Copyright © 2014 Anago Copyright © 2014 Anago
Resource Management in an inspection
organisation
29 April 2014 14.30-15.15
Copyright © 2014 Anago Copyright © 2014 Anago
Contents
Copyright © 2014 Anago Copyright © 2014 Anago
Lots of different planning questions
How much projects
are we planning to
do next year?
Which projects are
best suited for the
available capacity?
How much time per
skill do the projects
demand next
period?
In which order will
mr. Jones do his
tasks?
Which activity will
mr. Jones do
tomorrow?
Who is going to
work on what
project?
Which projects will
get capacity next
month?
Which deadline is
realisatic for my
project?
Which employee is
on holiday next
month?
Do we have to hire
extra employees?
And if yes, how
many?
How much FTE do
we have available for
next year?
Copyright © 2014 Anago Copyright © 2014 Anago
Levels of planning
Operational planning
(Mid Term Planning)
Tactical planning
(Long Term Planning)
1-6 months
1 year
1-4 weeks
Assign employees
to workload
Capacity check
Execution
Positioning Strategic planning
Copyright © 2014 Anago Copyright © 2014 Anago
Different questions on different levels
Strategic Tactical Operational
Years Year 0 Months
Month 6 M 3 Year n Month 0 M 1 Year 1
Demand for
capacity
Capacity
availability
Demand and
availability
matching
How much
projects are we
planning to do
next year?
Which projects are
best suited for the
available capacity?
How much time
per skill do the
projects
demand next
period? In which order
will mr. Jones do
his tasks?
Which activity
will mr. Jones
do tomorrow?
Who is going to
work on what
project?
Which
projects will
get capacity
next month?
Which
deadline is
realisatic for
my project?
Which employee
is on holiday
next month?
Do we have to
hire employees?
And if so, how
many?
How much FTE do
we have available
for next year?
Copyright © 2014 Anago Copyright © 2014 Anago
Planning on different levels
Strategic Tactical Operational
Years Year 0 Months
Month 6 M 3 Year n Month 0 M 1 Year 1
Demand for
capacity
Capacity
availability
Demand and
availability
matching
Hours / products / services
Fixed FTE
Fixed FTE vs Demand
products / services / service
level management
Fixed FTE per skill / Skill
management
Fixed FTE per skill
Assign capacity to demand
projects / activities
Contract hours per skill / Flex
workers
Rostering / Project- and
activity scheduling
Copyright © 2014 Anago Copyright © 2014 Anago
Planning on different levels
Strategic Tactical Operational
Years Year 0 Months
Month 6 M 3 Year n Month 0 M 1 Year 1
Demand for
capacity
Capacity
availability
Demand and
availability
matching
Hours / products / services
Fixed FTE
Fixed FTE vs Demand
products / services / service
level management
Fixed FTE per skill / Skill
management
Fixed FTE per skill
Assign capacity to demand
projects / activities
Contract hours per skill / Flex
workers
Rostering / Project- and
activity scheduling
Problems arise here…
Copyright © 2014 Anago Copyright © 2014 Anago
Planning on different levels
Strategic Tactical Operational
Years Year 0 Months
Month 6 M 3 Year n Month 0 M 1 Year 1
Demand for
capacity
Capacity
availability
Demand and
availability
matching
Hours / products / services
Fixed FTE
Fixed FTE vs Demand
products / services / service
level management
Fixed FTE per skill / Skill
management
Fixed FTE per skill
Assign capacity to demand
projects / activities
Contract hours per skill / Flex
workers
Rostering / Project- and
activity scheduling
Solutions are often
found in operational
scheduling tools
Copyright © 2014 Anago Copyright © 2014 Anago
Planning on different levels
Strategic Tactical Operational
Years Year 0 Months
Month 6 M 3 Year n Month 0 M 1 Year 1
Demand for
capacity
Capacity
availability
Demand and
availability
matching
Hours / products / services
Fixed FTE
Fixed FTE vs Demand
products / services / service
level management
Fixed FTE per skill / Skill
management
Fixed FTE per skill
Assign capacity to demand
projects / activities
Contract hours per skill / Flex
workers
Rostering / Project- and
activity scheduling
But the problem
already started at
tactical level…
Copyright © 2014 Anago
On tactical level most companies use
spreadsheets
Copyright © 2014 Anago
On tactical level most companies use
spreadsheets
Because…
• Excel supports own planning
methods
• Excel can easily be adapted
• Excel is available at every
workstation
Copyright © 2014 Anago
Customer Case
Resource Management in an inspection
organisation
Copyright © 2014 Anago
Resource Management in an inspection
organisation
• Inspection Organisation
• Mid Term Capacity Planning: 1 month – 1 year
• Facts: • 50 projects • 200 employees
• 15 regions
Copyright © 2014 Anago
Resource Management in an inspection
organisation
Copyright © 2014 Anago Copyright © 2014 Anago
Bottlenecks spreadsheets
• High risk of errors
• Many manual actions
• No multi-user support
• No authorisation or audit trail
• Connections to other systems is
difficult
• No smart assignment possible • …
Copyright © 2014 Anago
General problem
Balance supply
&Demand
Assignment employee to project
Gross Availability
Overhead tasks
Division Active/Reactive work
Available capacityYear planning Demand planning
Copyright © 2014 Anago
Assignment constraints
• Demand per project per period should be met
• Employees should not be over booked
• Only employees with the right skill can be assigned
• Some employees are required on a project (e.g. project
leader)
• Assignment should be sufficiëntly large
• Some projects require a minimum number of
employees
• Projects require an even spread across the regions
Copyright © 2014 Anago
But also ‘soft’ constraints
• Some employees like to be assigned to a specific
project (personal preferences)
• Some projects can be bundled (i.e. an employee can
work on these projects in the same period)
• Demand can be shifted over time
Copyright © 2014 Anago
LP optimal solution
• Minimalize shortage in demand
• While:
• Assignment < availability
• Employee has skill of project
• Assignment > minimal assignment
• For 70 employees, 20 projects and 4
periods this already takes 30 minutes
Copyright © 2014 Anago
Approach
• Quick Assignment algorithm
• Manual assignment possible
• ‘Freeze’ project assignments
• ‘Freeze’ employee assignments
• Re-run assignment
Copyright © 2014 Anago
Loop over project
Select employees of region with availiability >0
Loop over period
Select months that start this period
While Demand >0
Loop over region
Sort projects based on available employees
Sort employee on previous assignment & number of
skills
Then: Assign employee for availibility
If demand > availability AND demand > MinAssign
Then: transfer demand to next period
If demand next period >0
Else: Distribute demand over assigned employees
Assign required employees
Algoritm
Copyright © 2014 Anago
Results
• Assignment runs in 5 seconds
• Planner can easily assign employees
manually and then re-run assignment
• All team leaders can view actual planning
• 99,3% automatically planned
Copyright © 2014 Anago
Demo
Copyright © 2014 Anago Copyright © 2014 Anago
Questions
Copyright © 2014 Anago Copyright © 2014 Anago