College Promenade BIA Streetscaping

Update

February 28, 2017

Page 2: College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final

Agenda

Agenda Item

1. Welcome & Introductions

3. Recap of 2016 work & overview of 2017

construction work

4. Q & A / Discussion

2

Page 3: College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final

Work Area

3

Page 4: College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final

2016 Project Overview - Planned WorkFrom July to November 30

• On College Street:

– Replace existing curb and sidewalks with decorative pavers

– Complete TTC accessibility improvements.

• Parkettes:

– Install side-street parkettes, new light fixtures, and complete

landscape treatments including: seating, trees, plantings, bike rings

and public art on Roxton and Dovercourt Roads, Concord and

Ossington Avenues.

• Overall

– additional bike parking and custom bike racks

– 81 metal tree guards to 23 existing trees, add new trees.

4

Page 5: College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final

2016 Project Overview – Current StatusFrom July to Mid-October

• The sidewalk areas on the north side of College Street have

been removed

• Majority of the sidewalk pavers have been installed

• Some areas of sidewalk have asphalt in place as

underground work is required.

• All deficiencies and outstanding work will be delivered with

this year’s project

5

Page 6: College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final

2016 Project Issues• Late Start

– Delayed start due to utility locates

• Ministry of Labour visit – The choice of staging / fencing to deal with orders to the contractor

• Road collapse at Concord

• Damaged water pipes

• Diesel tank (west of Dovercourt)

• Two contaminated soil sites

• Action taken:– Worked within the City’s process and the Ministry of Environment and Climate

Change (MOECC) Technical Safety and Standards Association to address soil conditions / diesel tank.

– The plan for remediation is approved and can be implemented in 2017

6

Page 7: College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final

2016 Project Issues

• Lack of schedule and work information provided to the PM

resulted in challenges for City staff to keep residents and

business owners informed.

• Action taken:– Weekly meetings with the City staff and the contractor, bi-weekly meetings

with the BIA board and City Staff, ongoing communication with site inspectors,

adding a second inspector, replying to issues brought forth by councillors,

residents and businesses as they were raised. This led to:

• The City issuing a notice of default in August

• The City issuing a notice of default in September

• The City issuing a notice of termination in October

• The City bringing in a different contractor to temporarily restore the site

7

Page 8: College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final

Next Steps - 2017

Task Completion Date

Public Meeting February 28, 2017

Finalize the Engineering estimate and funding March 2017

Issue Tender March 2017

Award Contract May 2017

Contractor orders materials & utility locates May /June 2017

Phase 1 Construction Starts on South Side July 4, 2017

8

Page 9: College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final

2017 Construction Details

• Expected Start: July 4, 2017 Expected End: October 31,

2017*

* dates may be affected by weather

• Construction staging:

– Phase 1: work (including parkettes) starts on south side in stages

• Stage 1 - Rusholme to Dovercourt

• Stage 2a/b - Dovercourt to Ossington

• Stage 3 - Ossington to Shaw

– Phase 2 – complete the north side and north side parkettes

9

Page 10: College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final

2017 Construction Details• Phase 1 work:

– Remove existing sidewalks

– Install electrical for tree pits

– pour new concrete base for pavers

– Lay new pavers

– Keep 18 existing tree pits; cover with same grills and tree guards as north side

– Install new bike rings

– Complete parkette work at Ossington and Dovercourt

• Phase 2 work:

– Start at Shaw Street and work west

– Complete outstanding work from 2016 including removing asphalt and laying new

pavers

– Complete parkette work at the following locations

10

Page 11: College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final

Phase 1: South Side Stage 1

11

Page 12: College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final

Phase 1: South Side Stage 2a & 2b

12

Page 13: College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final

Phase 1: South Side Stage 3

13

Page 14: College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final

Phase 2: North Side

• Work will travel on the north

side from (east to west)

• Parkette work at Dovercourt,

Ossington, Roxton and

Concord, will be completed

within each section being

addressed

14

Page 15: College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final

Bike Racks, Benches

15

Page 16: College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final

Blue Rooms

16

Page 17: College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final

Traffic, Pedestrian & Cyclist Access

• Pedestrian access to residences and

businesses will remain open at all times,

with some adjustments to go around work

areas

• College Street will be limited to one lane in

the work areas, lane tapering outside of

work areas will be needed to direct traffic

• Cyclists can share the road driving through

the work zone and resume use of cycle

lane on College when lanes open up or

choose an alternate route around the work

zone

17

Page 18: College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final

TTC Service Adjustments

• For this project, the TTC will divert the 506 Carlton Streetcar

onto Dundas Street West between Lansdowne and Bathurst

Street until the end of construction.

• Buses will run on College Street through the work zone.

• Start dates for route changes and further details will be

provided in the construction notice.

18

Page 19: College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final

Questions

19

Page 20: College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final

Sign up for email updates at

toronto.ca/collegest