Farm to Market Road

Development Program

DA-12 6th Round

ULAT SA BAYAN

CY 2012 Accomplishment Report

Province Allocation Length%

AccompRemarks

Cotabato 42,485,502.00 11.53 65%3 proj. completed / 3 sites on going

Sultan Kudarat

22,500,000.00 6.50 61%2 proj. completed / 3 still on going

South Cotabato

38,100,000.00 6.77 38%1 completed/ 3 on going / 2 for implementation

Sarangani 20,000,000.00 5.45 33% 2 proj. on going

TOTAL 123,085,502.00 30.25 49%

Basak Bululawan FMR, Lebak SK

New Egaña to Barangay Proper, D’lotilla, Isulan, SK

Sta. Theresita FMR, Calean, Tacurong City

Polomolok to Sitio Marang FMR, Columbio, SK

Cabuling RCBC, Banga, So. Cot

Haliland Slab Bridge connecting

Maculan FMR, Lake Sebu, so. Cot

CY 2013

PROVINCE ALLOCATION %AGE SHARENORTH COTABATO 116,019,074.00 37%SULTAN KUDARAT 76,457,800.00 24%SOUTH COTABATO 59,000,000.00 19%SARANGANI 45,650,000.00 14%COTABATO CITY 18,000,000.00 5.71%TOTAL 315,126,874.00 100%

CY 2013

PROVINCE REGULAR BUB SPF PAMANA

NORTH COTABATO 39,000,000.00 47,419,074.00 8,600,000.00 21,000,000.00

SULTAN KUDARAT 37,100,000.00 37,357,800.00 2,000,000.00 -

SOUTH COTABATO 59,000,000.00 - - -

SARANGANI 31,900,000.00 10,750,000.00 3,000,000.00 -

COTABATO CITY 8,000,000.00 10,000,000.00 -

TOTAL 175,000,000.00 105,526,874.00 13,600,000.00 21,000,000.00