Farm to Market Road
Development Program
DA-12 6th Round
ULAT SA BAYAN
CY 2012 Accomplishment Report
Province Allocation Length%
AccompRemarks
Cotabato 42,485,502.00 11.53 65%3 proj. completed / 3 sites on going
Sultan Kudarat
22,500,000.00 6.50 61%2 proj. completed / 3 still on going
South Cotabato
38,100,000.00 6.77 38%1 completed/ 3 on going / 2 for implementation
Sarangani 20,000,000.00 5.45 33% 2 proj. on going
TOTAL 123,085,502.00 30.25 49%
Basak Bululawan FMR, Lebak SK
New Egaña to Barangay Proper, D’lotilla, Isulan, SK
Sta. Theresita FMR, Calean, Tacurong City
Polomolok to Sitio Marang FMR, Columbio, SK
Cabuling RCBC, Banga, So. Cot
Haliland Slab Bridge connecting
Maculan FMR, Lake Sebu, so. Cot
CY 2013
PROVINCE ALLOCATION %AGE SHARENORTH COTABATO 116,019,074.00 37%SULTAN KUDARAT 76,457,800.00 24%SOUTH COTABATO 59,000,000.00 19%SARANGANI 45,650,000.00 14%COTABATO CITY 18,000,000.00 5.71%TOTAL 315,126,874.00 100%
CY 2013
PROVINCE REGULAR BUB SPF PAMANA
NORTH COTABATO 39,000,000.00 47,419,074.00 8,600,000.00 21,000,000.00
SULTAN KUDARAT 37,100,000.00 37,357,800.00 2,000,000.00 -
SOUTH COTABATO 59,000,000.00 - - -
SARANGANI 31,900,000.00 10,750,000.00 3,000,000.00 -
COTABATO CITY 8,000,000.00 10,000,000.00 -
TOTAL 175,000,000.00 105,526,874.00 13,600,000.00 21,000,000.00