Opel Energy Systems Pvt. Ltd. BEE Accredited ISO 9001 - 2008 Company having 12 years of experience in the field of Thermal Equipments, Non Conventional Energy Generation and Energy Conservation Projects Our Moto is to SAVE ENERGY FOR NATION by providing very simple cost effective IDEAS to the industry. OESPL have received first prize as a Energy Service Company from MEDA for 2007-2008, 08-09, 09-10. The Director and team of OESPL, is having experience in the field of Manufacturing, Erection and Commissioning of thermal Equipment's, Energy Auditing, Process Instrumentation and Non Conventional Energy for 15 years. Biomass Briquette Fired Thermic Fluid Heaters Fuel Saving Devices And Systems For LPG/PNG/LNG/PROPANE/HSD/F.O. Waste Heat Recovery Systems On Furnace/Ovens/D.G. Sets/Boilers Energy Conservation Projects Fuel Saving Devices Biomass Briquette Conversion Systems Waste Heat Recovery Systems Industrial Energy Audits, Energy Conservation Projects, Thermal Efficiency Measurement, Foundry Thermal Equipments, Furnace Oil Conversion Systems, Waste Heat Conversion Systems, Solar Steam Generation Systems, Food Waste Biogas Plants For Industrial, Biomass Briquette Fired Thermic

Citation preview

Page 1: New Case Studies
Page 2: New Case Studies

WASTE HEAT RECOVERY CASE STUDIES

Page 3: New Case Studies

1. AIR HEATER ON THERMOPACK EXHAUST

WE SAVE ENERGY FOR NATION …!

Page 4: New Case Studies

Fuel In Use For TFH - PNGEquipment Installed - Air Pre HeaterHeat Recovered - 4 Lac Kcal/Hr X 3

Nos.Flue Gas Inlet Temp. - 250° Celsius Flue Gas Outlet Temp. - 120 CelsiusPayback Period - 4 Months

WE SAVE ENERGY FOR NATION …!

Page 5: New Case Studies

2. AIR HEATER ON THERMOPACK EXHAUST

WE SAVE ENERGY FOR NATION …!

Page 6: New Case Studies

WE SAVE ENERGY FOR NATION …!

Fuel In Use For TFH - PNGEquipment Installed - Air Pre HeaterHeat Recovered - 4 Lac Kcal/Hr X 3

Nos.Flue Gas Inlet Temp. - 250° Celsius Flue Gas Outlet Temp. - 120 CelsiusPayback Period - 4 Months

Page 7: New Case Studies

3. WASTE HEAT RECOVERY ON PAINTSHOP OVEN EXHAUST

WE SAVE ENERGY FOR NATION …!

Page 8: New Case Studies

Equipment Installed - Hot Water Generator Heat Recovered - 60000 Kcal/Hr.Flue Gas Inlet Temp. - 280° CelsiusFlue Gas Outlet Temp. - 120° CelsiusPayback Period - 9 Months

WE SAVE ENERGY FOR NATION …!

Page 9: New Case Studies

4. WHR HWG ON PAINTSHOP OVEN EXHAUST

WE SAVE ENERGY FOR NATION …!

Page 10: New Case Studies

Equipment Installed - Hot Water Generator

Heat Recovered - 250000 kcal/hrExhaust Temp from RTO - 225° CelsiusAnnual Savings - 50 LacsPayback Period - 12 Months

WE SAVE ENERGY FOR NATION …!

Page 11: New Case Studies

5. WHR HWG ON ANNELING FURNACE EXHAUST

WE SAVE ENERGY FOR NATION …!

Page 12: New Case Studies

Equipment Installed - Hot Water Generator

Heat Recovered - 222300 kcal/hrProject Cost - 52 Lacs.Annual Savings - 62 Lacs.Simple Payback - 10 Months

WE SAVE ENERGY FOR NATION …!

Page 13: New Case Studies

6. WHR HWG ON DG SET EXHAUST (2 Nos.)

WE SAVE ENERGY FOR NATION …!

Page 14: New Case Studies

Equipment Installed - Hot Water Generator Flue Gas Exhaust From D.G. Sets - 500° CelsiusHeat Recovered - 470000 Kcal/Hr.Heat Recovery Used For M - Hot Water Generation

@ 120° CelsiusSimple Payback - 8 Months

WE SAVE ENERGY FOR NATION …!

Page 15: New Case Studies

7. AIR HEATER ON BOILER EXHAUST

WE SAVE ENERGY FOR NATION …!

Page 16: New Case Studies

Equipment Installed - Air Pre HeaterHeat Recovered - 50000 Kcal/HrExhaust Temp from Boiler - 250° CelsiusFuel in Use - HSDPayback period - 12 Months

WE SAVE ENERGY FOR NATION …!

Page 17: New Case Studies

8. WHR HWG ON HT FURNACE EXHAUST

WE SAVE ENERGY FOR NATION …!

Page 18: New Case Studies

Equipment Installed - Hot Water Generator Heat Recovered - 100000 Kcal/Hr.Project Cost - 08 Lacs.Annual Savings - 16 Lacs.Simple Payback - 6 Months

WE SAVE ENERGY FOR NATION …!

Page 19: New Case Studies

9. WASTE HEAT RECOVERY CHARGE PREHEATER

WE SAVE ENERGY FOR NATION …!

Page 20: New Case Studies

Equipment Installed - Charge Preheated on Melting Furnace

Heat Recovered - 78000 Kcal/HrStack Temp at Exhaust - 500° CelsiusAnnual Saving - Rs. 15 Lacs Payback Period - 8 Months

WE SAVE ENERGY FOR NATION …!

Page 21: New Case Studies

10. WHR HWG ON MELTING FURNACE EXHAUST

WE SAVE ENERGY FOR NATION …!

Page 22: New Case Studies

Equipment Installed - Hot Water Generator Heat Recovered - 100000 Kcal/Hr. x 4 Nos.Total LPG Saving Achieved - 40 Kg/HrSimple Payback - 9 Months

WE SAVE ENERGY FOR NATION …!

Page 23: New Case Studies

11. WHR HWG ON PAINTSHOP OVEN EXHAUST

WE SAVE ENERGY FOR NATION …!

Page 24: New Case Studies

Equipment Installed - Hot Water Generator Heat Recovered - 350000 Kcal/Hr. Total LPG Saved from Project - 35Kg/HrAnnual Savings - 100 LacsSimple Payback - 9 Months

WE SAVE ENERGY FOR NATION …!

Page 25: New Case Studies

12. Biomass Briquette firing Conversion for Thermopack

WE SAVE ENERGY FOR NATION …!

Page 26: New Case Studies

Equipment Installed - Briquette fired ThermopackEquipments Replaced - LPG Fired Drying OvensWorking Temperature - 325° Celsius / 300° CelsiusTotal LPG Saved from Project - 100Kg/HrAnnual Savings - 150 LacsSimple Payback - 6 Months

WE SAVE ENERGY FOR NATION …!

Page 27: New Case Studies

13. Biomedical Waste Incinerator

WE SAVE ENERGY FOR NATION …!

Page 28: New Case Studies

Equipment Installed - Biomedical Waste Incinerator Capacity - 100 Kg/hrWorking Temperature - 1000° Celsius

WE SAVE ENERGY FOR NATION …!

Page 29: New Case Studies

14. Fuel Saving Devices for LPG/NG/PNG BURNERS

WE SAVE ENERGY FOR NATION …!

Page 30: New Case Studies

WE SAVE ENERGY FOR NATION …!

Page 31: New Case Studies

WE SAVE ENERGY FOR NATION …!