20
Route 659 (Belmont Ridge Road) Reconstruct to 4-Lanes Project Pardon Our Dust Meeting Belmont Station Elementary School October 27, 2016

Belmont Ridge Road Pardon Our Dust meeting

Embed Size (px)

Citation preview

Page 1: Belmont Ridge Road Pardon Our Dust meeting

Route 659 (Belmont Ridge Road) Reconstruct to 4-Lanes Project

Pardon Our Dust MeetingBelmont Station Elementary School

October 27, 2016

Page 2: Belmont Ridge Road Pardon Our Dust meeting

2

Northern Virginia Transportation Authority Loudoun County Virginia Department of Transportation Dewberry Consultants, LLC Shirley Contracting Company

The Project Team

Page 3: Belmont Ridge Road Pardon Our Dust meeting

3

Objectives

Project Location Project Purpose and Need Provide an Overview of Design FeaturesDescribe Construction Sequence Discuss the Project ScheduleAnswer Your Questions

Page 4: Belmont Ridge Road Pardon Our Dust meeting

4

Project LocationNorth

South

West East

Page 5: Belmont Ridge Road Pardon Our Dust meeting

• Improve traffic safetythrough improvements toroadway geometry, operations, and grade

separation of W&OD

• Improve capacity &reduce congestion

• Enhance Connectivity ofRegional MultimodalTransportation Network

• Complete 4 lane roadway section from Route 7 to

the Dulles Greenway 5

Project Purpose and Need

Page 6: Belmont Ridge Road Pardon Our Dust meeting

6

Major Design Features Typical Section

Four lane divided roadway 26’ Wide Grass Median 10’ Wide Shared Use Path on Both Sides

of the Road

Page 7: Belmont Ridge Road Pardon Our Dust meeting

7

Construction SequenceStages 1, 2 & 3

Page 8: Belmont Ridge Road Pardon Our Dust meeting

8

Bridge Construction SequenceStages 1 & 2

Page 9: Belmont Ridge Road Pardon Our Dust meeting

9

Major Design FeaturesGrade Separated Interchange Over

W&OD Trail

Page 10: Belmont Ridge Road Pardon Our Dust meeting

10

Major Design FeaturesW&OD Trail Parking Facility

Page 11: Belmont Ridge Road Pardon Our Dust meeting

11

• Wall 1: Hay Rd. to 876’ North, Aprox.13’ Tall Scheduled to complete by end of 2017.

Major Design FeaturesNoise Barriers

Page 12: Belmont Ridge Road Pardon Our Dust meeting

12

• Wall 2: Churchill Downs Dr. to Chesterton St. is 1,963 LF, Approx. 13’ Tall, and Scheduled to complete by end of 2017.

Major Design FeaturesNoise Barriers

Page 13: Belmont Ridge Road Pardon Our Dust meeting

13

• Wall 2: Churchill Downs Dr. to Chesterton St. is 1,963 LF, Approx. 13’ Tall, and Scheduled to complete by end of 2017.

Major Design FeaturesNoise Barriers

Page 14: Belmont Ridge Road Pardon Our Dust meeting

14

• Wall 3: Chesterton St. to 384’ North, Aprox.13’ Tall

Scheduled to be complete by end of 2017.

Major Design FeaturesNoise Barriers

Page 15: Belmont Ridge Road Pardon Our Dust meeting

15

Architectural Finish• Concrete Posts and Concrete Panels• Panels: Ashlar Stone Pattern with a 12 Inch Tall Coping on the Top Stained Color Hopsac

Major Design FeaturesNoise Barriers

Page 16: Belmont Ridge Road Pardon Our Dust meeting

16

Project Metrics

Total Project Budget: $61 MillionConstruction Contract Value: $45.5 MillionProject Length: 1.9 MilesRight-of-Way Acquisition: 26 ParcelsAdjustments to 5 UtilitiesProject Duration: 39 months

Page 17: Belmont Ridge Road Pardon Our Dust meeting

17

Construction Metrics Communications 13,000 LF

Line Relocations Overhead Power 9,000 LF Gas Line 7,000 LF Relocations 36” Water Main: 10,000 LF Earth Moving: 125,000 CY

(15,500 Truck Loads) Storm Drainage: 14,200 LF Pipe

155 Drainage Structures Pavement Stone: 45,000 Tons Asphalt Pavement: 80,000 Tons Noise Barrier: 47,000 SF Pavement Markings: 130,000 LF

Page 18: Belmont Ridge Road Pardon Our Dust meeting

18

September 2015 Notice To Proceed

October 2015 - July 2016 Complete Design / Permitting

Summer 2016 - Winter 2016 Right of Way Acquisition

Fall 2016 - Winter 2017 Utility Relocations

October 31, 2017 Grade Separation Complete

Fall 2016 - Winter 2017 Stage 1 Construction

Winter 2017 - Fall 2018 Stage 2 Construction

Winter 2018 Stage 3 / Complete Project

Project Schedule

Page 19: Belmont Ridge Road Pardon Our Dust meeting

Addressing Your Concerns… Regarding Construction

19

A majority of the construction operations will be on weekdays during normal daytime hours, generally 6:00 am to 6:00 pm.

Weekends will be utilized as make-up day due to weather. Flagging operations to a single lane will be performed to

place safety measures and equipment access. Nighttime operations will result in noise impacts. Notices will be distributed to email distribution list and

directly to fire, rescue, and school personnel. VDOT to send press releases for major traffic shifts. Speed limit will be reduced from 45 mph to 40 mph during

construction.

Page 20: Belmont Ridge Road Pardon Our Dust meeting

20

http://www.virginiadot.org/projects/northernvirginia/belmont_ridge_road_widening.asp

(this webpage will be updated throughout the project development)

Or Google: “Belmont Ridge Road Widening”

Questions and Answers

For More Information About Route 659 Widening Project: