PROJECT54 STATUS REPORT, OCTOBER 2009

Andrew Kun, Tom Miller

Page 2: Project54 Status Report, October 2009

Staff, students

Oskar Palinko, Mark Taipan Ivan Elhart, Michael Farrar, Michael

Litchfield, Zeljko Medenica, Nemanja Memarovic, Eric Ojala, Jon Oppelaar

Page 3: Project54 Status Report, October 2009

Outline

The Project54 system Deployment Development Outlook

Page 4: Project54 Status Report, October 2009
Page 5: Project54 Status Report, October 2009
Page 6: Project54 Status Report, October 2009

Outline

The Project54 system Deployment Development Outlook

Page 7: Project54 Status Report, October 2009

Deployment

In-vehicle systems Communications infrastructure

Page 8: Project54 Status Report, October 2009
Page 9: Project54 Status Report, October 2009

In-vehicle systems

>1,000 vehicles in NH >180 agencies: local, state

Page 10: Project54 Status Report, October 2009

Commercialization: 54ward

Page 11: Project54 Status Report, October 2009

Deployment

In-vehicle systems Communications infrastructure

Page 12: Project54 Status Report, October 2009
Page 13: Project54 Status Report, October 2009

NHDS data queries via Project 25

Page 14: Project54 Status Report, October 2009

NHDS wireless update system

Page 15: Project54 Status Report, October 2009

Locals: cellular service

5 servers for 9 agencies >35,000 queries since March 2007 >2,000 queries per month Expanding – local agencies very

interested

Page 16: Project54 Status Report, October 2009

Outline

The Project54 system Deployment Development Outlook

Page 17: Project54 Status Report, October 2009

Handheld computing

Remote databases: Cellular, 802.11 2D barcode scanner

Photos Tags

Symbol, HTC Pilot deployment

pending: Dover, NH Controlling access?

Page 18: Project54 Status Report, October 2009

Project 25 data base station

P25 radios available Inexpensive base station Pilot deployment pending: Newmarket,

NH

Page 19: Project54 Status Report, October 2009

In-car user interfaces

Page 20: Project54 Status Report, October 2009

Navigation study

Page 21: Project54 Status Report, October 2009

Navigation: paper directions

Page 22: Project54 Status Report, October 2009

Navigation: standard GPS

Page 23: Project54 Status Report, October 2009

Navigation: voice only

Page 24: Project54 Status Report, October 2009

Outline

The Project54 system Deployment Development Outlook

Page 25: Project54 Status Report, October 2009
Page 26: Project54 Status Report, October 2009

Photos, tags

Page 27: Project54 Status Report, October 2009
Page 28: Project54 Status Report, October 2009

Questions?