• Laichwiltach Territory
o We Wai Kai Nation
o Wei Wai Kum First Nation
Acknowledgment of Traditional Lands
2
North Island Hospitals Project
Campbell River Hospital 375 2nd Avenue
• 32,316 m2
• 95 Beds
• $274.5M, 40% Comox-Strathcona Regional Hospital District
Comox Valley Hospital 101 Lerwick Road
• 39,826 m2
• 153 Beds
• $331.7M, 40% Comox-Strathcona Regional Hospital District
3
Business
Case &
Design
Concept
Construction
Issue
RFQ
Issue RFP
Negotiate
Maintenance
3 years
5 months
to 2 years
Design
Concept
Plan
Contract Term
30 years
2 to 4
months
Progress – Design & Construction Phase
4
Excavation – Nearing Completion
Foundation Level 0 – Underway
• Footings
• Columns
• Exterior Walls
Level 1 Slab – Underway
• Forming
• Concrete
Construction Activities
8
Detail Design Review
• Clinical User Groups
• Mockup Spaces
• Technical Working Groups
Guidance / Feedback
• Public Meetings
• Aboriginal Working Group
• Public-Patient Advisory Committee
• Interiors Way Finding Working Group
• Art Working Group
Design Activities
12
18
Refinement - Labour Delivery Recovery Postpartum
Head Wall Configuration
Placement of Furnishings/ Equipment
Placement of Fixtures
18
North Island Hospitals Project
Industry Training
Authority
North Island Employment Foundations
Society
SD72
SD71
NVI Aboriginal
Training Society
North Island College
Vancouver Island
Construction Association
STEP Program
Campbell River
Chamber of Commerce
Comox Valley
Chamber of Commerce
19
Campbell River Hospital
• Knappett Industries (Excavation/Civil)
• Best choice (Form Work)
• Lower Mainland Steel (Rebar – Foundations)
• Harris Rebar (Rebar – Superstructure)
• Kone (Elevators)
• Strathcona Mechanical
• Keldon Electric and Data
• Surespan (precast Parkade)
• Translogic (Pneumatic Tubes)
• Upland Contracting / Island Ready Mix JV (Concrete Supply)
• Columbia Seal (Waterproofing)
• Dryco Systems (Exterior Back-up Wall Assembly)
• Holdfast Metworks (Structural Steel)
Comox Valley Hospital
• Knappett Industries (Excavation/Civil)
• Farmer (Form Work)
• Lower Mainland Steel (Rebar – Foundations)
• Harris Rebar (Rebar – Superstructure)
• Kone (Elevators)
• Keith Plumbing & Heating (Mechanical)
• Houle Electric
• Surespan (precast Parkade)
• Translogic (Pneumatic Tubes)
• Cumberland Ready Mix (Concrete Supply)
• Columbia Seal (Waterproofing)
• Dryco Systems (Exterior Back-up Wall Assembly)
• Holdfast Metalworks (Structural Steel)
20
Work Packages Awarded
Work Packages – December and January
Tenders In Review & Issued
•Closed and In Review
•Cladding
•Curtainwall & Glazing
•Tender Issued
•Close Date 5 December
•Roofing
•Close Date 10 December
•Fall Protection
December-January Issue
• Issue Date 14 December
•Drywall & Ceiling Systems
•Door Frames & Hardware
• Issue Date 15 December
•Exterior Masonry
• Issue Date 15 January
• Interior Masonry
•Overhead Doors & Rollers
•Sitework:
•Asphalt
•Site Concrete
•Site Furnishings
•Sidewalks & Curbs
•Soft Landscaping & Irrigation
21
Work Packages - Spring / Summer 2015
Spring 2015
• Issue Date 15 May
• Glass Doors & Screens
Interior Finishes Packages
• Issue Date 15 June
• Floor Finishes
• Tiling
• Epoxy Flooring
• Painting
• Millwork
• Lab Casework
• System Furniture
• Wall Protection & Handrails
• Signage
• Roller Shades & Blinds
22
Local North Island Remainder VI Other
September 137 0 33 23
October 110 0 26 29
November 120 0 25 30
0
20
40
60
80
100
120
140
160
# o
f W
ork
ers
Manpower Demographics Overall
23
Site Demographics – Campbell River Hospital
24
Local* 50%
North Island** 0%
Remainder Vancouver Island
16%
Mainland/Other 38%
On Site Workers – November (56)
*Local – Campbell River, Comox, Courtenay, Cumberland (& surrounding unincorporated areas)
**North Island – North/East/West of Campbell River
Community Engagement & Consultation
Quarterly Public Meetings
Newsletters
Website
Webcams
Public Patient
Advisory Committee
Interiors-Way finding
Working Group
Art Committee
Aboriginal Working Group
School Advisory
Committees
25
• Transit to/from temporary lots
o Weekdays
o Monday to Wednesday 8 am – 2 pm
o Thursday-Friday 8 – 11 am
• Temporary Lots west of Yucalta Lodge (144 stalls)
• Additional Volunteer Drivers Needed!
Hospital Parking Shuttle
26
Design and Construction of New Facilities July 2014 – April 2017
Service Commencement – Project Completion April 30, 2017
Commissioning and Transition Period Summer – Fall 2017
Move-In Late Fall 2017
27
Project Schedule
• Comox Valley
o Date: Tuesday, March 10, 2015 (7 – 9 pm)
o Location: Stan Hagen Theatre, North Island College
• Campbell River
o Date: Thursday, March 12, 2015 (7 – 9 pm)
o Location: Timberline Secondary/NIC Theatre
Community Information Meetings
28
For more information and updates, visit our website:
http://nihp.viha.ca/
North Island Hospitals Project Website