24
Quantitative Risk Analysis in Industry Roger Garrini Selex ES Ltd

QRA in industry - Roger Garrini

Embed Size (px)

Citation preview

Page 1: QRA in industry - Roger Garrini

Quantitative Risk Analysis in Industry

Roger Garrini Selex ES Ltd

Page 2: QRA in industry - Roger Garrini

2 © 2016 Selex ES Ltd – All rights reserved

Roger Garrini

• Started working life as a planner for AI Radar in 1976

• Project Manager for non-core radar work

– Cars, Laser Radar TDP, Space studies

• 1997 Moved to EW Division as a Project Manager

• 1998 Responsible for introducing new planning tools and PM processes ( EVM)

• 2004/5 Introduced Professional Risk tool

• 2012 Finmeccanica Faculty - Risk Management SME

• Currently UK IPR Manager

Introduction

Page 3: QRA in industry - Roger Garrini

3 © 2016 Selex ES Ltd – All rights reserved

• Support to Bids

• Support to Contracts

• Special Cases

Summary

Summary

Page 4: QRA in industry - Roger Garrini

© Copyright Selex ES Ltd 2016 All rights reserved

Bids

Page 5: QRA in industry - Roger Garrini

5 © 2016 Selex ES Ltd – All rights reserved

Risk on Bids

• Calculate the Project Risk Factor

• Low values may mean no analysis is required

• Project brainstorms the risks

• Often just causes are noted down and worries

• Sometimes there is a schedule

• Think about opportunities

• Scratch them into a tool

• Usually a mixture of spreadsheets, direct entry and some who don’t want to

• Cost focus

• Run the analysis

• Done!

Bids

Page 6: QRA in industry - Roger Garrini

6 © 2016 Selex ES Ltd – All rights reserved

Here is the Answer! Or is it?

Page 7: QRA in industry - Roger Garrini

7 © 2016 Selex ES Ltd – All rights reserved

Garbage in, Gospel Out?

• Produced an answer

• ...............................but usually fail the review

• Check it Out

• Listen to the risk bloke

• Review the risks

– Schedule data

• Who did the Estimates?

• Are there realistic plans for recovery? Or just a number!

• Are the risks focussed on/attached to deliverables and Events in the programme?

• Mitigation plans in place?

• Risk adjusted schedule or not?

Page 8: QRA in industry - Roger Garrini

8 © 2016 Selex ES Ltd – All rights reserved

Here is the Answer! Or is it?

• Smart Reviewer Questions • How Many Iterations?

• Spiky? • Look out for dinosaurs

• It says Residual? • Or Pretend?

• How Big is the Gap to Current

• How much is the mitigation going to cost

• Most Likely answer about 250 days?

• Calendar or Working time?

• Long Tail?

Page 9: QRA in industry - Roger Garrini

9 © 2016 Selex ES Ltd – All rights reserved

A Cost Risk Distribution

• 5000 Iterations, not too spiky, may be

stable • Eyes Glaze Over

• Most Likely around £100K • Too little, too much

• Long Tail?

Page 10: QRA in industry - Roger Garrini

10 © 2016 Selex ES Ltd – All rights reserved

Start again

• Derive a deliverable based schedule on a page • Logic or requirement

• It can be a big page

• What is our estimating error?

• Now try and add the risks to the schedule • Where do I put the risks?

• Is this really a risk?

• …………………… or what we’re supposed to do?

• What really is the impact ? The repair time and cost?

Bids

Page 11: QRA in industry - Roger Garrini

11 © 2016 Selex ES Ltd – All rights reserved

Gantt

• First pass shows plan for failure?

• Residual or Current?

• Risk Optimised Schedule or Original? • Or just the requirement

• Where did the Durations come from?

• Updated with Progress or the Original?

• Progress on Schedule or not

• Have the risks been updated in PRC

Page 12: QRA in industry - Roger Garrini

12 © 2016 Selex ES Ltd – All rights reserved

More Garbage in, Gospel Out?

• Why is the Risk Analysis showing 250 days delay

• And the Gantt shows 2-3 weeks

• Float!

• Total Float or Free Float?

• There is a strong case for ensuring that the schedule is risk adjusted and includes enough float

• Criticality and Cruciality help

• So is the Schedule Risk Adjusted?

• Do we care about the answer from the Gantt

• Or does this show we can meet the deadline after all

• 3 weeks delay may be ok if the we aimed to be early

Page 13: QRA in industry - Roger Garrini

13 © 2016 Selex ES Ltd – All rights reserved

So Gospel In?

• Analysis of Schedule Risk picture is a process of

work and you need to know where you are

• Original derived from logic

• Compatible with Bottom-up plans

• Has the Risk model been Adjusted for Risk and

Uncertainty

Page 14: QRA in industry - Roger Garrini

14 © 2016 Selex ES Ltd – All rights reserved

Current and residual shown together

• Pattern very different for

each

• Shows Mitigation must be

done • Must afford it

• Some Low Probability high

Impact risks – the tail

• Where are we in the

process?

Page 15: QRA in industry - Roger Garrini

15 © 2016 Selex ES Ltd – All rights reserved

Contingency

• Do you feel Lucky?

• What is the answer?

• It Depends!!

• Feel lucky and must win, Little or no

contingency – low confidence, high risk

• Not price sensitive, or feel unlucky high

contingency – high confidence

• The choice is yours

• But…

Page 16: QRA in industry - Roger Garrini

© Copyright Selex ES Ltd 2016 All rights reserved

Contracts

Page 17: QRA in industry - Roger Garrini

17 © 2016 Selex ES Ltd – All rights reserved

Progress Reviews

At least quarterly

• Update the risks (should be done monthly)

• Adjust the schedule if needed

• Update progress against the schedule model

• Run the cost analysis against both Current and Residual

• Run the schedule analysis

• Risk and Contingency

• Are we where we think we should be?

• Explain the surprises in a calm way!

• Progress on mitigation is key and is the controllable variable

Contracts

Page 18: QRA in industry - Roger Garrini

© Copyright Selex ES Ltd 2016 All rights reserved

Special Cases

Page 19: QRA in industry - Roger Garrini

19 © 2016 Selex ES Ltd – All rights reserved

Scenario

• Sub sub-contractor on a major aircraft programme

• Some slip meant the sub contractor declared we were the critical item

• Prime declared we would cause slip of the aircraft integration programme!

• Director promised a schedule risk analysis

Special Cases

Page 20: QRA in industry - Roger Garrini

20 © 2016 Selex ES Ltd – All rights reserved

What did we do?

• Created a detailed schedule for the three months left in the programme

• Produced a list of risks

• Some surprises

• Main risk - Acceptance based on Prime customer supplied test equipment

Only one, replacement lead time, 1 year

• Customer demanded 60 day approval lead time from the last documents prior to ATP

• Schedule Analysis

• One month late without risk –

Critical path documentation

• 14 months late with the risks

Page 21: QRA in industry - Roger Garrini

21 © 2016 Selex ES Ltd – All rights reserved

Next Step

• A grown-up conversation!!

• Finger pointing stopped , all worked to solve the problem

• Prime accepted the risk regarding test equipment

• Parallel approval of documents implemented

• Deletion of 60 day requirement

• Revised schedule and risk

• New Analysis showed completion– most likely now on time

Special Cases

Page 22: QRA in industry - Roger Garrini

22 © 2016 Selex ES Ltd – All rights reserved

Result

• Engineering team completed to best case

• Delivered early!

• Started time based support contract early

• Main programme delayed by some months by Prime not due to us!

Special Cases

Page 23: QRA in industry - Roger Garrini

THANK YOU FOR YOUR ATTENTION

Selex ES Ltd

Sigma House - Christopher Martin Road, Basildon

Essex SS14 3EL

Tel: +44 (0) 1268 823400 www.selex-es.com

Roger Garrini

Page 24: QRA in industry - Roger Garrini

This presentation was delivered

at an APM event

To find out more about

upcoming events please visit our

website www.apm.org.uk/events