Expo Light Rail Line
Expo Line Project Westside/Central Metro Service Council
November 2014
Expo Light Rail Line
6.6 mile corridor
7 new Stations
64,000 Daily Riders by 2030
Estimated Travel Time (Downtown LA to Santa Monica): 46 minutes
Estimated Cost: $1.5 billion
Final design in now complete
Project is 75% complete
Major construction started in 2012
Expo Line Project Description
Phase 2 Expo Line from Culver City to Santa Monica:
2
Expo Light Rail Line Expo Light Rail Line Construction Progress
Expo Phase 2 Construction Progress at a Glance
2014 Construction Highlights:
• Station construction is more than 68% complete
• All 7 bridges have been completed
• All 7 stations are under construction
• Track installation to be completed by fall
• Roadway widening work and final paving continues
3
Expo Light Rail Line Construction Update ROW Construction Progress
Venice Boulevard Median Construction
Sidewalk Concrete Pour at Overland Avenue
Rail Welding at the I-10 Box
OCS Pole Installation at Northvale Trench
4
Expo Light Rail Line Palms Station
Street view from Exposition Boulevard looking west
5
Expo Light Rail Line Westwood/Rancho Park Station
Street view from Exposition Boulevard looking east
6
Expo Light Rail Line Expo/Sepulveda Station
Street view from Exposition Boulevard looking west
7
Expo Light Rail Line Expo/Bundy Station
Street view from Exposition Boulevard looking east
8
Expo Light Rail Line 26th Street/Bergamot Station
Street view from looking east
9
Expo Light Rail Line 17th Street/SMC Station
Street view looking east
10
Expo Light Rail Line Downtown Santa Monica Station
Street view from Colorado Avenue looking east
11
Expo Light Rail Line
Expo/ Bundy
Expo/ Sepulveda
Westwood/ Rancho Park
Station Progress thru December 2014
• Platform foundation work completed • Track installation completed • Elevator installation nearing
completion • On-going electrical, train control
systems installation • Canopy and archway installation
Construction Progress
Palms
Palms Station Platform Paver Installation
12
Expo Light Rail Line
Expo/ Bundy
Expo/ Sepulveda
Palms
Station Progress thru December 2014
Westwood/ Rancho Park
Construction Progress
• Platform foundation work completed
• Track installation completed • Electrical and train control
systems installation on-going • Canopy installation
Westwood Rancho Park Station Platform Pavers
13
Expo Light Rail Line
Palms
Westwood/ Rancho Park
Expo/ Bundy
Station Progress thru December 2014 Construction Progress
Expo/ Sepulveda
• Platform foundation work completed • Track installation completed • Elevator installation nearing completion • Electrical and train control systems installation • Canopy and Archway installation • Utility Room construction
Sepulveda Station Plaza Progress
14
Expo Light Rail Line
Palms
Westwood/ Rancho Park
Expo/ Sepulveda
Station Progress thru December 2014 Construction Progress
Expo/ Bundy
• Platform foundation work completed • Track installation completed • Elevator installation nearing completion • Electrical and train control systems installation • Canopy and Archway installation • Utility Room construction
Bundy Station Elevator Installation Progress
15
Expo Light Rail Line Construction Progress
Venice Blvd to Motor Ave
• Venice bridge track installation completed • Venice Blvd roadway improvements
continue on the north side • Traffic signal and street light installation
Construction Activities thru December 2014 – Los Angeles
Motor Ave to Military Ave
• Complete roadway improvements at Overland Ave and Westwood Blvd • Traffic signal and street light installation
Westwood Boulevard Bus Pad Construction
Military Ave to Centinela Ave
• On-going track installation on ROW • Roadway improvements at Pico Blvd and
Barrington Ave • Traffic signal and street light installation
Pico Roadway Improvements
• Lane closures on Pico Blvd • Scheduled to begin:
Friday, December 5, 2014
16
Expo Light Rail Line Construction Update
Expo Right-of-Way (ROW) Construction Progress – Santa Monica
Maintenance Facility Building Progress Rail Installation at 19th Street
TPSS Installation at Olympic and Cloverfield
Downtown Santa Monica Station Concrete Pour
17
Expo Light Rail Line
Downtown Santa Monica
17th Street/ SMC
• Foundation work nearing completion
• On-going electrical and systems installation
• Canopy and archway installation
• Platform paver installation has been completed
• Track installation was completed in June
Station Progress thru December 2014
26th Street/ Bergamot
Construction Progress
26th Street /Bergamot Station Paver Installation
18
Expo Light Rail Line
Downtown Santa Monica
26th Street/ Bergamot
Station Progress thru December 2014
• On-going electrical and systems installation
• Canopy and archway installation • Paver installation has been
completed • Foundation work is complete • Track installation was completed
in July
17th Street/ SMC
Construction Progress
17th Street /SMC Station Tactile Warning Paver Installation
19
Expo Light Rail Line
17th Street/ SMC
26th Street/ Bergamot
• Foundation work on-going • Utility work on-going • Electrical Systems Installation • Platform paver installation to start
in November • Track installation to be completed
in October
Station Progress thru December 2014
Downtown Santa Monica
Construction Progress
Downtown Santa Monica Station Concrete Pour
20
Expo Light Rail Line Construction Progress
Centinela Ave to 4th Street
• Continue with track installation on ROW
• Traffic signal, street light and train control systems installation
• Final street improvements
• Sidewalk installation between Stewart and Cloverfield
• Irrigation and permanent fence installation
• OCS Pole and Catenary Wire installation
Ongoing Construction Activities thru December 2014 – Santa Monica
Olympic Bridge Rail Installation Progress
6th Street Track Installation
• 6th Street is the only remaining Expo 2 track crossing
• Scheduled to begin:
Wednesday, November 12, 2014
21
Expo Light Rail Line
• Soil removal and grading
• Irrigation, drainage systems, and curb and gutter
• Electrical and lighting conduits
Maintenance Facility • On-going installation of building pre-cast
panels
• Installation of Main building interior utilities and walls
• On-site rail installation to start in mid-October
• Foundation construction for secondary and third buildings continues
Expo Bikeway Design/Construction
Bikeway and Maintenance Facility
Maintenance Facility Building Foundation Progress
Typical Bike Path Design
22
Expo Light Rail Line Expo Light Rail Line Construction Timeline
Construction Progress and Timeline
Construction Timeline
2011 Pre-Construction Activities
2012 Bridge Construction, Utility Relocation and Guideway Excavation, and Soundwalls
2013 Bridge and Station Construction, Utility Relocation, Soundwalls, Track Installation and Street/Roadway Improvements
2014 Continue Street/Roadway Improvements, Track Installation, Utility Relocation Station Finishes, Electrical System, Train Control, and Landscaping Installation
2015 Continue Street/Roadway Improvements and Landscaping Installation, Systems Testing and Pre-Revenue Operations
23
Expo Light Rail Line
How to Reach Us
Contacts
Project Website: www.BuildExpo.org
Sign-up on our homepage to be added to the project database and receive notices via email.
Project Hotline: 213-922-EXPO (3976)
www.Facebook.com/ExpoLine www.Twitter.com/ExpoLine
Social Media:
Email: [email protected]
Community Relations Contacts: Torri Hill
SRJV Community Relations Manager 310-500-1485 or [email protected]
Heather Rozman SRJV Community Relations Coordinator 310-500-1487 or [email protected]
24