Upload
blakefelson
View
356
Download
1
Tags:
Embed Size (px)
Citation preview
72 unit luxury apartment building
Built in 1971
Attracts high rents due to location and strong amenity package
Showing age and losing ability to compete with new high rise buildings in SOMA
Objective: To plan and renovate the building lobby and exterior façade in less than 10 months within a budget of $675,000.*
(*not actual numbers)
To complete the project on time and under budget
To enhance the prestige of the property which will in turn raise rents and lower
vacancy
To not receive any Government citations or fines
To keep noise and overall disruption at a minimum
Lobby Renovation Plan
• New mezzanine window guard
• New wall tile
• New floor tile
• New column casing
• New lighting
• New furniture
Longest Activities Create Construction Drawings (30 days)
Construction Contractor Bid Solicitation (30 days)
Fabrication of Storefront (28 days)
Architect Bid Solicitation (20 days)
Fabrication of Glass Awning (20 days)
Solutions
Set Fabrications to begin upon approval of Construction Drawings, not upon Fire Dept. Permit Approval (speeds up project 15 days)
Crashing of Fabrication Activities
Mezzanine Window Guard Speed up by 7 days @ $1,200 per day
Reject – preceding task (fire sprinklers) will be completed in time, installation not a predecessor to next task
Storefront Speed up by 3 days @ $1,150 per day
AcceptAccept – Fabrication is precedent to Removal of Storefront, crashing allows installation to begin 3 days earlier
Glass Awning Speed up by 4 days @ $900 per day
Reject – installation cannot begin until storefront is installed
Project is ahead of Baseline Schedule
Crashing costs will be allocated from Budget Contingency Reserve