Upload
manuel-reyes
View
214
Download
0
Embed Size (px)
Citation preview
8/11/2019 07 - Project Planning.2012
1/25
2010 wibas GmbHFor internal use only - 1 -
Turning Visions into Business.
Project Management07 Project Planning
8/11/2019 07 - Project Planning.2012
2/25
2010 wibas GmbHFor internal use only - 2 -
1 Project Planning Overview
8/11/2019 07 - Project Planning.2012
3/25
2010 wibas GmbHFor internal use only - 3 -
Establish and maintain plans that define project activities
Establish Estimates(SG 1)
Develop a Project Plan(SG 2)
Obtain Commitmentto the Plan
(SG 3)
Planning-Data
Project-Plans
Project Monitoring andControl
8/11/2019 07 - Project Planning.2012
4/25
2010 wibas GmbHFor internal use only - 4 -
Establish Estimates(SG 1)
Estimates of project planning parameters are established and
maintained
Estimate theScope of the
Project
(SP 1.1)
EstablishEstimates of
Work Product
and Task
Attributes
(SP 1.2)
DetermineEstimates of
Effort and Cost
(SP 1.4)
Define theProject Life
Cycle
(SP 1.3)
Planning-Data
8/11/2019 07 - Project Planning.2012
5/25
2010 wibas GmbHFor internal use only - 5 -
Establish Estimates(SG 1)
Typical Work Products for Establishing Estimates
SP 1.1 Estimate theScope of the Project
1. Task descriptions
2. work package
descriptions
3. WBS
SP 1.2 EstablishEstimates of Work
Product and Task
Attributes
1. Technical approach
2. size and complexity of
tasks and work products3. Estimating models
4. Attribute estimatesSP 1.4 DetermineEstimates of Effort and
Cost
1. Estimation rationale
2. Project effort estimates
3. Project costs estimates
SP 1.3 Define the
Project Life Cycle1. Project life-cycle
phases
Planungs-Daten
8/11/2019 07 - Project Planning.2012
6/25
2010 wibas GmbHFor internal use only - 6 -
Develop a Project Plan(SG 2)
A project plan is established and maintained as the basis for
managing the project
Establish theBudget and
Schedule
(SP 2.1)
Plan for ProjectResources
(SP 2.4)
Plan for DataManagement
(SP 2.3)
Identify theProject Risks
(SP 2.2)
Planning-Data
Plan forNeeded
Knowledge and
Skills
(SP 2.5)
PlanStakeholder
Involvement
(SP 2.6)
Establish theProject Plan
(SP 2.7)
Project-PlansProject Monitoring
and Control
8/11/2019 07 - Project Planning.2012
7/25
2010 wibas GmbHFor internal use only - 7 -
Develop a Project Plan
(SG 2)
Typical WP for Developing a Project Plan
SP 2.1 Establishthe Budget and
Schedule
1. Project Schedules
2. Schedule
dependencies
3. Project budget
SP 2.4 Plan for ProjectResources
1. WBS work packages
2. WBS task dictionary
3. Staffing requirements
based on project size andscope
4. Critical facilities/equipment
list
5. Process/workflow
definitions and diagrams6. Program administration
requirements list
SP 2.3 Plan for Data
Management1. Data management plan
2. Master list of managed data
3. Data content and format
description4. Data requirements lists for
acquirers and for suppliers
5. Privacy requirements
6. Security requirements
7. Security procedures8. Mechanism for data
retrieval, reproduction, and
distribution
9. Schedule for collection of
project data10. Listing of project data to
be collected
SP 2.2 Identify theProject Risks
1. Identified Risks
2. Risk impacts and
probability of
occurence
3. Risks priorities
Planning-Data
SP 2.5 Plan for NeededKnowledge and Skills
1. Inventory of skill needs
2. Staffing and new hire
plans
3. Databases (e.g., skills and
training)
SP 2.6 PlanStakeholder
Involvement
1. Stakeholder
Involvement Plan
SP 2.7 Establish theProject Plan
1. Overall Project Plan
Project-PlansProject Monitoring
and Control
8/11/2019 07 - Project Planning.2012
8/25
2010 wibas GmbHFor internal use only - 8 -
Obtain Commitment to the Project Plan(SG 3)
Commitments to the project plan are established and maintained
Review Plansthat Affect the
Project
(SP 3.1)
ReconcileWork and
Resource
Levels
(SP 3.2)
Obtain PlanCommitment
(SP 3.3)
Project-Plans
8/11/2019 07 - Project Planning.2012
9/25
2010 wibas GmbHFor internal use only - 9 -
Obtain Commitment to the Project Plan (SG 3)
Typical WP for Obtaining Commitment to the Project Plan
SP 3.1 Review Plnas thatAffect theProject
1. Record the reviews of plans
that affect the projectSP 3.2 Reconcile Work andResource Levels
1. Revised methods and
corresponding estimating parameters
(e.g., better tools, use of off-the-shelfcomponents)
2. Renegotiated budgets
3. Revised schedules
4. Revised requirements list
5. Renegotiated stakeholder
agreements
SP 3.3 Obtain PlanCommitment
1. Documented requests for
commitments
2. Documented commitments
Project-Plans
8/11/2019 07 - Project Planning.2012
10/25
2010 wibas GmbHFor internal use only - 10 -
Project Planning is the basis for managing the project
Why do we do it?
! Cover all projects activities
! Provides the basis
for performing and controllingthe project's activities
Advice and Guidance
! Plan with results
! First estimate, then plan the schedule
! Make all plans consistent and
maintain the plans over the projectlife cycle.
!
Plan for corrective actions.
! Identify projects stakeholders and their roles and use the Project Lifecycle for identifying
the dates for stakeholder involvement.
! Obtain commitment of all stakeholders including team members.
8/11/2019 07 - Project Planning.2012
11/25
2010 wibas GmbHFor internal use only - 11 -
2 Schedule
8/11/2019 07 - Project Planning.2012
12/25
2010 wibas GmbHFor internal use only - 12 -
The work of the work breakdown structure is now scheduled
Scheduling means to arrange the work of the work breakdown structure suchthat time, budget and resource constraints are fulfilled.
Scheduling is typically done using a precedence diagramming method, e.g: aGANTT chart or a project network diagram.
8/11/2019 07 - Project Planning.2012
13/25
2010 wibas GmbHFor internal use only - 13 -
A GANTT Chart is a horizontal bar chart developed by Henry L.
Gantt
8/11/2019 07 - Project Planning.2012
14/25
2010 wibas GmbHFor internal use only - 14 -
A project network diagram shows the activities as boxes and the
dependencies between them
8/11/2019 07 - Project Planning.2012
15/25
2010 wibas GmbHFor internal use only - 15 -
Both diagrams provides a graphical view of the project, predict
the time required to complete the project, and show which
activities are critical to maintaining the schedule
! ES - earliest start time: the earliest time atwhich the activity can start given that its
precedent activities must be completed first.
! EF - earliest finish time, equal to the earliest
start time for the activity plus the time required
to complete the activity.! LF - latest finish time: the latest time at which
the activity can be completed without delayingthe project.
! LS - latest start time, equal to the latest finish
time minus the time required to complete the
activity.
Task Name
Duration
(ES) Earliest Start Earliest Finish (EF)
(LS) Latest Start Latest Finsih (LF)
8/11/2019 07 - Project Planning.2012
16/25
2010 wibas GmbHFor internal use only - 16 -
Calculating the critical path by determing the earliest start and
finish dates and the latest start and finish date! To calculate the earliest start and finish date, start from the first task. For each task, add
the duration to the earliest start (ES) to get the earliest finish (EF). For all successors, the
largest input EF becomes the ES.
! To calculate the latest start and finish date, start from the last task. For each task, subtractthe duration from the latest finish (LF) to get the latest start (LS). For all predecessors, the
smallest LS becomes the LF.
Initiate Build Cycle
1
Develop Support Material
1
Develop Heater Module
5
Develop Printing Module
3
Develop Reader Module
7
Perform System Testing
2
Plan Deployment
2
Confirm Build Cycle
2
8/11/2019 07 - Project Planning.2012
17/25
2010 wibas GmbHFor internal use only - 17 -
A plan is more than a schedule
A plan addresses technical as well as management activities.
A plan consists of:
! Budgets, schedules, and milestones
! data management
!
risk identification
! resource and skill requirement
! stakeholder identification and interaction (stakeholders are all roles involved in the project)
The overall project must be kept as a separate document (e.g. a maintainedproject definition) that serves as an entry point for new team members, quality
assurance and senior management.
8/11/2019 07 - Project Planning.2012
18/25
2010 wibas GmbHFor internal use only - 18 -
A plan needs commitment from all relevant stakeholders
otherwise the plan is likely to fail
! A plan must be aligned with other plans that affect the project (e.g. plans of other initiatives,
of suppliers, etc.)
! A plan must be aligned with the actual resources (budget, time, people, infrastructure).
! A plan must be agreed to by the team performing the work.
8/11/2019 07 - Project Planning.2012
19/25
2010 wibas GmbHFor internal use only - 19 -
o a pr n
8/11/2019 07 - Project Planning.2012
20/25
2010 wibas GmbHFor internal use only - 20 -
Exercise: 1h Scrum (1/2)
Task and Results:
1.
Sprint Goal: You are invited by a Business Angel tomake him a solution proposal (make a demo whathe will get)
Preparation Instructions:
! Explanation
! In the groups, decide who is Product Owner andwho is ScrumMaster (PM)
! Product Owner prepares Backlog for the Sprint
!
Teams set up place to work (get paper, pens,!
)
! Scrum Masters set up Sprint Board, Burndown
Chart,!.
8/11/2019 07 - Project Planning.2012
21/25
2010 wibas GmbHFor internal use only - 21 -
Exercise: 1h Scrum (2/2)
Task and Results:
1.
Sprint Goal: You are invited by a Business Angel tomake him a solution proposal (make a demo whathe will get)
Instructions:
! 10 min: Grooming: Estimate the Product Backlog
Items
! 10 min: Sprint Planning I
! 10 min: Sprint Planning II
!
Conduct 3 days
10 min. work
2 min Standup
! 10 min Sprint Review
! 10 min Sprint Retrospective
-------------
! 10 min: debrief
8/11/2019 07 - Project Planning.2012
22/25
2010 wibas GmbHFor internal use only - 22 -
Review Scrum against CMMI
Do:
! FOR SPi = SP 1.1 SP 3.3
3-4 people pick SPi and write answer to HowScrum implements Spi
UNTIL timebox ends
Timebox: 15 min
8/11/2019 07 - Project Planning.2012
23/25
2010 wibas GmbHFor internal use only - 23 -
Team 1 Team 2 Team 3 Team 4 Team 5 Team 6
Team did deliver
Product Owner (PO)satisfied
ScrumMaster ensuredtimes strictly
Change Request (CR)rejected
Only ScrumMasterdiscussed CR with PO
Standup with 3questions
ScrumMaster did not dowork
Review of the work
8/11/2019 07 - Project Planning.2012
24/25
2010 wibas GmbHFor internal use only - 24 -
Revision History
Rev.
no.State Date Comments Responsible
1.1 Finished 03.10.2004 Initial version Malte Foegen
1.2 Finished 21.06.2006 Revision History added, SEI Partner logo included, current template Malte Foegen
1.3 Finished 23.12.2007 Layout updates, added Scrum slides Malte Foegen
1.4 Finished 19.01.2008 Added sprint exercise and deleted other exercises Malte Foegen
1.5 Finished 23.01.2009 Added Sprint Review Slide Malte Foegen
1.6 Finished 18.01.2010 Updated layout Malte Foegen
1.7 Finished 21.01.2011 Extracted Scrum slides Malte Foegen
1.8 Finished 03.02.2012 New exercises Malte Foegen
Target status: finishedTemplate-Version: 2.11
8/11/2019 07 - Project Planning.2012
25/25
2010 wibas GmbHFor internal use only - 25 -
Otto-Hesse-Str. 19 B 64293 Darmstadt Germany Phone +49 / 6151 / 50 33 49 - 0 Fax +49 / 6151 / 50 33 49 33 www.wibas.com
Hintermettlen 7 6318 Walchwil Switzerland Phone +41 / 41 / 51122 - 90 Fax +41 / 41 / 51122 - 91 www.wibas.ch