Upload
khangminh22
View
0
Download
0
Embed Size (px)
Citation preview
Minutes of the 181st meeting of OCC (10.08.2021) Page 1 of 84
SOUTHERN REGIONAL POWER COMMITTEE
Minutes of the 181st Meeting of Operation Coordination Sub-Committee
held on 10.08.2021 through VC 1. Introduction
1.1. The 181st Meeting of Operation Coordination Sub-Committee (OCC) was held
on 10th August 2021through Video Conferencing (VC). The list of participants is
at Annexure-1.1.
1.2. Shri NRLK Prasad, Member Secretary I/c, SRPC & Chairperson of
Operation Coordination Sub-Committee (OCC) extended warm welcome to the
members and participants to the 181st Meeting of OCC. He informed that
Shri A Balan has been relieved from the duties of Member Secretary (SRPC)
with effect from 06.08.2021(AN) on appointment as Member (Planning), CEA.
He brought the following to the notice of members:
i) During the month of July 2021, Grid operated at above 50.05. Hz. for a
period of 19.59 % and 50Hz and above for a period of 61.01 %. There was
high frequency operation (above 50 Hz) on many days. On 18.07.2021 the
Grid operated at a frequency above 50 Hz for 82.93 % of time.
ii) A Special meeting of SRPC was convened on 14.07.2021 to deliberate
Transmission scheme for integration and evacuation of 18.5 GW REZ as
per the CERC Record of Proceeding (date of hearing: 25.06.2021) in
Petition No.200/MP/2019. The Minutes of the meeting is available at SRPC
website.
iii) New RSD Procedure has been implemented on trial basis for two months
from 01st August 2021. The experience during the trial operation would be
analyzed and future course of action would be decided accordingly.
iv) Night mode Operation of Solar inverters to control high voltages has been
implemented at Pavagada Solar Park w.e.f. 01st August 2021 on trial basis
for two months. The impact on the grid operation by night mode operation
of inverters at Pavagada Solar Park would be analyzed after the trial
operation and implementation on regular basis/ modalities would be
decided based on the outcome.
v) MoP has issued OM dated 20.07.2021 on the implementation of
“Revamped Distribution Sector Scheme-A Reforms based and Results
linked Scheme” with the objective of improving the quality and reliability
of power supply to consumers through a financially sustainable and
Minutes of the 181st meeting of OCC (10.08.2021) Page 2 of 84
operationally efficient distribution Sector. The Scheme aims to reduce the
AT&C losses to pan-India levels of 12-15% and ACS-ARR gap to zero by
2024-25.
vi) In the APTEL judgment dated 2nd August 2021 (available at SRLDC
website) in appeal No. 197/2019 certain directions have been issued to all
the State Commissions, Discoms and SLDCs with regards to curtailment of
power generated from Renewable Energy sources. All SLDCs to note the
Way forward for curtailment of RE power by State Load Dispatch Centre
mentioned in the APTEL judgment for compliance.
vii) There are four islanding schemes in service, Chennai, Neyveli, Hyderabad
and Kudankulam. Three new Islanding schemes, Visakhapatnam
(Simhadri), Vijayawada & Bengaluru are under implementation. All
SLDCs need to have SCADA display exclusively for the Islanding Schemes
to monitor important parameters like frequency, voltage, line loadings etc.
in the electrical boundary of the Island schemes. This would facilitate the
operator in the control room to analyze in real time the success rate of
formation of islands and to plan actions accordingly. He requested SLDCs
to furnish report on the healthiness of Islanding Schemes on regular
(monthly) basis. The settings of Under Frequency/Over frequency of all
participating generators to be revised appropriately so that no tripping of
the running Units takes place in the frequency range 47.5 – 52 Hz, and
extend support while the Island is on the course to stabilization. The revised
settings may be furnished to SRPC Secretariat for concurrence.
viii) He requested all the concerned entities to comply the mandatory
requirements of MoP orders in respect of Cyber Security. All RPCs are
requested to inform the states/ utilities to comply with the MoP orders dated
2nd July 2020 and 18th November 2020 regarding Testing of Equipment,
components and parts imported for use in the Power Supply system and
network in the country to check for any kind of embedded malware/Trojans
/cyber threat and for adherence to Indian standards.
1.3. OCC placed on record the excellent services rendered by Shri A Balan to
Southern Region Power System as Member Secretary of SRPC. The forum
wished him all the very best for the new assignment as Member (Planning),
CEA.
Then Superintending Engineer (O), SRPC took up the agenda.
Minutes of the 181st meeting of OCC (10.08.2021) Page 3 of 84
2. Confirmation of the Minutes of 180th Meeting of OCC
The 180th Meeting of OCC was held on 10.07.2021 through VC and the
Minutes were issued on 22.07.2021.
The Minutes of the 180th meeting of OCC were confirmed.
3 Agenda Items
3.1 Monthly Review of Maintenance schedules of ISGS
i) The list of maintenance schedules of ISGS and MPPs proposed to avail
during the current month and next month and postponed from these periods
are mailed to OCC Google Group every month on 4th normally.
ii) The outage schedules for the maintenance of various Generating Units are
regularly monitored in all OCC meetings and the Generators are requested
to avoid frequent changes in the outage planning.
iii) The maintenance schedules of the Generating Units of ISGS / MPPs to be
reviewed for the period of August / September 2021 have been circulated to
the constituents.
Deliberation:
(i) SRPC expressed concern on non-participation of representative of KGS
(NPCIL), NLC TS II during the deliberation on the outage of Generating
Units in the OCC meetings. SRPC requested KGS, NLC TS II to attend
the deliberations on outage of units regularly.
(ii) NTPC informed that RSTPS Unit-1 outage has been postponed due to
labor mobilization issues. The revival of RSTPS Unit- 3 under shut down
for maintenance work since 16.01.2021, further delayed to 31.08.2021.
(iii) It was noted with concern that the outage of RSTPS Unit- 3 has been
revised 19 times by NTPC. The following are the revised schedules of
RSTPS Units 1&3:
☛ RSTPS Unit-1 (200 MW) : 01.10.2021 to 13.01.2022 (105 days)
☛ RSTPS Unit-3 (200 MW) : 16.01.2021 to 31.08.2021 (228 days)
(iv) The original maintenance plan (AOH) for 2021-22 scheduled by NTPC in
respect of their Simhadri STPS Unit-1 (500 MW) scheduled originally to
avail for 35 days from 01.06.2021 – 05.07.2021 and Unit-4(500 MW) to
avail for 40 days from 18.10.2021.
Minutes of the 181st meeting of OCC (10.08.2021) Page 4 of 84
(v) NTPC informed that Simahdri STPS Unit-1 outage has been postponed
to avail from 15.10.2021 to 19.11.2021 on account of FGD.
TSTRANSCO requested NTPC to avail after 15th October, 2021
considering peak demand of Telangana during September/October
months.
(vi) After deliberation, The following revised schedules agreed for Simhadri
STPS Units 1&4:
☛ Simhadri STPS Unit-1(500 MW):15.10.2021 to 19.11.2021 (35 days)
☛ Simhadri STPS Unit-4 (500 MW):26.11.2021 to 04.01.2022(40 days)
(vii) SRPC informed that NLC TS II had revised their maintenance plans of
all the Units vide letter dated 02.08.2021. It was observed that the outage
of Unit 4 & 6 were overlapping during the 1st week of November, 2021.
There is a gap of only 5 days between the revival of Unit-1 planned for
23.08.2021, which is under off bar since 29.07.2021 and Unit-3 proposed
from 28.08.2021.
(viii) TANTRANSCO requested to postpone outage of NLC TS II Unit-3 to
15.09.2021 due to line loading issue.
(ix) The forum requested NLC to postpone Unit-3 outage and to revise other
Units outage also without any overlap. NLC TS-II assured to submit
revised schedules for all the Units.
(x) NLC TS II Expansion informed that Unit-2 (250 MW) 1st spell of
outage has been postponed to avail from 13.09.2021 instead of
01.09.2021 and Unit- 2 (250MW) 2nd spell of outage also would be
postponed to January 2022. OCC Forum requested NLC TS II Expansion
to schedule the outage to avail after May 2022 in view of January to May
months being SR Peak demand period. The revised schedules would be
as follows :
☛ NLC TS II ExpUnit-1(250 MW) :13.09.2021 to 12.10.2021 (30 days)
☛ NLC TS II ExpUnit-1(250 MW) to be availed after May 2022.
(xi) NNTPS vide mail dated 07.08.2021 had informed that NNTPS Unit-2,
the forced outage from 04.08.2021 has been converted to maintenance
outage would be revived on 13.08.2021. The outage was preponed for
carrying out water lancer commissioning works due to emergency
shutdown caused by Reheater Header drain welding crack. NNTPS
informed that the shutdown plan for water lancer commissioning or PG
Minutes of the 181st meeting of OCC (10.08.2021) Page 5 of 84
Test preparation would be taken with prior intimation to SRPC and the
balance outage days would be taken during December 2021 for Boiler
License Renewal.
(xii) The revised outage schedules would be as follows :
☛ NNTPS Unit-1 (500 MW) : 10.12.2021 to 03.01.2022 (25 days)
☛ NNTPS Unit- 2 (500 MW) :04.08.2021 to 15.08.2021 (12 days)
(xiii) The following maintenance schedules of MPPs Units were finalized in
the meeting :
☛ SEILP2, Unit-1 (660 MW) :COH 25.11.2021 to 05.01.2022 (42 days)
☛ SEILP2, Unit-2 (660 MW) :AOH 06.11.2021 to 20.11.2021 (15 days)
☛ ITPCL Unit-1 (600 MW): 15.06.2021 to 08.08.2021 (55 days)
☛ ITPCL Unit-2 (600 MW): 20.07.2021 to 09.08.2021 (21 days)
(xiv) All the maintenance schedules of ISGS/MPP Generating Units,
pertaining to the period of August / September, 2021were discussed in
the meeting and the approved list of maintenance schedules was mailed
to OCC Google Group on 12.08.2021 (Annexure -3.1).
(xv) All the beneficiaries were requested to note the schedules and all the
Generators were requested not to revise their AMP frequently unless
otherwise, if required, depending on the then Grid condition.
3.2 Processing of monthly outage proposals of Transmission Lines and
Elements in the Outage Coordination Meeting
(i) The outages proposed for the month of September 2021 in respect of
Transmission Lines and Elements proposed by other regions, State
Transmission Utilities, PGCIL and other transmission Entities has been
processed and discussed in the Outage Coordination Meeting held on
06.08.2021 through VC.
(ii) The list of outages of Transmission Lines and Elements, proposed for
September 2021 was mailed to OCC Google Group.
3.2.1 Review of AMP of Transmission Lines and Elements availed by PGCIL
SR- I & SR-II during the 1st quarter of 2021-22 (April – June) :
a) As per the Annual outage Plan and Outage Deviation Report data, furnished
by PGCIL SR1 & SR2, the outages availed by them were analyzed for the
period of 1st quarter of 2021-22 (Apr – June).
Minutes of the 181st meeting of OCC (10.08.2021) Page 6 of 84
b) It is a matter of concern that PGCIL SR 1 did not furnish their actual AMP
outage data for the 1st quarter.
c) PGCIL SR-II furnished the data of actual AMP availed during the 1st
quarter of 2021-22 (Apr – Jun).They have availed 30 out of 46 Nos of
Transmission Lines and 20 out of 25 Nos of Transmission Elements
including Reactors and ICTs. The details of Nos. of Transmission Lines and
Elements availed by them and the percentage of pending AMPs are
tabulated as shown below :
SL Entity
Total
AMP of
Lines /
Elements
planned
for 2021-
22
Total
AMP
planned
during
Q1
(Apr-
Jun)
AMP /
OSD
availed
during
Q1
(Apr-
Jun)
% availed
during Q1
against
planned
numbers in
Q1
(Apr-Jun)
% pending
for
2021-22
(To be < 75
%)
Transmission Lines (Intra Regional & Inter Regional)
1 PGCIL SR-I 81 22 27 * 61 % * 86 % *
2 PGCIL SR-II 128 46 30 65 % 77 %
Transmission Elements (Reactors & ICTs)
1 PGCIL SR-I 114 22 Included
in lines
Included in
lines
Included in
lines
2 PGCIL SR-II 126 25 20 80 % 84 %
* Inclusive of both Transmission lines and elements in respect of PGCIL SR 1
d) PGCIL SR-I was requested in the 173rd meeting of OCC to avail the
outage of the following major AMP shutdowns:
SL Transmission Line Originally
planned
Recommendation of
SRPC to shift to
1 765 kV Wardha – Nizamabad
1&2
1st & 2nd
February 2022
(2 days)
To avail by
December, 2021
2 Ramagundam – Chandrapur
1&2
1st February,
2022
To avail by
December, 2021
3 Jeypore – Gajuwaka 1&2 1st January,
2022
To avail by
December, 2021
The revised outage plan of the above Transmission Lines were yet to be
received.
Minutes of the 181st meeting of OCC (10.08.2021) Page 7 of 84
e) PGCIL SR-II& RSTCL were also requested to ensure that Talcher –
Kolar, Kudgi – Kolhapur & Raichur – Sholapur (PGCIL/RSTCL) outages
are not overlapping.
ISSUE:
(i) PGCIL SR-I & II to ensure completion of all AMP works by
December 2021 by Staggering of maintenance schedule of
Transmission Lines and Elements between August – December, 2021.
(ii) PGCIL SR-I to revise maintenance schedules of 765 kV Wardha –
Nizamabad 1&2, Ramagundam – Chandrapur 1&2 and Jeypore –
Gajuwaka 1&2 as recommended by SRPC in the 173rd OCC meeting.
(iii) PGCIL SR-II, RSTCL to ensure that Talcher – Kolar, Kudgi –
Kolhapur & Raichur – Sholapur (PGCIL/RSTCL) outages are not
overlapping.
Deliberation:
(i) PGCIL SR-I & II informed that the deviation with respect to the
planned AMP schedules for the 1st quarter of 2021-22 was due to the
guidelines of MoP not to avail the major shutdowns of transmission
lines and elements during the period of April / May, 2021. They
assured to revise their AMP schedules for the rest of the periods of
2021-22 and to complete the major shutdowns for AMP by December,
2021.
(ii) PGCIL assured that the Outage of 765 kV Wardha – Nizamabad 1&2
would be availed on 21st& 22nd August, 2021 respectively and would
not be availed again after forthcoming Pongal / Shanranti during this
year 2021-22.
(iii) PGCIL also assured that Ramagundam – Chandrapur 1&2 would be
availed by forthcoming Pongal / Shanranti during this year 2021-22.
3.2.2 Planned Stringing work of the 400 kV Thirunelveli–Kanarpatti Ckt-2, not
requested for approval in advance in the Outage Coordination meeting
(i) TANTRASCO had requested for outage of 400 kV Thirunelveli –
Kanarpatti Ckt-2 from 27.05.2021 on daily basis through PNOCC category
almost for a period of two months. SRPC had requested SRLDC to furnish
the actual outage history of this line in respect of the ongoing stringing
works.
Minutes of the 181st meeting of OCC (10.08.2021) Page 8 of 84
(ii) The reason for not proposing in the 178, 179 & 180th OCC Outage
Coordination Meetings / Mid Reviews such a long well planned work
were sought from TANTRANSCO. A complete consolidated plan of
outage for this line is to be furnished for getting approved.
(iii) SRPC has requested SRLDC to furnish the details of requests made by
TANTRANSCO in respect of 400 kV Thirunelveli–Kanarpatti Ckt 1 & 2
vs Agenda for the 181stmeeting of OCC (10.08.2021) Page 4 of 27 date of
the outage actually availed by them to take up the issue in the OCC
meeting.
(iv) TANTRANSCO vide their mail dated 27.07.2021 informed that 50% of
works were completed by availing line clear from 27.05.21 on daily basis
and the works could not be completed due to intermittent heavy rains,
non-issue of line clear in the 11 kV, 33 kV, 110 kV, 230 kV Crossings etc.
and they need this outage on daily basis up to 26.08.21 for completion of
the above said work. TANTRANSCO also requested to complete the EHT
line crossings of certain vital 400 kV, 230 kV, 110 kV feeders by Hotline
method since line clear could not be given in these feeders during this
wind and monsoon season.
(v) It is a serious matter of concern that such a long planned stringing work
for a period of two months has not been requested by TANTRANSCO in
the Outage Coordination meeting and instead the outage was requested for
availing daily basis. The opportunity of Outage Coordination Meetings /
Mid Reviews was not utilized by TANTRANSCO.
ISSUE:
(i) TANTRANSCO to submit consolidated detailed plan of outage for
400 kV Thirunelveli–KanarpattiCkt-2 for approval by OCC in the
181st Meeting in respect of remaining works.
(ii) TANTRANSCO to make use of the opportunities of Outage
Coordination Meetings / Mid Reviews in future
Deliberation:
(i) SRPC expressed concern on non-utilization of the opportunity of
Outage Coordination Meetings / Mid Reviews by TANTRANSCO.
Requested TANTRANSCO to avoid such lapses in future and to make
use of the opportunities of Outage Coordination Meetings / Mid
Reviews properly.
Minutes of the 181st meeting of OCC (10.08.2021) Page 9 of 84
(ii) TANTRANSCO informed that 40 days of outage is required and the
outage was planned considering the wind forecast and evacuation of
wind power. They assured to submit their consolidated detailed plan of
outage up to the end of August, 2021 through PNOCC category and
thereafter to submit the proposal vide 181st Mid Review in respect of
their remaining part of pending works.
3.2.3 Outages of 400 kV Thiruvalam Bus II proposed by PGCIL in the 180th
OCC Mid Review
(i) The following Transmission Lines were proposed by PGCIL SR-II for the
approval in the 180th OCC Mid Review for the construction works of 400
kV Thiruvalam Bus II & Bus Sectionalizer Bay (420) of Thiruvalam
complete shut down for both PGCIL & TANTRANSCO for removal of
Bus-II jumpers at TNEB side and erection of jack bus at PGCIL side under
Series Reactor Bay Extension Works:
a) Thiruvalam 400 kV Bus 2 (From 02nd to 03rd August 2021)
b) Bus Sectionalizer Bay (420) of Thiruvalam 400 kV Bus-2 and
Thiruvalam 400 kV Bus 2 (From 02nd to 10th August 2021)
c) Thiruvalam 400 kV Bus 2 (From 09th to 10th August 2021)
(ii) As the outage proposals exceed three days, TANTRANSCO did not
concur the same in the 180th Mid Review and wanted to discuss in the
181st OCC meeting.
ISSUE:
(i) Schedule of outage of 400 kV Thiruvalam Bus II & Bus Sectionalizer to
be finalised.
Deliberation:
(i) SRPC informed that the issue has been deliberated in the 181st OCC
Outage Coordination meeting and TANTRANSCO has concurred the
following shutdown schedules :
☛ Thiruvalam 400 kV Bus 2 : 17th,18th, 22nd , 23rd 25th & 26th August
2021
☛ Bus Sectionalizer Bay (420) of Thiruvalam 400 kV - BUS 2 and
Thiruvalam _TN – 400 kV - Bus 2: 17th to 26thAugust 2021
(ii) PGCIL SR II had also proposed Thiruvalam Bus 1 & Bus Sectionalizer
bay (419) of Thiruvalam – 400 kv Bus 1 and Thiruvalam_TN – 400 kv
Bus 1 @ 400 kV Thiruvalam for removal of Bus jumpers connected to
Minutes of the 181st meeting of OCC (10.08.2021) Page 10 of 84
TANTRANSCO, dismantling of Bus-1 Section equipment.
TANTRANSCO concurred the following schedule :
☛ Thiruvalam 400 kV Bus 1: 7th ,8th ,11th ,12th,15th &16th September 2021
☛ Bus Sectionalizer Bay (419) of Thiruvalam 400 kV - BUS 1 and
Thiruvalam _TN – 400 kV - Bus 1 :7th to 16th September 2021
3.2.4 Availing of Bay shut down of 400 kV and below
(i) In the meeting, PGCIL SR II informed that they are facing difficulties to
plan outage of bays of 400 kV & below lines well in advance and to take
the approval for the same as there are enormous numbers of such bays.
The decision taken in the 125th meeting of OCC needed to be followed for
bay shut down. The decision is as follows:
3.2.2.5 In the Meeting procedure for availing bay shut down was
reviewed. After deliberations it was agreed that individual bay S/D would
not be routed through OCC. S/D would be requested by entity and
approved by SRLDC and code would be exchanged. Bay S/Ds of 765 kV
would be routed through OCC.
(ii) ED, SRLDC emphasized the importance of taking approval of Bay outage
of 400 kV & below lines for the security of Grid. He pointed out that the
outage of Bays of 400 kV & below lines are having much impact on the
other outages, advance planning of such Bays are essential and the
planning of outage of these Bays do not require elaborate study.
(iii) SRPC sensitized that the outages would be viewed seriously in case of any
Grid incident / disturbance and emphasized the importance of taking prior
approval from SRLDC before availing the outage of Bays of 400 kV &
below lines. SRPC also reminded the requirement of taking approval of
outage of Bays of 765 kV lines through OCC meeting / OCC Outage
Coordination meeting.
Conclusion:
(i) Approval for the outage of Bays of 765 kV lines in respect of all the
Transmission Entities are required to be taken through OCC meeting /
OCC Outage Coordination meeting as per the prevailing practice.
(ii) Shutdown of Bays of 400 kV & below lines are to be availed through
PNOCC on D-10 to D-3 days or on D-1 day under emergency category.
Minutes of the 181st meeting of OCC (10.08.2021) Page 11 of 84
3.2.5 Auto-Reclosure (A/R) to keep into non-auto mode for 765 kV Raichur-
Sholapur line1 from 13.08.2021, 07:00 Hrs to 05.09.2021, 18:00 Hrs on
daily basis
(i) SRLDC had sought approval of SRPC by forwarding the mail received on
06.08.2021, 21.52 hr from S/I, RTAMC, PGCIL SR-I requesting to concur
the A/R reclose to keep into non-auto mode for 765 kV Raichur-Sholapur
line1 for replacement of defective OPGW from 07.08.2021 07:00 Hrs to
21.08.2021 18:00 on daily basis.
(ii) SRPC had informed to SRLDC that PGCIL to ensure alternate path for the
data availability if the nature of work is urgent to replace the defective
OPGW under emergency category and disabling the A/R may be done as
per system requirement under intimation to the Constituents.
(iii) SRLDC had replied that the shutdown could not be facilitated under
emergency category as the outage would be till 21st August 2021 and this
would be maintenance works and required the concurrence of both SRPC &
WRPC and suggested to schedule for 10th August 2021, after taking the
approval from 181st OCC Meeting.
(iv) PGCIL SR-I vide mail dated 09.08.2021 had revised the schedule and
requested for approving the same for availing during 13.08.2021, 07:00 Hrs
to 05.09.2021, 18:00 Hrs on daily basis. They informed that increase in the
link losses at OPGW link on 765kV Raichur – Sholapur 1 line were
observed during the routine maintenance. Therefore, the same was affecting
the ULDC/ telecom traffic.
(v) PGCIL has proposed to replace the OPGW of 765kV Raichur – Sholapur
Ckt1 in the following spans:
1) Tower No 77 to Tower No 83 ; 2.427 km
2) Tower No 132 to Tower No 134 : 0.872 km
3) Tower No 141 to Tower No 146 : 1.964 km
4) Tower No 190 to Tower No 192 : 0.955 km
Deliberation:
(i) After deliberation, OCC approved the outage to avail during 13.08.2021,
07:00 Hrs to 05.09.2021, 18:00 Hrs on daily basis.
(ii) PGCIL SR-I to avail the outage after obtain approval from WRPC.
3.2.6 NTPC, NLC, NNTPS & KKNPP outage proposals of Transmission Lines
and Elements in the 181st Outage Coordination Meeting.
Minutes of the 181st meeting of OCC (10.08.2021) Page 12 of 84
There was no representation form NTPC, NLC, NNTPS & KKNPP in the
outage Coordination meeting held on 06.08.2021 to process the outages
proposed by them.
1) NTPC: Main Bay at Ramagundam proposed from 08.09.2021 –
14.09.2021 for CTs replacement :
The Outage was approved to avail from 08.09.2021 to 14.09.2021
subject to availability of Tie bay and ICT.
2) NLC : 230 kV Neyveli TS II – Villiyanur Ckt 1, proposed for 13th &
14th September 2021:
It was concluded in the Outage coordination meeting (06.08.2021) that
NLC may discuss with PED and apply in the Mid review to avail on
daily basis as requested by PED.
Subsequently, PED confirmed by mail dated 18.08.2021 for the LC by
NLC in the Neyveli - Villianur 230 kV line on daily basis only to avail
on 13.09.21 &14.09.2021 (9.00 hrs to 17.00 hrs) subject to PED’s
condition that NLC shall plan the shutdown as per the approved
schedule and strictly adhere to the LC timings ie from 09:00 hrs to
17:00 hrs and shall not seek extension of LC at the end of the day.
3) NNTPS: 400 kV Kalivanthapattu - NNTPP-1 proposed to avail during
September 2021:
It was concluded in the Outage coordination meeting (06.08.2021) that
NNTPS may avail the LC of 400 kV Kalivanthapattu– NNTPP1 during
their Unit-2 outage proposed from 16.08.2021to 25.08.2021 and apply
under PNOCC, subject to their work at NNTPP side of the PGCIL Line.
Subsequently, NNTPS vide mail dated 07.08.2021 had informed that
Unit-2 was under emergency shutdown from 04.08.2021due to Reheater
Header drain welding crack and hence preponed the shutdown for
carrying out water lancer commissioning works.
In the meeting NNTPS informed that Unit-2 would be revived on
15.08.2021. Therefore, as decided in the Outage Coordination meeting,
LC of 400 kV Kalivanthapattu – NNTPP 1 would be availed during
Unit-2 outage period up to 15.08.2021.
4) KKNPP: 400 kV KKNPP - Tirunelveli line 2 (ACL22) for Insulator
Cleaning to avail on 15th September 2021:
Minutes of the 181st meeting of OCC (10.08.2021) Page 13 of 84
In the Outage coordination meeting (06.08.2021) the outage was not
concurred as the line 1 was not brought back by NPCIL and the outage was
not planned to avail during Unit-1outage period.
ISSUE:
(i) CGS / ISGS who had proposed outage of their transmission line /
element not attending the outage coordination meeting.
(ii) It is a matter of concern that outage plan could not be discussed in the
Outage Coordination meeting effectively due to the absence of the
entity who has proposed the outage.
Deliberation:
(i) NTPC, NLC, NNTPS & KKNPP and other Generators were requested to
participate in the Outage coordination meeting to discuss the outages of
transmission lines / elements, if any proposal by them are scheduled for
deliberation in the outage coordination meeting.
(ii) SE (O), SRPC stated that outages of transmission lines and elements
proposed by the entities would be rejected, if the concerned entities not
participating in the outage coordination meeting. The outages deliberated in
the outage coordination meeting and referred for OCC only be further
considered in the OCC meetings.
3.2.7 Tirunelveli – Abhishekapatti Line outage on alternate days from 11th
August 2021 to 10th September 2021
(i) TANTRANSCO had proposed the outage of Tirunelveli –
Abhishekapatti Line on alternate days for stringing work to avail from
11th August 2021 to 10th September 2021 for consideration in the 181st
Outage Coordination Meeting.
(ii) TANTRANSCO had been requested to apply the same under PNOCC.
Deliberation:
(i) TANTRANSCO informed that they had not applied the LC on the Portal
under PNOCC as decided in the outage Coordination meeting.
(ii) OCC advised TANTRANSCO to apply immediately so that the LC
could be availed from 14.08.2021.
3.2.8 Major outages proposed by other region discussed in Outage Coordination
Meeting
Minutes of the 181st meeting of OCC (10.08.2021) Page 14 of 84
The following major outage proposals were discussed:
(i) 400 kV Bhadravati - Bhadravati HVDC 1 & 2, 500 kV Bhadravati
HVDC POLE 2 were proposed by PGCIL (WR) to avail during
September, 2021 with Station Power restriction of 500 MW; ATC-TTC
reduction up to 1050 MW.
(ii) 765 kV Sholapur – Raichur 1 & 2 for Line and Reactor AMP works were
proposed by PGCIL (WR) to avail during September, 2021 with ATC-
TTC reduction up to 550 MW.
(iii) 765 kV Wardha – Nizamabad 1&2, Nizamadbad ICT 1&2 were
proposed by PGCIL to avail during September, 2021 for Line Bay and
ICT AMP works with ATC curtailment of 600 MW.
(iv) TSTRANSCO had requested to postpone these outage proposals to
November, 2021 in view of their anticipated peak demand during
September & October, 2021.
(v) The following concluded in the outage coordination meeting:
a) 400 kV Bhadravati - Bhadravati HVDC 1 & 2, 500 kV Bhadravati
HVDC POLE 2, Nizamadbad ICT 1&2 & 765 kV Sholapur – Raichur
1 & 2 were postponed to avail during November, 2021
b) 765 kV Wardha – Nizamabad 1&2 to avail on 21st & 22nd August,
2021 respectively.
c) Considering the peak demand of Telangana, PGCIL was requested to
postpone the intra-regional 765 kV Nizamabad – Maheshwaram Ckt 1
& 765 kV/400 kV NizamabadI CT1 to November 2021.
3.2.9 Shutdown proposal of 400 kV Ramagundam-Chandrapur D/C line for
line diversion work
(i) M/s. Singareni Collieries Ltd (SCCL) vide letter dated 07.08.2021
(Annexure-3.2.9) has requested for the shutdown of 400 kV
Ramagundam- Chandrapur D/C line for line diversion work to be
executed by PGCIL on depository work basis.
(ii) M/s. SCCL has proposed to start their new Indaram Open Cast Coal
Mine Project. Therefore, they have requested for the shutdown of 400
kV Ramagundam-Chandrapur D/c line for the line diversion work at
location No. 35 to 40 at Indaram village from 03.09.2021 to
20.09.2021.
Minutes of the 181st meeting of OCC (10.08.2021) Page 15 of 84
(iii) TSTRANSCO had requested to postpone the outage proposals of
major transmission lines involving TTC reduction to November,
2021 in view of their anticipated peak demand during September &
October, 2021.
(iv) PGCIL SR-I had requested vide mail dated 09.08.2021 to approve the
shutdown of the said lines from 03.09.2021 to 20.09.2021.
Deliberation:
(i) PGCIL SR-I requested the OCC to approve the outage proposal of
M/s. SCCL from 03.09.2021 to 20.09.2021 stating that the line
diversion would be on few locations.
(ii) SRPC/SRLDC observed that the line diversion work to be routed
through CEA/CTUIL. PGCIL may inform CTUIL about the
proposed diversion work on 400 kV Ramagundam-Chandrapur D/c
line with a copy to SRPC/SRLDC.
(iii) PGCIL SR-I informed that the suggestion of SRPC/SRLDC would be
communicated to higher management for needful.
(iv) SRLDC informed that the outage would be facilitated on receipt of
PGCIL intimation to CTUIL regarding the diversion works.
3.2.10 Outage of 400 kV Simhadri – Kalpaka Ckt 4:
(i) In the outage coordination meeting, the proposal of APTRANSCO
for the outage of 400 kV Simhadri – Kalpaka Ckt 4 had been
approved subject to NTPC Simhadri STPS Unit-1 outage.
(ii) In the meeting APTRANSCO requested to remove the condition of
Unit outage of Simadri STPS to avail the outage of 400 kV Simhadri
– Kalpaka Ckt 4.
(iii) After deliberation, the outage of 400 kV Simhadri - KalpakaCkt 4
agreed to be availed by APTRANSCO without linking with unit
outage of Simahadri STPS.
3.2.11 The list of approved outages of Transmission Lines and Elements,
has been uploaded in PWC Web portal as well as on SRPC Website
and mailed to OCC Google Group on 12.08.2021.
Minutes of the 181st meeting of OCC (10.08.2021) Page 16 of 84
3.2.12 Tripping of switchable line reactors at Nellore during single phase
auto reclose of 400 kV Nellore- Sriperumbudur D/C line:
PGCIL, SR-I vide E-mail dated 06.08.2021 (Annexure-3.2.12) had
requested that to ensure operation of auto reclose successfully, tripping
of respective switchable line reactors at Nellore may be agreed during
single phase Auto reclose of Nellore-Sriperumbudur 400kV line Ckt-I &
II due to high voltage oscillations during trippings. The line reactor could
be taken into service after successful auto reclose. Otherwise, auto
reclose would never be successful due to sustained high voltage
oscillation at 1.3pu (approx.).
Deliberation:
(i) PGCIL-, SR1 informed that, high voltage oscillation approx.. 1.3 p.u. have
been observed during tripping of 400 kV Nellore- Sriperumbudur line Ckt-
I for longer periods, and requested for tripping of respective switchable
line reactors for faults in the Nellore- Sriperumbudur line Ckt-I&II to
ensure auto reclose operation during single phase faults and also avoid
high voltage oscillations during multi-phase faults. PGCIL further
informed that earlier after noticing the high voltage at Hindupur on single
phase the same scheme was implemented at NP Kunta- Hidupur lines.
Similar scheme was implemented at Raichur-Sholapur line in WR also.
(ii) SRPC observed that there was one tripping(B-N fault) noted on Hindupur-
N P Kunta line on 22;00 hours of 21.05.2021. PGCIL, SR-I informed that
that incident would be studied and will revert back.
(iii) SRLDC opined that for the time being it could be agreed - to trip the
respective switchable line reactors during faults in the lines on trial basis
and performance shall be monitored. The line reactor could be taken into
service as per requirement after tripping event.
(iv) After deliberation, OCC greed to implement on trial basis tripping of
respective switchable line reactors at Nellore during single phase auto
reclose of 400 kV Nellore- Sriperumbudur line Ckt I &II.
3.3 Monthly Review of LGBR for the next five months (Availability &
Requirement)
The Availability & Requirement in respect of the State System are reviewed
every month for the next five months. Constituents are requested to submit this
data by 3rd of the month. Constituents were also requested to furnish the detailed
Minutes of the 181st meeting of OCC (10.08.2021) Page 17 of 84
Availability &Requirement for the period from August 2021 to December
2021.
Deliberation:
(i) All the states had furnished the five months ahead LGB (August 2021
to December 2021). The abstract/analysis of the information furnished
by states is at Annexure-3.3
(ii) The following had been noted:
a) APTRANSCO: Energy shortage during October 2021 and
December 2021:
APTRANSCO informed that they are not expecting any issue in
meeting the LGB during the period from August 2021 to December
2021. The shortage projected during October and December is
meager and would be taken care of in coordination with DISCOMs.
b) TSTRANSCO: Demand and Energy shortage observed in most of
the months:
TSTRANSCO informed that the shortage would be met through
power exchanges.
c) KPTCL: Comfortable LGB :
SRPC observed that the availability projected includes
Yelahanaka Diesel Generation which needed to be excluded.
KPTCL informed that even excluding Yelahanaka Diesel
Generation, Karnataka LGB could be met. Revised LGBR
would be submitted excluding Yelahanaka Diesel.
d) KSEBL: Demand shortage from October to December 2021:
KSEBL informed that the shortage, if any, in real time would be
met comfortably through RTM.
e) TANTRANSCO: Comfortable LGB. Meager shortage in terms of
energy observed would be met through RTM.
3.4 First Meeting of the Standing Committee on Communication System
Planning in Power Sector (SCCSPPS) – follow-up action.
(i) The first Meeting of Standing Committee on Communication System
Planning in Power Sector (SCCSPPS) held on 09.03.2021 and the minutes of
the meeting had been issued on 14th July, 2021. In this regard, CEA vide
Minutes of the 181st meeting of OCC (10.08.2021) Page 18 of 84
letter dated 23.07.2021(Annexure-3.4.i- letter along with Minutes) has
requested RPCs to make following information available to the PCD
Division, CEA, in respect of the power utilities in their respective regions
within three weeks from the date of issue of the letter:
1. Item B2.1:Status of implementation of OPGW laying on all upcoming
lines (132kV and above) and existing lines identified to provide reliable
communication and data acquisition system for 132 kV and above
substations for State Sector and Central Sector portion and additional
requirement of OPGW, if any.
2. Item B2.3: Details of intervening lines for providing 100% redundancy
with route diversity and main lines having no OPGW (in case of LILO
line) so that installation of OPGW on these lines shall be taken on
priority by the concerned utilities.
3. Item B2.4: Details of:
(a) Inter-State and Intra-State nodes with radial connectivity; and
(b) links which are running at present over public network such as GPRS/
Leased.
Deliberation:
i) SE(O), SRPC informed that as per MoM of the first Meeting of Standing
Committee on Communication System Planning in Power Sector
(SCCSPPS) many actionable/follow up points are to be complied by the
entities. The information as requested by CEA needed to be furnished
within the timeline to enable CEA to coordinate for way forward.
ii) TATRANSCO informed that there is a requirement of around 3000 km
OPGW and 300 terminal equipments to cover all the S/Ss in
TANTRANSCO system and desired to know that whether they can
submit this requirement as an additional DPR to NLDC for PSDF
funding. SE(O), SRPC clarified that the additional requirement from
each entity is also requested by CEA and accordingly TANTRANSCO
would furnish the requirement to SRPC/CEA. The request from CEA is
for some specific information including future requirement. After
assessing the information gathered, further course of action for funding
etc. may be decided by CEA/MoP.
iii) The entities were requested to furnish the information sought by
CEA by 13th August 2021 to SRPC.
Minutes of the 181st meeting of OCC (10.08.2021) Page 19 of 84
(ii) Formation of sub-committee – Standing Committee on
Communication System Planning in Power Sector
(a) CEA vide communication related 28.07.2021(Annexure-3.iv.ii) has
informed that Standing Committee on Communication System
Planning in Power Sector in its first Meeting held on 09.03.2021 had
been decided to form a Sub-Committee with Members from CEA,
RPCs, POSOCO, CTU, KSEB, HVPNL, WBSETCL and MPPTCL
to deliberate on the following matters:
1. Item B.7.3: Remote controlling of transmission lines/Generators
from LDCs through communication channels and its applications
in maintaining Grid stability.
2. Item B.7.6: Policies to be adopted in the sharing of real time data
about transmission lines/generators/grid conditions between
STUs/CTUs through their communication networks.
3. Item B.7.7: Policies to be adopted in the visibility and accessibility
to the real time Grid operations/Grid conditions of other Utilities
through the interlinked communication channels.
(b) Shri A Kesavan, Executive Engineer has been nominated from SRPC
in the Sub Committee.
OCC noted the above.
3.5 Blackout at UPCL station on 22nd July 2021
(a) UPCL vide E-mail dated 27.07.2021 has informed the following
regarding the tripping of transmission lines emanating from 400 kV and
220 kV Switchyards during the total black out of UPCL at around
15:08:21 hours on 22nd July 2021:
(i) Before the occurrence, both Units at UPCL were running at
approximately 535 MW each and both Hassan lines and Kemar line-
1 were in service while Kemar line-2 was under outage for breaker
maintenance work at Kemar end.
(ii) Unit-2 tripped as SPS operated (on tripping of both 400 kV
Transmission lines) as designed. Tripping of Unit-1 followed on
loss of Power as the remaining 220kV line-1 to Kemar, which
carried over 464 MW then; also tripped on over current protection.
Minutes of the 181st meeting of OCC (10.08.2021) Page 20 of 84
(iii) Recently adopted bus split arrangement at Kemar was not adequate
enough to control load on remaining Kemar line in this case.
(iv) Based on the information received from Kemar S/S, the Bus coupler
was already out and both Bus carried load independently then.
Before the occurrence, Kemar-1 was carrying 42 MW load, which
rose to 144 MW after one Hassan line trip and then finally reached
to 464 MW after both Hassan Lines tripped and one unit isolated
under SPS scheme.
(v) During the disturbance, oscillations in the order of around 700 MWs
(from 223 MWs to 866 MWs) were observed on the Unit#1; finally
settling down to 495 MWs; before blackout.
(vi) It will be appreciated that only load shedding scheme at Kemar end;
as proposed by SRLDC, would have possibly prevented station
blackout at UPCL and subsequent impact on 220kV network
beyond Kemar.
(vii) Line over current protection would be coordinated adequately in
that case, as though thermal rating of the line for continuous loading
is less than 290 MW; thermal capacity of the line to carry higher
load for few seconds will be substantially higher.
Deliberation:
(i) Vice President, UPCL informed that before the incident i.e., before
black out of UPCL station on 22.07.2021, both Units at UPCL were
running at approximately 535 MW each and both Hassan lines and
Kemar line-1 were in service while Kemar line-2 was under outage
for breaker maintenance work at Kemar end. On SPS operation as
designed, Unit-2 tripped (on tripping of both 400 kV Transmission
lines). Tripping of Unit-1 followed on loss of Power as the
remaining 220kV line-1 to Kemar, which carried over 464 MW then;
also tripped on over current protection. He observed that recently
adopted bus split arrangement at Kemar was not adequate enough to
control load on remaining Kemar line in this case and requested
SRPC/SRLDC to analyze the incident and frame a solution. He
expressed concern that the implemented SPS scheme at Kemar is not
yet furnished by KPTCL to UPCL.
Minutes of the 181st meeting of OCC (10.08.2021) Page 21 of 84
(ii) CGM, SRLDC noted that there are multiple SPSs in place at UPCL
to act at different contingencies, like during outage of 220 kV lines,
outage of 400 kV lines etc. In the SPS which was agreed to
implement and KPTCL informed as implemented, backing
down/SPS is envisaged at 285 MW only, so there won’t be any issue
if 250 MW loading on each circuit is reached. Normally both the
buses would be in tied condition. Bus arrangement would be kept
ready with isolators; whenever the flow exceeds 265 MW the bus
will be split and the proposed configuration would be in place
immediately. He requested KPTCL to share the exact logic
implemented by KPTCL to SRLDC as well as to UPCL. It was
observed that during the incident when there was a double circuit
outage (UPCL-Hassan) within a gap of three minutes, the 220 kV
Kemar line was also out and bus coupler at Kemar was kept out and
the chance for acting the SPS was ruled out. He requested KPTCL to
confirm the same.
(iii) KPTCL informed that on that day UPCL-Kemar Line I was taken
under maintenance (relay works) and bus coupler was kept open. So
the logic designed failed to operate at that particular moment. He
confirmed that all SPSs for protection were enabled.
(iv) Vice President, UPCL stated that the line loading of 220 kV lines are
completely under purview of Karntaka SLDC. He requested
SRLDC/SRPC for thorough analysis of the issues and to design a
SPS incorporating all the contingencies.
(v) CGM, SRLDC observed that when UPCL-Hassan lines were out,
one unit could have gone out and the other unit may have reduced
generation as per SPS logic in place at UPCL and desired to know
from UPCL that whether it happened.
(vi) Vice president, UPCL informed that one unit tripped immediately,
but before backing down could take place, since Kemar-UPCL line I
was also out, line loading touched around 500 MW and got tripped.
During the disturbance, oscillations in the order of around 700 MWs
(from 223 MWs to 866 MWs) were observed on the Unit#1; finally
settling down to 495 MWs; before blackout. He expressed concern
that despite of two reactors in place at UPCL, high voltages were
observed at UPCL and recently Hassan lines were tripped due to
Minutes of the 181st meeting of OCC (10.08.2021) Page 22 of 84
over voltage. KPTCL should expedite the commissioning of
Hebbanahalli reactors.
(vii) KPTCL informed that commissioning of Hebbanahalli reactors is
delayed due to some local constraints and assured that works would
be expedited. The issue had already been taken up with Higher
management. Expressed concern on UPCL reactors are switched IN
and OUT by UPCL without prior intimation to KPTCL. CGM
SRLDC requested UPCL to inform KPTCL/SRLDC of such
switching action (at 400 kV level) well in advance which was
agreed by UPCL.
Conclusion:
1. KPTCL to share the SPS logic implemented at Kemar end to SRPC/
SRLDC /UPCL at the earliest.
2. After receiving the logic implemented by KPTCL at Kemar end
further studies would be carried out in this regard taking care of all
the possible contingencies/UPCL concerns. Actions like reviewing
the logic/implementation of under frequency scheme etc. may be
thought off accordingly.
3. KPTCL would apprise the management on the urgent requirement
of commissioning Hebbanahalli reactors and action would be taken
up for commissioning of the reactors immediately.
3.6 Automatic Under Frequency Load Shedding (AUFLS) Scheme - Review of
Settings
(i) As per the decision in the 2nd meeting of NPC held on 16th July 2013, the
following AUFLS scheme at four (4) stages of frequency viz. 49.2 Hz,
49.0 Hz, 48.8 Hz & 48.6 Hz had been implemented in all the regions.
(ii) In the 8th Meeting of NPC, it was decided that the frequency settings of
AUFLS scheme (with 4 stages ) may be raised by 0.2 Hz viz. 49.4, 49.2, 49.0
& 48.8 Hz and quantum of load shedding may be worked out considering the
requirement to increase the frequency to 50 Hz.
(iii) In the 9th meeting of NPC, it was decided that a Sub-Committee may be
formed under the chairmanship of Member Secretary, WRPC, with
representatives from POSOCO and all the RPCs to study the AUFLS Scheme
and submit its report to the NPC. Subsequently, NPC Secretariat vide letter
dated 19.01.2021 has formed the Sub-Committee under the Chairmanship of
Minutes of the 181st meeting of OCC (10.08.2021) Page 23 of 84
Member Secretary, WRPC with representatives from POSOCO and all the
RPCs to study the AUFLS Scheme.
(iv) In the 10th meeting of National Power Committee (NPC) held on 09th April
2021 (Minutes of the meeting awaited) it was decided that the AUFLS
scheme (with 4 stages ) viz. 49.4, 49.2, 49.0 & 48.8 Hz with existing
quantum of load shedding shall be implemented in all the Regions. The
quantum of load shedding would be reviewed based on the
recommendation of the Sub- Committee to study the AUFLS scheme.
The existing frequency settings of AUFLS scheme 49.2 Hz, 49.0 Hz,
48.8 Hz & 48.6 Hz needed to be raised by 0.2 Hz.
Implementation of revised frequency setting of AUFLS scheme
(with 4 stages) viz. 49.4, 49.2, 49.0 & 48.8 Hz with existing
quantum of load shedding.
Deliberation/Conclusion:
(i) SE(O), SRPC requested all states to implement the revised settings by
15th August 2021. Confirmation in this regard may kindly be sent to
SRPC/SRLDC.
(ii) TSTRANSCO informed that the revised settings had already been
implemented.
(iii) The SLDCs agreed to implement the revised setting by 15th august
2021 and to furnish the date of implementation and PTR to
SRPC/SRLDC.
3.7 Utilization of inverters at Solar Park in night mode for controlling high
voltages
i. SRLDC had furnished a note on Reactive Power Capability of Invertors, its
utilization and way forward for pilot project.
ii. SRPC Secretariat had noted that all such pilot schemes in India are being
implemented in consultation with NLDC and suggested that since the issue
is not regional specific, NLDC may come up with a National perspective
and requested SRLDC to arrange for views of NLDC on the notes for
facilitating deliberation in SRPC forums.
iii. NLDC vide letter dated 06.07.2020had furnished their comments for further
discussion at SRPC level.
Minutes of the 181st meeting of OCC (10.08.2021) Page 24 of 84
iv. As decided in the In the 180th OCC Meeting held on 09.07.2021 the
communications from NLDC along with SRLDC Note on the Reactive
Power Capability of Invertors, its utilization and way forward for pilot
project had been made available to the constituents.
v. In the 180th OCC meeting it was decided to have special meeting to
deliberate the proposal. Accordingly, a special Meeting was conducted on
27.07.2021 through video conferencing (MoM available at SRPC website).
vi. The Trial operation of solar inverters at Pavagada Solar Park (2050MW) in
night mode (voltage control mode) for controlling high voltage has been
implemented from1stAugust2021 for two months as pilot project.
Deliberation:
i. SRLDC presented the operational experience and lessons learnt during the
first week of trail operation(Annexure-3.7.i). The following noted:
a) An Implementation meeting was held on 29.07.2021 with developers
along with KSPDCL. Accordingly detailed operating procedure was
issued on 31.07.2021.
b) The preparatory works was started from 31.07.2021 evening as Night
mode is to be enabled during generation hours. Despite the preparatory
works and lot of persuasion, only 98 MVAR was realized on first day
with few developers participating. However from 01.08.2021 evening
onwards most of the developers have joined except Fortum solar.
Fortum Solar has joined from 04.082021 onwards 18:00 Hrs.
c) SRLDC has issued Q Schedule for controllable plants and revised from
time to time based on grid conditions and constraints expressed by
developers. It is understood that night mode has to be enabled during
generation hours only as otherwise inverters enter into sleep mode.
d) Maximum reactive absorption of 329 MVAR at 400kV level was seen
on 10.08.2021 early hours with participation from all identified
developers. It was noted that the number of tripping /opening of 400kV
lines at Pavagada has come down from 3 to 1 on most of the days and
the voltage at Pavagada SS was mostly around 422 kV. The voltage at
the substation nearby, Pavagada, was observed to be less than 430 kV.
e) It was noted that there were certain constraints like Shutdown of
Substation for maintenance, SCADA Q control availability only during
Minutes of the 181st meeting of OCC (10.08.2021) Page 25 of 84
generation mode and inability to interact in night mode, Some inverters
were giving alarms and Tripping of inverters after 4 MVAR per feeder
although higher capability is available, Fan Speed increasing
abnormally during night mode in one of the inverters, OEM warranty
issues, Apprehension about life of the inverters etc. The technical issues
are being taken up with OEM by the developer for further
understanding.
ii. Keeping in view of the preparatory works started by SRLDC from 18:00 Hrs
of 31.07.2021, SRLDC requested the forum to consider the commencement
of trial operation from 18:00 Hrs of 31.07.2021.
iii. ED, SRLDC added that it is admirable that the Pavagada connected lines
could keep in service during the night hours after implementation of night
mode operation at Pavagada and reduction of voltage of around 3-4 kV with
the lines in service. Tumkur and Hiriyur voltages also had improved as a
consequent. Further studies needed to be carried out regarding the correlation
between MVAR absorption/ active power consumption and
temperature/weather etc. MVAR absorption capability of inverters with
different thyristors also needed to be analyzed. The sudden changeover at
18:00 hours (high voltage fluctuation) needed to be correlated to the ramp of
the falling of the solar generation and picking up of the load. He informed
that during the N P Kunta visit it was understood that STATCOM absorption
of active power is little more than the active power absorption by solar
inverters for the same MVAR absorption. It was also observed that though the
NP Kunta STATCOM was designed for 100 MVAR (2x50 MVAR) the
maximum absorption possible is around 70 MVAR. He requested the forum
to approve the request of SRLDC for considering the commencement of trial
operation from 18:00 Hrs of 31.07.2021. He opined that TSTRANSCO had
not commissioned the reactors as recommended by Standing Committee
(SRLDC didn’t approach CERC regarding TSTRANSCOs concern), despite
many Special Meetings and follow ups KPTCL system also has many high
voltage nodes. In such a scenario SRLDC is trying to utilize the available
resource/capability optimally and the effort put needed to be appreciated and
concurrence may be given to the request of SRLDC. He requested the forum
to opine on this. He stated that if so specific about the time period of trial run,
the trail run may be closed prior by one day ie by 29.09.2021also.
Minutes of the 181st meeting of OCC (10.08.2021) Page 26 of 84
iv. SE(O), SRPC said that the implementation of night mode operation should
be as agreed by all concerned entities in the Meeting (joint meeting of OCC
and CC members) on 27.07.2021. SRLDC would have commenced the
preparatory from 1800 Hrs of 01.08.2021 well within the agreed date. There
was no urgency to deviate from the decision. Implementation of any scheme
or project should be as per the decision and any alteration by the
implementing agency may be cited in future for other cases which involves
commercial implication.
v. ED, SRLDC suggested that the views of SLDCs would be sought to take a
decision on this issue.
vi. DE, TSTRNSCO opined that as this change in starting time was due to some
technical issues, appreciating effort put by SRLDC for implementation of the
scheme which is helping the Grid, TSTRANSCO is agreeing for the review of
starting time of the scheme.
vii. KPTCL informed that the reliability of the system had been increased
(reduction of line opening) after the implementation of the scheme. KPTCL
requested SRLDC to try to bring more SPDs to the loop.
viii. ED SRLDC informed that they are putting huge effort to make more SPDs
participation. On the first day 100 MVAR absorption only was possible and
as of now (10.08.2021) around 350 MVAR absorption had been observed. All
SPDs where the feasibility is there have been participated, only the quantum
of schedule given by SRLDC had been changed by certain SPDs citing some
technical issues.
ix. APTRANSCO appreciated the efforts put by SRPC & SRLDC and OCC
forum to implement the scheme as a national perspective. The consequences
of deviation of one day may be ignored while a huge effort is put on this
implementation which is beneficial for the whole region. APTANSCO has no
objection in considering the starting time of the implementation from 18:00
Hrs of 31.07.2021.
x. After deliberation, it was agreed that the commencement of implementation
of night mode operation at Pavagada Solar Park from 1800 Hrs of
31.07.2021.
xi. SE(O), SRPC said that commercial issues would be taken up by SRLDC in
the Commercial Sub-Committee meeting. Closing date and time of the trial
operation may be discussed and decided in the next OCC Meeting. He
Minutes of the 181st meeting of OCC (10.08.2021) Page 27 of 84
clarified that this is agreed as a special case and the same shall not be quoted
as precedent for any other case in future by constituents.
Conclusion:
(i) The Trial operation of solar inverters at Pavagada Solar Park
(2050MW) in night mode (voltage control mode) for controlling high
voltage is implemented from 1800 Hrs of 31.07.2021 for two months as
pilot project.
(ii) The commencement of implementation of night mode operation at
Pavagada Solar Park is from implementation of Trial operation run
starting period and would be considered as 18:00 Hrs of 31.07.2021.
(iii) Closing date and time of the trial operation may be discussed and
decided in the 182nd meeting of OCC.
(iv) SRLDC would take up in the Commercial Sub-Committee of SRPC
about DSM Methodology etc. on account of night mode trial operation
at Pavagada Solar Park.
3.8 Enhancing the power import to Kerala through 110 kV Konaje –
Manjeswaram interstate Line
(a) Item Proposed by KSEBL (for 39th TCC/SRPC) : KSEBL has stated the
following:
The Power import to Kerala through the 110 kV Konaje – Manjeswaram
interstate line is to be enhanced. The power import at present is just to the
tune of 22 MW which is even much lower at many times. Enhancing the
import is essential to resolve the power crisis in Kasargode district.
Deliberation:
(i) SE(O), SRPC informed that this agenda item proposed by KSEBL for
deliberation in the 39th TCC /SRPC Meetings. He stated that before
bringing to the SRPC/TCC level, the issues needed to be brought to the
Sub-Committees and requested all the entities to follow the procedure.
(ii) Dy CE, KSEBL informed that the increase in power is necessitated by
Railways since they have approached KSEBL for more power. At present
around 22 MW is drawn by KSEBL through this line which may be
enhanced to 30 MW to meet the additional requirement of Railways.
(iii) KPTCL informed that the 110 kV Konaje - Manjeshwaram line, out of
11.4 km of line length 5.5. km length is under jurisdiction of KPTCL.
Minutes of the 181st meeting of OCC (10.08.2021) Page 28 of 84
There was a proposal to strengthen the Karnataka portion and in principle
KSEBL had agreed to bear the entire cost of strengthening the line. This is
dealt by the concerned division of KPTCL and already taken up with
KSEBL.
(iv) SE(O), SRPC observed that the request of KSEBL is for enhancement of
power of very less quantum which could be allowed for the time being. He
desired to know the system strengthening at Kasargode and whether
additional power requirement is for long term.
(v) KSEBL stated that 400 kV Kasargode S/S is coming up and system
strengthening is planned in Kasargode and this requirement is for short
period. Once the system is strengthened there won’t be need of power
drawal through this line.
(vi) KPTCL informed that they are taking up with field people and would revert
back on the issue. Previously when enhanced the power flow some
protection issues were faced.
(vii) SE(O), SRPC suggested that this issue may be bilaterally discussed by
KPTCL and KSEBL and outcome may be intimated to SRPC/SRLDC.
Conclusion:
(i) Enhancement of power drawal to KSEBL through 110 kV Koneje -
Manjeswaram line would be bilaterally discussed among KSEBL & KPTCL
and outcome/Decision would be intimated to SRPC/SRLDC.
3.9 Preparedness for cyclones/inclement weather condition during August-
November months
(a) Item Proposed by SRLDC (for 39 TCC/SRPC): SRLDC has stated the
following:
i. It was observed during past years, there were cyclonic conditions during
August -November months. Hence, it is prudent to be in preparedness for
handling such situations. All constituents are requested to take following
measure in advance:
a. Emergency Restoration system (ERS) may made available at
appropriate location near to coastal areas.
b. Sufficient spares including Fuel, bunkering facilities, hydrogen etc for
restoration may be identified and kept ready for relocating.
Minutes of the 181st meeting of OCC (10.08.2021) Page 29 of 84
c. SLDCs are requested to keep Black start restoration procedures ready
with real time grid operators.
d. Transmission line maintenance and vegetation management may be
done in advance to avoid trippings.
Deliberation:
(i) SRLDC stated that during last few years our region had met cyclonic
conditions/extreme weather conditions during August to November
months which caused destruction to transmission, distribution and
generation systems. All entities to carry out all the pre maintenance
activities, ensuring the readiness of the ERSs & sufficient spares, stock
of fuel, bunkering facilities etc well in advance. SLDCs should be
ready with updated Black Start Restoration Procedure.
(ii) CGM, SRLDC observed that the main issues faced were lot of tower
collapse which needs ERS for restoration. At Vallur bunkering issues
were noticed. In some stations, the conveyer belt was open and open
bunkers also were issues. All should take leanings from the past
Cyclones and should act accordingly. Coastal area should be given first
priority. Secondary fuel, Hydrogen, healthiness of transmission lines
etc should be ensured. Secondary communication availability should be
ensured.
Conclusion:
(i) All the constituents were requested to take measures in advance as
suggested by SRLDC/ lesson learned from the past incidences.
3.10 SRLDC agenda Items
A. SRLDC has proposed the following new items for discussion:
a) Revival of Kadamparai Units:
b) Significant OD/UD of states in the month of July 2021
c) Operating Procedure for Southern Region 2021:
d) Total Transfer Capability (TTC) Determination of S1-(S2&S3):
e) Status of PSS/E Basecase Submission:
f) Procedure for PSS/E Base case preparation Methodology
g) Availing status of OCC Approved Outages:
h) Outage procedure in Intra State network:
Minutes of the 181st meeting of OCC (10.08.2021) Page 30 of 84
i) Islanding Scheme Monitoring:
j) EHV Transmission Elements Details: -
k) Declaration of High and Low demand seasons of Southern Region
for 2022-23
l) Status of the implementation of the modified SPS scheme for Kaiga
ICTs:
m) Status of FO Cable in 400kV NCTPS Vallur line-1 and 2:
n) Status of Restoration of 400kV/220kV RTPS ICT#2:
o) Frequent GDs in Karnataka due to Operational & Protection Issues
during July 2021:
p) Frequent tripping of lines
q) Non-Furnishing of Details for Grid Events by Constituents:
B. SRLDC has proposed the following follow up items:
a) List of Substations with Single Bus Operation
b) Follow up of special meeting held with RE developers on 25.02.2021
(i) SCADA as per RE frame work/ FTC and Actual Position viz.
points not provided
(ii) SCADA points provided but data not coming /consistent
(iii) Nodal officer confirmation for SCADA validation & taking up real
time SCADA issues
(iv) Providing VOIP
(v) Voltage control mode of operation within the capability limits.
(vi) LVRT/HVRT
(vii) Measurement of Harmonics, Flicker and DC Injection
(viii) Uploading of weather parameters on monthly basis in specified
format
(ix) Registration with CEA
(x) Geo-tagging Information for each wind turbine with NIWE
(xi) Update on meeting held with RE developers at Anantapur (NP
Kunta) on 6th August 2021
c) Update on Night mode Operation of Inverters at Pavagada Solar Park to
contain Over voltage
Minutes of the 181st meeting of OCC (10.08.2021) Page 31 of 84
d) Renewable energy (RE) curtailment
a. As per Regulation 6.4.5 and Regulation 5.2(u) of the Grid Code and
similar provisions enshrined in respective State Grid Codes
“generation based on renewable energy sources such as solar and
wind are to be treated as “must run‟ and such generation can only be
curtailed or backed down if grid security or safety of equipment or
personnel is endangered” Accordingly, RE may not be curtailed
except for the reasons mentioned in the grid code.
b. All SLDCs may submit details of curtailment viz. MW, MU, Time
etc. along with detailed reason to SRLDC in writing before 11 AM&
display the same in their websites.
e) SCADA Data availability issues
i. Non-reporting of real time SCADA data MTPS Stg-3 (Tamil Nadu)
ii. Non-reporting of real time SCADA data from N P Kunta
iii. Non-reporting of real time SCADA data from 400 kV SEPL station
iv. Partial reporting of real time SCADA data from 230kV Kalpakam
(MAPS) Station.
f) Real time data discrepancy issues
C. Status review of the following:
a) Commissioning of Bus reactors & STATCOMS as approved in various
meetings & Standing Committee.
b) Review of operational performance of Condenser mode of operation of
N’Sagar & Srisailam LB.
c) Status review of AUFR, df/dt & Automatic disconnection of Radial
feeders under ADMS.
d) Review of forecast vs Actual demand of SR constituents
e) Status review of ATC / TTC calculation by SLDCs and LGBR
submission
f) Condenser mode of operation in other Hydro stations:
The details of the above items furnished by SRLDC are at Annexure-3.10.
A a Revival of Kadamparai Units:
(i) TN SLDC informed that U-2 & U3 at Kadamparai HEP are put back to
operation (generation mode & Pump mode operation). Unit 1 & Unit-4
Minutes of the 181st meeting of OCC (10.08.2021) Page 32 of 84
overhauling will be completed by 15th August 2021. TN SLDC may
deliberate on the revival of units.
(ii) In the Meeting EE, TANTRANSCO informed that except Unit IV all
the units are put back to operation (generation and pump mode). Unit IV
would be coming up by last week of August 2021.
(iii) On a query by CGM, SRLDC, TANTRANSCO informed that the
performance would be analyzed keeping all the units in generator mode
simultaneously and subsequently testing would be done for operation of
four units on Pump mode operation also.
A b Significant OD/UD of states in the month of July 2021
% TimeOD> Min DSM Limit at Low Freq(<49.90 Hz) & % time UD>Min DSM Limit at High
freq. (>50.05 Hz)
S. No. Date AP(%/MW) KA(%/MW) TN(%/MW) TS(%/MW)
1 01-07-2021
7.15(UD)/-
1011
2 02-07-2021 4.86(UD)/-883
5.42(UD)/-766
3 03-07-2021
4.51(UD)/-475 4.86(UD)/-553
4 04-07-2021
4.93(UD)/-
1173 7.22(UD)/-417
5 05-07-2021 9.51(OD)/1195
4.72(OD)/484
6 06-07-2021 14.38(OD)/1431
6.25(OD)/321
7 07-07-2021
4.03(UD)/-841
8 08-07-2021
7.71(UD)/-
1004 6.53(UD)/-634
9 09-07-2021
7.01(UD)/-788 4.38(UD)/-659
10 10-07-2021
4.93(UD)/-610
11 11-07-2021
4.65(UD)/-579
12 12-07-2021
10.07(UD)/-718 5.14(UD)/-728 9.17(UD)/-552
13 13-07-2021
4.38(UD)/-729
14 14-07-2021
7.92(UD)/-685
15 17-07-2021
4.79(UD)/-632
16 18-07-2021 6.25(UD)/-725 7.08(UD)/-894 8.47(UD)/-922
17 19-07-2021 14.86(UD)/-
1090 7.36(UD)/-715
18 20-07-2021 5.83(UD)/-920 7.36(UD)/-480
19 21-07-2021 8.12(UD)/-746
20 22-07-2021 5(UD)/-361
21 23-07-2021 4.1(UD)/-457
22 24-07-2021 4.03(OD)/786
23 25-07-2021 4.51(UD)/-1000 10.14(UD)/-
1855 4.93(UD)/-972
24 27-07-2021 4.58(UD)/-776
Minutes of the 181st meeting of OCC (10.08.2021) Page 33 of 84
(i) In the Meeting, SRLDC observed that during July 2021 there was more
under drawal incidents compared to over drawal incidents July 2021
being a low demand month.
(ii) CGM, SRLDC noted that heavy under drawal of all the states in SR will
transform to a national issue when already system is operating at high
frequency and will cause congestion in network towards Northern
Region. Such situation in WR was the cause for grid disturbance in 2012.
Better planning should be done to avoid such heavy under drawls to
ensure that inter regional links are operated well within the limits.
Kolahapur-Kolahapur in WR is violating n-1 for significant period of
time which had been communicated to planner as a feedback but it will
take time to resolve the issues. He requested all states to initiate action to
avoid OD/UD on a sustained basis very urgently.
A c Operating Procedure for Southern Region 2021:
(i) SRLDC has released “Operating Procedure for Southern Region 2021”
on 20.07.2021.
(ii) In the Meeting, SRLDC informed that all the constituents had been
requested to furnish the comments/observations, if any, but no reply had
been received from any of the entity. Requested all the constituents to
give their feedback or suggestions if any at the earliest.
A d Total Transfer Capability (TTC) Determination of S1-(S2&S3):
(i) At present after the commissioning of HVDC Raigarh – Pugalur Bipole
(3000 MW), the S1-(S2&S3) TTC is around 7250 – 8600 MW. The TTC is
calculated using the PSS/E cases submitted by constituents. The wide range
of TTC across S1-(S2&S3) corridor is attributed to the LGBR. At present the
limiting factor is N-1 of Inter-connecting Transformer for the past few
months which are given below:
S. No. Month Bid Area TTC/ATC
(MW) Limiting Factor
1 March Revision - 1
S1-
(S2&S3)
8575 N-1 of 500 MVA ICT will
lead to overloading of
2x315 MVA ICT at
400/230kV Allundur ICT
2 April Revision - 1 8400
3 June Revision - 0 7650
4 July Revision - 0 7250
5 August &
September 7250
N-1 violation 2x315 MVA
ICT at 400/230kV
Minutes of the 181st meeting of OCC (10.08.2021) Page 34 of 84
Revision - 0 Thiruvallam ICT
6 October – 0 7700
N-1 of 500 MVA ICT will
lead to overloading of
2x315 MVA ICT at
400/230kV Allundur ICT
7 November-0 8000
N-1 violation of 500 MVA
ICT will lead to
overloading of 2x315
MVA ICT at 400/230kV
Allundur ICT
(ii) It is observed from the simulations that there is high co-relation between
TTC and ICT loading in S2 control area. The high loading on ICT at
400/230kV Allundur (2x 315 + 1x 500 ) , 400/230kV Thiruvallam,
400/230kV Checknoorani would limit the S1-(S2&S3) TTC corridor in
future.
(iii) Hence constituents are requested to do transformer augmentation to avoid
Limitation of S1-(S2&S3) transmission corridor.
Deliberation:
(i) SRLDC stated that ICT loading is the constraints (limiting factor) for
ATC/TTC of S1-(S2&S3) at present. TANTRANSCO needed to augment
the transformers at Allundur, Thiruvalam & Checknoorani.
TANTRANSCO needs to take/ explore the augmentation of Transformers
at these S/Ss. Alternate solution for resolving the issues also may be taken
up with STU (Planners). At present (low demand) there is no constraints,
but during next peak constraints are envisaged and to avoid the ATC/TTC
reduction, timely actions in consultation with planners should be initiated.
TANTRANSCO should declare ATC/TTC declaration at the earliest.
Drawal would be limited if TANTRANSCO is not coming forward with
concrete action in this regard.
(ii) TANTRANSCO informed that they would take up with their planners and
the update would be furnished in the next OCC Meeting.
Conclusion:
(i) TANTRANSCO to start declaring ATC/TTC declaration.
(ii) TANTRANSCO to explore the augmentation of transformation capacity of
identified S/Ss.
Minutes of the 181st meeting of OCC (10.08.2021) Page 35 of 84
(iii) TANTRANSCO to take up with STU (Planners) regarding the constraints
and seek alternative solution and plan accordingly.
A e Status of PSS/E Base case Submission:
(i) The constituents are requested to submit the PSS/E Base case of 4 different
scenarios Peak: - 1800 Hrs. Off-Peak: 0300 Hrs. Morning Peak: 0900
Hrs. Solar Peak: - 1300 Hrs. for the upcoming month by 20th of every
month to enable RLDC to determine the Margin for STOA and declare
TTC by 26th of every month. The status of PSS/E case submitted by
constituents is given below. TTC calculation by each control area is
mandatory as per the “Detailed Procedure for relieving Congestion in real
time Operation, 2013” approved by CERC. Constituents are requested to
furnish the PSS/E cases timely before OCCM and Declare the Control area
Drawl Capability in their website
S. No. State
ATC/TTC
Computation
furnished to
SRLDC
PSS/E Case
Submitted
Four (4)
Scenarios
Submitted
1 Andhra Pradesh Yes Yes Yes
2 Telangana No No (Received
on 28th)
No
3 Karnataka No No (Received
on 28th)
No
4 Tamil Nadu No Yes Yes
5 Kerala Not Applicable Yes Yes
6 Puducherry No No No
(ii) Telangana, Tamil Nadu & Karnataka may furnish the TTC/ATC details at the
earliest.
Deliberation:
(i) SRLDC expressed concern that Telangana, Karnataka and Tamil Nadu are not
furnishing the PSS/E Case in time. During last month data was received from
Telangana, & Karnataka on 28th. The usual practice is declaring the TTC by
26th of every month by SRLDC. He requested the states to furnish the required
information in time. It is observed that ATC/TTC calculation is submitted
only by APTRANSCO. But they need to put it on their website so that NLDC
may also put the same on their website. He requested all the states to submit
Minutes of the 181st meeting of OCC (10.08.2021) Page 36 of 84
the ATC/TTC declaration to SRLDC which would be vetted by SRLDC and
the same needed to be uploaded on the state website.
Conclusion:
(i) APTRANSCO to take necessary steps to declare ATC/TTC on their
website.
(ii) Telangana, Karnataka and Tamil Nadu to submit the AC/TTC calculation to
SRLDC and the vetted data by SRLDC may be uploaded on their website.
(iii) All the States to submit the PSSE base case in time every month (positively
before 20th of every month)
A f Procedure for PSS/E Base case preparation Methodology
1. Peak demand consideration:
1) NLDC is providing all India and Region wise 3 months ahead demand
forecast based on Average demand for each 5 min block has been
worked out for 3rd Month of previous three years to identify the peak and
off-peak demand time.
2) RLDC will estimate the state wise demand forecast based on % State
Demand to Regional Demand derived from last three years.
3) Estimated state demand data will be communicated to Constituents by
RLDC for consideration and preparation of three months ahead base case
Morning Peak
Evening peak,
Off peak
Solar peak and any other scenario as required
2. LGBR
1) Node-Wise Load data, Hydro, Wind and Solar generation data will be
taken from state cases
2) State thermal generators Dispatch will be based on on/off status and
Merit Order along
3) Drawl of State: ISGS thermal share of each state and LTA + MTOA
to be the quantum to be utilized for State Drawl
Minutes of the 181st meeting of OCC (10.08.2021) Page 37 of 84
4) The submitted Cases will be used to form a regional updated case. The
ISGS generation Optimization will be done resembling the real-time
optimal dispatch utilizing the state-wise Drawl Share.
5) The Timelines maybe followed as below:
S. NO. DESCRIPTION RESPONSIBILITY TIMELINE
1 Preparation of All India and
Regional Load Forecast on 03
month ahead basis
NLDC To be Shared by
1st
Week
2 Preparation of State-Wise
Forecast
on 03 month ahead basis
SRLDC To be shared by
10th
of Every month
3 Preparation of State base
cases based on the
methodology suggested and
submission
CONSTITUENT To Be shared by
20th
of Every month
4 Stitching of sate cases and
preparation of SR cases
SRLDC To be done by
26th
of Every month
3. The States are requested to submit the TTC and Declare TTC in their
website along-with PSS/E cases submission.
A g. Availing status of OCC Approved Outages:
(i) As per the NLDC outage co-ordination procedure dated 28th February
2013, the indenting agency are requested to provide the availing status of
the OCC approved outages on D-3 by 10:00 Hrs., however at present for
better flexibility the outage requests are being considered up to 23:59 Hrs.
of D-3. However, RLDCs has to process the outage and issue the approved
list on D-2 basis by 10:00 Hrs. which gives a time of only 10 Hrs. i.e.,
from D-3 23:59 to D-2 to 10:00 Hrs.
(ii) Hence for better processing of the outages the constituents are requested to
follow the NLDC Outage co-ordination procedure and provide the
requesting status of the approved outages by D-3 on 10:00 Hrs.
Deliberation:
(i) SRLDC presented the Outage Proposal Procedure (Annexure-A.g.iii).
SRLDC informed that as per procedure the indenting agency are requested
to provide the availing status of the OCC approved outages on D-3 by
10:00 Hrs., however at present for better flexibility the outage requests are
being considered up to 23:59 Hrs. of D-3. However, RLDCs has to process
Minutes of the 181st meeting of OCC (10.08.2021) Page 38 of 84
the outage and issue the approved list on D-2 basis by 10:00 Hrs. which
gives a time of only 10 Hrs. i.e., from D-3 23:59 to D-2 to 10:00 Hrs.
Hence for better processing of the outages the constituents are requested to
follow the NLDC Outage co-ordination procedure and provide the
requesting status of the approved outages by D-3 on 10:00 Hrs. At present
lot of shut proposals are coming which needs TTC/ATC reduction and also
real time assessment crucial while approving shut downs. Inter Regional
shutdowns, any way NLDC would be approving on D-1. But D-2 approvals
needed to be furnished to NLDC which would be published on D-1.
(ii) PGCIL, SRTS-I stated that all the outage proposals are being discussed in
the Outage Coordination Meeting of OCC and again restricting the time
lines for processing the outage is not appreciable. PGCIL requested that at
least 17 hours or as per NLDC procedure 16 hours may be appropriate.
(iii) CGM, SRLDC observed that there is need for modeling the system after
taking into consideration of all the approved shut downs for which time is
required. He suggested that D-3 may be open upto 14:00 hours.
(iv) PGCIL SR I & SR II agreed to provide the availing status of the OCC
approved outages on D-3 by 14:00 Hrs.
(v) After deliberation, OCC agreed that all the concerned utilities shall provide
the status of availing the OCC approved outages on D-3 by 14:00 Hrs.
(vi) SRLDC requested all the constituents to note the same and follow the time
schedule strictly to enable SRLDC to concur the outages after proper study
in real time.
A h Outage procedure in Intra State network:
(i) In the state of Karnataka during the month of July there have multiple grid
disturbances with generation & load loss to the tune of 1000 MW within a
span of 2 weeks.
(ii) The outages were caused due to
a) Radialization of 220kV transmission lines
b) lines kept open to control over-loading
c) Non-Availability of N-1
d) Bus – Split operation
Minutes of the 181st meeting of OCC (10.08.2021) Page 39 of 84
(iii) Hence outage planning is of crucial importance for better grid operation.
As per the NLDC outage co-ordination procedure, SLDC should approve
the outages latest by 1200 Hrs. of D-1 day. These details would be helpful
in avoiding the impact of simultaneous parallel outages in ISTS & Intra
state network. All constituents are requested to share the Approved Outage
List by 1200 Hrs. of D-1 basis.
Deliberation:
(i) SRLDC informed that due to lack of proper coordination of outage
planning number of disturbances are happening. Many 220kV
transmission lines were radialized, many lines kept open to control over-
loading, there is non-Availability of N-1(even in some cases n also not
available) & and many buses are in split operation etc.. In such a grid
condition tripping of a single line causes grid disturbances, in the state of
Karnataka during the month of July 2021 there have been such
multiple grid disturbances with generation & load loss to the tune of
1000 MW within a span of 2 weeks. SRLDC should have a proper
knowledge on the outages of transmission lines in the region well in
advance so that proper study can be carried out to see whether any system
constraints are envisaged and can take immediate action/advise the
concerned utilities accordingly. Many times RTPS ICTs are overloaded
continuously which was informed to KPTCL time and again. He requested
KPTCL to manage the loading to bring to the limit to avoid disturbances.
(ii) CGM, SRLDC added with concern that there is no strengthening of
evacuation scheme carried out / specific evacuation scheme built up to
match with huge addition of wind/solar generation to the 220 kV system.
Mostly all the loads are being met by RE and the power needed to flow to
other places i.e towards the south part of Karnataka which is the challenge.
Wind & Solar generation will be at peak at Gadag and Koppal areas and
this challenge appear during this period every year. Since many buses are
spilt to reduce the over loading which indirectly reduces the reliability and
this situation will worsen in coming years. At present Karanataka system
is anchored at Kudgi, Narendra, Guttur and Dhoni etc. for injecting
adequate power. Once more generation comes up at 400 kV (Kadak,
Koppal & Kudgi) injection at these points also will be constrained which
will cause more loading to 230 kV system. He opined that multi pronged
action needed to be taken to address these issues by KPTCL as follows:
Minutes of the 181st meeting of OCC (10.08.2021) Page 40 of 84
1. Coordinate all shutdowns, study the scenario and act accordingly.
2. Try to avoid split bus operation, and ensure n-1 availability at crucial
nodes.
3. Feed back to planner and to concerned authorities needed to be
furnished and accordingly strengthening of the grid to be looked into.
He observed that if it is not done as narrated above, the issue of
generation/load loss will aggravate in coming years.
(iii) KPTCL informed that this is the first time KPTCL observed wind & solar
generation at peak simultaneously, when demand is comparatively very
less. All the generation at 220 kV and below are at Kudgi, Dhoni, RTPS.
Tripping at RTPS caused due to more power flow to Dhoni. The MUST
RUN Status of RE and more Hydro in this season is becoming challenge
to system operator. There is no proper plan about the system capacity to
accommodate more addition of RE and way forward to tie up this issue.
The problems faced by system operators had been apprised to Regulators
as well as transmission wing and planners. For Gulbarga zone, Kalburgi
400 kV S/S is coming up which may solve the issue in Gulbarga zone. A
Special meeting may be convened with SRPC/SRLDC and STU/planners
and transmission wing of KPTCL to discuss on these issues.
(iv) CGM, SRLDC desired to know whether KPTCL SLDC is mandated by
KERC/KGSC to give feedback to their planner. He re-emphasized that
765 kV system coming at Gadag and Koppal is for express high way for
upcoming wind and not for injection to KPTCL/KPCL generation and
KPTCL cannot lean on this system. KPTCL clarified that this issue had
been taken up with planners previous year also as mandated by
KERC/KGSC.
Conclusion:
(i) KPTCL need to plan the outages of transmission elements in
coordination, study the scenario and approve/avail accordingly.
(ii) KPTCL to try to avoid split bus operation, and ensure n-1 availability at
crucial nodes.
(iii) Feed back to planner and to concerned authorities needed to be furnished
and accordingly strengthening of the grid to be looked into.
Minutes of the 181st meeting of OCC (10.08.2021) Page 41 of 84
A i Islanding Scheme Monitoring:
(i) The review of the Southern Region Islanding schemes has been taking
place during the past few months. The following islanding schemes have
been agreed and are under implementation
a. Hyderabad (Ramagundam) Islanding Scheme
b. Chennai Islanding Scheme
c. Neyvelli Islanding scheme
d. Visakhapatnam (Simhadri) Islanding scheme
e. Bengaluru Islanding Scheme
f. Vijayawada Islanding Schme
(ii) Hence as a part of actionable points, a geographical map of island is to be
created in SCADA, which will enable the system operator to visualize the
critical details in the Island such as
1. Transmission Line Loading
2. Sub-Station Voltage’s
3. The map should display:
Load Generation Balance and mismatch of the Island
Quantum of AUFR and DF/DT different stages in island
Flows on Island-forming elements
SPS load quantum in island-scheme wise
Renewable energy in island
(iii) All the constituents are requested to share the Grid –Display with SRLDC
for further monitoring & improving the success of Islanding Scheme
Deliberation:
(i) SRLDC informed regarding the implemented/proposed Islanding
Schemes in SR and emphasized on the requirement of having a
geographical map of island to be created in SCADA of SLDCs, which
will enable the system operator to visualize the critical details in the
Island like Transmission Line Loading, Sub-Station Voltage’s and the
maps may include Load Generation Balance and mismatch of the Island,
Minutes of the 181st meeting of OCC (10.08.2021) Page 42 of 84
Flows on Island forming elements, Quantum of AUFR and DF/DT
different stages in island, SPS load quantum in island-scheme wise,
Renewable energy in island etc. The Grid-Display may be shared with
SRLDC for further monitoring & improving the success of Islanding
Schemes on Regional basis.
(ii) MS (I/c), SRPC stated that this requirement is time bound, i.e by October
2021 this requirement should be met. This information would be helpful
not only in monitoring the healthiness of the Islanding scheme, but also
during the future review exercises. He further informed that all future
review exercises would be based on fulfillment of LGB for a majority of
the time ascertained on the basis of the SCADA plots of Anticipated
Generation vs Anticipated Load taken over a period of time (say one to
two years) instead of simply basing on PLF based generation/average
load S/S data. He requested all constituents to maintain the actual
SCADA data (if not available at lower voltage level, corresponding
boundary energy meter data to be used). The main purpose is to ascertain
the success rate of Island which would be obtained by considering the
cumulative anticipated generation Plot Vs anticipated cumulative load
plot in that particular island and if they are basically close to each other
the Island will withstand/successful in case the Island is formed. States
needs to keep integrity of SCADA data. Next review will be based on
this data. The SCADA Display mentioned by SRLDC should be made
available by October 2021. This is even the requirement from MoP also.
(iii) PGCIL SR-I informed that for facilitating Visalhapatnam (Simhadri)
Islanding scheme, Jeypur-Gazuwaka shut down was availed and the
required works were completed. Vijayawada-Vemagiri shu-down is
planned during August 2021. With that all the works to be carried out by
SR-I for Visakhapatnam Islanding scheme would be completed. The
shutdown is being availed on D-1 basis in PN OCC outage proposal
(reason as for facilitating Visakhapatnam Islanding). Requested that the
shutdown of elements availed for facilitating the Islanding schemes may
be considered under deemed availability category.
A j EHV Transmission Elements Details: -
(i) Constituents are requested to provide consolidated statement of the
transmission elements charged/commissioned in the previous month for
updation of SRLDC Database & PSS/E base case which is used for
Minutes of the 181st meeting of OCC (10.08.2021) Page 43 of 84
TTC/ATC computations, PoC base case and Real-Time Security Desk
which is used for various studies and making real-time decision during
system operation. The Google Sheets Link - Transmission Element
Commissioning Details - Google Sheets link maybe used for populating
the elements as and when being commissioned.
(ii) In the Meeting, SRLDC requested all concerned to note the above and
use the link mentioned above for populating the elements as and when
being commissioned.
(iii) KPTCL informed that they are receiving the information from different
wings and the same would be shared by email to SRLDC.
(iv) SRLDC informed that along with sharing of the mails, the link may also
needed to be updated so that a data base would in place which will help
in TTC/ATC computations, PoC base case and Real-Time Security
Desk which is used for various studies and making real-time decision
during system operation.
Ak Declaration of High and Low demand seasons of Southern Region for
2022-23
(i) As per regulation 42(3) of Central Electricity Regulatory Commission
(Terms and Conditions of Tariff) Regulations, 2019 “The High
Demand Season” (period of three months, consecutive or otherwise)
and ‘Low Demand Season’ (period of remaining nine months,
consecutive or otherwise) in Southern region shall be declared by
SRLDC by 30th September for the year 2022-23
(ii) As per the procedure for computation of “High and Low demand
seasons” discussed in 170th OCC meeting for declaration of 2021-22
seasons. it is proposed to declare April 2022, February 2023 and
March 2023 as High demand season for 2022-2023 year.
(iii) In the meeting it was noted that the same procedure was adopted for
declaring High demand season for SR for 2022-23. SRLDC presented
the calculation part.
(iv) After deliberation, OCC agreed that SRLDC may declare April
2022, February 2023 and March 2023 as High demand season for
the year 2022-2023.
Minutes of the 181st meeting of OCC (10.08.2021) Page 44 of 84
Al Status of the implementation of the modified SPS scheme for Kaiga ICTs:
(i) Implementation of the modified SPS scheme at Kaiga End is as follows:
Stage-I Implemented
Stage-II
Provision (Single ICT more than 500MWe for 5 Seconds)
made at Kaiga End – Respective implementation agency can
extend the signal to Kadra and Kodasalli PH during ICT shut
down condition.
Stage-III Implemented
(ii) KPTCL and KPCL are requested to furnish the status of the implementation
of the modified SPS scheme.
Deliberation/Conclusion:
(i) SRLDC observed that out of the three stages of modified SPS scheme at
Kaiga, Stage I & Stage III are implemented. Stage II which is designed to
give signals for Hydro Stations of KPTCL needed to be implemented.
(ii) CGM, SRLDC stated that Kaiga is connected to Kadra and Kodasalli
and Karwar is the main load point (around 30 MW). During Monsoon
season (almost three months, Kadra and Kodasalli would be running at
full load most of the time along with full generation at Kaiga at 220 kV
level. Kaiga ICTs are heavily over loaded and there won’t be N-I and
tripping of one ICT will lead to black out of Kadra, Kodasalli and even
two units of kaiga connected to 220 kV level. This may have impact on
the other units of Kaiga also since some times APS is met from these
units. It was agreed that at a particular threshold which can be mutually
agreed, Kadra and Kodasalli lines may be tripped if there is only one ICT
and the other ICT is heavily over loaded which will avoid poisoning of
Kaiga Units. Because of network issues it is not possible to connect
Kodasalli to Nagjheri, Naghjeri generation overloading to Nagjheri-
Ambewadi lines also.
(iii) KGS intimated that Stage I & III are already in place. W.r.t Stage-II,
wiring at Kaiga end (upto relay contact) is over, extension to Kadra and
Kodasalli is pending.
(iv) KPTCL informed that they would take up with KPCL to expedite
the implementation. KPTCL confirmed that PLCC is available and
logic at Kadra and Kodasalli to be wired.
Minutes of the 181st meeting of OCC (10.08.2021) Page 45 of 84
Am Status of FO Cable in 400kV NCTPS Vallur line-1 and 2:
(i) Due to non-availability of FO cable in 400kV NCTPS Vallur line-1 and 2,
currently LDP is not enabled in these lines. Because of this, during
transient fault in one of the lines, distance protection overreach in other
line is being observed and hence there is a need to bring LDP back to
service by completing pending works related to FO cable availability.
(ii) Also, it may be noted that during multiple tripping of lines and generators
in North Chennai Area on 19-03-2020 at 12hrs, this issue aggravated the
disturbance since DT was not sent to NCTPS end during LC of line-1 at
Vallur end.
(iii) In this regard, TANTRANSCO and NTECL are requested to furnish the
status of rectification of FO cable.
Deliberation:
(i) CGM, SRLDC requested TANTRANSCO to appreciate the gravity of the
issue. North Chennai & Vallur units (total 5 units) are in risk due to non-
availability of FO cable (LDP not available) in 400kV NCTPS Vallur
line-1 and 2. Time and again SRLDC/SRPC had raised the issue. During
FOG season many trippings in Kalanathapattu, North Chennai and Vallur
area are observed and reclosing the lines becomes very tedious.
(ii) CE, P & C, Chennai informed that the issue had been taken up seriously
and action had been taken up to lay direct cables. By end of September
2021 works for establishing permanent connection would be completed.
An Status of Restoration of 400kV/220kV RTPS ICT#2:
(i) 400kV/220kV RTPS ICT# 2 got tripped on 23-07-2021 at 18:47hrs and
is still under outage. Due to outage of 400kV/220kV RTPS ICT# 2,
frequent grid occurrences are happening in the downstream 220kV
connected SS of KPTCL.
(ii) In this regard, KPCL is requested to furnish the status of restoration of
400kV/220kV RTPS ICT#2.
(iii) In the meeting, KPCL informed that KPCL had taken up the issue with
TELK (OEM). The detailed report about the problems along with the
offer for rectification work is being received. Since Y-Phase winding
needs full replacement at least 4 months for rectification as informed by
RTPS.
Minutes of the 181st meeting of OCC (10.08.2021) Page 46 of 84
(iv) SRLDC cautioned that ICT loadings should be controlled to avoid
tripping of the ICTs. CGM, SRLDC enquired regarding the availability
of spare ICTs or ICT under procurement to replace the faulty ICT at
RTPS at least for wind season.
(v) KPCL informed that at present one each 500 MVA & 315 MVA
transformers are available. KPTCL requested KPCL to explore the
possibility of getting spare transformer from PGCIL.
(vi) KPCL ensured that they will take up with TELK requesting for early
restoration works and mean time other feasibilities also would be
explored.
Ao Frequent GDs in Karnataka due to Operational & Protection Issues
during July 21:
(i) Multiple Tripping in 400kV/220kV RTPS, 220kV Kushtagi SS & 220kV
Sindhanur SS and Complete Outage of 220kV Lingasugur SS, 220kV
Mallat SS, 220kV Bagewadi SS, 220kV Vajramatti SS, 220kV Almatti
PH, 220kV Bagalkot SS, 220kV Baluti SS, 220kV Fortune Five(Greenco)
Wind Station, 220kV Atria Wind Station and 220kV Gadag SS in
Karnataka were observed during the following instances during July 2021
resulting in huge amount of generation loss and load loss causing threat to
grid security.
S.
No.
Date and
Time of
Event
No of
220kV SS
under
Complete
Outage
Generation
Loss (MW)
Load
Loss(MW)
Remarks
1 23-07-
2021 at
18:18hrs
Nil Nil Nil Multiple Tripping in 400kV/220kV
RTPS, 220kV Mallat and 220kV
Lingasugur SS
2 23-07-
2021 at
18:18hrs
Nil Nil Nil Multiple Tripping in 400kV/220kV RTPS
and 220kV Mallat SS
3 26-07-
2021 at
14:06hrs
8 967 157 Complete Outage of 220kV/110kV
Bagewadi SS, 220kV/110kV Vajramatti
SS, 220kV Almatti PH, 220kV/110kV
Bagalkot SS, 220kV Baluti SS, 220kV
Fortune Five(Greenco) Wind Station,
220kV Atria Wind Station and
220kV/110kV Gadag SS
4 26-07-
2021 at
16:25hrs
8 320 79 Complete Outage of 220kV/110kV
Bagewadi SS, 220kV/110kv Vajramatti
SS, 220kV Almatti PH, 220kV/110kV
Bagalkot SS, 220kV Baluti SS, 220kV
Minutes of the 181st meeting of OCC (10.08.2021) Page 47 of 84
Fortune Five(Greenco) Wind Station,
220kV Atria Wind Station and
220kV/110kV Gadag SS
5 29-07-
2021 at
13:46hrs
10 1028 225 Multiple Tripping in 400kV/220kV
RTPS, 220kV/110kV Kushtagi SS &
220kV/110kV Sindhanur SS and
Complete Outage of 220kV/110kV
Lingasugur SS, 220kV/110kV Mallat SS,
220kV/110kV Bagewadi SS,
220kV/110kV Vajramatti SS, 220kV
Almatti PH, 220kV/110kV Bagalkot SS,
220kV Baluti SS, 220kV Fortune
Five(Greenco) Wind Station, 220kV Atria
Wind Station and 220kV/110kV Gadag
SS
With respect to this, in general the following points needed review:
a. Cascaded tripping of lines. Lack of N-1 during antecedent conditions
b. Not enabling A/R in 220kV connected lines.
c. SPS during overloading of 220kV Gadag-Dhoni lines and 220kV
Vajramatti-Kudgi lines has to be explored to back down the generation from
RE/Almatti PH
d. Radial operation of many 220kV SS.
e. Many bus split operation at 220kV SS affecting system reliability.
f. Outage of many 220kV lines.
g. No (N-1) during antecedent conditions. Strengthening of 220kV system is
the need of the hour.
h. Over-current protection disabling for 220kV lines to be reviewed.
OCC noted the above.
Ap Frequent tripping of lines
(i) Details of frequent tripping of lines during July 2021 are given below
(Tripping of lines on OV protection are not included):
S. No. Name of the Element
No. of
Trippings
1 230kV TTPS KKNPP 4
2 220 kV AMBEWADI - PONDA 1 6
Minutes of the 181st meeting of OCC (10.08.2021) Page 48 of 84
(ii) All constituents are requested to take appropriate remedial actions in
order to avoid frequent tripping of lines.
(iii) In the Meeting, KPTCL informed that now a days the number of
tripping of 220 kV Ambewadi-Ponda Line is increasing and duration of
outages are also observed to be high. Test charging of lines from Goa is
also taking more time. Opening the jumper in KPTCL Jurisdiction Goa is
carrying out the healthiness checking of the line. Also in the 6 outages
mentioned by SRLDC, 5 are under Goa jurisdiction.
(iv) DGM, SRLDC noted that the cause of fault, distance etc from Ponda end
is not able to observe due to non-availability of PLCC.
(v) CGM, SRLDC informed that they would discuss with WRLDC to get a
clear picture of the issues and if needed a Special Meeting may be
convened among Goa, WRLDC, KPTCL, SRLDC & SRPC.
Aq Non-Furnishing of Details for Grid Events by Constituents:
(i) All constituents are requested to furnish data timely in SRLDC Tripping
portal.
(ii) It may be noted that delay / non-furnishing of information delays analysis
of the event and further obstructs the information dissemination by
SRLDC to all concerned.
(iii) In the Meeting, SRLDC presented that details of non furnishing of the
tripping details and noted that more trippings are observed in KPTCL
system and lakh of information sharing also is prominently from KPTCL.
(iv) ED, SRLDC expressed concern and requested KPTCL to escalate this
issue with higher management emphasizing that without proper details of
the tripping fault anlysis and further planning is quite impossible.
(v) Appreciating the concerns expressed by SRLDC, KPTCL informed that
the issue had already been escalated to RT wing of KPTCL and ensured
that the required information would be made available to SRLDC in the
stipulated time period.
B a List of Substations with Single Bus Operation:
(i) States were asked to submit the list of substations with Single bus
operation and submit the action plan for making them double bus through
bus coupler in 178th OCC meeting.
Minutes of the 181st meeting of OCC (10.08.2021) Page 49 of 84
(ii) List has received from AP, Telangana, Karnataka & Tamilnadu. It is
requested Kerala to send the list.
Deliberation:
(i) SRLDC informed that the information as sought by SRLDC had been
received from all of the constituents.
(ii) DGM, SRLDC requested all the states to explore the possibilities to
shift into double bus/multi bus operation wherever only single bus
operation is available at present. CGM, SRLDC noted that at 220 kV
level with huge injection, single bus operation is threatening for grid
security, one single bus trip will cause huge generation loss and may
lead to cascade tripping. He requested all the states to take immediate
action to migrate to dual bus operation wherever possible and also such
cases where some augmentation is required to make multi bus available
can be referred to Planning wing and accordingly actions should be
initiated. System should be geared up to adopt high wind and solar at all
time.
(iii) TANTRANSCO informed that there are a total of 125 230 KV S/Ss
(TANTRANSCO+ TABGEDCO) in which 55 S/Ss are having Main I
& Main 2 bus configuration and the rests(70) are having single bus
configuration. 8 stations had been identified for migrating to double bus
operation for which works had been started. 48 single bus operated
Stations were listed out for transforming to double bus under PSDF
funding but due to space constraints in installing the bus coupler the
proposal couldn’t work out. Even one committee was formed to study
the feasibility.
(iv) KPTCL informed that wherever possible migration had been carried
out. Due to space constraints further possibility of shifting S/Ss under
single bus to double bus is ruled out.
(v) APTRANSCO informed that the feasibility is available only at S/Ss and
the concerned wing will be insisted to carry out the change.
(vi) TSTRANSCO informed that there is no provision for changing the
single bus operation to double bus operation. Further studies would be
carried out to see the feasibility
Minutes of the 181st meeting of OCC (10.08.2021) Page 50 of 84
(i) MS (I/c), SRPC enquired whether the non feasibility highlighted by States
for changing to double bus operation is exclusively due to space constraints.
He requested all the states to take immediate action to change to double bus
operation wherever possible on priority and suggested that PSDF funding
may be sought for covering the same under R & M works. As per
Regulation/ technically/ system reliability & security point of view this is
required. He expressed concern that in Telangana one hydro station at 220
kV had come up recently, with single bus operated S/S and even transfer bus
is not available which cannot be appreciated. Newly coming up stations
should necessarily take care of these aspects. In view of the large no. of
stations with single-bus operation, all states were requested to further study
on these aspects and may come up with appropriate plan to provide double
bus operation, wherever feasible.
B b Follow-up of Operational Issues as per Special meeting held on 25.02.2021
1 The updates furnished by SRLDC in the Meeting are as follows:
Description of the
Issue. Pending as on Previous OCC (180th
OCC) Completed as compared to
previous OCC Pending as on date
SCADA as per RE
frame work/ FTC and
Actual Position viz
points not provided
FRV-1,FRV-2, AZURE, NTPC 4 FRV-1,FRV-2,
AZURE, NTPC
4 All the pending NP
Kunta plants has given
the schedule for
validation/addition
4
SCADA points
provided but data not
coming /consistent
Nodal officer
confirmation for
SCADA validation &
taking up real time
SCADA issues
Pavagada: Fortum Finasurya
Npkunta: , FRV, FRV2
Tuticorin: -Mytrah
4 Npkunta: FRV, FRV2 2 Pavagada: Fortum
Finasurya
Tuticorin: -Mytrah
2
(i) SRLDC had reiterated the concern in the delay made even to identify a Nodal Officer and opined that this issue needed
to be taken up seriously.
Providing VOIP Pavagada: - All
Npkunta: Acme Bhiwadi, Hisar,
Karnal, FRV, FRV2, NTPC,SB
Energy, Tata, Azure
Tuticorin: Pending-Girel,
Mytrah
32 Nil 0 Pavagada: - All
Npkunta: Acme
Bhiwadi, Hisar, Karnal,
FRV, FRV2, NTPC,SB
Energy, Tata, Azure
Tuticorin: Pending-
Girel, Mytrah
32
NPKunta: Fibre patching of voice can be done for Spring and Ayana in SPR-6 Telecom panel again using a media converter
can be merged in to Single port in SDH Panel of NPkunta PGCIL.With this methodology will help in getting multiple VOIP
connections without augmenting or using existing infrastructure.The above implemention will be planned and tested by
SRLDC, SR-1,APSPCL,Spring and Ayana in next 15 days.
Minutes of the 181st meeting of OCC (10.08.2021) Page 51 of 84
Voltage control mode
of operation within the
capability limits.
Pavagada: Pending-Adyah
Block 1, 10, 13,2,3,6,
RenewTn2, Acme Rewari,
Kurukshetra, Fortum, Fortum
Solar, KREDL, SB Energy,
Yarrow, Avada Solar, Solarise
–P-22, Parampujya, TATA
Renewable
Npkunta: Acme Bhiwadi, Hisar,
Karnal, FRV, FRV2, NTPC,SB
Energy,
Tutuicorin: Girel, Mytrah
NIl 0 Same as Previous OCC 0
No progress
LVRT/HVRT Pavagada: Fortum,
Npkunta: Acme Bhiwadi, Hisar,
Karnal, FRV, FRV2,
6 FRV, FRV2, 2 Pavagada: Fortum,
Npkunta: Acme Bhiwadi,
Hisar, Karnal,
4
Athena: LVRT and HVRT to be enabled and set as per 2019 regulations. In case of any difficulty to be set as per 2013
regulations by 25.08.2021. These would be done with the support of OEM as communicated by Athena.
Measurement of
Harmonics, Flicker and
DC Injection
All are pending except Ayana 33 prngAgnitra has
conducted the test,
report awaited
1 Except Ayana and
Sprng all are pnding
32
Npkunta: Pending plants are given a scheduleAt 33kV side at APSPCL end: The schedule and necessary action for finalization
of testing agency to be completed by August 2021. Tests to be completed by 30.09.2021
At 220kV side at POWERGRID end: The schedule and necessary action for finalization of testing agency to be completed by
October 2021. Tests to be completed by 30.11.2021
Uploading of weather
parameters on monthly
basis in specified
format
All are pending 34 ANP_SBEnegy,ANP_spr
ingagnitra 2 AllexceptANP_SBEnegy,A
NP_springagnitra 32
Registration with CEA Pavagada-AvvadaSolarise,KREDL
NPKunta–,FRV,FRV2,
NTPC pendingTirunelveli-Mytrah
6 NP Kunta – FRV,
FRV2, NTPC
3 Pavagada- Avvada
Solarise, KREDL
Tirunelveli- Mytrah
3
KREDEL officials had met SRLDC on 08.07.2021 and had ensured that all pending issues with Kredel will be addressed
within three days.
Geo tagging
Information for each
wind turbine with
NIWE
Mytrah, GIREL, Orange 3 Orange is taking up
with project vendor
and they have
submitted data to
NIWE. GIREL have
submitted data to
NIWE
Note: Currently
NIWE is facing
Issues with their
portal once it is
corrected, both
GIREL and Orange
will be done.
0 Mytrah, GIREL,
Orange
3
2 Update on meeting held with RE Developers at Anantapuramu (NP Kunta) on 6th
August 2021
Minutes of the 181st meeting of OCC (10.08.2021) Page 52 of 84
(i) SRLDC informed that ED, SRLDC along with a team of members from
SRLDC & SRPC had visited the N P Kunta site on 06.08.2021 to 07.08.2021.
A meeting to discuss the pending issues at NP Kunta Ultra Mega Solar Park
was held on 06.08.2021. The meeting was held in two sessions. The first
session was held at NTPC Conference Hall, Kadiri at 10:30 Hrs with
participants from SRLDC, SRPC, NTPC, FRV along with their O&M Partners
and OEM to discuss issues and their way forward w.r.t NTPC, FRV I & II.
GM, Kayankulam joined through Video conference. Second Session was held
at APSPCL conference, NP Kunta at 15:00 Hrs room with participants from all
developers along with their O&M Partners and OEM to discuss their
operational issues.
(ii) The Record Notes of the above Meetings are at Annexure-3.10 Bb.
B.c Update on Night mode Operation of Inverters at Pavagada Solar Park to
contain Over voltage
(i) This item is covered under Item No 3.7. SRLDC informed that States may
visit the Pavagada Solar Park to witness/understand the Night Mode
Operation of Pavagada Solar park. All the states to communicate regarding
the possible date for the visit along with number of officials for the visit so
that SRLDC in coordination with KSPDCL could arrange the visit.
B.d Renewable energy (RE) curtailment
(i) As per Regulation 6.4.5 and Regulation 5.2(u) of the Grid Code and similar
provisions enshrined in respective State Grid Codes “generation based on
renewable energy sources such as solar and wind are to be treated as “must
run‟ and such generation can only be curtailed or backed down if grid
security or safety of equipment or personnel is endangered” Accordingly,
RE may not be curtailed except for the reasons mentioned in the grid code.
(ii) All SLDCs may submit details of curtailment viz. MW, MU, Time etc.
along with detailed reason to SRLDC in writing before 11 AM& display the
same in their websites.
Deliberation:
(i) SRLDC highlighted the following directives of the APTEL Order dated
02.08.2021 on Appeal NO. 197/2019:
1) POSOCO is directed to carryout similar exercise for the period up to
31.10.2020 and submit report to Respondent Commission within 3
Minutes of the 181st meeting of OCC (10.08.2021) Page 53 of 84
months. Tamil Nadu SLDC and Appellant are directed to submit details
to POSOCO
2) Directions to all State Commissions, Discoms and SLDCs w.r.t to RE
curtailment
a) Guiding factors would apply till such time FoR or the Central
Government formulates guidelines w.r.t to RE curtailment
b) Any curtailment of Renewable Energy shall not be considered as
meant for grid security if the backing down instruction were given
under following conditions:
System Frequency is in the band of 49.90Hz-50.05Hz
Voltages level is between: 380kV to 420kV for 400kV systems &
198kV to 245kV for 220kV system
No network over loading issues or transmission constraints
Margins are available for backing down from conventional
energy sourc
State is overdrawing from the grid or State is drawing from grid
on short-term basis from Power Exchange or other sources
simultaneously backing down power from intra- state
conventional or non-conventional sources.
c) As a deterrent, the curtailment of RE for the reasons other than grid
security shall be compensated at PPA tariff in future. Compensation
shall be based on the methodology adopted in the POSOCO report.
d) POSOCO is directed to keep the report on its website.
e) SLDC shall submit a monthly report to the State Commission with
detailed reasons for any backing down instructions issued to solar
power plants.
All the states were requested to note the above for compliance.
(ii) All SLDCs are submitting details of curtailment viz. MW, MU, Time etc.
along with detailed reason to SRLDC in writing before 11 AM & display
the same in their websites. He requested AP to furnish the information in
time since this information to be passed on to NLDC and subsequently to
higher ups from NLDC.
(iii) The time block in which maximum curtailment was carried out is not
available at present. SRLDC would circulate a format in which all the
states may furnish the information by Tuesday of every week for the
previous week.
Minutes of the 181st meeting of OCC (10.08.2021) Page 54 of 84
B e SCADA Data availability issues
1.1. Non-reporting of real time SCADA data MTPS Stg-3(Tamil Nadu)
Reported SAS issue at Mettur.
Following up since 168th OCCM.
Gateway at Mettur Stg3 replaced on 16th July 2021. Data unstable.
In the Meeting, SRLDC informed that the issue had been resolved in July
2021 and observed to be stable.
1.2. Non-reporting of real time SCADA data from NP Kunta
Galiveedu PS-1 is not reporting to SRLDC Backup Control Centre since
Jan 2021.
Developer wise data of NTPC (connected to NPKunta PS-1).
Redundancy of data from GVD PS-1 & NPL PS-1 is lost vide Email
dated on 07.04.2021
Letter issued to Galiveedu PS-1 & NP Kunta PS-1 regarding non-
reporting to SRLDC BCC.
Restoration: NP Kunta PS-1 on 19th July 2021 & Galiveedu PS-1 on 26th
July 2021.
In the Meeting, SRLDC informed that the issues w.r.t NP Kunta PS-1 was
resolved on 19th July 2021 & at Galiveedu PS-1 on 26th July 2021. In the
Special meeting held on 25.02.2021 a time line for verification of quality data
from Inverter, Weather station etc. had been put. But it was not strictly
followed by RE developers. A Review Meeting with NP Kunta
Developers/APSPCL was held on 06.08.21 and new time lines for validation
was agreed by all.
1.3. Non-reporting of real time SCADA data from 400KV SEPL station
Data not reporting to SRLDC since past few months.
400kV SEPL (Main Channel): not getting loop. Link not healthy;
(Secondary Channel): loop ok but data not reporting though this healthy
link.
Mail sent to SEPL on 19th Jan 2021 and link tested. Follow up mail sent
on 28th Apr 2021& 31st May 2021.
Mux equipment to be rectified by SEPL, vendor has collected the MUX
In the Meeting, SRLDC informed that the issues are pertaining to SEPL,
vendor has collected the MUX. Rectification is still awaited by SEPL.
Minutes of the 181st meeting of OCC (10.08.2021) Page 55 of 84
1.4. Partial reporting of real time SCADA data from 230kV Kalpakam (MAPS)
Station
Lines- except 230kV Kalpakam-Echur lines, all other 230kV lines are not
reporting.
GT HV and LV side MVAR data of both units are not reporting.
Issue yet to be resolved. Reminder mail sent on 15th March 2021 & Letter
issued on 01st June 2021
As per last OCCM, transducers procured & yet to receive at site. MAPS/
POWERGRID may update.
In the Meeting, SRLDC informed that the issue is still pending and there is no
update from PGCIL/MAPS. GM, PGCIL, SR II informed that RTU
procurement is under process and conversion to 104 Protocol is being carried
out. He ensured the support from PGCIL and requested MAPS to allow to
carry out the works.
B f Real time data discrepancy issues:
Updated Data discrepancy file shared vide mail dated on 09th July 2021.
All utilities are requested to initiate action on rectification of the
identified points.
Discrepancy points are updated monthly and followed up through mail as
well as in Communication meetings.
CGS stations may update the status on the points.
Few points attended by POWERGRID SR-1, POWERGRID SR2,
Karnataka & AP.
In the Meeting, SRLDC informed that Updated Data discrepancy file had
been shared vide mail dated on 05th August 2021. With PGCIL, day to day
basis, S/S wise, the issues are being taken up wherever data discrepancy is
noted. Next week NTPC issues would be taken up for which communication
had already been sent to NTPC for identifying a nodal officer for joint
verification/rectification. He observed that even after identifying the points
rectification is pending from most of the entities and requested all to arrange
to resolve the issues.
B g Communication issues:
Minutes of the 181st meeting of OCC (10.08.2021) Page 56 of 84
(i) Outcome of Dual link availability testing conducted for regional entities
reporting to SRLDC:
IL&FS, NCC (SEIL-2) reporting in single channel. Reply from
entities on restoration:
SEIL-2: OPGW from SEIL -2 (SGPL) to NPS (Nellore Pooling
Station) is completely out of service. Action to be taken by
POWERGRID.
IL & FS: Faulty card replaced at both ends, but data still reporting
in single channel. Replaced faulty card on 28th July 2021. Data
reporting in both channels
Letters sent in this regard on 31-05-2021.
In the Meeting, PGCIL informed that OPGW is to be replaced in this line
for around 3 km length, and 10 days S/D is required since online work
cannot be feasible in that terrain. S/D was availed three days back, but
unfortunately second line also tripped. At present SEIL is not facilitating
the S/D. SEIL is suggesting November-December period for concurring for
S/D. He expressed concern regarding the difficulties in arranging the
workforce for small works. He ensured that possible support to get the
works done.
It was noted that IL & FS issue had been attended.
Items under 3.10. C were discussed under items 6,7,&9
4. Follow up issues
4.1 Reserve Shut Down (RSD) – Implementation of new Procedure
i. Implementation of new RSD procedure on trial basis for two months was
agreed in the special meeting held on 03.09.2020. All the utilities had
conveyed concurrence for implementation of new RSD procedure on trial
basis for two months.
ii. In the 178th OCC Meeting, SRLDC had informed that implementation of
RSD had already been taken up with NLDC/PWC for implementation
and changes in WBES have been agreed upon by PWC. It was agreed by
SRLDC that action for the implementation would be expedited in
coordination with PWC as requested by the Forum, especially felt by
TSTRANSCO.
Minutes of the 181st meeting of OCC (10.08.2021) Page 57 of 84
iii. Subsequently, TSTRANSCO vide letter dated 27.05.2021had requested
SRPC/SRLDC to take immediate action to implement the RDS
procedure (trial run for two months) at the earliest or modify the
Entitlement ON bar & OFF bar quantity to reduce part load
compensation liability of TSDICOMs who is actually not a part in part
load operation.
iv. In the 179th OCC Meeting, the following had been noted:
a) In principle all the states had agreed for the procedure for
implementation off bar.
b) SRLDC would revert back within one week after detailed study on
the issues in implementing the off bar in consultation with
commercial division of SRPC. Accordingly States would be informed
and if needed special meeting may also be convened with states to
appraise the outcome of the studies and to decide on further course of
action.
c) MS SRPC had opined that the decision may be taken at the earliest
since SRPC members/higher management have already given consent
for trial run of new RSD procedure.
d) TS SLDC had requested SRLDC to avoid further delay and SRLDC
had agreed to expedite.
v. In the 180th OCC Meeting, the following had been noted:
a) SRLDC had presented the status of implementation. It was noted that
a web based application was developed by SRLDC internal IT team.
SRLDC demonstrated base case for new RSD procedure.
b) SRLDC informed that by 14.07.2021 all the works w.r.t the
implementation including testing would be over. From 15.07.2021
mock trial (without commercial implication) may be started (till
18.07.2021) to experience the impact by States. In consultation with
SRPC, trial run for 2 months may be started from 19.07.2021. The
data would be jointly validated jointly by SRLDC and SRPC before
officially submitting to SRPC for commercial accounting.
vi. As agreed in the 180th meeting, a workshop was conducted on
13.07.2021 with participation from all the concerned entities wherein it
was agreed for Mock trial for 10 days from 15.07.2021 to 24.07.2021.
Minutes of the 181st meeting of OCC (10.08.2021) Page 58 of 84
vii. The mock trial had been successfully completed on 24.07.2021.
viii. Subsequently, a Meeting was carried out on 27.07.2021 wherein the
experience of mock trial run of the experience were shared by SRLDC/
State SLDCs/SRPC and the following were decided:
a) Trail Operation of New RSD Procedure will be implemented
from 01.08.2021 for a period of two months i.e. till 30.09.2021.
b) All data would be validated by SRLDC/SRPC before using the same
for commercial implications.
c) Comments and observations, if any, would be communicated to
SRLDC/SRPC on a weekly basis.
d) A Special Meeting would be convened in the last week of September
2021(tentatively on 21.09.2021) to decide upon further course of
action.
e) The NEW RSD Procedure along with study and communications in
this regard from SRPC is at Annexure-4.1.viii.
ix. Trail Operation of New RSD Procedure has been implemented
from 01.08.2021.
Deliberation:
(i) SRLDC informed that NEW RSD procedure had been commenced from
00:00 hours of 01.08.2021 as per the communication received from
SRPC. SRLDC presented on the experience of the implementation of
the new RSD procedure (Annexure-4.1.1)
(ii) TSTRANSCO observed that NEW RSD procedure have helped
TSTRANSCO in grid operation (technically & economically) and
reiterated the gratefulness to SRLDC and SRPC teams.
(iii) APTRANSCO informed that they are comfortable with the NEW RSD
procedure.
(iv) TANTRANSCO informed that on 9th TANTRANSCO had brought the
Kudgi Unit and schedule requested was around 216 MW, but scheduled
power during peak hours was only 155 MW. As per NEW RSD
whoever brought back the unit should get the requested power
throughout the day.
(v) SRLDC informed that other than KSEBL all the other states punched
for Kudgi Unit and total requisition was more than one unit capacity
Minutes of the 181st meeting of OCC (10.08.2021) Page 59 of 84
(937 MW). To bring back unit on bar w.r.t Kudgi is around 35 hours.
Next day there was no requisition received from any of the states not
even to meet one unit technical minimum. Only one unit was brought
on bar. Whatever requisition received was adjusted on pro rata basis to
all states. TANTRANSCO was given 165 MW and the rest was
distributed on prorata basis.
(vi) SRLDC opined that since Kudgi Unit take 35 hours to come up on bar
from cold start and this issue will always arise. TANTRANSCO
punched on 7th and KPTCL punched on 8th for 9thAugust 2021. The
current procedure allows the states to join the new RSD procedure on
D-1 basis also. He opined that if forum agrees for modification in the
procedure such that D-1 request cannot be entertained for existing unit,
and would be considered only for additional unit, the program may be
changed accordingly. He informed that one more case will also to be
looked into. Suppose one 500 MW capacity has come on bar with a
request from two states with a commitment for three days. On second
day another state comes with a request for 200 MW (total 700 MW).
With 200 MW another unit could not be brought on bar. According, as
per the current methodology 200 MW would be adjusted on prorate
basis.
(vii) SE(O), SRPC opined that for the time being let continue with approved
procedure. After gaining more experience the procedure may be
reviewed if required.
4.2 Status update of Primary Frequency Response testing at ISGS & IPPs
i. The following had been noted in the 180th Meeting of OCC:
(i) NNTPS had informed that they have placed work order on 07.05.2021.
(ii) NTPC Simhadri had informed that it is tentatively planned to carry out
the testing for all the units from 21.07.2021(12 days may be required),
one by one. The schedule of testing will be intimated shortly. He
requested all beneficiaries to support to facilitate the testing. W.r.t
SEIL, SRLDC informed that due to COVID-19restrictions testing was
on hold and once issues are contained, status would be updated.
(iii) SEIL(P1) informed that they were in touch with Solvino and they
informed after the pandemic is in control, they will give the date.
(iv) SEIL(P2) informed that Work Order had been placed.
Minutes of the 181st meeting of OCC (10.08.2021) Page 60 of 84
(v) SRLDC observed that all the generators had been placed Order and
testing needed to be scheduled.
ii. NLCIL had informed (vide E-mail dated 26.07.2021) the following
schedule:
NLC New Neyvelli Thermal Power Station Unit-1 from 26th to 27th
July 2021
NLC TPS I Expansion Unit-1 & 2 from 28th to 31st July 2021
NLC TPS II Stage II Unit-4 from 1st to 2nd August 2021.
iii. Subsequently, NLCIL vide E-mail dated 28.07.2021 had informed that M/S
Solniva had conducted the "Primary Frequency Response test as per IEGC
clause 5.2 (g) at NLCIL -TPS-1 Expn Unit -2 of TPS-1 Expn, with 100%
load test is carried out at 16.00 hrs to 20.00 hrs on 28.07.2021.
iv. NTPC Simhadri had informed that it has tentatively planned to carry out the
testing for all the units from 21.07.2021(12 days may be required), one by
one. The schedule of testing will be intimated shortly.
v. Subsequently, through mail dated 21.07.2021 had shared that as discussed
in 180th OCC, NTPC is planning to test RGMO response of Simahadri
Stage 2 Units (Unit 3 & 4) from 10.08.21 to 13.08.21. The desired schedule
is was also attached.
The following were noted in the meeting
a) Primary Frequency Response (PFR) Testing completed during July-
Aug-2021
NNTPP Unit-1 on 26th & 27th July 2021
NLC TS-1 Expansion Unit-1 &2 on 28th to 31st July 2021
NLC TS-2 Unit-4 on 1st & 2nd August 2021
b) SRLDC executives witnessed the testing at NLC TPS-2
c) Earlier completed units
Ramagundam TPS: Unit-4,6 & 7, Talcher Stage2: Unit-3,4&5,
Vallur NTECL: Unit-1 &3
d) It was noted that 12 no. of units out of 27 units completed by M/s
Solvina. M/s Siemens yet to start testing (6 Units)
e) NTPC Simhadri informed that the PFRT had started from
10.08.2021morning.
Minutes of the 181st meeting of OCC (10.08.2021) Page 61 of 84
f) SRLDC expressed concern that the testing schedule (date etc- not states
schedule) needed to be informed to the Nodal officer identified for
witnessing the testing which was not complied by NTPC. He expressed
that without signature from POSOCO payment may not be possible and
without coordinator’s signature the testing is not valid.
g) NTPC informed that on 21st July 2021 mail had been sent and there was
no reply from SRLDC/SRPC.
h) SRLDC informed that the mail was not received by the nodal
officer/coordinator from SRLDC w.r.t PFRT.
i) ED, SRLDC expressed that as per POSOCO document for PFRT
procedure the identified nodal officer should visit the site and witness
the test. In case no response had been received from SRLDC, VTPC
might have informed to at least Control Room officials to convey the
message to the concerned wing. Contractual terms and conditions
needed to be complied.
j) SE(O), SRPC endorsed the views of SRLDC and opined that the
schedule of testing should have been taken up with the Nodal Officer
when there is identified Nodal Officer/Coordinator and the details of the
nodal officer already shared.
k) NTPC Simhadri informed that even the testing agency didn’t
communicate the requirement of witnessing by SRLDC. Requested
SRLDC to help in resolving the issue since the testing had already
started on10.08.2021.
l) SRLDC also opined that Siemens should have informed SRLDC since
they know the procedure. SRLDC will take up with NLDC and NLDC
will talk with Siemens in this regard. In our Region, this is the first
testing being carried out by Siemens. Solvino is intimating the testing
schedule well in advance to SRLDC. If POSOCO is not witnessing the
test physically, a group with all concerned entities was being formed
and tests reports were being uploaded and was being validated by
NLDC/POSOCO. At present POSOCO is visiting the site and
witnessing the tests.
m) ED, SRLDC concluded that SRLDC may explore the possibility of
sending one official to Simadri to witness the ongoing testing. Further
course of action would be decided in consultation with NLDC.
Minutes of the 181st meeting of OCC (10.08.2021) Page 62 of 84
4.3 Shifting of PMUs
i. In the 36th meeting of SRPC held on 12.07.2019, it was agreed that some
PMUs installed as part of URTDSM project in SR may be optimized by
shifting them to critical substations, lift irrigation substations and
substations with FACTS devises etc. Accordingly SRLDC had suggested
for shifting of PMUs at Vemagiri to KTS VII (PST) & Vemagiri to
Ramadagu (LI).
ii. In the 177th OCC Meeting, it was noted that three Nos of PMUs connected
to 400 kV Vemagiri-Gowthami-1, Gowthami-2, Konasema-2, GVK-1 and
GVK-2 feeders are dismantled by M/s.GE T&D India Ltd and the 3 No’s
removed PMUs were handed over to M/s.GE T&D India Ltd.
iii. In the 180th Meeting, TSTRANSCO had informed that Ramagudu and
Veltoor PMUs are integrated and data is reporting. At KTPS VII PMU
works had been started on 05.07.2021
In the Meeting DE, TSTRANSCO had informed that the works are
completed, commissioning tests are going on and would be
commissioned shortly.
4.4 MVAR absorption capability of SDSTPS units:
i. The less absorption of MVAR by SDSTPS unit compared to their
capability curve since a limiter has set at this MVAR level was being
addressed in Special Meeting (High Voltage issues) and subsequent OCC
Meetings. APGENCO / APTRANSCO to take up the issue of less
absorption of MVAR by Krishnapattanam units with OEM and ensure
maximum absorption within the capability curve.
ii. In the 175th/176thOCC Meetings, APGENCO had informed that the issue
had been taken up with OEM (Mitsubishi). OEM had indicated
involvement of cost in this work. Requested OEM to furnish the budget
requirement and accordingly further actions would be decided. Since
OEM is from Japan, some more time is required and further development
iii. In the 177th OCC Meeting it was noted that Chief Engineer (Generation),
APGENCO vide letter dated 07.04.2021had intimated that the issue have
been taken up with OEM(m/s MELCO, Japan) and requested to review the
settings of AVR for further improvement in reactive power absorption
without any adverse effects on the generator to support the grid. The
budgetary offer from the OEM is awaited and it was expected that the
Minutes of the 181st meeting of OCC (10.08.2021) Page 63 of 84
works may be started by August 2021. The PSS tuning may also be
carried out during this period which was pending in 2021. It was observed
that the absorption of MVAR is at 500-520 level after the commissioning
of two numbers of 80 MVAR reactors at SDTPS.
iv. In the Meeting, APGENCO informed that budjectory offer had been
received from OEM and the same is put up for higher management
approval. The works would be taken up during the next overhaul which is
scheduled in November/December 2021 and PSS tuning also would be
carried out.
4.5 Daily Load Forecasting by SLDCs
SLDCs are requested to furnish the load forecast error (forecast Vs actual
demand) for the month of July 2021to SRLDC along with reasons for
substantial deviations.
States were requested to break the state load into area wise like district
wise/Substation wise while carrying out the forecasting incorporating
weather conditions etc.
In the Meeting, SRLDC presented the load forecast error (forecast Vs
actual demand) for the month of July 2021(Annexure-4.5)
On 21st July 2021 TSTRANSCO load forecast error was observed to be
around 32 %.
TSTRANSCO informed that unpredicted rains started from 20th July 2021
which continued on 22.07.2021 also. This was the reason of the huge error.
KSEBL informed that there was fluctuation of climate during 11th & 12th
July 2021 which was the cause for high error around 15 %).
4.6 Renewable forecasting
(i) All states had been requested to furnish the implemented forecast, day
ahead forecast & actual also (before 5th of every month). It was noted
that this data was being sought by higher forums and other entities.
Deliberation:
(i) SRLDC presented the RE forecasting for July 2021(Annexure-4.6 i)
AP Wind: forecast on higher side for most of the days.
Solar: forecast on higher side for most of the days
SRLDC expressed that the day wise actual and forecast is being presented
so that the variation may be observed.
Minutes of the 181st meeting of OCC (10.08.2021) Page 64 of 84
(ii) ED SRLDC observed that average error may be less but variation
between actual and forecast in many blocks are high. On a query by
MS, I/c, ED SRLDC clarified that forecast error also have remarkable
impact on LGB of states, some corrective actions are based on these
errors.
(iii) SRLDC felt that States may also come up with a presentation on the
variation of actual & forecast since states are mostly operating on the
state specific forecast.
(iv) ED, SRLDC stated that it will help in improving the forecast error,
merely presenting the error will not help in system operation and real
cause for this huge variation needed to be looked into like improper
weather component etc. and will formulate better mythology for
arriving at accurate forecast.
(v) MS I/c, SRPC opined that percentage error is also important and it
may also be projected.
(vi) APTRANSCO informed that wind forecast error was around 75 % on
09.08.2021. 40 MU Wind generation was forecasted by Wind
Developers where as actual received was 10 MU. Real time system
operation is disturbed. SLDC is not able to take from day ahead
market, and also because of price/quantum mismatch RTM availing
RTM power also restricted. Being MUST RUN, SLDCs are bound to
avail RE at any time, and huge error in RE forecast is taking SLDC
operator to uncertainty on decision of LGB. How to improve the
planning is unknown to SLDC operator. He opined that forecast error
formula needed to be revised. He opined that full responsibility for
huge deviation in drawal is entrusted on SLDC by Grid Operator.
Violation messages are also being issued.
(vii) TANTRNSCO informed that they are also facing the issues endorsed
by APTRANSCO and opined that vendors should be forced to
improve the forecasting methodology.
(viii) KPTCL also expressed the difficulties faced by grid operator and
opined that there is an urgent need for devising a better forecast tool
for RE.
Minutes of the 181st meeting of OCC (10.08.2021) Page 65 of 84
(ix) ED, SRLDC the only solution is to improve the forecast. SLDCs have
to explore the methodology to improve the forecast. He assured
support in devising the methodology for arriving at forecast.
(x) After deliberation, concluded that individual SLDCs may discuss
the real issues faced by SLDCs with their forecast
providers/vendors. Technical support would be extended by
SRLDC/SRPC. In case it is felt that a Special Meeting to discuss the
issues would be planned accordingly. SLDCs are requested to give
presentation on the forecast Vs actual w.r.t RE for the month of
August 2021 in next Meeting. It was suggested that all the states
may please note the issues on a daily basis and the presentation
may include that also.
4.7 Communication & Cyber Security Audit
(i) As per the requirement of clause 10 of Central Electricity Regulatory
Commission (Communication System for inter-State transmission of
electricity) Regulations, 2017, RPC Secretariat shall issue necessary
instructions to all stakeholders to comply with the audit requirements
within the time stipulated by the RPC Secretariat and an Annual Report
on the audit carried out by respective RPCs shall be submitted to the
Commission within one month of closing of the financial year.
(ii) In the 178th OCC Meeting, it was noted that Cyber security audit was
not carried out by many of the entities. NLCIL had earlier committed
that they would take action to carry out the Cyber security Audit in line
with NTPL. NLCIL informed that the action taken would be intimated
by mail.
(iii) In the meeting, on a query by NLCIL, it was clarified that cyber
security audit needed to be carried out for all the PCs, ICTs, servers etc.
SRPC had furnished the format for this purpose and requested that
NLCIL may carry out the cyber security audit in coordination with
NTPL as NLCIL had committed earlier.
(iv) MS I/c, SRPC added that all thermal power plants comes under CERT,
Thermal for which NTPC is the nodal officer. Each generator may have
a CISO, who will coordinate with CERT, Thermal. He requested
NLCIL representative to take up with the CISO of their plant and carry
out the required actions w.r.t Cyber Security Audit. CCMP (Cyber
Crisis Management Plan) also should be in place with each entity. It is
Minutes of the 181st meeting of OCC (10.08.2021) Page 66 of 84
the responsibility of the each entity to decide on what all systems are to
be brought under Cyber Security Umbrella.
All the entities to carry out the Cyber Security Audit/VA/VAPT
at an interval as mandated by Regulations in future.
4.8 Ensuring Proper Functioning of under Frequency Relays (AUFR) &
df/dt Relays
i. In the 178th OCC meeting, the states had agreed the list of identified
S/S for inspection/functionality test for the year 2021-22
ii. SRPC vide letter dated 25.05.2021hadcommunicated the list of
substations to states along with FORMATS for furnishing the report.
iii. It was noted that KPTCL & APTRANSCO had carried out the testing
and reports were shared.
iv. Utilities may carry out the inspection and submit the report in the
prescribed format before 31.01.2022.
In the Meeting TANTRANSCO informed that TANTRANSCO had
carried out the inspection and reports had been furnished to SRPC.
4.9 PSS Tuning
i. SRPC is following a specific plan for the PSS tuning exercise, and is
regularly pursued with generating Stations. Seven Meetings (till 31st
March 2021) were conducted with generators to analyze the PSS test
reports. Recommendations were communicated to each generator after
the Meetings.
ii. The 9th Meeting of PSS Tuning was held on 20.07.2021 and analysis of
around 16 units was carried out. The action taken in respect of the
recommendations in the 9thmeeting of PSS tuning may be updated.
iii. The PSS Tuning of the units due may please be carried out and the report
to be submitted to SRPC/ SRLDC.
iv. SRPC requested that the generators advised for retuning/resubmission of
the report may take action accordingly. The standard format for
furnishing the reports had been shared.
4.10 TSGENCO: Request for approval of SPS at BTPS switch yard
(i) TSGENCO has requested for approval for implementation of SPS at
BTPS switchyard to avoid balck out of station during the tripping of 400
Minutes of the 181st meeting of OCC (10.08.2021) Page 67 of 84
kV Julurupadu line I & line II feeders. The letter dated 27.07.2021in this
regard is at Annexure-4.10.i
(ii) In the Meeting, SRLDC presented their observations on the proposal
(Annexure- 4.10.ii). SRLDC informed the following:
a) The proposed SPS is in order and fulfils the intent.
b) The loading of the ICT during only one line outage of 400kV
BTPS-Jullurupadu also needs attention and
TSGENCO/TSTRANSCO may also take into consideration
accordingly.
c) By passing of the time delays involved in various comparative
SPS actions by predetermining the Unit to be tripped, and
extending trip signal to the same may be looked into.
(iii) TSTRANSCO informed that the concerns of SRLDC would be taken
up with BHEL and final implementing logic would be framed and the
same would be shared to SRPC/SRLDC before implementation.
(iv) MS (I/c), SRPC informed that the possibility of non-operation of SPS
also needed to be envisaged and action in such cases as suggested
above at (ii) c) may be framed.
(v) OCC in principle agreed for the implementation of SPS at BTPS
switchyard to avoid black out of station during the tripping of 400 kV
Julurupadu line I & line II feeders
5. Frequency related Issues
5.1 High Frequency
(i) SRLDC presented the under drawal of states when frequency was above
50.05 Hz.
(ii) The Regional Grid had operated above IEGC range ie 50.05 Hz for 19.59
% of the time. It was also noted that the frequency on some of the days
was higher for considerable duration of times.
(iii) Maximum frequency had touched 50.23 Hz at 18:03 hours of 03.07.2021
(Graph at Annexure-5.1.A). At that incident KPTCL was underdrawing
by 700 MW. Also the duration of time Grid operated above IEGC limit is
observed to be high which is to be looked into seriously.
(iv) The under drawal of states when frequency was above 50.05 Hz
Minutes of the 181st meeting of OCC (10.08.2021) Page 68 of 84
(Annexure-5.1.B). The maximum under drawal touched by States during
July 2021 was also presented.
(v) Constituents were advised to avoid under drawal at high frequencies. SRPC
requested all the constituents that action needs be taken to adhere to the
schedule since it has commercial/operational impacts even for under
drawal.
5.2 Pump mode operation
It was noted that during July 2021, there was no pump mode consumption at
Srisailam and at Kadamaprai. N’sagar pump mode consumption was around
23.04 MU.
5.3 Low Frequency
It was noted that the frequency of grid operation was at times lower than
IEGC range. Grid had operated below IEGC range ie 49.90 Hz for 5.35 %
of time during the month.
(i) SRLDC informed that minimum frequency touched 49.52 Hz at
22:12 hrs on 06.07.2021. Drawal of Southern Regional states at that
instance were also projected which were in limits.(Graph
atAnnexure-5.3.A). During that incident APTRANSCO was over
drawing by around 1100 MW.
(ii) Over drawal by SR constituents at frequency less than 49.90 Hz
(Annexure-5.3.B)was presented by SRLDC. The maximum over
drawal touched by States also was presented.
6. Voltage Related Issues
6.1 Low Voltage
(i) Details of capacitors installed during July 2021 in the prescribed format
to be submitted by all the states.
(ii) SRPC expressed concern that KPTCL has not furnished the data in
proper form. The plan for 2021-22 is not furnished even though there was
spill over from the plan for 2020-21. The report is being furnished to
CERC on monthly basis.
(iii) KPTCL informed that they would take up with concerned wing and the
required information would be furnished at the earliest.
Minutes of the 181st meeting of OCC (10.08.2021) Page 69 of 84
6.2 High Voltage issues
6.2.1 MVAR Interchange
In the 169th OCC Meeting it was suggested that MVAR testing may be taken
up after the COVID -19 pandemic issues settle down.
In the Meeting, SRLDC informed that testing had not been taken up due to
prevailing COVID-19 pandemicconditions.
6.3 RE Generators for Reactive Compensation & High Voltage
All the states were again requested to kindly examine and ensure voltage based
MVAR interchange for RE generators.
6.4 Status review of Bus/Line Reactors, Line Reactors and STATCOM
Status of implementation of Bus / Line Reactors approved in the Standing
Committee/SRPC pending for commissioning by the SR constituents is at
Annexure- 6.4.
All the Constituents/Entities were requested to update the status. It is
noted that SRPC Meeting/Standing Committee meeting would be
scheduled shortly and this information is very much required.
Reactors added during 2020-21 & 2021-22 may be furnished separately
by all entities.
6.5 Reactor status
a) Hoody reactor: Commissioning by end of August 2021.
b) KKNPP reactor: KKNPP had sought some clarifications from the
contractor. After receiving the response, work order may be placed by
September end.
c) KGS reactor: Tendering is over. Tender opening is extended up to
18.08.2021 as per the request from bidders.
7. Network Protection/Security issues
7.1 U/F &df/dt Relays Schemes
Concerned to update the status on regular basis.
7.2 Implementation of SRPC recommended quantum
(i) It was noted that all States had implemented AUFR and df/dt schemes
fully.
Minutes of the 181st meeting of OCC (10.08.2021) Page 70 of 84
(ii) SRLDC presented the load relief realized as a percentage of AUFR
quantum declared in the identified feeders during the month of July 2021
as follows: (Detailed Presentation is at Annexure-7.2.A)
AP: 86 %, TS: 111 %, KAR: 56%, KER: 73%, TN: 78%, Pudu: 85%
&SR: 107 %.
In the Meeting, SRLDC observed that w.r.t KPTCL the realization is
very less. KPTCL informed that the less realization was due to low
demand prevailed in the state throughout the month. He expressed that
feeders of around 4000 MW loading had already identified for
AUFR/df/dt and further addition of feeders is not possible.
(iii) SRLDC expressed concern regarding the less response w.r.t KARand
requested to analyze the same.
S.NO State SCADA
mapped %
Status
1 AP 98 All the stages vetting completed.
2 TS 88 TSTRANSCO*
*Informed that additional RTUs at 132 kV level are required to achieve
100 %. Project is taken under PSDF funding. Tenders are floated.
3 KAR 100
4 KER 100
5 TN 88 Some of the RTUs are faulty. After
rectification the percentage will increase.
6 Pudu 92
7 SR 94
8. RGMO/FGMO
(i) As per 5th Amendment to IEGC, gas stations above 50 MW Installed Capacity
were also to come under RGMO/FGMO Operation w.e.f. 1st October 2017.
(ii) Inadequate response was needed to be taken up by SLDCs with respective
SERC’s in line with Hon’ble CERC Orders in respect of Petition No.
84/MP/2015 and 302/MP/2013.The non-performance of the generators under
SRLDC control would be taken up by SRLDC with the respective generators.
(iii) SRLDC vide communication dated had furnished (Annexure-8.iii) the
Southern Region Frequency Response characteristics for the event of
1500MW generation loss in Northern Region happened due to multiple
trippings at 400/220kV Akal(Rajasthan) & 400kV Jaisalmer-2(Rajasthan) on
11thJune, 2021 at 16:02 Hrs.FRC has been calculated state wise and generating
station wise.
Minutes of the 181st meeting of OCC (10.08.2021) Page 71 of 84
Sl.No. State/Region FRC (%)
1 Andhra Pradesh 5
2 Telangana -22
3 Karnataka 39
4 Tamil Nadu -1
5 Kerala -55
6 Puducherry 171
7 Southern Region 33
(iv) Constituents are requested to submit the same for their control area.
(v) SRLDC vide E-mail dated 17.06.2021 had informed that at 16:03 Hrs on 11th
June 2021, 220 kV Akal-Bhu -1&2 tripped due to snapping of B-phase jumper
which resulted into 1200MW wind generation loss and 300MW solar
generation loss in Northern region. Frequency dropped from 50.09 Hz to 49.92
Hz.
(vi) RGMO analysis based on SRLDC SCADA data was attached in the google
spreadsheet and all generators were requested to enter data pertaining to the
event in the above spreadsheet.
(vii) In the 180thOCC Meeting, SRLDC had informed that for 11.06.2021 incident,
analysis is yet to be received from many generators. He requested all the
generators to update the Google Spread Sheet shared at the earliest. In case
response is not updated it will be taken from SRLDC SCADA and analysis
will be presented in 181st OCC meeting.
(viii) SRLDC had communicated the following two incidences for July 2021.
Incident1: It has been reported that at 10:25 Hrs dated 20th July
2021 multiple-element tripping at 220kV Akal(Raj) occurred which
resulted in generation loss of 1550MW at AKAL wind . During the
incident, the frequency dropped from 50.08 to 49.93Hz.
Incident2: On 22nd July 2021 at 15:08 Hrs tripping of both the thermal
units of UPCL ( 2 X 600MW) and all the Hydro units of Varahi (4 X
115MW) was reported. 1400 MW Generation loss occurred. During the
incident, frequency dropped from 49.99 to 49.86Hz.
(ix) In the Meeting, SRLDC informed that the response had not been received
from many generators for the incidences in July 2021. SRLDC presented the
response for the incidence on 11.06.2021(Annexure-8.ix) : The abstract is
as furnished below:
Minutes of the 181st meeting of OCC (10.08.2021) Page 72 of 84
RGMO PERFORMANCE : RGMO EVENT 11.06.2021 16:02 Hrs
STATE HYDRO THERMAL TOTAL
Possible Actual Possible Actual Possible Actual %
AP 0.00 0.00 106.56 25.46 106.56 25.46 24%
TG 0.00 0.00 117.13 40.10 117.13 40.10 34%
KAR 24.13 22.18 67.31 20.00 91.44 42.18 46%
KER 29.32 9.44 0.00 0.00 29.32 9.44 32%
TN 6.10 0.10 61.57 43.02 67.67 43.12 64%
CGS 0.00 0.00 450.69 220.61 450.69 220.61 49%
SR 59.55 31.72 803.26 349.19 862.81 380.91 44%
The following were noted:
(i) It was observed that being a less demand season, many units were out.
(ii) AP: Rayalseema Unit VI: (all other units out): no response.
Krishnapatanam: Unit I : Insufficient response. Unit II out.
Vijayawada: Units 5 & 6 : No response. All other units : Partial
response.
SRLDC desired to know from SLDC that whether in Rayalseema Unit
VI (new unit-600 MW) RGMO logic is enabled or not.
APGENCO informed that RGMO is in place, and due to very poor coal
quality response observed is very less. As per APGENCO data 3.95 %
response have been observed.
W.r.t Krishanapatanam (800), the power requirement is less and when
operated at 500 MW (sliding pressure zone) there is no margin for
RGMO response.
SRLDC expressing concern regarding the non response of APGENCO
units of higher capacity observed that in case of contingencies more
response is expected from these units. In the high penetration scenario
RGMO response takes a noticeable role. SRLDC requested
SLDC/APGENCO to take up with generators. It was suggested that each
generator may come up with the anlysis and the logic implemented may
also may be presented. Understanding of the logic may be gained.
(iii) NLCIL:
NLCIL I Expn: No response from both the units
Minutes of the 181st meeting of OCC (10.08.2021) Page 73 of 84
NLCIL II Expn: partial response
NLCIL TS II Stage II : Unit II & III no response.
(iv) NTPL: responded well (68 %)
(v) NTPC-Ramagundam: All 500 MW and above units responded well.
(vi) SEIL Phase I & II: responded only upto 30-36 %. SEIL informed that
they would analyze the response.
(vii) NTECL Vallur TPS: All units responded.
(viii) KPCL: Most of the units were out: BTPS: Unit III: 700 MW:
insufficient response : KPTCL informed that they will check up and
come back. KPTCL informed that they are also conducting meetings
with generators. Hydro units responded.
JSWL: responded.
(ix) TSGENCO: KTPS Unit VIII: 800 MW: less response: TSGENCO
informed that there is a need for correction in the logic which had
been taken up with OEM and would be rectified quickly.
KTPS Stage VI: 500 MW unit responded well
KTPP: one unit under RSD. Other unit: 500 MW 28 %. Was
operating at partial load.
Singareni units showed no response. Units were under partial load.
SRLDC informed that earlier also Singareni units were not
responded.
(x) TANGEDCO: All thermal units responded at an average level.
SRLDC informed that during testing at NLC base frequency was kept at
50.02 Hz instead of 50 Hz.
Conclusion:
a) By next OCC all generators may review the logic implemented in each
units. The logic implemented in NTPC, Ramagundam, Simhadri and
NTECL vallur etc had been shared to all in earlier Meeting minutes and
also it is available in SRLDC Operating Procedure also. All the
generators may take these as reference and the same may be
implemented in their units.
b) All the generators may present on the logic implemented at their units
and may examine whether modification is needed.
Minutes of the 181st meeting of OCC (10.08.2021) Page 74 of 84
c) SE(O), SRPC had informed that a separate Meeting for the analysis of
RGMO may be convened shortly as was the practice earlier.
d) SRLDC requested all the generators to furnish the response whenever
incident is posted and the consolidated response needed to be submitted
to CERC.
9. Automatic Demand Side Management Scheme (Petition No. 250/MP/2012)
& GSES (Petition No. 265/MP/2012)
(a) It was noted that all states had implemented revised ADMS logic. (Alarm at
49.90 Hz and below for 10 minutes, Trip at 49.85 Hz, Min DSM limit for
15 Minutes).
(b) ADMS feeders may also be mapped, for enhanced visualization and
analysis of ADMS operation. All states were requested to identify
additional feeders which could be tripped through SCADA rotationally with
load relief of (OD-Max dev limit). Any loads tripped under ADMS should
be brought back only under the directions of SLDC keeping in view the
frequency, overdrawal etc.
(c) It was noted that the States could support the ADMS relief (feeder tripping)
through SoE. Incidence can be validated accordingly.
(d) The following were noted in the 180th meeting of OCC:
(i) SRLDC had expressed concern that no states are giving updates on the
status of ADMS incidences. SRLDC had suggested that ADMS
feeders may be mapped to SCADA.
(ii) KPTCL had informed that feeders identified are more and individual
mapping is difficult and opined that as group mapping may be done on
area basis.
(iii) KSEBL had informed that ADMS scheme is covered under Innovative
Project funded through PSDF. Within two to three weeks scheme will
be taken over and commissioned. A separate server will be available
for ADMS and information can be fetched from this server. All the
information like initiation of ADMS tripping signal, list of feeders
tripped, quantum of relief etc would be available in the server. The
system will assure the required quantum of relief also. If at first
tripping required quantum of relief was not realized, system will
initiate another sequence of tripping. ADMS feeders are not mapped to
SCADA.
Minutes of the 181st meeting of OCC (10.08.2021) Page 75 of 84
(iv) ED, SRLDC had suggested that KSEBL may share these details to
other states. He requested all the states (AP, TS and TN) to take an
immediate initiative in this regard so that at least by this month end
area-wise monitoring is possible.
(v) APTRANSCO had informed that the analysis had made for the
incidences during the month of May 2021. With respect to incidences
during June 2021, analysis will be carried out and observations would
be furnished shortly.
(vi) KPTCL had informed that w.r.t KPTCL around 3000 feeders are
identified for ADMS tripping. DISCOM-wise relief may be obtained.
If in need feeder wise mapping also may be carried out.
(vii) AP, TS and TN would explore the possibility of mapping the ADMS
feeders to SCADA and the status may be updated to SRLDC/SRPC
within a month. In case feeder wise mapping is not possible, area
wise/DISCOM wise grouping may be done and monitored.
(viii) TSTRANSCO to furnish the list of feeders identified for ADMS
scheme at the earliest.
(ix) States are requested to extend the status points to SRLDC whenever
ADMS are acted.
(e) SRLDC vide E-mail dated 03.08.2021 (Annexure-9.e) had furnished the
ADMS incidences during July 2021. It was noted that there was total of 10
instances matched for ADMS tripping—(AP-5, TS & KAR- 2, TN-1).
(f) The following noted in the meeting:
a) APTRANSCO informed that during the incidents for June & July
2021(till 09.07.2021) there was no ADMS tripping observed in AP
system due to nonfunctioning of the logic. M/s GE had rectified the
issues and the logic had been enabled on 09.07.2021 and healthiness is
checked every day morning and evening. ADMS was acted for one
incident two days back (08.08.2021). And also mapping of feeders under
ADMS to SCADA is completed and visibility had checked on
04.08.2021. He informed that APTRANSCO vide communication dated
05.08.2021(Annexure-9.f) had submitted a report in this regard.
b) DE, TSTRANSCO informed that only 20 MW relief was obtained for
the incident on 06.07.2021. There were some configuration changes like
LILOing, radial to grid connected etc to the feeders identified for
Minutes of the 181st meeting of OCC (10.08.2021) Page 76 of 84
ADMS. Review had been carried out and new feeders have been
identified which is under management approval. As and when approval
is obtained, the same would be implemented and informed to
SRPC/SRLDC accordingly. SRLDC requested TSTRANSCO to furnish
the details of ADMS operation on 06.08.2021 which was agreed by
TSTRANSCO.
c) KPTCL informed that ADMS was acted for the two incidences in July
2021 and the details would be furnished today itself (10.08.2021)
d) TANTRANSCO informed the following regarding the ADMS operation
on 24.07.2021.
Group I acted time : 19.36 Hrs -Load relief :160MW
Group II acted time : 19.41 Hrs -Load relief :180MW
Group III acted time : 19.46 Hrs -Load relief :94MW
Total Load Relief :434 MW
e) SRLDC requested all the constituents to furnish the details of ADMS
operation for the previous month by 5th of current month.
f) W.r.t ADMS SCADA mapping KSEBL informed that ADMS scheme as
intimated in the 180th OCC meeting will be in place within two weeks.
TANTRANSCO informed that they have mapped the feeders to
SCADA. KPTCL informed that AGMS feeders had been mapped to
SLDC SCADA and the same needed to be extended to SRLDC.
Mapping of feeders on ESCOM wise is given priority and later on feeder
wise mapping would be taken up.
10. Grouping of loads (IEGC clause 5.4.2 (e))
Regulations in respect of Grouping of loads to be complied by all the concerned
utilities.
11. LVRT Implementation / Status review of Pending points as discussed in 4th
RE/LVRT meeting
Quarterly reports of the SR constituents jointly validated by SRLDC/SRPC
Secretariat are being communicated to Hon’ble CERC in this regard to monitor
the installation and performance of LVRT installed on existing WTGs as per
the directives of Hon’ble CERC.
SRPC noted that TANTRANSCO is not updating the information regarding the
SCADA Availability compared to the installed capacity. TANTRANSCO was
Minutes of the 181st meeting of OCC (10.08.2021) Page 77 of 84
requested to furnish the information at the earliest so that LVRT report may be
furnished to CERC incorporating the same.
All the States are requested to furnish the Quarterly Reports in the
specified time period.
12. Implementation of SAMAST by State Utilities
The following had been noted in the previous meetings of TCC/SRPC:
a) APTRANSCO had informed that sanction of grant from PSDF has been
received but funds were yet to be received. They were in the process of
preparation of software requirement specification for calling tenders.
b) KPTCL had informed that SAMAST project has been approved by PSDF
and 9 Cr has been sanctioned from PSDF. Tendering process is under
progress.
c) KSEBL had informed that they had submitted DPR (Rs 53 crores) to
NLDC for funding from PSDF and requested for expeditious approval of
the scheme.
d) TANTRANSCO had informed that out of 13 modules, 6 modules viz.
Scheduling, DSM, Metering, Grid Connectivity, Entity User Management
and RPO were completed/in progress. For remaining 7 modules
development work was completed and testing is in progress. It will be
implemented within two months.
e) TSTRANSCO had informed that SAMAST DPR (around Rs.50 Crores)
was submitted to the Techno Economic Committee of PSDF long back.
The DPR was revised multiple times. The amount was reduced to Rs. 45
Crores. It was understood that the number of meters would be restricted
for funding. TSTRANSCO would not be in a position to go ahead with
SAMAST implementation if funding for metering reduced.
f) The following noted in the meeting:
APTRANSCO: Hardware tendering is under process. Software
requirement also being prepared.
KPTCL: LOI has been issued.
KSEBL: Tendering for meters completed. Software part is in the final
stage. .
TANTRANSCO: Testing is under progress. Time frame of
implementation would be updated.
Minutes of the 181st meeting of OCC (10.08.2021) Page 78 of 84
TSTRANSCO: Single line diagrams for S/Ss and Generating stations
which would be submitted shortly. On a query to SE(O), SRPC
TSTRANSCO informed that earlier request was to furnish the Grid map
which was already submitted. NLDC is insisting on some undertaking
also. SE(O), SRPC clarified that all the requirement for PSDF funding/
clarification sought needed to be fulfilled by TSTRANSCO and requested
to expedite the action.
All the states are requested to furnish the status update on the
Implementation of SAMAST.
13. Automatic Generation Control (AGC) Central Sector implementation
(a) As per CERC Order dated 28.08.2019 all ISG stations whose Tariff is
determined or adopted by CERC should be AGC-enabled before 28th
February 2020.
(b) In the 9th Meeting of NPC, RPCs were requested to furnish the status
update of the implementation status on monthly basis.
(c) Status update as on 31.07.2021 is as below:
Entity Generator Status
NTPC Simhadri STPS Stage- II
(2 x 500 MW)
AGC implemented (18.11.2018)
Ramagundam STPS Stage- II
(4x500 MW)
Commissioned on 31.03.2021.
Simhadri STPS Stage- I
(2 x 500)
Simgadri STPS Stage-I units are kept in service
from evening 4 to 7 hours as advised by
NLDC(since last one week). The observations will
be sent to NLDC from Corporate office.
Ramagundam STPS Stage-I
(3x200 MW)
AGC implementation works would be taken
after the maintenance/ renovation works.
Talcher STPS ( 4 x 500)
NTECL Vallur TPS (3 x 500 MW) AGC is in place from 14.06.2021.
NLCIL TPS II (7 x 210 MW) By month end
TPS I Expn ( 2 x 210 MW) By month end. TPS II Expn ( 2 x 250 MW)
NNTPS (2 x 500 MW)
NTPL NTPL (2 x 500 MW) NTPL informed that AGC at NTPL is in
operation from 14.06.2021. Performance is
observed to be satisfactory.
NP-
Kunta
Solar in AP
AGC :5 blocks of 50 MW i.e. 5
x 50 = 250 MW
During the visit to NP Kunta on 06.08.2021 it
was told that material has come for
implementation. SRLDC agreed that they will
update the actual status from NLDC.
Minutes of the 181st meeting of OCC (10.08.2021) Page 79 of 84
14. AGC at state Level- Pilot Project identification & Implementation
Status update is as follows:
State Generator Status
Andhra
Pradesh
Krishnapatnam (2 x 800 MW) APTRANSCO vide
communication dated 05.08.2021
(Annexure-14 ) had informed that
implementation of AGC at
SDSTPS, Krishnapatnam is under
examination and pending with AP
& not pending in Hon’ble
APERC.After finalization at
management level in coordination
with generator M/s.APPDCL and
AP Disoms, the proposal will be
submitted to the Hon’ble APERC
for approval to implement the
AGC scheme at Krishnapatanam.
In addition to Krishnapatnam planning AGC at VTPS, RyTPP, Upper
Sileru& Lower Sileru.
Karnataka Sharavathy Generating Station (1035
MW)
Implementation of AGC Pilot
under USAID GTG Scheme
completed. Available MW for
AGC is 10 % of Live load up to
maximum of 100MW (10% 0f
1035 MW).
KPTCL informed that at
Sharavathi testing is over. In
coordination with KPCL the units
would be put under AGC
operation.
Varahi Under Ground Power House(4 x
115 MW)
Hardware & software deployment
and configuration completed (Nov
2020)Go-live pilot completed (Jan
2021).Available MW for AGC is
20% of live load upto maximum
of 80 MW as per the programme
planned.
KPTCL informed that at Varahi
testing is over. In
coordination with KPCL the units
would be put under AGC
operation.
Kerala Kuttiady Unit No. 5 (50MW) Operational
State Regulator has been
approached for putting AGC on
regular basis
Idukki Unit No.1 (130MW) AGC would be implemented once
Minutes of the 181st meeting of OCC (10.08.2021) Page 80 of 84
the Optical Fibre link from SLDC
to Idukki PH is established
Tamil Nadu North Chennai TPS Stage-II ( one unit
i.e. 1 x 600 MW) Software: Algorithm
developed and completed.
Hardware: Procurement under
progress by intend. Technical
suitability awaited and work
would be completed within
three months from the date of
PO.
MTPS - II (2 x 600 MW) Enquiry (OI no. 35/21-22)
floated for supply, erection and
commissioning of software,
hard ware and implementation
of AGC in MTPS II. Tender-
Techno Commercial bid- to be
opened on 17.08.2021.
Telangana KTPS- VI (500 MW)
Kothagudem E (132 MW) downward)
Placed the PO. Material delivery
expected by 06.05.2021.
15. Status of Implementation of the revised FGD Installation / ESP Up-
gradation Plan
(i) CEA/MoP is seeking updated information in respect of implementation of
revised FGD installation/ESP Up-gradation Plan and the regular updated
may kindly be furnished.
All the concerned to comply with norms, as per CPCB timelines and changes
thereof since the activity is monitored by Hon’ble Supreme Court /
Government.
16. PSP- daily Demand and Consumption pattern
CEA had sought daily Demand and Consumption pattern and the reasons for
significant variations w.r.t last year and past few days. The format in this regard
has been communicated to States and SRLDC by mail dated 21.04.2020 by
SRPC.
All the states were requested to furnish the information on regular basis.
17. Category-wise Consumption Pattern
CEA vide E-mail dated 17.03.2020 had sought category-wise consumption of
electricity in the States/UTs. RPCs had been requested to discuss/collect the data
in OCC meetings on a regular basis in the prescribed format.
Minutes of the 181st meeting of OCC (10.08.2021) Page 81 of 84
The status of data furnished is as below:
APTRANSCO May 2021
TSTRANSCO May 2021
KPTCL May 2021
KSEBL May 2021
TANTRANSCO May 2021
Puducherry March 2021
SRPC requested Puducherry to submit the information in soft copy including
previous month and current month.
All the states were requested to furnish the information on regular basis
18. Emergency Restoration System (ERS)
Transmission
Utility
Requirement
as per MoP
Existing Status/Remarks as noted in
180th OCC
APTRANSCO 3 2 APTRANSCO informed that *
* against the suggested quantity of 3 sets of ERS in the state by MoP, 2 sets of ERS infra
structure consisting of 20 Nos towers were procured by AP and placed at three different
locations, 3 nos in Srikakulam, 7 nos in Visakhapatanam and 10 Nos in Nellore coastal
districts to meet the exigencies in case of natural calamities for restoration in the existing
transmission network. No other ERS System is under procurement.
KPTCL 2 2
KSEBL 1 0 KSEBL had informed that #
# because of ROW issues ERS may not be useful in Kerala which was the opinion arrived in
the pre-bid meeting. KSEBL had informed that they have taken up the issue with
Transmission wing and a communication from Transmission wing would be arranged to
SRPC in this regard. In the 181st OCC Meeting they will take up and will arrange the
communication. It was emphasized that the information needed to be put up to SRPC/TCC
forums.
TANTRANSCO 2 0
TANTRANSCO informed that PO
had been issued. Supply of material is
awaited.
TSTRANSCO 1 0 TSTRANSCO informed that
prequalification meeting is being on.
Technical evaluation would be carried
out next week and works are under
progress.
PED Nil Nil
PGCIL 4 4 SR-I & SR- II Two Nos. Each
All the states were requested to furnish the updates on monthly basis. The
same would be put up to TCC/SRPC forum.
Minutes of the 181st meeting of OCC (10.08.2021) Page 82 of 84
19. REMC Project under SR SLDCs
The following were noted in the 180th OCC Meeting:
(i) TSTRANSCO informed that SAT is under progress. Few issues had been
cropped up, the issues pointed out had been taken up with PGCIL & ABB
and works are going on.
(ii) APTRANSCO vide communication dated 05.08.2021(Annexure-19.ii)
had informed that AP has opened a separate Bank Account and requested
M/s.PGCIL to intimate the prescribed formats in which the Contractor’s
bills are to be submitted (along with other relevant information if any to
be submitted by AP) for release of REMC grant from Ministry of Power
(MoP) through M/s.PGCIL to the said Bank Account.
SRLDC informed that the status would be updated shortly.
20. Compliance of CEA Regulations for Grid connectivity of RE Sources
The updated status on RE SCADA availability as noted in the 181st Meeting of
OCC is at Annexure-20
All the states are requested to update the status to SRPC on monthly basis.
21. Black Start Procedure
a. Point to point mock exercise for black start to be carried out by all
constituents.
b. Mock drills conducted in June 2021 are to be furnished.
c. Mock drills scheduled for August 2021&September 2021 to December 2021
were to be furnished.
In the 180th Meeting of OCC, SRLDC had informed that they had shared a
Google Sheet to fill the details regarding the schedule for Mock Drills. Entities
may update in the same.
In the Meeting, SRLDC informed that except AP & TS, all other states needed
to update the Google spread sheet.
22. Bus Bar Protection (BBP) scheme at 400/ 220 kV Kalapaka Substation.
(i) APTRANSCO vide letter dated 02nd August 2021 (Annexure-22.i) had
requested for approval to keep 400kV bus bar out of service till
commissioning new M/s Siemens numerical bus bar scheme at 400/220 kV
Kalapaka substation as a part of Retrofitting works in place of existing old
M/s ABB make RADSS static 400kV Bus bar protection scheme.
Minutes of the 181st meeting of OCC (10.08.2021) Page 83 of 84
(ii) In the meeting, APTRANSCO requested to BBP at 400 kV Kalpaka S/S
out of service for two months to undertake replacement works of the
existing BB Protection with Numerical BBP
(iii) After deliberation, OCC agreed to keep out of service BBP at 400/220 kV
Kalpaka S/S to undertake replacement works of the existing BB Protection
with Numerical BBP.
23. Items for Information:
(i) CEA has issued the minutes of the 10th Meeting of NPC held on 09.04.2021
(Annexure-23.i).
(ii) Member (GO&D), CEA has taken a Meeting on 29.07.2021 with SLDCs of
AP & TN on RE curtailment. He had expressed concern regarding
curtailment of RE and advised for compliance of IEGC Clause 5.2u strictly
by all the entities.
(iii) CEA vide E-mail dated 28.07.2021 had requested all RPCs to inform the
states/ utilities to comply with the MoP orders dated 2nd July 2020 and
18th November 2020 (Annexure-23.iii) regarding Testing of Equipment,
components and parts imported for use in the Power Supply system and
network in the country to check for any kind of embedded malware/trojans
/cyber threat and for adherence to Indian standards.
(iv) Central Transmission Utility of India Limited (CTUIL) vide letter dated 01st
July 2021 has intimated that CERC vide Record of Proceeding (date of
hearing: 25.06.2021) in Petition No.200/MP/2019 has directed CTU to
coordinate with Secretariat of SRPC to hold the RPC meeting within 15
days from the date of issuance of Record of Proceeding to discuss the
developments and implementation of the transmission scheme in phase-
wise manner with the constituents of Southern Region. CTU has also been
directed to file the minutes of the meeting within a week thereafter.
Accordingly, a Special SRPC meeting was convened on 14.07.2021 to
deliberate Transmission scheme for integration and evacuation of 18.5 GW
REZ. The Minutes of the meeting is available at SRPC website.
(v) CEA had communicated regarding the Chinese Machine Vision (MV) and
expanding Chinese CCTV footprints in India. It is requested that the
comments may kindly be furnished to CEA at the earliest.
Minutes of the 181st meeting of OCC (10.08.2021) Page 84 of 84
24. Grid Highlights July 2021
(i) Frequency remained within IEGC range during July 2021 (49.90 - 50.05
Hz) for 75.54 % of time. Average frequency for the month was 50.00 Hz.
(ii) Frequency remained below 49.90 Hz for 5.18 % of time during July 2021.
(iii) Frequency remained above 50.05 Hz for 19.28% of time during July 2021.
(iv) 2 MW of Solar energy commissioned by M/s Garrison Engineer (M/s
Military Engineer service), INS Kalinga (Navy) Bheemunipatnam (M),
Visakhapatnam District on 19.06.2021(APTRANSCO).
(v) 1 MW of Solar energy commissioned by Kanti Brothers oils Pvt. Limited,
Kallur, Kurnool District on 31.07.2021( APTRANSCO).
(vi) 2 MW of Solar energy commissioned by Kanti Brothers oils Pvt. Limited,
Kallur, Kurnool District on 31.07.2021(APTRANSCO).
25. Conclusion:
Member Secretary I/c, SRPC thanked all the officials participated in the
deliberation. He requested all the members to comply with the
decisions/recommendations arrived in the Meeting. He observed that the inputs
received in this meeting would be helpful for the ensuing TCC/ SRPC meetings.
26. 182nd Meeting of OCC
The 182nd Meeting of OCC would be conducted on 09th September 2021
(Thursday) through Video Conferencing (VC).
****