Upload
shan-reev
View
222
Download
0
Embed Size (px)
Citation preview
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 1/54
EFFLUENT WATER TREATMENT AND INJECTION
PLANT (NK)
Project No. EF/1761
Class 1
CONTRACT NO. 14050642 Page 1 of 54
PIPELINE DESIGN BASIS Rev 1
Doc. No. : 14050642-100-PL-DBM-0001 Date 19.06.2016
PROJECT :Effluent Water Treatment And InjectionPlant (NK)
CONTRACT NO : 14050642
OWNER : KUWAIT OIL COMPANY
CONTRACTOR :Dodsal Engineering & Construction Pte.Ltd.
DOCUMENT NO. : 14050642-100-PL-DBM-0001
DOCUMENT REVISION STATUS : 1
DOCUMENT TYPE : E (Engineering Drawing/Document)
1 19.06.2016Re-Issued For Design
(Ref.14050642-KD-T-01011)SV AC PC
0 17.06.2015Issued For Design
(Ref.14050642-KD-T-00882)MD AC PC
B 02.06.2015Re-Issued For Approval
(Ref.14050642-KD-T-00172& 14050642-KD-T-00038)
SV AC PC
A 17.11.2014 Issued For Review / Approval PJ SV PC
Rev Date Description Prepared By Checked By
Approved
By
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 2/54
EFFLUENT WATER TREATMENT AND INJECTION
PLANT (NK)
Project No. EF/1761
Class 1
CONTRACT NO. 14050642 Page 2 of 54
PIPELINE DESIGN BASIS Rev 1
Doc. No. : 14050642-100-PL-DBM-0001 Date 19.06.2016
REVISION RECORD:
RevisionNo.
Reason for Revision Date
A Issued for Review / Approval 17.11.2014B Re-Issued for Approval 02.06.2015
0 Issued for Design 17.06.2015
1 Re-Issued for Design 19.06.2016
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 3/54
EFFLUENT WATER TREATMENT AND INJECTION
PLANT (NK)
Project No. EF/1761
Class 1
CONTRACT NO. 14050642 Page 3 of 54
PIPELINE DESIGN BASIS Rev 1
Doc. No. : 14050642-100-PL-DBM-0001 Date 19.06.2016
PAGE INDEX
Page Revision Page Revision
B C D 1 2 3 B C D 1 2 31 50 √
2 51 √ X 3 52 √
4 53 √
5 √ 546 √ 557 X 568 57
9 5810 √ 5911 √ 6012 6113 6214 6315 √ 6416 6517 √ 6618 √ X 671920 √ 21 √
22 √
23 √
24 √ X 25 √ X 26 √ X 27 √
28 √
29 √ X 30 √
31 √ X 32 √
33 √
34 √
35 √ X 36 √ X 37 √ X 38 √ X 39 √
40 √
41 √
42 √ X 43 X 44 √
45 √
46 √ X 47 √
48 √ X 49 √
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 4/54
EFFLUENT WATER TREATMENT AND INJECTION
PLANT (NK)
Project No. EF/1761
Class 1
CONTRACT NO. 14050642 Page 4 of 54
PIPELINE DESIGN BASIS Rev 1
Doc. No. : 14050642-100-PL-DBM-0001 Date 19.06.2016
TABLE OF CONTENTS
1.
GENERAL ..................................................................................................................... 7
2.
OBJECTIVE ................................................................................................................... 7
3.
PROJECT DESCRIPTION ............................................................................................. 7
4.
SCOPE OF THIS DOCUMENT ...................................................................................... 8
5.
TERMINOLOGY ............................................................................................................ 9
5.1.
DEFINITIONS ..................................................................................................... 9
5.2.
ABBREVIATIONS ............................................................................................ 10
6.
DESIGN CODES, SPECIFICATIONS AND STANDARDS .......................................... 11
6.1.
INTERNATIONAL CODES AND STANDARDS ............................................... 11
6.2.
PROJECT REFERENCE SPECIFICATION / ADDENDUMS / DRAWINGS /
DOCUMENTS: ................................................................................................. 17
6.3.
ORDER OF DOCUMENT PRECEDENCE ........................................................ 20
7.
GENERAL DESIGN DATA .......................................................................................... 21
7.1.
BATTERY LIMIT .............................................................................................. 21
7.2.
UNITS OF MEASUREMENT ............................................................................ 21
7.3.
COORDINATE SYSTEM .................................................................................. 22
8.
SITE CONDITION & DESIGN DATA ........................................................................... 23
8.1.
SITE CONDITION / ENVIRONMENT DATA ..................................................... 23
8.2.
BASIC DESIGN DATA ..................................................................................... 23
8.3.
PIPELINE CATEGORIES ................................................................................. 24
8.4.
DESIGN LIFE SPAN ........................................................................................ 25
8.5.
PIPELINE TEMPERATURE & PRESSURE ..................................................... 26
8.6.
PIPELINE FLANGE RATING PHILOSOPHY ................................................... 26
9.
PIPELINE MATERIALS ............................................................................................... 27
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 5/54
EFFLUENT WATER TREATMENT AND INJECTION
PLANT (NK)
Project No. EF/1761
Class 1
CONTRACT NO. 14050642 Page 5 of 54
PIPELINE DESIGN BASIS Rev 1
Doc. No. : 14050642-100-PL-DBM-0001 Date 19.06.2016
9.1.
GENERAL ........................................................................................................ 27
9.2.
LINE PIPE ........................................................................................................ 27
9.3.
CARBON STEEL PIPE DESIGN PROPERTIES .............................................. 28
9.4.
RTRP PIPE DESIGN PROPERTIES ................................................................ 29
9.5.
BRANCH CONNECTIONS ............................................................................... 29
9.6.
RTRP PIPE JOINTS ......................................................................................... 29
9.7.
MATERIAL CERTIFICATION ........................................................................... 30
10.
PIPELINE FITTINGS ................................................................................................... 30
10.1.
PIPELINE BENDS ............................................................................................ 30
10.1.1 GENERAL ........................................................................................................ 30
10.1.2 ELASTIC BENDS ............................................................................................. 31
10.1.3 COLD FIELD BENDS ....................................................................................... 32
10.1.4 HOT INDUCTION BENDS ................................................................................ 32
10.2. BARRED TEE .................................................................................................. 32
10.3.
INSULATING FLANGE JOINTS / INSULATION GASKET KIT........................ 32
10.4.
PIG LAUNCHER/RECEIVER ........................................................................... 32
10.5.
PIG SIGNALLERS ........................................................................................... 34
10.6.
PIPELINE ANCHORS ...................................................................................... 34
10.7.
FLANGES, BRANCH CONNECTIONS AND FITTINGS .................................. 34
10.8.
VALVES ........................................................................................................... 35
11.
PIPELINE ANCILLARIES ............................................................................................ 36
11.1.
PIPELINE TRACING ........................................................................................ 36
11.2.
PIPELINE MARKERS ...................................................................................... 36
11.3.
PIPELINE WARNING SIGNS ........................................................................... 36
12.
PIPELINE DESIGN CRITERIA .................................................................................... 37
12.1.
GENERAL ........................................................................................................ 37
12.2.
PIPELINE WALL THICKNESS CALCULATION .............................................. 37
12.3.
DESIGN FACTOR ............................................................................................ 38
12.4.
STRESS CALCULATION AT ROAD CROSSINGS ......................................... 38
12.5.
PIPELINE AT ABOVE GROUND / BELOW GROUND TRANSITION .............. 38
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 6/54
EFFLUENT WATER TREATMENT AND INJECTION
PLANT (NK)
Project No. EF/1761
Class 1
CONTRACT NO. 14050642 Page 6 of 54
PIPELINE DESIGN BASIS Rev 1
Doc. No. : 14050642-100-PL-DBM-0001 Date 19.06.2016
12.6.
PIPELINE UPHEAVAL BUCKLING CHECK.................................................... 39
12.7.
ON-BOTTOM STABILITY OF PIPELINES IN WET AREAS ............................ 39
13.
PIPELINE ROUTING ................................................................................................... 40
13.1.
GENERAL APPROACH ................................................................................... 41
13.2.
ROUTE ALIGNMENT SHEET .......................................................................... 41
13.3.
TERRAIN AND INSTALLATION ...................................................................... 42
13.4.
SEPARATION DISTANCES AND EXCLUSION ZONES ................................. 43
13.5.
TOPOGRAPHICAL & GEOTECHNICAL DATA ............................................... 49
14.
DESIGN PHILOSOPHY AND PHYSICAL DATA ......................................................... 49
14.1.
PIGGING, HYDRO TESTING & INSPECTION ................................................. 49
14.2.
NON DESTRUCTIVE TESTING ....................................................................... 50
14.3.
PIPELINE DEWATERING AND DRYING ......................................................... 50
14.4.
FIRE AND SAFETY REGULATIONS ............................................................... 50
14.5.
SITE TIE-IN REQUIREMENTS ......................................................................... 50
14.6.
STRUCTURAL INTEGRITY: ............................................................................ 51
15.
WELDING REQUIREMENTS ....................................................................................... 51
16.
TESTING AND PRE-COMISSIONING ......................................................................... 52
17.
CORROSION PROTECTION ....................................................................................... 52
17.1.
CATHODIC PROTECTION .............................................................................. 52
17.2.
EXTERNAL CORROSION ............................................................................... 53
ATTACHMENT-1: PIPELINE SCHEMATIC DIAGRAM ............................................................. 54
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 7/54
EFFLUENT WATER TREATMENT AND INJECTION
PLANT (NK)
Project No. EF/1761
Class 1
CONTRACT NO. 14050642 Page 7 of 54
PIPELINE DESIGN BASIS Rev 1
Doc. No. : 14050642-100-PL-DBM-0001 Date 19.06.2016
1. GENERAL
Kuwait Oil Company (K.S.C), hereafter referred as COMPANY, as a major player of
global oil and gas sector has a long term strategy for the development of North Kuwait
(NK) Fields. North Kuwait Fields is located approximately 90kms from north of Kuwait
city.
The purpose of this project is to provide sufficient injection water to meet the
requirements of the north Kuwait well injectors.For this, an effluent water treatment and injection plant shall be built in a location between
the SABRIYAH and RAUDATAIN fields of north Kuwait having a treatment design
capacity of 1,045,000 BWPD with 550,000 BWPD for injection and balance 495,000
BWPD will be transferred to existing central processing injector facility (CIPF existing).
The plant shall receive a continuous supply of effluent water from existing Gathering
Centers GC-15, GC-23, GC-24, GC-25 and an intermittent supply of effluent water from
new GC-29, GC-30 and GC-31 (all routed from existing CIPF).
For this purpose, the COMPANY has entered into a contract with DODSAL
ENGINEERING & CONSTRUCTION PTE LIMITED, hereafter referred as
CONTRACTOR, for Engineering, Procurement, Construction and Related Activities,
with a Contract No. 14050642.
2. OBJECTIVE
The objective of this document is to define the relevant pipeline design data, general
philosophies, design criteria, methodology, relevant codes and standard and other
important considerations to be adopted for the detailed engineering of the pipelines
involved for New EWTIP project.
3. PROJECT DESCRIPTION
The purpose of this project is to provide sufficient injection water to meet the
requirements of the North Kuwait well injectors. To this end, the EW Treatment and
Injection Plant (NK) (EWTIP) will be located between the Sabriyah and Raudatain fields.
510 MBWPD EW injection facilities for injecting water into 51 no of wells (550
MBWPD Water Injection Pipelines Distribution System up to Manifolds). The EWTIP
1
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 8/54
EFFLUENT WATER TREATMENT AND INJECTION
PLANT (NK)
Project No. EF/1761
Class 1
CONTRACT NO. 14050642 Page 8 of 54
PIPELINE DESIGN BASIS Rev 1
Doc. No. : 14050642-100-PL-DBM-0001 Date 19.06.2016
treatment system is divided into two identical trains each designed to treat 522.5
MBWPD. The plant includes collection tanks that receive effluent water from:
• GC-15 (200 MBWPD normal; 220 MBWPD design)
• GC-25 (200 MBWPD normal; 220 MBWPD design)
• GC-23 (150 MBWPD normal; 165 MBWPD design)
• GC-24 (200 MBWPD normal; 220 MBWPD design)
• GC-29 (240 MBWPD design)
• GC-30 (240 MBWPD design)
• GC-31 (240 MBWPD design)
Collected effluent water from GCs is treated in the EW treatment facility to meet the
required quality specification for injection. Prior to injection, the treated water is stored in
the Treated Water Tanks. These tanks may also receive effluent water from GC-29, GC-
30 and GC-31 to maintain the required amount of injection water, should one of the
primary source GCs be shut down.
A portion of the treated effluent water is also to be transferred from the treatment plant to
the effluent water collection tank of the CIPF (EF/1071, Effluent Water Injection Plant,
Phase I). To minimize the size of the Treated Water Tanks and eliminate the need to
install new dedicated treated effluent water transfer pumps, this treated water is pumped
directly from the outlet of the new effluent water treatment plant upstream of the Treated
Water Tanks.
Inline Booster and High Pressure (HP) Injection Pumps are capable of maintaining a
minimum operating pressure of 255 barg (3700 psig) at the inlet of farthest injector
wellhead along with injection headers and injection lines to injection wells.
4. SCOPE OF THIS DOCUMENT
The scope of this document is to define the design criteria for the permanent works
relevant to this project like pipeline engineering design data, analysis methods and
design methods to be used for detail engineering of pipeline sections.
The CONTRACTOR shall design and install all pipelines as indicated on the P&ID’s
up to the interfaces and Tie-Ins to existing pipework. Refer to Drawing Number
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 9/54
EFFLUENT WATER TREATMENT AND INJECTION
PLANT (NK)
Project No. EF/1761
Class 1
CONTRACT NO. 14050642 Page 9 of 54
PIPELINE DESIGN BASIS Rev 1
Doc. No. : 14050642-100-PL-DBM-0001 Date 19.06.2016
14050642-0100-PL-DWG-0001: Schematic of Interconnecting Pipework for an overall
view of the Pipeline and Off-Sites Works.
The new Pipelines will connect and transport the various products between GC-15,
GC-23, GC-24, GC-25, GC-29, GC-30 and GC-31, Fuel Gas Headers, Recovered oil
headers, Brackish Water Header , Treated Water distribution header, Treated Water
Manifold, Wellhead Flow Lines, EWTIP, CIPF, B.S-131, B.S-132 & various tie-ins to
existing pipeline in North Kuwait. Refer to the Schematic & Layout represented in
Figure-1 shows the overall view of the Pipeline and Off-site works.
The pipelines are required for the following services:
Effluent Water
Treated Water
Fuel Gas
Recovered Oil
Brackish Water (Fire Water)
Injection Water.
5. TERMINOLOGY
For the purpose of this document, the words and abbreviations listed below shall have
the explanations as follows:
5.1. DEFINITIONS
COMPANY Kuwait Oil Company (K.S.C)
CONTRACTOREPC Contractor nominated to carry out the project,
Dodsal Engineering and Construction Pte Ltd.
PROJECT Works related to contract no: 14050642.
WORK Activities required to be completed by the CONTRACTOR
SHALL
The word “SHALL” is understood to be mandatory to
comply with the requirements.
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 10/54
EFFLUENT WATER TREATMENT AND INJECTION
PLANT (NK)
Project No. EF/1761
Class 1
CONTRACT NO. 14050642 Page 10 of 54
PIPELINE DESIGN BASIS Rev 1
Doc. No. : 14050642-100-PL-DBM-0001 Date 19.06.2016
SHOULDThe word “SHOULD” is understood to be strongly
recommended to comply with the requirements.
5.2. ABBREVIATIONS
API American Petroleum Institute
ASME American Society of Mechanical Engineers
ASTM American Society for Testing and Materials
BS British Standard
EWTIP Effluent Water & Treatment Injection Plant
CIPF Central Injection Pumping Facilities
B.S Booster Station
GC Gathering Centres
CA Corrosion Allowance
CP Cathodic Protection
DF Design Factor
KM Kilo meters
FEED Front End Engineering Design
FG Fuel Gas
ROW Right of Way
SMYS Specified Minimum Yield Strength
HSAW / SSAW Helical or Spiral Submerged Arc Weld
LSAW Longitudinal Submerged Arc Weld
LP Low Pressure
MBOPD Thousand U.S Barrels of Oil Per Day
MSS Manufacturers Standardization Society
NACE National Association of Corrosion Engineers
SMLS Seamless
TCP Temporary Cathodic Protection
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 11/54
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 12/54
EFFLUENT WATER TREATMENT AND INJECTION
PLANT (NK)
Project No. EF/1761
Class 1
CONTRACT NO. 14050642 Page 12 of 54
PIPELINE DESIGN BASIS Rev 1
Doc. No. : 14050642-100-PL-DBM-0001 Date 19.06.2016
ASME B 16.21 Non-metallic Flat Gaskets for Pipe Flanges
ASME B 16.25 Butt-Welding Ends
ASME B 16.34 Valves – Flanged, Threaded and Welding End
ASME B16.47Large Diameter Steel Flanges NPS 26 through
NPS 60
ASME B 16.48 Line Blanks
ASME B 16.49Factory-made wrought Butt-welding induction
Bends for transportation & distribution system
ASME B 31.4Pipeline Transportation Systems for Liquid
Hydrocarbons and Other Liquids
ASME B 31.8Gas Transmissions and Distribution Piping
Systems
ASME B 31.3 Process Piping
ASME B 46.1 Surface texture
ASME
Section VIII - Boiler and Pressure Vessel Code
Section II Div. 1 Part A – Ferrous material
specifications
Section II Div. 1 Part D – Properties (Materials)
Section V – Non Destructive Examination
Section VIII Div. 1 - Pressure VesselsSection IX – Welding and brazing Qualifications
AMERICAN PETROLEUM INSTITUTE (API)
API 5L Specification for Line Pipe (45th Edition)
API 6D Specification for Pipeline Valves
API 6F Specification for Fire test for valves
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 13/54
EFFLUENT WATER TREATMENT AND INJECTION
PLANT (NK)
Project No. EF/1761
Class 1
CONTRACT NO. 14050642 Page 13 of 54
PIPELINE DESIGN BASIS Rev 1
Doc. No. : 14050642-100-PL-DBM-0001 Date 19.06.2016
API RP 1102
Recommended Practice for Liquid Petroleum
Pipelines Crossing Railroads and Highways (7th
Edition)
API STD 1104Standard for welding Pipelines and related
Facilities (20th Edition)
API RP 1109 Marking Liquid Petroleum Pipeline Facilities
API RP 1110 Recommended Practice for the Pressure Testing ofSteel Pipelines (5th Edition)
American Society for Testing and Materials (ASTM):
ASTM A 694 / M
Standard Specification for Carbon and Alloy Steel
Forgings for Pipe Flanges, Fittings, Valves and Parts
for High Pressure Transmission Service
ASTM E 94 Standard Guide for Radiographic Examination
ASTM E 165Standard Test Method for Liquid Penetrant
Examination
ASTM E 709 Standard Guide for Magnetic Particle Examination
ASTM E 747
Standard Practice for Design, Manufacture and
Material Grouping Classification of Wire Image
Quality Indicators (IQI) Used for Radiology
American Welding Society (AWS):
AWS A 2.4Standard Symbols for Welding, Brazing and
Non-Destructive Examination
AWS A 5.5 / M
Specification for Low Alloy Steel Electrodes for
Shielded Metal Arc Welding
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 14/54
EFFLUENT WATER TREATMENT AND INJECTION
PLANT (NK)
Project No. EF/1761
Class 1
CONTRACT NO. 14050642 Page 14 of 54
PIPELINE DESIGN BASIS Rev 1
Doc. No. : 14050642-100-PL-DBM-0001 Date 19.06.2016
British Standards (BS):
BS EN 558
Industrial Valves Face-to-Face and Centre-to-Face
Dimensions of Metal Valves for use in Flanged Piping
Systems
BS EN 1011
Welding Recommendations for Welding of Metallic
Materials Part 1: General Guidance for Arc WeldingPart 2: Arc Welding of Ferrite Steels
BS EN 1759Flanges and their Joints – Circular Flanges for
Pipes, Valves, Fittings and their Accessories
BS 3900
Methods of Tests for Paints: Part F 11: Determination
of Resistance to Cathodic Disbonding of Coatings for
use on Land Based Buried Structures
BS 5930 Code of Practice for Site Investigations
BS 6031 Code of Practice for Earthworks
BS EN ISO 6507 Metallic Materials – Vickers Hardness Test
BS PD 6513 Magnetic Particle Flaw Detection
BS 7361
Cathodic Protection Part 1 – Code of Practice for Land
and Marine Applications
BS PD 8010Code of Practice for Pipelines Part 1: Steel Pipelines
on Land
BS 8110 Structural Use of Concrete
BS EN ISO 17292Metal Ball Valves for Petroleum, Petrochemical
and Allied Industries
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 15/54
EFFLUENT WATER TREATMENT AND INJECTION
PLANT (NK)
Project No. EF/1761
Class 1
CONTRACT NO. 14050642 Page 15 of 54
PIPELINE DESIGN BASIS Rev 1
Doc. No. : 14050642-100-PL-DBM-0001 Date 19.06.2016
International Standards Organization (ISO):
ISO 15589
Petroleum and Natural Gas Industries – Cathodic
Protection of Pipeline Transportation Systems
Part 1: On-Land Pipelines.
Manufacturers Standardization Society of the Valve and Fittings Industry
(MSS):
MSS SP-6
Standard Finishes for Contact Faces of
Pipe Flanges Connecting Ends of Flanges of
Valves and Fittings
MSS SP-25Marking Systems for Valves, Fittings, Flanges and
Unions
MSS SP-44 Steel Pipe Flanges
MSS SP-53
Quality Standard for Steel Casting and Forging for
Valves, Flanges and Fittings and Other Piping
Components – Magnetic Particle Examination
Method
MSS SP-55
Quality Standard for Steel Castings for Valves,
Flanges and Fittings and Other Piping
Components – Visual Method for Evaluation of
Surface Irregularities
MSS SP-72Ball Valves with Flanged or Butt Welding Ends for
General Service
MSS SP-75Specification for High Test Wrought Butt Welding
Fittings
MSS SP-97
Integrally Reinforced Forged Branch Outlet
Fittings – Socket Welding, Threaded, and Butt-
welding Ends.
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 16/54
EFFLUENT WATER TREATMENT AND INJECTION
PLANT (NK)
Project No. EF/1761
Class 1
CONTRACT NO. 14050642 Page 16 of 54
PIPELINE DESIGN BASIS Rev 1
Doc. No. : 14050642-100-PL-DBM-0001 Date 19.06.2016
National Association of Corrosion Engineers International (NACE):
NACE MR 0175 /
ISO 15156
Petroleum and Natural Gas Industries -Materials for use
in H2S-containing environments in Oil and Gas
production: Parts 1 to 3 (2009 & its latest technical
circulars)
NACE SP 0177Mitigation of Alternating Current and Lightning Effects
on Metallic Structures and Corrosion Control Systems
NACE TM 0177
Laboratory Testing of Metals for Resistance to
Sulfide Stress Cracking and Stress Corrosion Cracking
in H2S Environments
NACE RP 0274 High Voltage Electrical Inspection of Pipeline Coatings
NACE TM 0284
Evaluation of Pipeline and Pressure Vessel Steels for
Resistance to Hydrogen-Induced Cracking
NACE SP 0286 Electrical Isolation of Catholically Protected Pipelines
NACE RP 0472
Methods and Controls to Prevent In-Service
Environmental Cracking of Carbon Steel Weldments in
Corrosive Petroleum Refining Environments.
NACE SP 0169Control of External Corrosion on Underground
submerged piping systems
NACE SP 0200 Steel Cased Pipeline Practices
NACE SP 0502Pipeline External Corrosion Direct Assessment
Methodology
NACE SP 0572Design, Installation, Operation and Maintenance of
Impressed current deep Anode Beds
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 17/54
EFFLUENT WATER TREATMENT AND INJECTION
PLANT (NK)
Project No. EF/1761
Class 1
CONTRACT NO. 14050642 Page 17 of 54
PIPELINE DESIGN BASIS Rev 1
Doc. No. : 14050642-100-PL-DBM-0001 Date 19.06.2016
6.2. PROJECT REFERENCE SPECIFICATION / ADDENDUMS / DRAWINGS /
DOCUMENTS:
KOC Specifications:
015-IH-1001 Rev.1 Pipeline Construction
015-IH-1002 Rev.1 Pipeline Design
015-IH-1004 Rev.1 Pipeline Pigging and Hydrostatic test
015-IH-1005 Rev.1 Pipeline Dewatering, drying and Purging
015-IH-1008 Rev.1 Pipeline Field Welding Non Sour
Service
015-IH-1009 Rev.1 Flow lines
015-LH-1002 Rev.1 Piping design
015-PH-1910 Rev.1 Cathodic Protection (CP) Transformer
Rectifier Units
015-SH-1006 Rev.1 Topographical Survey
015-WH-1001 Rev.0 Welding Procedure Approval and
Welding Quality Requirement
015-WH-1002 Rev.0 Field Welding Requirements including:
welding, Heat treatment and NDT of
piping
015-WH-1006 Rev.1 Cathodic Protection Design
Requirements
Document No. Description
KOC-L-002 Rev.3 RP for Protection of KOC Services
KOC-L-012 Rev.1 Cathodic Protection Material
KOC-L-015 Rev.2External Cathodic Protection of Underground
Steel Pipeline and Piping Networks
KOC-MP-005 Rev.1 Pipeline Pig Trap Systems
KOC-MP-010 Rev.1 Piping Material Classes
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 18/54
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 19/54
EFFLUENT WATER TREATMENT AND INJECTION
PLANT (NK)
Project No. EF/1761
Class 1
CONTRACT NO. 14050642 Page 19 of 54
PIPELINE DESIGN BASIS Rev 1
Doc. No. : 14050642-100-PL-DBM-0001 Date 19.06.2016
EWTIP-20-PL-SPC-0002
Rev.1 ADDENDUM TO KOC SPECIFICATION:
PIPELINE DESIGN (015-IH-1002 REV1)
EWTIP-20-PL-SPC-0003
Rev.0 ADDENDUM TO KOC SPECIFICATION:
FLOWLINES (015-IH-1009 REV2)
EWTIP-20-PL-SPC-0004Rev.0
SPECIAL CRITERIA TO KOC STANDARD FOR
EXTERNAL COATING OF PIPELINES PART 4
FUSION BONDED EPOXY COATING (KOC-P-
004 PART4 REV2)
EWTIP-20-PL-SPC-0005
Rev.0 ADDENDUM TO KOC SPECIFICATION PIG
LAUNCHERS/RECEIVERS (015-IH-1006 REV1)
EWTIP-20-PL-SPC-0006
Rev.0
SPECIAL CRITERIA TO KOC STANDARD FOR
INTERNAL COATING OF PIPELINES (KOC-P-
005 REV1)
EWTIP-20-PL-SPC-0007
Rev.0
SPECIAL CRITERIA TO KOC STANDARD FOR
EXTERNAL COATING OF UNDERGROUND
PIPING/PIPELINES - HIGH BUILD EPOXY
COATING (KOC-P-004 PART8 REV1)
EWTIP-20-PL-SPC-0008
Rev.0
SPECIAL CRITERIA TO KOC RECOMMENDED
PRACTICE FOR THE PROTECTION OF KOC
SERVICES: CLEARANCE REQUIREMENTS
FOR BURIED PIPELINES, CABLES,
UNDERGROUND STRUCTURES, BUILDINGS
AND HOUSING PROJECTS (KOC-L-002 REV3)
EWTIP-20-PL-SPC-0009
Rev.0
SPECIAL CRITERIA TO KOC STANDARD FOR
EXTERNAL COATING OF UNDERGROUND
PIPING/PIPELINES - HIGH BUILD POLY-
URETHANE COATING (KOC-P-004 PART9
REV1)
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 20/54
EFFLUENT WATER TREATMENT AND INJECTION
PLANT (NK)
Project No. EF/1761
Class 1
CONTRACT NO. 14050642 Page 20 of 54
PIPELINE DESIGN BASIS Rev 1
Doc. No. : 14050642-100-PL-DBM-0001 Date 19.06.2016
EWTIP-20-PL-SPC-0010
Rev.1
SPECIFICATION FOR HIGH DENSITY
POLYETHYLENE (HDPE) LINERS FOR
CARBON STEEL PIPELINES
EWTIP-20-PL-SPC-0011
Rev.1
SPECIFIC CRITERIA TO KOC STANDARD FOR
ELECTRIC WELDED PIPES (KOC-MP-017
REV1)
EWTIP-20-PL-SPC-0012
Rev.1 PIPELINE LEAK DETECTION SPECIFICATION
EWTIP-20-PL-SPC-0013
Rev.0
Special Criteria To Standard For Seamless Line
Pipe to API 5L ( KOC-MP-018 Rev.1)
EWTIP-20-PL-SPC-0014
Rev.0
Criteria To Standard For Submerged Arc Welded
(SAW) Pipe to API 5L ( KOC-MP-019 Rev.1)
EWTIP-20-PL-SPC-0015
Rev.0
ADDENDUM TO KOC SPECIFICATION:
PIPELINE PIGGING AND HYDROSTATIC TEST
(015-IH-1004 REV1)
EWTIP-20-PL-SPC-0016
Rev.0
ADDENDUM TO KOC SPECIFICATION
PIPELINE DEWATERING, DRYING AND
PURGING (015-IH-1005 REV1)
EWTIP-20-PL-SPC-0017
Rev.1
Project Specific Criteria to Material Specification
For Induction Bend (KOC-MS-002 Rev.1)
EWTIP-20-PL-SPC-0018
Rev.1
Addendum to Specification for Pipeline
Construction ( 015-IH-1001 Rev.1)
EWTIP-20-PL-SPC-0019
Rev.0
PROJECT SPECIFIC CRITERIA FOR KOC
RECOMMENDED PRACTICE FOR EXTERNAL
CATHODIC PROTECTION OF UNDERGROUND
STEEL PIPELINES & PIPING NETWORKS
6.3. ORDER OF DOCUMENT PRECEDENCE
In case of conflict on technical requirements, the most stringent requirements asdefined by the company shall apply as per clause no 1.2 and 3.3 of Appendix-F
of the contract.
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 21/54
EFFLUENT WATER TREATMENT AND INJECTION
PLANT (NK)
Project No. EF/1761
Class 1
CONTRACT NO. 14050642 Page 21 of 54
PIPELINE DESIGN BASIS Rev 1
Doc. No. : 14050642-100-PL-DBM-0001 Date 19.06.2016
In case of conflict on codes, standards, company specifications, regulatoryrequirements, following order of precedence shall apply:
a. Regulatory Requirements
b. Addendum and project specific criteria to KOC specifications andstandards
c. KOC standards & Specifications
d. International Codes and Standards
Should there be an inconsistency, conflict or discrepancy between any of the
Standards, Specifications or Regulatory requirements, the most stringent and safest
requirement applicable to the project shall prevail to the extent of the inconsistency,
conflict or discrepancy. Any inconsistencies critical to the design shall be brought to
the attention of KOC for resolution.
7. GENERAL DESIGN DATA
7.1. BATTERY LIMIT
The design battery limit between pipeline and piping are the flanges at the
launcher / receiver and before first isolation valve on the bypass line near
barred tee & the code break between ASME B 31.3 and ASME B 31.8 / ASME
B31.4 as per P & ID.
7.2. UNITS OF MEASUREMENT
SI units shall be used for all calculations and on all drawings. For convenience,
data in imperial units may be included for reference.
Design Unit Standards(Note 1)
Item SI units Imperial Units
Oil Flow m /hr. bbl/d
Gas Flow MMm3/d MMscf/d
Density kg/m3 lbs./ft3
Pressure bar(a) or bar(g) psia or psig
Differential Pressure bar/mbar psi
Temperature °C °F
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 22/54
EFFLUENT WATER TREATMENT AND INJECTION
PLANT (NK)
Project No. EF/1761
Class 1
CONTRACT NO. 14050642 Page 22 of 54
PIPELINE DESIGN BASIS Rev 1
Doc. No. : 14050642-100-PL-DBM-0001 Date 19.06.2016
Viscosity MPa cP
Kinematic Viscosity cSt cSt
Mass kg lbs
Pipe diameters, valve size,
instrument tubing (note 2) mm inch
Energy MJ Btu
Power kW hp
TimeSeconds, hours,
daysSeconds, hours, days
Piping (note 2), Structural,
Isometric, Site (Layouts,
Topographical etc.), and
Vendor Drawings
Metric English
Vessel Dimensions Metric English
Electrical Equipment Cabinets
& other equipment inside
control buildings
Metric English
Notes:
1. Standard conditions are defined as 14.696 psia and 60°F (1.01325
bar(a) and 15°C)
2. All piping and tubing to be SI sizes.
7.3. COORDINATE SYSTEM
The co-ordinate system to be used for mapping on the project shall be:
Projection : Universal Transverse Mercator
Zone : UTM 38R
Datum : World Geodetic System (WGS-84)
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 23/54
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 24/54
EFFLUENT WATER TREATMENT AND INJECTION
PLANT (NK)
Project No. EF/1761
Class 1
CONTRACT NO. 14050642 Page 24 of 54
PIPELINE DESIGN BASIS Rev 1
Doc. No. : 14050642-100-PL-DBM-0001 Date 19.06.2016
Field maps showing injection well locations and pipeline routings used in
the FEED study.
Alignment sheets for produced water pipelines, injection water trunk
lines and the recovered oil pipelines.
Schematics of the high pressure pipelines used for hydraulic simulations
and materials quantity determination.
8.3. PIPELINE CATEGORIES
The pipeline categories shall comply with the requirements of KOC
specification:
Application of codes and Group Standards, which has been reproduced for
design purpose as in below table,
Table 8.1 : Pipeline Categories
S.No. Applicable Project Pipelines
Approx.
Length
(KM)
Product
type
Design
Code
1 20” RTRP Pipeline from GC-15 in CIPF to EWTIP 1.72Effluent
Water
ASME
B31.4
2 16” RTRP Pipeline from GC-23 in CIPF to EWTIP 1.73Effluent
Water
ASME
B31.4
3 20” RTRP Pipeline from GC-24 in CIPF to EWTIP 1.72Effluent
Water
ASME
B31.4
4 20” RTRP Pipeline from GC-25 in CIPF to EWTIP 1.72Effluent
Water
ASME
B31.4
5 6” CS Pipeline from B.S-131 to EWTIP (2 nos.)17 (8.5
each)Fuel Gas
ASME
B31.8
620” CS HDPE lined Pipeline from EWTIP to
Sabriyah manifold distribution47.0
Injection
Water
ASME
B31.4
7
20” CS HDPE lined Pipeline from EWTIP to
Rudatain manifold distribution 16.4
Injection
Water
ASME
B31.4
1
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 25/54
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 26/54
EFFLUENT WATER TREATMENT AND INJECTION
PLANT (NK)
Project No. EF/1761
Class 1
CONTRACT NO. 14050642 Page 26 of 54
PIPELINE DESIGN BASIS Rev 1
Doc. No. : 14050642-100-PL-DBM-0001 Date 19.06.2016
8.5. PIPELINE TEMPERATURE & PRESSURE
Table 8.2: Temperature and Pressure
Pipelines
Operating
Pressure
(barg)
Design
Pressure
(barg)
Operating
Temperature
(°C)*
Design
Temperature
UG / AG
(°C)
Distribution Lines 278 331 30-60 -3 / 93
Flow Lines 278 331 30-60 -3 / 93
Treated Water Return
Line to CIPF (existing
1071)
5.9 11 30-60 -3 / 93
Fuel Gas 25.5 46 30-60 -3 / 93
Effluent Water 4 15 30-60 -3 / 93
Oily Water 8.41 10.5 30-60 -3 / 93
Brackish Water 4.13 15 30-60 -3 / 93
8.6. PIPELINE FLANGE RATING PHILOSOPHY
For the selected material class, the flange rating shall be selected by applying
the chosen design pressure and temperature in the appropriate rating table in
the Piping Material specification and shall in accordance to ASME B 16.5 &
ASME 16.47.
Pipeline Flange Rating
Effluent water 150 #
Recovered Oil 300 #
Fuel Gas 300 #
Brackish Water 300 #
1
1
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 27/54
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 28/54
EFFLUENT WATER TREATMENT AND INJECTION
PLANT (NK)
Project No. EF/1761
Class 1
CONTRACT NO. 14050642 Page 28 of 54
PIPELINE DESIGN BASIS Rev 1
Doc. No. : 14050642-100-PL-DBM-0001 Date 19.06.2016
manufacturer’s design.
For mechanical handling considerations and to avoid pipe damage during
construction the pipe diameter to wall thickness ratio should not exceed 96 in
general as per clause 403.2.5 of ASME B31.4.
All carbon steel pipes of API 5L X60 material shall be of SMLS construction up
to 20 inch.
Pipe material shall be Reinforced Thermosetting Resin Pipe (RTRP) for
Effluent Water, Treated water and Brackish Water and pipe shall bemanufactured by Dual Helical Filament Winding Process in accordance with
COMPANY standard for RTRP pipes and fittings: KOC-MP-011 Part 1.
9.3. CARBON STEEL PIPE DESIGN PROPERTIES
The properties shown in table below are to be used for calculations involving
carbon steel line pipe with reference to API 5L, 45th Edition.
Table 9.1: Pipeline Design Properties
Property Units Pipeline
Material API 5L, 45th
Edition All CS Pipelines in Table 8.1
Material grade L415 (X60) L245 (B)
Yield strength Min
SMYSMPa
415245
Yield strength Max MPa
565
450
Ultimate Tensile
StrengthMPa
520415
Density Kg/m3 7850
Young’s’ Modulus MPa 203000
Thermal Co-efficient
of Expansion mm / 11.7 x 10-6
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 29/54
EFFLUENT WATER TREATMENT AND INJECTION
PLANT (NK)
Project No. EF/1761
Class 1
CONTRACT NO. 14050642 Page 29 of 54
PIPELINE DESIGN BASIS Rev 1
Doc. No. : 14050642-100-PL-DBM-0001 Date 19.06.2016
mm /C
Poisson’s Ratio 0.3
9.4. RTRP PIPE DESIGN PROPERTIES
The properties shown in table below shall be given to vendor for the RTRP Line
pipes with reference to ASTM D 2996
Table 9.2: Pipeline Design Properties
Property Units Resin Type
Epoxy ResinPolyester & Vinyl
Ester Resin
Tensile Strength 103 psi 4-13 6-13
Tensile Modulus 106 psi 0.35 0.3 – 0.64
Elongation at Break % 3-15 < 2
Flexural Strength 103 psi 13-21 8.5-23
Specific Gravity 1.11 – 1.40 1.1 – 1.46
9.5. BRANCH CONNECTIONS
For all pipeline pig trap nozzle fittings, the thickness shall be as per the
adjoining B31.3 piping class, however the material grade of the branch fitting
shall be the same as the pipeline.
9.6. RTRP PIPE JOINTS
The RTRP pipe joint methods shall be as follows:
Taper-Taper adhesive bonded pipes & fittings joints 1
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 30/54
EFFLUENT WATER TREATMENT AND INJECTION
PLANT (NK)
Project No. EF/1761
Class 1
CONTRACT NO. 14050642 Page 30 of 54
PIPELINE DESIGN BASIS Rev 1
Doc. No. : 14050642-100-PL-DBM-0001 Date 19.06.2016
The RTRP piping shall be joined adopting most appropriate joining method(s)
based on design conditions, service fluid & pipe size.
The manufacturer shall suggest and recommend the most appropriate joining
method(s) to contractor based on KOC standards well ahead of the start of the
project for review & approval.
The jointing method shall be in accordance with CL.10. of KOC design
specification KOC-MP-011 part-2.
Flanged Joints shall be used at the transition points of RTRP pipes to Steelpipes.
9.7. MATERIAL CERTIFICATION
The specific requirements for documentation and certification of all materials
and equipment to be procured are included in the individual Project technical
Specifications or Material Requisition.
10. PIPELINE FITTINGS
The material used shall satisfy the requirements of NACE MR 0175 / ISO
15156 where applicable, pipeline fittings shall be ASTM, ANSI / ASME, API
and other international standards as applicable. Dimensional standards i.e.
tolerance, in general, shall be as per the relevant code.
The final material grade and wall thickness shall be confirmed. Factors to be
considered include ASME B31.4 / B31.8 requirements as applicable, KOC
specifications and contract specific requirements.
All butt welded fittings shall comply with ANSI B16.9.
RTRP fittings shall be in accordance with KOC standard for RTRP pipes and
fittings, KOC-MP-011 Part 1 and Part 2.
10.1. PIPELINE BENDS
10.1.1 GENERAL
The use of Cold Field bends and hot induction bends shall be avoided andwherever possible bends shall be formed by bending pipe with its elastic limits
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 31/54
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 32/54
EFFLUENT WATER TREATMENT AND INJECTION
PLANT (NK)
Project No. EF/1761
Class 1
CONTRACT NO. 14050642 Page 32 of 54
PIPELINE DESIGN BASIS Rev 1
Doc. No. : 14050642-100-PL-DBM-0001 Date 19.06.2016
10.1.3 COLD FIELD BENDS
Cold field bends may be used at locations of horizontal or vertical changes in
direction. Miter or “lobster -back” bends shall not be used. Cold field bends shall
have a minimum bending radius of 40D, where D is the pipeline outside
diameter. Cold field bends shall be in accordance to Cl.9.2.1 of 15-IH-1002.
10.1.4 HOT INDUCTION BENDS
All bends shall be produced by induction bending. Bend radius shall be 5D
(where D is the pipe OD). All the bends shall be supplied with straight tangent
ends at least 500 mm in length. Induction Bends shall be manufactured in
accordance with COMPANY specification KOC-MS-002 and addendum
EWTIP-20-PL-SPC-0017. Hot bends shall be in accordance to Cl.9.2.3 of 15-
IH-1002.
10.2. BARRED TEE
Barred tees shall be installed in piggable lines where pipeline branch
connections of 25% and above of main pipeline diameter are required. Barred
tees shall be manufactured to a proven design that shall allow the smooth
passage of pigging tools without the risk of snagging or deflection. All barred
tees shall comply with the requirements of ASME B16.9/ MSS-SP-75 and also
to sour service conditions. Barred Tees shall be formed extruded outlet,
integral type and meeting the design code requirements of the existing header
pipe.
10.3. INSULATING FLANGE JOINTS / INSULATION GASKET KIT
Insulating flange joints shall be installed at each end of the pipeline to
electrically isolate the buried pipeline cathodic protection system from the
above ground station pipe work. All insulating flange joints shall be installed
above ground (not buried).
10.4. PIG LAUNCHER/RECEIVER
Pig launchers and receivers shall be designed for the same service conditions
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 33/54
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 34/54
EFFLUENT WATER TREATMENT AND INJECTION
PLANT (NK)
Project No. EF/1761
Class 1
CONTRACT NO. 14050642 Page 34 of 54
PIPELINE DESIGN BASIS Rev 1
Doc. No. : 14050642-100-PL-DBM-0001 Date 19.06.2016
1004, rev.1 and EWTIP-20-PL-0015, rev.0.
10.5. PIG SIGNALLERS
Pig signallers shall be located on pig launchers / receiver facilities on pipeline
system to monitor the passage of pigs. Details of the required facilities shall be
as per relevant P&IDs. Pig signallers shall be bi-directional ultrasonic flanged
intrusive type with a trigger penetrating into the main bore of the pipe which will
be moved by the passing pig and a mechanical indicator mounted externally on
the pressure housing. They shall be mounted vertically on top of the pipe with
two x 2-in NB isolation ball valves to isolate the pig signaller from the pipeline.
Pig signaller isolation ball valves shall be full bore and end connections shall be
as per piping class. A portable jacking tool for removing the unit whilst the
pipeline is under pressure shall be provided.
10.6. PIPELINE ANCHORS
Full thrust anchors shall be installed at both ends of the various pipeline at the
transition where the pipeline changes from buried to above ground before the
permanent pig launcher/ receiver and as per the results of the Pipeline Stress
Analysis.
Calculations shall be performed to design the anchors, anchor flanges and
concrete blocks of reinforcement. Stress induced at the pipeline transition point
shall be calculated and verified for no failure.
10.7. FLANGES, BRANCH CONNECTIONS AND FITTINGS
Threaded connections (Pipe to pipe, fittings), slip-on flanges and miter
connections shall not be used in any part of the pipeline system. “Pup” pieces
shall not be less than 300mm length or one pipe diameter whichever is greater.
For mechanical strength reasons, there shall be no branch or instrument
connections smaller than DN 50 mm (2”) on the pipeline which are exposed to
service. Gaskets for flanged connections shall be as per project specification
for the relevant pressure class. The number of flanged connections in the
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 35/54
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 36/54
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 37/54
EFFLUENT WATER TREATMENT AND INJECTION
PLANT (NK)
Project No. EF/1761
Class 1
CONTRACT NO. 14050642 Page 37 of 54
PIPELINE DESIGN BASIS Rev 1
Doc. No. : 14050642-100-PL-DBM-0001 Date 19.06.2016
12. PIPELINE DESIGN CRITERIA
12.1. GENERAL
The design criteria for the project are based on providing safe, environmentally
acceptable, low cost pipelines that are fit for their intended uses. All pipelines
and facilities shall be designed to the codes and standards identified in this
document and provide a 25-year service life.
Steel pipelines shall be designed in accordance with ASME B31.4 / B31.8 as
applicable. RTRP pipelines shall be designed in accordance with KOC
standard for RTRP pipes and fittings: KOC-MP-011, part 1 and Engineering
design and installation: KOC-MP-011 Part 2.
12.2. PIPELINE WALL THICKNESS CALCULATION
Pipeline Wall thicknesses are to be based on Pressure containment and
combined stresses plus corrosion allowance. The minimum selected wall
thickness shall be based on the following:
The OD/WT ratio maximum shall be ≤ 96 (land installation)
External interference by third parties is not considered to be criteria for
minimum pipe wall thickness as the pipeline shall be laid in designated pipeline
corridors. The minimum wall thickness consideration shall be 6.35mm.
The minimum thickness provided in FEED shall govern. The selected thickness
during detailed engineering shall be greater than or equal to FEED thickness
calculation.
Pipeline wall thickness shall be calculated as per ASME B 31.4 for hydrocarbon
liquid services and as per ASME B 31.8 for hydrocarbon gas services as
appropriate and pipeline stress shall be checked as per the code ASME B 31.8
& B 31.4
RTRP Pipeline wall thickness shall be per manufacturer standard based on
design pressure & temperature provided in Appendix-1 of this design basis.
1
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 38/54
EFFLUENT WATER TREATMENT AND INJECTION
PLANT (NK)
Project No. EF/1761
Class 1
CONTRACT NO. 14050642 Page 38 of 54
PIPELINE DESIGN BASIS Rev 1
Doc. No. : 14050642-100-PL-DBM-0001 Date 19.06.2016
12.3. DESIGN FACTOR
Design factors to be used for calculating pipeline wall thickness shall be as
given in following Table 12.1.
Table 12.1: Design Factors
Fluid Design Factor
Effluent Water 0.72
Treated water 0.72
Fuel Gas 0.72 / 0.6 / 0.5
Distribution and Injection
Pipelines / Flow lines0.72
Brackish Water 0.72
Recovered Oil 0.72
12.4. STRESS CALCULATION AT ROAD CROSSINGS
Stresses in pipeline at road crossings shall be checked using methods
specified in API RP 1102, Steel Pipelines Crossing Railroads and Highways.
Stresses shall be checked for fully corroded pipeline, i.e., after deducting
corrosion allowance from the pipeline nominal wall thickness.
12.5. PIPELINE AT ABOVE GROUND / BELOW GROUND TRANSITION
The Pipeline shall be subject to movements due to thermal expansion at the
inlet / outlet of pig traps. This movement shall induce stresses in the pipeline
and the connected above-ground piping. In order to limit the stresses within
allowable limits, the pipeline movement at the above ground – below ground
transition shall be reduced, either by providing adequate flexibility in the
pipeline configuration at the approach to the scraper traps or by providing
suitably-sized anchor blocks.
The stress analysis shall be carried out and the pipeline movement shall be
reduced as per detailed specification for pipeline flexibility analysis (14050642-
100-PL-SPC-0001).
1
1
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 39/54
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 40/54
EFFLUENT WATER TREATMENT AND INJECTION
PLANT (NK)
Project No. EF/1761
Class 1
CONTRACT NO. 14050642 Page 40 of 54
PIPELINE DESIGN BASIS Rev 1
Doc. No. : 14050642-100-PL-DBM-0001 Date 19.06.2016
13. PIPELINE ROUTING
A pipeline route survey shall be carried out prior to producing detailed route
alignment sheets which will include topographical, geotechnical and
underground investigation. The horizontal clearance between the pipelines
and the existing cable shall meet KOC-E-008 & KOC-L-002 requirements.
All pipelines installed in the new pipeline corridors will have 1 m berm constructed
from natural ground level for protection. The information included in the drawings,documents, specifications and alignment sheets must be reviewed fully to
appreciate the extent of the design parameters. All pipeline corridors depending
on the number of pipelines to be installed will have permanent six meter access
tracks constructed along each pipeline corridor to be used for pipeline
construction and also for permanent maintenance roads after construction
activities are completed. The location of permanent access tracks shall be shown
on the Pipeline Route Alignment sheets. No sectionalizing valves will be required
on any of the routes of the pipelines for intermediate isolation.
There are numerous rig track, gatch and asphalt road crossings, above and
below ground utilities to be crossed on all of the pipeline route corridors.
The minimum distance from the base of any power pylon shall be 20 meters as
per clause 11.4.2 of KOC-L-002. Where the pipeline runs parallel with a buried
power cable, the horizontal clearance between the pipeline and the existing cable
shall not be less than 3 meters. This shall be increased where there is a likelihood
of CP interference.
A Cathodic protection system shall be designed and installed on all steel buried
pipelines. A corrosion monitoring study shall also be carried out to review any
corrosion monitoring requirements on the various pipelines.
All carbon steel pipework will be externally coated along with the welded joints. All
carbon steel pipework will be welded to sour service conditions.
It is to be aware that there are other CONTRACTORS, working in the area along
with well drilling, road construction and other third party activities in North Kuwait.
Therefore interface is required with other CONTRACTORS to avoid any
disruption or impact to their work which would cause delay to their schedule.
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 41/54
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 42/54
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 43/54
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 44/54
EFFLUENT WATER TREATMENT AND INJECTION
PLANT (NK)
Project No. EF/1761
Class 1
CONTRACT NO. 14050642 Page 44 of 54
PIPELINE DESIGN BASIS Rev 1
Doc. No. : 14050642-100-PL-DBM-0001 Date 19.06.2016
Mechanical Equipment operation
parallel to existing pipelines**- 5m**
Pipelines that run parallel with power
lines*- 20m*
Pipeline in the same trench as Fiber
Optic Cable- 0.5m
Pipeline or existing service and cable
buried crossings1.0 m -
*For distance between pipelines and overhead lines shall be as per
clause 11.4.3 of KOC-L-002.
**For protection of existing services during construction in accordance
with clause 17.0 of KOC-L-002.
# The distance can be further reduced upto 1m with manual excavation.
13.4.2. PIPELINE BURIAL DEPTH
Minimum cover for pipelines shall be generally 1 m from gradeelevation; however it shall be 1.2m under field roads as per clause
17.3.8 of KOC-L-002. Pipeline burial depth from ground surface to top
of pipe shall be as per table 13.2 below
Table 13.2 Pipeline Burial Depths
Location Minimum Cover
Normal Terrain and sand Dunes 1.0 m
Minor road / Track Crossing (Uncased) 1.2 m
Asphalt Road and Rig Track crossings(Cased) 1.2 m*
Sabkha crossings/ High Water table Areas
(Note1) 1.5 m
* Minimum cover from top of casing pipe.
Note 1: No high water table / Sabkha areas are identified in this project.
Note that the above indicated cover values are the minimum between
top of pipe and natural ground surface. In addition, pipelines shall have
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 45/54
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 46/54
EFFLUENT WATER TREATMENT AND INJECTION
PLANT (NK)
Project No. EF/1761
Class 1
CONTRACT NO. 14050642 Page 46 of 54
PIPELINE DESIGN BASIS Rev 1
Doc. No. : 14050642-100-PL-DBM-0001 Date 19.06.2016
thickness shall meet the applicable Code requirements for road
crossing.
Sleeve pipe shall be sealed at each end with “Pull-On” type end seals to
prevent ingress of soil / water. Major Asphalt road crossings shall be
based on trenchless installation method using non-open cut techniques
like horizontal directional drilling, auger-boring, thrust-boring or micro-
tunneling techniques. But subject to approval by COMPANY, Open Cut
shall be carried out.
Crash Barriers shall be installed at all road crossings to protect the
installed pipeline and crossing vents from Third Party damage in
accordance with the drawings. All crossing methods shall be subject to
COMPANY approval. Pipeline safety shall be checked in accordance
with API 1102 – Steel Pipeline Crossing Railroads and Highways. all
road crossings shall be recorded during Topographic survey.
New pipelines shall be buried below existing pipelines with a minimum
clearance of 1.0m, unless otherwise agreed by the COMPANY.
All Major asphalt road crossings shall be made at an angle of 90
degree to the road Centre line by an approved ‘non-disruptive’ road
crossing method of carrier pipe without any casing if approved by
COMPANY. Specific crossing drawings shall be created for each major
crossing.
The minimum pipeline burial depth for the general route, road and track
crossings as given in table 13.2.
The following wheel loadings were taken into account in determining the stressesimposed on the carrier pipe / casing pipe at each crossing:
Asphalt Road / Highway / Track crossings: As per KOC specification 015-IH-
1002, 112kN per wheel at 900mm centers with maximum of four (4) wheels per
axle. Contact area per API RP 1102 is 0.093 square meters, giving surface
pressure = 1204 kN/m2.
Rig Track crossings: The total load of rig is 1100 KN and the maximum Tandem
axle wheel load is 550KN. The contact area, over which the wheel load isapplied, shall be taken as 0.403 square meters.
1
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 47/54
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 48/54
EFFLUENT WATER TREATMENT AND INJECTION
PLANT (NK)
Project No. EF/1761
Class 1
CONTRACT NO. 14050642 Page 48 of 54
PIPELINE DESIGN BASIS Rev 1
Doc. No. : 14050642-100-PL-DBM-0001 Date 19.06.2016
CrossingMinimum Crossing
Angle
Existing pipelines and cables,
Unimproved roads, track & Asphalt roads
60° (note-1)
Overhead power lines 90° (note-2)
Notes: 1. Wherever it is not feasible to maintain minimum 60°, the
crossing angle between proposed pipeline and existing pipeline / cables
can be reduced up to minimum 30°.
2. Wherever underground pipeline crosses overhead power
transmission lines, it shall be preferably be at right angle (90°). In
unavoidable locations, the horizontal angle of intersection shall be
maintained within 70° to 110° to the overhead power line.
13.4.5. PIPELINE CROSSING DRAWINGS
Detailed crossing drawings shall be generated for major asphalt road
crossings based on confirmed alignment of pipelines as per topographic
and geotechnical survey findings shall be provided. The crossing
drawings shall include as a minimum:
The road / track / ROW / pipelines / utility / feature to be crossed
in relation to the pipeline.
Profile including bend information and depth of cover (if
applicable).
Plan, at a scale not greater than 1:500.
COMPANY requirements, including minimum clearances,
protection requirements, etc.
Cathodic Protection details.
Pipeline markers.
Line size, material grade and wall thickness.
Crossing co-ordinates. Proposed method of Construction / Installation
1
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 49/54
EFFLUENT WATER TREATMENT AND INJECTION
PLANT (NK)
Project No. EF/1761
Class 1
CONTRACT NO. 14050642 Page 49 of 54
PIPELINE DESIGN BASIS Rev 1
Doc. No. : 14050642-100-PL-DBM-0001 Date 19.06.2016
13.4.6. PIPELINE PRESERVATION:
Pipeline preservation is not envisaged for this project. However, if
required, the pipeline preservation shall be carried out for Fuel Gas
Pipelines after construction, and hydro testing activities are completed.
The fuel gas carbon steel pipelines at the termination points of the
pipelines at the various installation boundary fences shall have welded
steel caps on the ends of the last pipe along with a 2 “ ball valve .Thepipelines shall be filled with nitrogen to a pressure of one barg and this
internal pipeline pressure shall be monitored to check that there is a
positive pressure in the pipeline until it is connected to the installation
facility pipeline. A temporary CP system must be installed and working
on the pipelines until a permanent CP system is designed and
commissioned. HDPE lined water injection pipelines, FBE lined
recovered oil pipelines and Pipelines constructed of RTRP do not
require nitrogen preservation.
13.5. TOPOGRAPHICAL & GEOTECHNICAL DATA
Topographic survey drawings, reports and geotechnical reports shall comply
with Project requirement as defined in scope of work for Topographical &
Geotechnical survey for Pipeline route corridor.
14. DESIGN PHILOSOPHY AND PHYSICAL DATA
14.1. PIGGING, HYDRO TESTING & INSPECTION
All carbon steel pipelines shall have a hydro test of 1.25 times the design
pressure in accordance with ASME B31.4 for water injection pipelines.
Fuel gas pipeline shall be hydro tested at 1.25 times the design pressure as
per table 841.3.2-1 ASME B31.8.
All RTRP pipelines shall have a hydro-test at 1.5 times the design pressure for
a period of 30 minutes as a strength test followed by a hydro-test at 1.33 times
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 50/54
EFFLUENT WATER TREATMENT AND INJECTION
PLANT (NK)
Project No. EF/1761
Class 1
CONTRACT NO. 14050642 Page 50 of 54
PIPELINE DESIGN BASIS Rev 1
Doc. No. : 14050642-100-PL-DBM-0001 Date 19.06.2016
the design pressure for a period of 8 hours in accordance with KOC standards
for RTRP Pipes & Fittings: Engineering Design and Installation, KOC-MP-011
part 2 or as required by company.
The Water injection lines, Recovered Oil lines and Fuel Gas Lines shall be
designed as piggable. For details and the requirement of permanent or
temporary pig traps on the individual systems refer schematic drawing. Pipeline
pigging and hydrostatic testing shall be carried out in accordance with KOC
Standard 015-IH-1004 and associated Project Addendum EWTIP-20-PL-SPC-0015.
14.2. NON DESTRUCTIVE TESTING
In road crossing, populated areas, Tie-ins and weld repair locations, All butt
welds shall be subjected to 100% X-ray radiography or UT and all fillet welds
shall be 100% tested with liquid penetrant / wet magnetic particle crack
detection method in accordance with company specifications 015-IH-1008 and
015-WH-1002.
14.3. PIPELINE DEWATERING AND DRYING
Pipeline dewatering and drying shall be conducted in accordance with KOC
Standard 015-IH-1005 and associated Project Addendum EWTIP-20-PL-SPC-
0016.
14.4. FIRE AND SAFETY REGULATIONS
All relevant safety requirements of KOC’s Fire and Safety Regulations and
KOC’s HSE policy Shall be adhered to while performing the works within KOC
pig-trap areas and pipeline route.
14.5. SITE TIE-IN REQUIREMENTS
The associated pipeline facilities required at tie-in sites include other valves
and piping. These facilities, up to the code break locations identified on the
P&IDs, shall be designed in accordance with ASME B31.4.
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 51/54
EFFLUENT WATER TREATMENT AND INJECTION
PLANT (NK)
Project No. EF/1761
Class 1
CONTRACT NO. 14050642 Page 51 of 54
PIPELINE DESIGN BASIS Rev 1
Doc. No. : 14050642-100-PL-DBM-0001 Date 19.06.2016
Positive isolation by spading / blinding shall be used for welded tie-ins. All tie-in
locations shall be identified and a tie-in schedule produced.
It shall be confirmed that the connecting piping is adequately protected from
overpressure of the pipeline.
Hot tapping shall be in accordance to KOC-MP-038: KOC recommended
practice for hot-tapping and plugging.
14.6. STRUCTURAL INTEGRITY:
The pipelines shall be checked for structural integrity taking into account the
anticipated stress conditions in the pipeline during installation, hydrostatic
testing and operation. As a minimum the following calculations/checks shall be
performed.
Internal pressure
Pipeline road and track crossing analysis in accordance with API 1102
Pipeline stress analysis
Pipeline flexibility and tie-in analysis for above ground pipe work
The stress analysis of the pipeline system shall be performed using the latest
version of Caesar II program and evaluated in accordance with the governing
code requirements. The stress analysis shall be carried out as per detailed
specification for pipeline flexibility analysis (14050642-100-PL-SPC-0001).
15. WELDING REQUIREMENTS
Welding shall be in accordance with API 1104: Welding of Pipelines and Related
Facilities, in conjunction with Project Specification EWTIP-20-PL-SPC-0002: Addendum
to KOC specification: Pipeline Design (015-IH-1002, rev.1), EWTIP-20-PL-SPC-0018:
Addendum to KOC specification for pipeline construction (015-IH-1001, rev.1).
It shall be in line with company standards 015-IH-1008, 015-IH-1001 and 015-IH-1002.
For sour service pipeline welding, a project specific welding specification is developed
and followed. Refer Document No: Weld key plan / Weld table: 14050642-700-QA-PRO-
0045.
1
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 52/54
EFFLUENT WATER TREATMENT AND INJECTION
PLANT (NK)
Project No. EF/1761
Class 1
CONTRACT NO. 14050642 Page 52 of 54
PIPELINE DESIGN BASIS Rev 1
Doc. No. : 14050642-100-PL-DBM-0001 Date 19.06.2016
16. TESTING AND PRE-COMISSIONING
During the detail engineering phase of the project the optimum method of pipeline
testing and pre-commissioning shall be developed which shall take into account
method(s) of test water supply and disposal, dewatering, required level of dryness,
method of pipeline drying and introduction of product into the pipeline. Reference
shall be as per the Philosophy for cleaning, Gauging, Hydro testing, Dewatering,Drying and Purging of Flow lines/ Pipelines. The cleaning, gauging, testing, drying
and pre-commissioning activities shall be performed generally in accordance with the
above philosophy and Company specifications 015-IH-1004 and 015-IH-1005 with
Project Addendums EWTIP-20-PL-SPC-0015 and EWTIP-20-PL-SPC-0016.
17. CORROSION PROTECTION
17.1. CATHODIC PROTECTION
The underground pipelines shall be protected by the application of high-
integrity coating systems supplemented with impressed current cathodic
protection (ICCP). Temporary CP utilizing sacrificial anodes shall be used to
protect the pipelines during construction, and prior to commissioning of the
permanent ICCP systems. CONTRACTOR shall carry out a detailed corrosion
study to confirm the requirements for corrosion fittings, corrosion monitoring
sample pits and locations along the various pipelines. Reference shall be made
to company specification KOC-MP-035: Internal Corrosion Monitoring
Equipment for Facilities and Pipelines.
Insulating flange joints shall be provided at the location of underground to
aboveground transition of pipelines and wherever applicable as per clause 7.11
of KOC-L-015 for cathodically protected pipelines.
All carbon steel pipelines will be electrically isolated from pigging facilities by a
properly designed cathodic isolation device downstream of the bypass tee.
Pipeline/piping portions including valves and flanges in valve pits shall be
protected against corrosion to KOC standards and ensure integrity of cathodic
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 53/54
EFFLUENT WATER TREATMENT AND INJECTION
PLANT (NK)
Project No. EF/1761
Class 1
CONTRACT NO. 14050642 Page 53 of 54
PIPELINE DESIGN BASIS Rev 1
Doc. No. : 14050642-100-PL-DBM-0001 Date 19.06.2016
protection system. All pipe supports shall ensure integrity of cathodic protection
system.
Cathodic protection shall be installed to provide the level of protection required
by the KOC standard KOC-L-015.
17.2. EXTERNAL CORROSION
17.2.1. COATING
The carbon steel pipes shall be externally coated with a shop applied
dual-layer fusion bonded epoxy corrosion coating as per company
specification KOC-P-004 part 4 rev.2 and field joint external coating for
girth welds, pipeline fitting and flanges shall be protected with fusion
bonded epoxy coating as per company specification KOC-P-004 part
7, rev.2.
Above ground installations shall be in accordance to Company
standard KOC-P-001.
Coating thickness DFT and other characteristics shall comply to Table-
1 and Table-3 of KOC-P-004 part 4 rev.2
7/26/2019 14050642 100 PL DBM 0001_Pipeline Design Basis_Rev 1
http://slidepdf.com/reader/full/14050642-100-pl-dbm-0001pipeline-design-basisrev-1 54/54