIfcProductDimensions orother key properties

• SMART SELECTION SETS• CUSTOM BREAKDOWN STRUCTURE• CONSTRUCTION METHODOLOGY• COST CLASSIFICATION• SCHEDULE CREATION TEMPLATE

CAPTURED EXPERT LOGICIFC BIM MODEL

*ACCORDING TO ISO 21511

GENERATE CUSTOM

BREAKDOWN STRUCTURE

IMPORT/CREATECOST VERSION

AUTOGENERATE SCHEDULE

SCHEDULE FINE-TUNING

METHODOLOGIES FLOWLINE

SCHEDULE OPTIMISATION

RESOURCE LEVELING

4D/5D SIMULATION

DEVELOPMENT

MULTIPLE SCHEDULE VERSIONS

• IFC

• POWER BI

• ORACLE PRIMAVERA

• MS PROJECT

• EXCEL

EXPORT/REPORTADD/CHANGE/DELETE:

NON-BIM TASKS, RELATIONS, DURATION

4D/5D BIM PLANNING - LEVEL 2

Page 5: 4D/5D BIM PLANNING - bexelmanager.com

BENEFITS:

1.5X FASTER THAN 4D/5D BIM PLANNING LEVEL 2

REUSABILITY

CAPTURING EXPERTS LOGIC

DETAILED SCHEDULE

AUTOMATED UPDATES

SAFETY MEASURES DEFINED IN METHODOLOGIES

FLEXIBLE APPROACH

MANAGE TEMPLATES - EXCHANGE (IMPORT/FINE-TUNE/EXPORT)

ZONES

CREATION TEMPLATE

IfcEntity IfcObjectTypeIfcMaterialIfcProductDimensions orother key properties

• SMART SELECTION SETS• CUSTOM BREAKDOWN STRUCTURE• CONSTRUCTION METHODOLOGY• COST CLASSIFICATION• SCHEDULE CREATION TEMPLATE

CAPTURED EXPERT LOGICIFC BIM MODEL

*ACCORDING TO ISO 21511

GENERATE CUSTOM

BREAKDOWN STRUCTURE

IMPORT/CREATECOST VERSION

AUTOGENERATE SCHEDULE

SCHEDULE FINE-TUNING

METHODOLOGIES FLOWLINE

SCHEDULE OPTIMISATION

RESOURCE LEVELING

4D/5D SIMULATION

DEVELOPMENT

MULTIPLE SCHEDULE VERSIONS

• IFC

• POWER BI

• ORACLE PRIMAVERA

• MS PROJECT

• EXCEL

EXPORT/REPORTADD/CHANGE/DELETE:

NON-BIM TASKS, RELATIONS, DURATION

LEVEL 3CONTAINMENT CLASH PROJECT SPECIFIC ZONES RELATIONS DATA ENRICHMENT

4D/5D BIM PLANNING - LEVEL 3

Page 6: 4D/5D BIM PLANNING - bexelmanager.com

METHODOLOGYLevel 02 Model sub-categories

ZONE 02 Sectors

ZONE 03Levels

METHODOLOGYLevel 01 Model

categories

ZONE 04Subsectors

ZONE 01 Buildings

Concrete finishing

Concrete pouring

Reinforcement

Formwork

4D/5D BIM PLANNING - LEVEL 3

Page 7: 4D/5D BIM PLANNING - bexelmanager.com

METHODOLOGYLevel 02 Model sub-categories

Novo Brdo E3

Novo Brdo E2

Building Type L

Building Type M

Building Type S

Building Type Z

Building Type So

Foundation slab

Concrete walls

Concrete stairs

Concrete slab

Concrete finishing

Concrete pouring

Reinforcement

Formwork

-1 garaža na kleti objektov

0. pritičje garaža in kleti objektov

0. pritičje

1. nadstropje

2. nadstropje

Phase 01

Phase 02

Phase 03

Phase 04

Phase 05

3. nadstropje

4. terasa

5. streha

ZONE 01Construction

Sectors

ZONE 02 Buildings

ZONE 03Building

Levels

METHODOLOGYLevel 01 Model

categories

ZONE 04Construction

Phases

4D/5D BIM PLANNING - LEVEL 3

Page 8: 4D/5D BIM PLANNING - bexelmanager.com

ZONE 01Stationsberug

ZONE 02Stationierung

METHODOLOGYLevel 01 Model

Categories

Asphaltbinder

Füllmassen

Asphalttrag

Frostschutz

4D/5D BIM PLANNING - LEVEL 3

Page 9: 4D/5D BIM PLANNING - bexelmanager.com

4D/5D BIM PLANNING - LEVEL 3

TASKIfcTask

TASK TIME INFORMATION IfcTaskTime

TASK COST INFORMATIONIfcCostValue

TASK CONSTRAINTINFORMATION

IfcMetric(subtype of IfcConstraint)

TASK RELATIONIfcRelSequence

TASK CALENDARIfcWorkCalendar

IFC 4D/5D MVD