Manufacturing process sequence

Page 3: Week 5

- What is your primary process? Why did you choose this process?> Primary process is sawing because it match with bamboo.

- What is your secondary process? Why did you choose this process?> Secondary process is drilling and pushing drilling we use electric

driller to drill and pushing we push corner and sharp out.

- What is your tertiary process? Why did you choose this process?> Last lackeying because we want it to be beautiful.

Manufacturing process sequence

Page 4: Week 5

Product function

- With your selected material, how is your material compatible with product geometry and manufacturing processes?

> We choose bamboo, eucalyptus wood because we have to cut it and drill it.

- What is the normal applied load to the material? Can your material take such load?

> Load is about 0.02 – 1.6 kg and braches can carry 20 N of things.

- What is the normal ambient conditions to your material?> It can use in every where.

- With your selected manufacturing process, how is your process compatible with the product geometry?

> Process that we use can compatible with the product geometry by using driller drill and sawing by saw.

Page 5: Week 5

Manufacturing cost

Page 6: Week 5

Manufacturing cost

Equation c=cM+cT+cPcM=cw*wp(1-a)cP=ct*t

Top BodycM=20.6 Bath/part , cP=4.15 Bath/partc=cM+cP=24.75 Bath/part

Low BodycM=10.3 Bath/part , cP=2.5 Bath/part

Page 7: Week 5

Manufacturing cost

Leg

cM=0.042 Bath/part , cP=4.15 Bath/part

c=cM+cP=4.192 Bath/part

Branches

cM=0.665 Bath/part , cP=4.15 Bath/part

c=4.815 Bath/part

Page 8: Week 5

Manufacturing cost

Product

C=ctop+clow+cleg+cbranch

c=(24.75*1)+(12.8*1)+(4.192*3)+(4.815*6)

c=79.016 Bath/part