Shooting Schedule The first shoot will take place on Thursday 12 th November we will begin the shoot at 12:20pm and finish the shoot at 15:00pm this will allow us to have enough time to get some of the filming completed, we aim to reach about 30-40 seconds completed in this shoot. The second shoot will take place on Friday 13 th November and we will begin a little earlier then the previous shoot due to this being our media lesson and using time wisely would be key, in this shoot we will be then introducing the character we will start shooting at 11:00am and finish shooting at 12:20pm The third shoot will then take place on Monday 16 th November and we will begin at 12:20pm and then finish at 14:20pm in this shoot we will be finishing up the last seconds of the production and hopefully it will be finished at this point. The final shoot will take place on Thursday 19 th November and will begin at 12:20pm and end at 15:00pm, this shoot is back up just in case our production does not run smoothly or we miss a shot out by this time we would have looked at the production.

Shooting Schedule

Embed Size (px)

Citation preview

Page 1: Shooting Schedule

Shooting Schedule 

The first shoot will take place on Thursday 12th November we will begin the shoot at 12:20pm and finish the shoot at 15:00pm this will allow us to have enough time to get some of the filming 

completed, we aim to reach about 30-40 seconds completed in this shoot.  

The second shoot will take place on Friday 13th November and we will begin a little earlier then the previous shoot due to this being our media lesson and using time wisely would be key, in this shoot we will be then introducing the character we will start shooting at 11:00am and finish 

shooting at 12:20pm  

The third shoot will then take place on Monday 16th November and we will begin at 12:20pm and then finish at 14:20pm in this shoot we will be finishing up the last seconds of the production and 

hopefully it will be finished at this point.  

The final shoot will take place on Thursday 19th November and will begin at 12:20pm and end at 15:00pm, this shoot is back up just in case our production does not run smoothly or we miss a 