Expo Light Rail Line

Expo Line Project Westside/Central Metro Service Council

November 2014

Expo Light Rail Line

6.6 mile corridor

7 new Stations

64,000 Daily Riders by 2030

Estimated Travel Time (Downtown LA to Santa Monica): 46 minutes

Estimated Cost: $1.5 billion

Final design in now complete

Project is 75% complete

Major construction started in 2012

Expo Line Project Description

Phase 2 Expo Line from Culver City to Santa Monica:

2

Expo Light Rail Line Expo Light Rail Line Construction Progress

Expo Phase 2 Construction Progress at a Glance

2014 Construction Highlights:

• Station construction is more than 68% complete

• All 7 bridges have been completed

• All 7 stations are under construction

• Track installation to be completed by fall

• Roadway widening work and final paving continues

3

Expo Light Rail Line Construction Update ROW Construction Progress

Venice Boulevard Median Construction

Sidewalk Concrete Pour at Overland Avenue

Rail Welding at the I-10 Box

OCS Pole Installation at Northvale Trench

4

Expo Light Rail Line Palms Station

Street view from Exposition Boulevard looking west

5

Expo Light Rail Line Westwood/Rancho Park Station

Street view from Exposition Boulevard looking east

6

Expo Light Rail Line Expo/Sepulveda Station

Street view from Exposition Boulevard looking west

7

Expo Light Rail Line Expo/Bundy Station

Street view from Exposition Boulevard looking east

8

Expo Light Rail Line 26th Street/Bergamot Station

Street view from looking east

9

Expo Light Rail Line 17th Street/SMC Station

Street view looking east

10

Expo Light Rail Line Downtown Santa Monica Station

Street view from Colorado Avenue looking east

11

Expo Light Rail Line

Expo/ Bundy

Expo/ Sepulveda

Westwood/ Rancho Park

Station Progress thru December 2014

• Platform foundation work completed • Track installation completed • Elevator installation nearing

completion • On-going electrical, train control

systems installation • Canopy and archway installation

Construction Progress

Palms

Palms Station Platform Paver Installation

12

Expo Light Rail Line

Expo/ Bundy

Expo/ Sepulveda

Palms

Station Progress thru December 2014

Westwood/ Rancho Park

Construction Progress

• Platform foundation work completed

• Track installation completed • Electrical and train control

systems installation on-going • Canopy installation

Westwood Rancho Park Station Platform Pavers

13

Expo Light Rail Line

Palms

Westwood/ Rancho Park

Expo/ Bundy

Station Progress thru December 2014 Construction Progress

Expo/ Sepulveda

• Platform foundation work completed • Track installation completed • Elevator installation nearing completion • Electrical and train control systems installation • Canopy and Archway installation • Utility Room construction

Sepulveda Station Plaza Progress

14

Expo Light Rail Line

Palms

Westwood/ Rancho Park

Expo/ Sepulveda

Station Progress thru December 2014 Construction Progress

Expo/ Bundy

• Platform foundation work completed • Track installation completed • Elevator installation nearing completion • Electrical and train control systems installation • Canopy and Archway installation • Utility Room construction

Bundy Station Elevator Installation Progress

15

Expo Light Rail Line Construction Progress

Venice Blvd to Motor Ave

• Venice bridge track installation completed • Venice Blvd roadway improvements

continue on the north side • Traffic signal and street light installation

Construction Activities thru December 2014 – Los Angeles

Motor Ave to Military Ave

• Complete roadway improvements at Overland Ave and Westwood Blvd • Traffic signal and street light installation

Westwood Boulevard Bus Pad Construction

Military Ave to Centinela Ave

• On-going track installation on ROW • Roadway improvements at Pico Blvd and

Barrington Ave • Traffic signal and street light installation

Pico Roadway Improvements

• Lane closures on Pico Blvd • Scheduled to begin:

Friday, December 5, 2014

16

Expo Light Rail Line Construction Update

Expo Right-of-Way (ROW) Construction Progress – Santa Monica

Maintenance Facility Building Progress Rail Installation at 19th Street

TPSS Installation at Olympic and Cloverfield

Downtown Santa Monica Station Concrete Pour

17

Expo Light Rail Line

Downtown Santa Monica

17th Street/ SMC

• Foundation work nearing completion

• On-going electrical and systems installation

• Canopy and archway installation

• Platform paver installation has been completed

• Track installation was completed in June

Station Progress thru December 2014

26th Street/ Bergamot

Construction Progress

26th Street /Bergamot Station Paver Installation

18

Expo Light Rail Line

Downtown Santa Monica

26th Street/ Bergamot

Station Progress thru December 2014

• On-going electrical and systems installation

• Canopy and archway installation • Paver installation has been

completed • Foundation work is complete • Track installation was completed

in July

17th Street/ SMC

Construction Progress

17th Street /SMC Station Tactile Warning Paver Installation

19

Expo Light Rail Line

17th Street/ SMC

26th Street/ Bergamot

• Foundation work on-going • Utility work on-going • Electrical Systems Installation • Platform paver installation to start

in November • Track installation to be completed

in October

Station Progress thru December 2014

Downtown Santa Monica

Construction Progress

Downtown Santa Monica Station Concrete Pour

20

Expo Light Rail Line Construction Progress

Centinela Ave to 4th Street

• Continue with track installation on ROW

• Traffic signal, street light and train control systems installation

• Final street improvements

• Sidewalk installation between Stewart and Cloverfield

• Irrigation and permanent fence installation

• OCS Pole and Catenary Wire installation

Ongoing Construction Activities thru December 2014 – Santa Monica

Olympic Bridge Rail Installation Progress

6th Street Track Installation

• 6th Street is the only remaining Expo 2 track crossing

• Scheduled to begin:

Wednesday, November 12, 2014

21

Expo Light Rail Line

• Soil removal and grading

• Irrigation, drainage systems, and curb and gutter

• Electrical and lighting conduits

Maintenance Facility • On-going installation of building pre-cast

panels

• Installation of Main building interior utilities and walls

• On-site rail installation to start in mid-October

• Foundation construction for secondary and third buildings continues

Expo Bikeway Design/Construction

Bikeway and Maintenance Facility

Maintenance Facility Building Foundation Progress

Typical Bike Path Design

22

Expo Light Rail Line Expo Light Rail Line Construction Timeline

Construction Progress and Timeline

Construction Timeline

2011 Pre-Construction Activities

2012 Bridge Construction, Utility Relocation and Guideway Excavation, and Soundwalls

2013 Bridge and Station Construction, Utility Relocation, Soundwalls, Track Installation and Street/Roadway Improvements

2014 Continue Street/Roadway Improvements, Track Installation, Utility Relocation Station Finishes, Electrical System, Train Control, and Landscaping Installation

2015 Continue Street/Roadway Improvements and Landscaping Installation, Systems Testing and Pre-Revenue Operations

23

Expo Light Rail Line

How to Reach Us

Contacts

Project Website: www.BuildExpo.org

Sign-up on our homepage to be added to the project database and receive notices via email.

Project Hotline: 213-922-EXPO (3976)

www.Facebook.com/ExpoLine www.Twitter.com/ExpoLine

Social Media:

Email: info@buildexpo.org

Community Relations Contacts: Torri Hill

SRJV Community Relations Manager 310-500-1485 or torri.hill@skanska.com

Heather Rozman SRJV Community Relations Coordinator 310-500-1487 or heather.rozman@skanska.com

24

Recommended