BIM for Contractor: beyond 3D
Alexander Kolpakov Director, BIM department PE, LEED AP, PMP
Agenda
• Introduction
• 3D model and coordination
• BIM to field
• Integrated 4D/5D BIM – Location Based Scheduling & Model Based Estimating
Salimus Consultancy JLT
• Established in 2010
• Based in Dubai
• Services:
- Sustainability certification (LEED, Estidama, BREAM)
- Commissioning
- Energy modeling
- Building Information Modelling
3D model
- Clash detection and coordination
- Shop drawings production
- Fabrication
- Digital Layout
Clash detection and coordination
Shop Drawings
Fabrication Revit Fabrication CAD MEP
Fabrication
Digital Layout
Integrated Workflow for Model based Estimating and Planning
Model based Estimating and Planning Workflow
3D model Model based
Quantities
Quantity based Construction
Schedule
3D 5D 4D
Model Based Quantities
Concrete
Rebar
Formwork
Cladding; Surface Finish
TOIs Takeoff Items
$/Qty
TOQs Takeoff Quantities
$/Qty
Resources $/Qty
Column ‘Type 1’
Equipment
Labor
Materials
2/3D Design 5D Cost 4D Time
Integrated Process Overview
Gantt Chart 4D Simulations
Procurement Demand
Cash Flow
Resource Graphs
Flowline
5D BIM
Location Based Quantities
Level 3
Level 1
Level 2
Location 800 m2
1000 m2
1000 m2 Location
Location
8 days
10 days
10 days
4D BIM Location Based Schedule
4D BIM Flowline diagram vs Gantt Chart
Flowline diagram
Model based Estimating and Planning Workflow
3D model Model based
Quantities
Quantity based Construction
Schedule
3D 5D 4D
Benefits of 4D & 5D BIM
Design variations are estimated within minutes
Faster and more effective processes
10% schedule compression
Increased cost control
Realistic Construction Schedules
Sub-contractors buy in
Avoidance of Schedule conflicts