“OYU TOLGOI” PROJECT

03.09.2014 Oyu Tolgoi Project, Erdenes Oyu Tolgoi

Embed Size (px)

Citation preview

Page 1: 03.09.2014 Oyu Tolgoi Project, Erdenes Oyu Tolgoi

“OYU TOLGOI” PROJECT

Page 2: 03.09.2014 Oyu Tolgoi Project, Erdenes Oyu Tolgoi

Oyu Tolgoi Ownership Structure

Other shareholders

Shareholders meeting

THR Oyu Tolgoi Oyu Tolgoi Netherlands

B.V.

Board of Directors

~49% ~51%

34% ~0,2% ~65,8%

Government of Mongolia

(formerly Ivanhoe Mines)

Page 3: 03.09.2014 Oyu Tolgoi Project, Erdenes Oyu Tolgoi

OYU TOLGOI MANAGEMENT

1. GANBOLD Davaadorj

Chief Executive Officer,

Erdenes Oyu Tolgoi LLC

2. OTGOCHULUU Chuluuntseren

Director General,

Department of strategic policy and planning

at Ministry of Mining, Mongolia

3. TEMUULEN Ganzorig

1. Jean-Sébastien Jacques

Chief Executive, Rio Tinto's Copper group

2. Batsukh Galsan

Chairman, Oyu Tolgoi Board of Directors

3. Rowena Albones

Chief Financial Officer, Rio Tinto’s Copper group

6. Craig Kinnell

Chief Executive Officer, Oyu Tolgoi LLC

5. Chris Bateman

Chief Financial Officer, Turquoise Hill Resources

4. Kay Priestly

Chief Executive Officer, Turquoise Hill Resources

Members of the Board of Directors 34% 66%

GoM

Mongolian shareholder

Page 4: 03.09.2014 Oyu Tolgoi Project, Erdenes Oyu Tolgoi

Oyu Tolgoi is situated in the southern Gobi region of Mongolia, approximately 550 kilometers south of the capital, Ulaanbaatar.

Page 5: 03.09.2014 Oyu Tolgoi Project, Erdenes Oyu Tolgoi

Oyu Tolgoi deposit (Umnugovi province), is situated approximately 80 kilometers north of Chinese border, the biggest consumer of copper.

Page 6: 03.09.2014 Oyu Tolgoi Project, Erdenes Oyu Tolgoi

OYU TOLGOI EXPLORATION CAMPS

Exploration camp (April,

1997)

1997 оны 9-р

сар IMMI, 2001

IMMI, 2004 Construction camp, 2007

Exploration camp (September, 1997)

Page 7: 03.09.2014 Oyu Tolgoi Project, Erdenes Oyu Tolgoi

CROSS-SECTION, OYU TOLGOI DEPOSIT

Page 8: 03.09.2014 Oyu Tolgoi Project, Erdenes Oyu Tolgoi

December 27, 2012 Oyu Tolgoi’s concentrator plant with approximate capacity of 100,000 tonnes of ore processed per day, was turned on.

OYU TOLGOI TIMELINE

Page 9: 03.09.2014 Oyu Tolgoi Project, Erdenes Oyu Tolgoi

December 27, 2012 Started processing open pit ore through the Concentrator.

OYU TOLGOI TIMELINE

Page 10: 03.09.2014 Oyu Tolgoi Project, Erdenes Oyu Tolgoi

January, 2013 First copper concentrate was produced.

OYU TOLGOI TIMELINE

Page 11: 03.09.2014 Oyu Tolgoi Project, Erdenes Oyu Tolgoi

July 9, 2013 Commencement of first shipment from the mine site.

OYU TOLGOI TIMELINE

Page 12: 03.09.2014 Oyu Tolgoi Project, Erdenes Oyu Tolgoi

Financials

№ Unit 2013

Actual

2014

Plan

YTD June

2014

1 Gross Revenue $ m 83.7 2,653.3 644.4

2 Total Expenditure $ m 1,499.3 1,249.8 467.0

Year-to-date, Oyu Tolgoi project’s tax and other payments totaled approximately $920m.

Page 13: 03.09.2014 Oyu Tolgoi Project, Erdenes Oyu Tolgoi

Concentrator

№ Unit 2013

Actual 2014 Plan YTD June 2014

1 Milled ore mt 20.3 33.9 13.3

2 Concentrate produced kt DMT 290.0 692.3 242.9

3 Concentrate content

Cu % 26.4 25.3 25.3

Au g/t 16.8 34.6 22.9

Ag g/t 52.4 59.2 50.1

4 Metal produced

Cu kt 76.7 175.1 61.5

Au koz 157.0 771.1 178.6

t 4.9 24.0 5.6

Ag

koz 488.8 1,317.8 391.4

t 15.2 41.0 12.2

Page 14: 03.09.2014 Oyu Tolgoi Project, Erdenes Oyu Tolgoi

Logistics and Sales

№ Unit 2013

Actual

2014

Plan

YTD June

2014

1 Shipments DMT (kt) 74.9 883.0 276.2

2 Customer collection DMT (kt) 23.6 860.1 252.5

The expected shipments and customer collection is over 900,000 tonnes of copper concentrate, above plan.

Page 15: 03.09.2014 Oyu Tolgoi Project, Erdenes Oyu Tolgoi

OYU TOLGOI’S WORKFORCE (as of June 2014)

Mongolian national workforce ratio is 94%

94%

6%

OT's total workforce /3022/

Nationals /2834/

Expat /188/

Page 16: 03.09.2014 Oyu Tolgoi Project, Erdenes Oyu Tolgoi

THANK YOU FOR YOUR ATTENTION