30
Campbell River Quarterly Public Meeting December 4, 2014

NIHP Campbell River Community Information Meeting presentation, Dec. 4, 2014

Embed Size (px)

Citation preview

Campbell River Quarterly Public Meeting

December 4, 2014

• Laichwiltach Territory

o We Wai Kai Nation

o Wei Wai Kum First Nation

Acknowledgment of Traditional Lands

2

North Island Hospitals Project

Campbell River Hospital 375 2nd Avenue

• 32,316 m2

• 95 Beds

• $274.5M, 40% Comox-Strathcona Regional Hospital District

Comox Valley Hospital 101 Lerwick Road

• 39,826 m2

• 153 Beds

• $331.7M, 40% Comox-Strathcona Regional Hospital District

3

Business

Case &

Design

Concept

Construction

Issue

RFQ

Issue RFP

Negotiate

Maintenance

3 years

5 months

to 2 years

Design

Concept

Plan

Contract Term

30 years

2 to 4

months

Progress – Design & Construction Phase

4

5

6

7

Excavation – Nearing Completion

Foundation Level 0 – Underway

• Footings

• Columns

• Exterior Walls

Level 1 Slab – Underway

• Forming

• Concrete

Construction Activities

8

Concrete Delivery

9

Level 1 Suspended Slab

10

Full Crane Capacity

11

Detail Design Review

• Clinical User Groups

• Mockup Spaces

• Technical Working Groups

Guidance / Feedback

• Public Meetings

• Aboriginal Working Group

• Public-Patient Advisory Committee

• Interiors Way Finding Working Group

• Art Working Group

Design Activities

12

Campbell River Hospital

13

Heliport

15

Heliport

Early Mockups

Sink

Paper Towel

Sharps

Soap

16

17

Refinement – Psychiatry InPatient Unit

17

Experimenting with Room Setup

18

Refinement - Labour Delivery Recovery Postpartum

Head Wall Configuration

Placement of Furnishings/ Equipment

Placement of Fixtures

18

North Island Hospitals Project

Industry Training

Authority

North Island Employment Foundations

Society

SD72

SD71

NVI Aboriginal

Training Society

North Island College

Vancouver Island

Construction Association

STEP Program

Campbell River

Chamber of Commerce

Comox Valley

Chamber of Commerce

19

Campbell River Hospital

• Knappett Industries (Excavation/Civil)

• Best choice (Form Work)

• Lower Mainland Steel (Rebar – Foundations)

• Harris Rebar (Rebar – Superstructure)

• Kone (Elevators)

• Strathcona Mechanical

• Keldon Electric and Data

• Surespan (precast Parkade)

• Translogic (Pneumatic Tubes)

• Upland Contracting / Island Ready Mix JV (Concrete Supply)

• Columbia Seal (Waterproofing)

• Dryco Systems (Exterior Back-up Wall Assembly)

• Holdfast Metworks (Structural Steel)

Comox Valley Hospital

• Knappett Industries (Excavation/Civil)

• Farmer (Form Work)

• Lower Mainland Steel (Rebar – Foundations)

• Harris Rebar (Rebar – Superstructure)

• Kone (Elevators)

• Keith Plumbing & Heating (Mechanical)

• Houle Electric

• Surespan (precast Parkade)

• Translogic (Pneumatic Tubes)

• Cumberland Ready Mix (Concrete Supply)

• Columbia Seal (Waterproofing)

• Dryco Systems (Exterior Back-up Wall Assembly)

• Holdfast Metalworks (Structural Steel)

20

Work Packages Awarded

Work Packages – December and January

Tenders In Review & Issued

•Closed and In Review

•Cladding

•Curtainwall & Glazing

•Tender Issued

•Close Date 5 December

•Roofing

•Close Date 10 December

•Fall Protection

December-January Issue

• Issue Date 14 December

•Drywall & Ceiling Systems

•Door Frames & Hardware

• Issue Date 15 December

•Exterior Masonry

• Issue Date 15 January

• Interior Masonry

•Overhead Doors & Rollers

•Sitework:

•Asphalt

•Site Concrete

•Site Furnishings

•Sidewalks & Curbs

•Soft Landscaping & Irrigation

21

Work Packages - Spring / Summer 2015

Spring 2015

• Issue Date 15 May

• Glass Doors & Screens

Interior Finishes Packages

• Issue Date 15 June

• Floor Finishes

• Tiling

• Epoxy Flooring

• Painting

• Millwork

• Lab Casework

• System Furniture

• Wall Protection & Handrails

• Signage

• Roller Shades & Blinds

22

Local North Island Remainder VI Other

September 137 0 33 23

October 110 0 26 29

November 120 0 25 30

0

20

40

60

80

100

120

140

160

# o

f W

ork

ers

Manpower Demographics Overall

23

Site Demographics – Campbell River Hospital

24

Local* 50%

North Island** 0%

Remainder Vancouver Island

16%

Mainland/Other 38%

On Site Workers – November (56)

*Local – Campbell River, Comox, Courtenay, Cumberland (& surrounding unincorporated areas)

**North Island – North/East/West of Campbell River

Community Engagement & Consultation

Quarterly Public Meetings

Newsletters

Website

Webcams

Public Patient

Advisory Committee

Interiors-Way finding

Working Group

Art Committee

Aboriginal Working Group

School Advisory

Committees

25

• Transit to/from temporary lots

o Weekdays

o Monday to Wednesday 8 am – 2 pm

o Thursday-Friday 8 – 11 am

• Temporary Lots west of Yucalta Lodge (144 stalls)

• Additional Volunteer Drivers Needed!

Hospital Parking Shuttle

26

Design and Construction of New Facilities July 2014 – April 2017

Service Commencement – Project Completion April 30, 2017

Commissioning and Transition Period Summer – Fall 2017

Move-In Late Fall 2017

27

Project Schedule

• Comox Valley

o Date: Tuesday, March 10, 2015 (7 – 9 pm)

o Location: Stan Hagen Theatre, North Island College

• Campbell River

o Date: Thursday, March 12, 2015 (7 – 9 pm)

o Location: Timberline Secondary/NIC Theatre

Community Information Meetings

28

For more information and updates, visit our website:

http://nihp.viha.ca/

North Island Hospitals Project Website

29

Thank You!!

Questions?

30