WASTE HEAT RECOVERY CASE STUDIES

Page 3: New Case Studies

1. AIR HEATER ON THERMOPACK EXHAUST

WE SAVE ENERGY FOR NATION …!

Page 4: New Case Studies

Fuel In Use For TFH - PNGEquipment Installed - Air Pre HeaterHeat Recovered - 4 Lac Kcal/Hr X 3

Nos.Flue Gas Inlet Temp. - 250° Celsius Flue Gas Outlet Temp. - 120 CelsiusPayback Period - 4 Months

WE SAVE ENERGY FOR NATION …!

Page 5: New Case Studies

2. AIR HEATER ON THERMOPACK EXHAUST

WE SAVE ENERGY FOR NATION …!

Page 6: New Case Studies

WE SAVE ENERGY FOR NATION …!

Fuel In Use For TFH - PNGEquipment Installed - Air Pre HeaterHeat Recovered - 4 Lac Kcal/Hr X 3

Nos.Flue Gas Inlet Temp. - 250° Celsius Flue Gas Outlet Temp. - 120 CelsiusPayback Period - 4 Months

Page 7: New Case Studies

3. WASTE HEAT RECOVERY ON PAINTSHOP OVEN EXHAUST

WE SAVE ENERGY FOR NATION …!

Page 8: New Case Studies

Equipment Installed - Hot Water Generator Heat Recovered - 60000 Kcal/Hr.Flue Gas Inlet Temp. - 280° CelsiusFlue Gas Outlet Temp. - 120° CelsiusPayback Period - 9 Months

WE SAVE ENERGY FOR NATION …!

Page 9: New Case Studies

4. WHR HWG ON PAINTSHOP OVEN EXHAUST

WE SAVE ENERGY FOR NATION …!

Page 10: New Case Studies

Equipment Installed - Hot Water Generator

Heat Recovered - 250000 kcal/hrExhaust Temp from RTO - 225° CelsiusAnnual Savings - 50 LacsPayback Period - 12 Months

WE SAVE ENERGY FOR NATION …!

Page 11: New Case Studies

5. WHR HWG ON ANNELING FURNACE EXHAUST

WE SAVE ENERGY FOR NATION …!

Page 12: New Case Studies

Equipment Installed - Hot Water Generator

Heat Recovered - 222300 kcal/hrProject Cost - 52 Lacs.Annual Savings - 62 Lacs.Simple Payback - 10 Months

WE SAVE ENERGY FOR NATION …!

Page 13: New Case Studies

6. WHR HWG ON DG SET EXHAUST (2 Nos.)

WE SAVE ENERGY FOR NATION …!

Page 14: New Case Studies

Equipment Installed - Hot Water Generator Flue Gas Exhaust From D.G. Sets - 500° CelsiusHeat Recovered - 470000 Kcal/Hr.Heat Recovery Used For M - Hot Water Generation

@ 120° CelsiusSimple Payback - 8 Months

WE SAVE ENERGY FOR NATION …!

Page 15: New Case Studies

7. AIR HEATER ON BOILER EXHAUST

WE SAVE ENERGY FOR NATION …!

Page 16: New Case Studies

Equipment Installed - Air Pre HeaterHeat Recovered - 50000 Kcal/HrExhaust Temp from Boiler - 250° CelsiusFuel in Use - HSDPayback period - 12 Months

WE SAVE ENERGY FOR NATION …!

Page 17: New Case Studies

8. WHR HWG ON HT FURNACE EXHAUST

WE SAVE ENERGY FOR NATION …!

Page 18: New Case Studies

Equipment Installed - Hot Water Generator Heat Recovered - 100000 Kcal/Hr.Project Cost - 08 Lacs.Annual Savings - 16 Lacs.Simple Payback - 6 Months

WE SAVE ENERGY FOR NATION …!

Page 19: New Case Studies

9. WASTE HEAT RECOVERY CHARGE PREHEATER

WE SAVE ENERGY FOR NATION …!

Page 20: New Case Studies

Equipment Installed - Charge Preheated on Melting Furnace

Heat Recovered - 78000 Kcal/HrStack Temp at Exhaust - 500° CelsiusAnnual Saving - Rs. 15 Lacs Payback Period - 8 Months

WE SAVE ENERGY FOR NATION …!

Page 21: New Case Studies

10. WHR HWG ON MELTING FURNACE EXHAUST

WE SAVE ENERGY FOR NATION …!

Page 22: New Case Studies

Equipment Installed - Hot Water Generator Heat Recovered - 100000 Kcal/Hr. x 4 Nos.Total LPG Saving Achieved - 40 Kg/HrSimple Payback - 9 Months

WE SAVE ENERGY FOR NATION …!

Page 23: New Case Studies

11. WHR HWG ON PAINTSHOP OVEN EXHAUST

WE SAVE ENERGY FOR NATION …!

Page 24: New Case Studies

Equipment Installed - Hot Water Generator Heat Recovered - 350000 Kcal/Hr. Total LPG Saved from Project - 35Kg/HrAnnual Savings - 100 LacsSimple Payback - 9 Months

WE SAVE ENERGY FOR NATION …!

Page 25: New Case Studies

12. Biomass Briquette firing Conversion for Thermopack

WE SAVE ENERGY FOR NATION …!

Page 26: New Case Studies

Equipment Installed - Briquette fired ThermopackEquipments Replaced - LPG Fired Drying OvensWorking Temperature - 325° Celsius / 300° CelsiusTotal LPG Saved from Project - 100Kg/HrAnnual Savings - 150 LacsSimple Payback - 6 Months

WE SAVE ENERGY FOR NATION …!

Page 27: New Case Studies

13. Biomedical Waste Incinerator

WE SAVE ENERGY FOR NATION …!

Page 28: New Case Studies

Equipment Installed - Biomedical Waste Incinerator Capacity - 100 Kg/hrWorking Temperature - 1000° Celsius

WE SAVE ENERGY FOR NATION …!

Page 29: New Case Studies

14. Fuel Saving Devices for LPG/NG/PNG BURNERS

WE SAVE ENERGY FOR NATION …!

Page 30: New Case Studies

WE SAVE ENERGY FOR NATION …!