11W-Ch 10&11 Capital Budget Basics & CF estimation-2011-12-skraćeno

Embed Size (px)

Citation preview

  • 8/2/2019 11W-Ch 10&11 Capital Budget Basics & CF estimation-2011-12-skraeno

    1/38

    10-1

    CHAPTER 10 & 11The Basics of Capital Budgeting &Cash Flow Estimation

    Should webuild this

    plant?

  • 8/2/2019 11W-Ch 10&11 Capital Budget Basics & CF estimation-2011-12-skraeno

    2/38

    10-2

    Capital Budgeting Overview Project Classifications

    Analysis Methods/Decision Rules

    Comparison of NPV & IRR

    Optimal Capital Budget

  • 8/2/2019 11W-Ch 10&11 Capital Budget Basics & CF estimation-2011-12-skraeno

    3/38

    10-3

    What is Capital Budgeting? Long-term Strategic Decisions

    Analysis of Future Cash Flows

    Large Expenditures (Fixed Assets)

    Basis for Future Growth

  • 8/2/2019 11W-Ch 10&11 Capital Budget Basics & CF estimation-2011-12-skraeno

    4/38

    10-4

    5 Steps to Capital Budgeting1. Estimate CFs (inflows & outflows)

    2. Assess riskiness of CFs

    3. Determine the Risk-adjusted Cost of Capital

    4. Find NPV and/or IRR (and other methods)

    5. Accept if NPV > 0 and/or IRR > WACC

  • 8/2/2019 11W-Ch 10&11 Capital Budget Basics & CF estimation-2011-12-skraeno

    5/38

    10-5

    Project Classifications Replacement

    Maintenance

    Cost Reduction Expansion

    Existing Products or Markets

    New Products or Markets

    Safety or Environmental

    R&D (Long-term)

    Long-term Contracts (Specific Customers)

  • 8/2/2019 11W-Ch 10&11 Capital Budget Basics & CF estimation-2011-12-skraeno

    6/38

    10-6

    Major Capital Budgeting

    Methods Payback ( + Discounted Payback)

    Discounted Cash Flow (DCF or NPV)

    Internal Rate of Return (IRR)

    Profitability Index (not used in practice)

    Modified Internal Rate of Return (MIRR)

  • 8/2/2019 11W-Ch 10&11 Capital Budget Basics & CF estimation-2011-12-skraeno

    7/38

    10-7

    Independent vs Mutually

    Exclusive Projects? Independent projects if the cash

    flows of one are unaffected by the

    acceptance of the other.

    Mutually exclusive projects if the

    cash flows of one can be adverselyimpacted by the acceptance of theother.

  • 8/2/2019 11W-Ch 10&11 Capital Budget Basics & CF estimation-2011-12-skraeno

    8/38

    10-8

    Normal vs Nonnormal cash flow

    streams? Normal streamNegative CF followed

    by a series of positive CFs. 1 change

    of sign Nonnormal stream Two or more

    changes of sign Most common:

    Negative CF followed by positive CFs,then negative CF to terminate

    Nuclear Power, Toxic Waste

  • 8/2/2019 11W-Ch 10&11 Capital Budget Basics & CF estimation-2011-12-skraeno

    9/38

    10-9

    Payback Method The number of years required to

    recover a projects cost, or How longdoes it take to get our money back?

    Calculated determining when thecumulative cash flow for the projectturns positive.

  • 8/2/2019 11W-Ch 10&11 Capital Budget Basics & CF estimation-2011-12-skraeno

    10/38

    10-10

    Calculating Payback

    PaybackL = 2 + / = 2.375 years

    CFt -100 10 60 100

    Cumulative -100 -90 0 50

    0 1 2 3

    =

    2.4

    30 80

    80

    -30

    Project L

    PaybackS = 1 + / = 1.6 years

    CFt -100 70 100 20Cumulative -100 0 20 40

    0 1 2 3

    =

    1.6

    30 50

    50

    -30

    Project S

  • 8/2/2019 11W-Ch 10&11 Capital Budget Basics & CF estimation-2011-12-skraeno

    11/38

    10-11

    Strengths & Weaknesses of

    Payback Strengths

    Provides an indication of a projects risk and

    liquidity. Easy to calculate and understand.

    Weaknesses Ignores the time value of money

    Discounted Payback Alternative

    Ignores CFs occurring after the payback

  • 8/2/2019 11W-Ch 10&11 Capital Budget Basics & CF estimation-2011-12-skraeno

    12/38

    10-12

    Net Present Value (NPV)

    Method Sum of the PVs ofALL cash inflows and

    outflows of a project:

    NPV = CFt/(1 + r)t + CF0

    OR

    n

    0tt

    t

    )r1(

    CFNPV

  • 8/2/2019 11W-Ch 10&11 Capital Budget Basics & CF estimation-2011-12-skraeno

    13/38

    10-13

    Project Ls NPV, r=10% Year CFt PV of CFt

    0 -100 -$100

    1 10 9.09

    2 60 49.59

    3 80 60.11

    NPVL = $18.79

    NPVS = $19.98

  • 8/2/2019 11W-Ch 10&11 Capital Budget Basics & CF estimation-2011-12-skraeno

    14/38

    10-14

    Rationale for NPVNPV= PV of inflows PV outflows (Cost)

    = Net gain in Wealth

    If projects are independent, accept if theproject NPV > 0

    If projects are mutually exclusive, accept

    projects with the highest positive NPV, Accept S if mutually exclusive (NPVs >

    NPVL) & both if independent

  • 8/2/2019 11W-Ch 10&11 Capital Budget Basics & CF estimation-2011-12-skraeno

    15/38

    10-15

    Internal Rate of Return (IRR)

    Method IRR is the discount rate that forces PV of

    inflows equal to costs. NPV = 0:

    IRRL = 18.13% and IRRS = 23.56%.

    n

    0tt

    t

    )IRR1(

    CF0

  • 8/2/2019 11W-Ch 10&11 Capital Budget Basics & CF estimation-2011-12-skraeno

    16/38

    10-16

    Project IRR vs Bond YTM

    Same Concept

    YTM on the bond would be the IRR

    of the bond project

    EXAMPLE: Assume a 10-year bond

    with a 9% annual coupon sells for$1,134.20.

    Solve for IRR = YTM = 7.08%

  • 8/2/2019 11W-Ch 10&11 Capital Budget Basics & CF estimation-2011-12-skraeno

    17/38

    10-17

    Rationale for IRR

    If IRR > WACC, the Projects return

    is greater than its costs.

    There is excess Return left over to

    boost stockholders returns.

  • 8/2/2019 11W-Ch 10&11 Capital Budget Basics & CF estimation-2011-12-skraeno

    18/38

    10-18

    IRR Acceptance Criteria

    If IRR > r, accept project.

    If IRR < r, reject project.

    If projects are independent, acceptboth projects, as IRR > r = 10%

    If projects are mutually exclusive,accept S, because IRRs > IRRL.

  • 8/2/2019 11W-Ch 10&11 Capital Budget Basics & CF estimation-2011-12-skraeno

    19/38

    10-19

    NPV Profiles

    A graphical representation of project NPVs atvarious different costs of capital.

    r NPVL NPVS0 $50 $405 33 29

    10 19 2015 7 1220 (4) 5

  • 8/2/2019 11W-Ch 10&11 Capital Budget Basics & CF estimation-2011-12-skraeno

    20/38

    10-20

    Drawing NPV profiles

    -10

    0

    10

    20

    30

    40

    50

    60

    5 10 15 20 23.6

    NPV($)

    Discount Rate (%)

    IRRL = 18.1%

    IRRS = 23.6%

    Crossover Point = 8.7%

    SL

    .

    .

    . ...

    .

    ..

    . .

  • 8/2/2019 11W-Ch 10&11 Capital Budget Basics & CF estimation-2011-12-skraeno

    21/38

    10-21

    Main Reasons why NPV & IRRDecisions may Conflict

    Reinvestment Rate Assumptions aredifferent

    Size (scale) differences the smaller project freesup funds at t = 0 for investment. The higher theopportunity cost, the more valuable these funds,so high r favors small projects

    Timing differences the project with fasterpayback provides more CF in early years forreinvestment. If r is high, early CF good, NPVS >NPVL.

  • 8/2/2019 11W-Ch 10&11 Capital Budget Basics & CF estimation-2011-12-skraeno

    22/38

    10-22

    Reinvestment Rate Assumptions

    NPV method assumes CFs are reinvested atr, the opportunity cost of capital.

    IRR method assumes CFs are reinvested atIRR.

    Assuming CFs are reinvested at the opportunity

    cost of capital is more realistic, so NPV method isthe best.

    NPV method should be used to choose betweenmutually exclusive projects.

  • 8/2/2019 11W-Ch 10&11 Capital Budget Basics & CF estimation-2011-12-skraeno

    23/38

    10-23

    Profitability Index (PI)

    PI is the Ratio of the PV of the CashInflows to the PV of Investment

    PI = [ [CFinflowt/(1+r)t]] CFinvest0

    PIL = $158.1/$100 = 1.581

    PIs = $159.7/$100 = 1.597

  • 8/2/2019 11W-Ch 10&11 Capital Budget Basics & CF estimation-2011-12-skraeno

    24/38

    10-24

    Theory says to accept all positive NPVprojects.

    Two problems can occur when there isnot enough internally generated cash to

    fund all positive NPV projects:An increasing Marginal Cost of Capital.

    Capital Rationing

    Optimal Capital Budget

  • 8/2/2019 11W-Ch 10&11 Capital Budget Basics & CF estimation-2011-12-skraeno

    25/38

    10-25

    Externally raised capital can have largeflotation costs, which increase the cost

    of capital.

    Investors often perceive large capital

    budgets as being risky, which drives upthe cost of capital.

    Increasing Marginal Cost ofCapital

  • 8/2/2019 11W-Ch 10&11 Capital Budget Basics & CF estimation-2011-12-skraeno

    26/38

    10-26

    Capital rationing occurs when acompany chooses not to fund allpositive NPV projects.

    The company typically sets an upperlimit on the total amount of capitalexpenditures that it will make in theupcoming year.

    Capital Rationing

  • 8/2/2019 11W-Ch 10&11 Capital Budget Basics & CF estimation-2011-12-skraeno

    27/38

    10-27

    Cash Flow Estimation

    Estimating Relevant Cash Flows

    Adjusting for Inflation

  • 8/2/2019 11W-Ch 10&11 Capital Budget Basics & CF estimation-2011-12-skraeno

    28/38

    10-28

    Relevant Project Cash Flows

    2 Cardinal Rules Use Cash Flows NOT Accounting Income

    Use Incremental After-tax Cash Flows Cash Flows Included

    Opportunity Costs

    Externalities Cash Flows NOT Included

    Finance Costs

    Sunk Costs

  • 8/2/2019 11W-Ch 10&11 Capital Budget Basics & CF estimation-2011-12-skraeno

    29/38

    10-29

    Example Project Initial Investment

    Depreciable Investment ($240,000)

    Changes in Working Capital ($20,000)

    Operations (no inflation)

    New sales: 100,000 units/year @ $2/unit

    Variable cost: 60% of sales

    Life of the project

    Economic life: 4 years

    Depreciable life: MACRS 3-year class

    Salvage value: $25,000

    Tax rate: 40%

    WACC: 10%

  • 8/2/2019 11W-Ch 10&11 Capital Budget Basics & CF estimation-2011-12-skraeno

    30/38

    10-30

    Determining Project Value

    Estimate relevant Cash Flows

    0 1 2 3 4

    Initial OCF1 OCF2 OCF3 OCF4Invest +

    TerminalCFs

    NCF0 NCF1 NCF2 NCF3 NCF4

  • 8/2/2019 11W-Ch 10&11 Capital Budget Basics & CF estimation-2011-12-skraeno

    31/38

    10-31

    Investment Cash Flows

    Initial Investments (Depreciable Cost)

    Equipment $200,000

    Ship/Installation 40,000Net Investment CF0 $240,000

    Change in Working Capital Inventories $25,000 (Asset)

    Acct/Payables $5,000 (Liability)

    NetNOWC $20,000

  • 8/2/2019 11W-Ch 10&11 Capital Budget Basics & CF estimation-2011-12-skraeno

    32/38

    10-32

    Annual Depreciation Expense

    Year Rate x Basis Depr1 0.33 x $240 $ 792 0.45 x 240 1083 0.15 x 240 364 0.07 x 240 17

    1.00 $240

    Due to the MACRS -year convention, a3-year asset is depreciated over 4 years.

  • 8/2/2019 11W-Ch 10&11 Capital Budget Basics & CF estimation-2011-12-skraeno

    33/38

    10-33

    Annual Operating Cash Flows1 2 3 4

    Revenues 200 200 200 200- Op. Costs (60%) -120 -120 -120 -120

    - Depr Expense -79 -108 -36 -17Oper. Income (EBIT) 1 -28 44 63- Tax (40%) - -11 18 25Oper. Income (AT) 1 -17 26 38

    + Depr Expense 79 108 36 17Operating CF 80 91 62 55

  • 8/2/2019 11W-Ch 10&11 Capital Budget Basics & CF estimation-2011-12-skraeno

    34/38

    10-34

    Terminal Cash Flow

    Recovery of NOWC $20,000

    Salvage value 25,000

    Tax on SV (40%) -10,000

    Terminal CF $35,000

  • 8/2/2019 11W-Ch 10&11 Capital Budget Basics & CF estimation-2011-12-skraeno

    35/38

    10-35

    Estimated Project CFs (NoInflation)

    IRR & NPV at WACC = 10%. NPV = -$4.01 million

    IRR = 9.28%

    Payback = 3.30 yrs

    0 1 2 3 4

    -260 80 91 62 55

    +Terminal CF

    3590

    CCF -260 -180 -89 -27 63

  • 8/2/2019 11W-Ch 10&11 Capital Budget Basics & CF estimation-2011-12-skraeno

    36/38

    10-36

    What if the expected AnnualInflation is 5%. Is NPV biased?

    Yes, inflation included in the discountrate (WACC)

    Inflation NOT included in CFs

    CFs should be adjusted for Inflation

  • 8/2/2019 11W-Ch 10&11 Capital Budget Basics & CF estimation-2011-12-skraeno

    37/38

    10-37

    Operating CFs, Inflation = 5%

    1 2 3 4

    Revenues 210 220 232 243Op. Costs (60%) -126 -132 -139 -146- Depr Expense -79 -108 -36 -17- Oper. Income (BT) 5 -20 57 80- Tax (40%) 2 -8 23 32

    Oper. Income (AT)3 -12 34 48

    + Depr Expense 79 108 36 17Operating CF 82 96 70 65

  • 8/2/2019 11W-Ch 10&11 Capital Budget Basics & CF estimation-2011-12-skraeno

    38/38

    10 38

    Estimated Project CFsadjusted for Inflation

    0 1 2 3 4

    -260 82 96 70 65

    Terminal CF 35100

    IRR & NPV at WACC = 10%. NPV = $14.78 million.

    IRR = 12.56%.

    Payback = 3.12 yrs