Vocational Center Center For Vocational Training, Handicrafts and Therapeutic Support December 2013

Vocational center

Embed Size (px)

Citation preview

Vocational Center

Center For Vocational Training, Handicrafts and

Therapeutic Support

December 2013

Topics

Vision Description Goals Target audiences Professions Program Plan Equipping Costs Operation

Vision

Centralizing Vocational Training, Operations & crafts

3

Description

4

The Vision:

A center which allows our resident youth to experience artistic creativity and vocational training by offering exposure, familiarity and implementation of handicrafts and professional skills. This experience - which requires prior thought in design, control in implementation of acquired knowledge, patience and accuracy, ability to listen and learn - allows our resident youth to acquaint themselves, and progress in those subjects which seem most appropriate for them, whether as a first step in their vocational training, in whichever subject they choose, or as general support during their educational process in which the said characteristics are essential.

The Method:

Our hope is to submit plans in order to obtain Ministry of Education or Ministry of Labor recognition that would entitle us to hand out official diplomas.

Goals

Center For Vocational Training in a diploma

level.

Concentration equipment maintenance

Improving working conditions

Upkeep of maintenance equipment

Maintaining the appearance of the village5

Target audience

Shanti House youth

Youths from the region

Year of Service volunteers

Maintenance staff

Volunteers

6Objectives are in chronological order

Courses Carpentry and Woodwork - Wood, furniture design, construction, furniture restoration,

painting, etc. Locksmithing - Welding, bending and processing of tin and iron, beating of joints, etc. Electricity - Basics, safety rules, basic electricity circuits (home lighting) and more.

According to training program certification. Plumbing - Familiarity with basic residential water and sewage systems, methods for

installation of piping and fittings, handling of common problems in residential buildings etc. Housekeeping - Plasterwork, Painting, Gypsum Walls, Construction Gardening – Fundamentals of planting and principles of irrigation Mosaics - Stone, ceramics and glass Stained glass - Glass Fusion - Glass and enamel Photography – Shooting, developing and printing Sculpture - Stone and wood, including carving Drawing - Basics and hands-on experience Pottery – Creation, including sculpting in ceramics Collage – Basic composition and creation of images Pebbles - Decoration, design and creation of useful decorative objects. Polishing of stones

and jewelry7

Facilities

Fixed roof size 500 sq.m which includes: Office with two computers - 12 sq.m Toilet and kitchenette - 8 sq.m Storage Tools - 20 sq.m Storage Materials - 30 sq.m Classroom - 30 sq.m Workshop open area - 150 sq.m Storage space - 250 sq.m

Vehicle Parking - 500 sq.m All enclosure fencing with gate entry and exit

8

9

Village Plan

Workshop program

10

Costs & Equipping

11

Workshops building costs       $3.60

Description Measure Unit NIS Total NIS Total $ Ingredients

Construction structure200 sqm 1,200

240,00066,667

Includes establishing and building a stone wall

Plaster       30,000 8,333  Entrance area 250 sqm 250 62,500 17,361  Building Carpentry       30,000 8,333 DoorsElectricity       50,000 13,889 Main Board and 100 pointsPlumbing       30,000 8,333 Six Plumbing PointsGoals frames       50,000 13,889 Sliding Main GateFlooring and wall cladding 175 sqm 350 61,250 17,014  Aluminum       20,000 5,556 Services window and a window officeTotal 573,750 159,375  Variance            Planning and management General   10% 57,375 15,938 Planning and supervision costsUnexpected General   10% 57,375 15,938 Planning and supervision costsEquipping       220,000 61,111  Total 334,750 92,986  Total 908,500 252,361  Total + VAT 1,072,030 297,786  

Operation

12

Operating costs   $3.60

Description Monthly NISAnnual

NIS USDOperational Manager 10,000 120,000 33,333

Professional Staff 17,200 206,400 57,333

Current expenses 2,000 24,000 6,667

Materials 9,000 108,000 30,000

Maintenance 3,000 36,000 10,000

Total 41,200 494,400 137,333$

13

Thanks

Professionals who helped us in planning :

Engineers:

Architect: Shimon Evgi

Shanti House: Michael Ben Yosef