Shutdown Summer 104-week
Who
Main InjectorDuration
Mike Frett/John Featherstone Remove Sand From MI40 penetrations Install when finished (PLUS) 4wJohn Featherstone/Mike FrettRauchmiller MichaelMoore Jack ( CT)Zolli Tim (CT)Johnson SeanMain Injector Corrosion repair (beam tubes) 4d-6dJohn Featherstone/Mike FrettBurk DaveCampbell MattChlebek MarkFolkie Jim
Who
Tevatron Duration
Scott McCormick
Warm A3 (PLUS) 4w
Scott McCormick
Dymond Bill
Williams James
Aponte, Sabina
Lambert Dan (ct)
Plant Derek
Greskoviak Jason
Warm Straights (PLUS) 4w
Scott McCormick
Sylejmani Sali
Jones Robert
Stone Brent
Who
P-Bar Duration
Henry Gusler
New gauges and leak check Ln2 rough vacuum 2d
Henry Gusler
Crabtree Phil
Shaffer Earl
Sellberg Greg
Rehose SMA Magnets 2w
Kelly Doug
Samayavong Inpeng
Sorenson Steve
WhoDave Augustine (ALL)•Ext: 4451•Pager (630) 905-5081•augustine@fnal.gov
John Featherstone (MI)•Ext: 5605•Pager (630) 266-5457•feather@fnal.gov
* Taking over for Merill Albertus
Scott McCormick (Tev)•Ext: 3691•Pager (630) 722-6795•smc@fnal.gov
Mike Frett*(MI)•Ext: 4663•Pager (630) 722-1057•mfrett@fnal.gov
Henry Gusler•Ext: 2675•Pager (630) 722-5209•smc@fnal.gov
Oliver Kiemschies (TD)•Ext: 3925•Cell (630) 364-6533•ollie@fnal.gov
What
MI (Team 1) (~4 weeks)• Install lead blankets at MI40 kickers• Leak check flourinert side of MI40 kickers • Remove Sand from MI40 penetrations; install when finished • Install shield Wall 307 • Remove lead blankets from MI40 kickers
MI (Team 2) (4-6 days)• Corrosion repair; Replace beam tube clamps on the MI Beam tube
ring wide. Some areas will be hot. Buff off any rust on beam tube
WhatPBar (Team 1)• New Gauges and Leak Check LN2 rough vacuum (2 days)
Pbar (Team 2)• Rehose SMA Magnets (~2 weeks)
Tev• Talk to Scott• A1 warm up and repair cold leaks, F1 warm up only if time allows. E0: Install
V-Goniometer, repair leaky bellows and install Pixel detector. E11- replace flying wire, E17 replace flying wire, B48 install e-cloud detector, A0 TEL2 install new beam screen and F sector has 2 turbo 151 installations
Where
•Usually keys are given out in MCR (Tev may get from Scott early)•There WILL be permanent shutdown keys (i.e. keys that you don’t have to turn in at the end of the day) for most•You will be given a card by a task master with which to get a key with.
Location of the MCR
Layout of MCR
<- Keys
<- TeV LOTO
MI & Booster LOTO ->
<- NuMI LOTO
Usually RWP’s are next where keys are.At the beginning of this shutdown, the RWP’s will be in the room next to the MCR, along with RSO’s
LOTO
When
• Day 0 (Sunday, July 18th) Tev – We are setting up a meeting with Scott McCormick Thursday or Friday to work out details
• Day 1 (Monday, July 19th) Everyone Else. No access until 8am• Some people may be shuffled as jobs complete
Why
• We will try to have separate job & task numbers for tunnel jobs
(http://tdserver1/project/jobfiles/Current_Jobs/TD_work_for_AD/refmenu.htm)
• AD Pays for OT (see me for the task number)• Still working on approval process (doesn’t sound like
you’ll have to “hand” a sheet to anyone though)
Good Luck!
Stay Safe!