CONSTRUCTION OF CEMENT CONCRETE ROAD

Page 3: RIGID PAVEMENT -ANIL GUPTA (P.W.D)

3

SUBMITTED TO - SUBMITTED BY-

H.O.D CIVIL ENGINEERING Dr .V.K.GUPTA

HINDUSTAN COLLEGE OF SCIENCE & TECHNOLOGY

ANIL GUPTAVII SEM

1206400013

Page 4: RIGID PAVEMENT -ANIL GUPTA (P.W.D)

4

PUBLIC WORKS DEPARTMENT- AN OVERVIEW

Public Works Department (PWD), under the Ministry of Public Works department, is the pioneer in construction arena of Uttar Pradesh.

It plays a pivotal role in the implementation of government construction projects

To accelerate the construction of bridges in the state, Uttar Pradesh State Bridge Corporation was founded in 1973.

In year 2004-05, Uttar Pradesh state highways authority was established to overcome with problem of pavements in state.

Page 5: RIGID PAVEMENT -ANIL GUPTA (P.W.D)

5

INTRODUCTION

Development of a country depends on the connectivity of various places with adequate road network.

Roads constitute the most important mode of communication in areas where railways have not developed much.

India has one of the largest road networks in the world (over 3 million km at present).For the purpose of management and administration, roads in India are divided into the following five categories:

• National Highways (NH)• State Highways (SH)• Major District Roads (MDR)• Other District Roads (ODR)• Village Roads (VR)

Page 6: RIGID PAVEMENT -ANIL GUPTA (P.W.D)

6

WHAT IS ROAD AND PAVEMENT ?

Road is an open, generally public way for the passage of vehicles, people, and animals.

Pavement is finished with a hard smooth surface. It helped make them durable and able to withstand traffic and the environment. They have a life span of between 20 – 30 years.

• FUNCTIONS• One of the primary functions of pavement is load distribution. It can be

characterized by the tire loads, tire configurations, repetition of loads, and distribution of traffic across the pavement, and vehicle speed

Page 7: RIGID PAVEMENT -ANIL GUPTA (P.W.D)

7

TYPES OF PAVEMENTSThere are various types of pavements depending upon the materials used; a briefs description of all types is given here-

FLEXIBLE PAVEMENT

Bitumen has been widely used in the construction of flexible pavements for a long time. This is the most convenient and simple type of construction. The cost of construction of single lane bituminous pavement varies from 20 to 30 lakhs per km in plain area.Flexible pavement have-

Have low flexural strength

Load is transferred by grain to grain contact

Have low completion cost but repairing cost is high

Have low life span (High Maintenance Cost)

Page 8: RIGID PAVEMENT -ANIL GUPTA (P.W.D)

8

RIGID PAVEMENT

• Rigid pavements, though costly in initial investment, are cheap in long run because of low maintenance costs, The cost of construction of single lane rigid pavement varies from 35 to 50 lakhs per km in plain area,

• Rigid pavement have-

Deformation in the sub grade is not transferred to subsequent layers

Design is based on flexural strength or slab action

Have high flexural strength

No such phenomenon of grain to grain load transfer exists

Have low repairing cost but completion cost is high

Life span is more as compare to flexible (Low Maintenance Cost)

Page 9: RIGID PAVEMENT -ANIL GUPTA (P.W.D)

9

Longitudinal joint

Transverse joint

Subgrade Base

Surface Texture

Surface smoothness Thickness Design

Dowel bars

Concrete materials

Tiebars

Basic Components of a Concrete Pavement

Page 10: RIGID PAVEMENT -ANIL GUPTA (P.W.D)

10

Using mix Concrete , there some Point to construct the road-

1. Preparation of base2. Form working3. Preparation of subgrade4. Watering of base5. Joints6. Material mix & placing7. Compaction

Page 11: RIGID PAVEMENT -ANIL GUPTA (P.W.D)

11

Using mix Concrete , there some Point to construct the road-

8. Finishing of surface8A. Floating8B. Belting8C. Brooming9. Curing10. Joint filling11. Edging12. Open to traffic

Page 12: RIGID PAVEMENT -ANIL GUPTA (P.W.D)

12

1. Preparation of subgrade

1. Rolling on sub grade by roller2. Filling the granular soil in the weak part and pot

holes3. Correct the soil coat , Camber , longitudinal slop When concrete direct laid on subgrade, For preventing the water-seepaging into the soil , used water proof paper on entire length.

Page 13: RIGID PAVEMENT -ANIL GUPTA (P.W.D)

13

PREPERATION OF SUB GRADE

Page 14: RIGID PAVEMENT -ANIL GUPTA (P.W.D)

14

ROLLING OF SUBGRADE

Page 15: RIGID PAVEMENT -ANIL GUPTA (P.W.D)

15

2. Preparation of base

Choose any one type of base1. W.B.M. base As base material of W.B.M. Road; stone ballast, concrete 10-15cm layer are used. For bonding between concrete slab & W.B.M. used 1:2 cement wash on W.B.M.2. Concrete base On the road used 10cm Cement concrete(1:2:4) or lime concrete(16:32:64)

Page 16: RIGID PAVEMENT -ANIL GUPTA (P.W.D)

16

3. Granular medium material layer 10-15cm composite layer of sand , moorum , bajri are used for better drainage facilities4. Stabilization soil

Page 17: RIGID PAVEMENT -ANIL GUPTA (P.W.D)

17

3. Form work Material for form work- Wooden sheets, battens, plywood, fibre hard board, steel plates, angles, rope, minerals.

1. before using form work, it should free from all type material like as dust ,cement. 2. To placing the concrete in appropriate depth used 2.5-5cm thick and 3mtr long wooden sheeting.

Page 18: RIGID PAVEMENT -ANIL GUPTA (P.W.D)

18

3. The depth of wooden block must be same as level of slab thick. 4. After 24hrs form work displaced next length of road.

Page 19: RIGID PAVEMENT -ANIL GUPTA (P.W.D)

19

4. Watering of base

If base is dryThan using the sprinkling process on it properly after that placing the concrete.

Page 20: RIGID PAVEMENT -ANIL GUPTA (P.W.D)

20

5. JOINTS

Where is necessary to provide transverse, Longitudinal joints; there wedge of woods, metals fix on level of concrete. After setting of concrete it should be pull out. If provided the dowel bar in joints, bars should be fit at right position.

Page 21: RIGID PAVEMENT -ANIL GUPTA (P.W.D)

21

6. Material mix & placing

Mixer is equipment that mix the concrete using distinct amount of cement , concrete, sand and water. Concrete slab should have more than 5-10cm thick cause of drying.Used two type mixer-1. Batch mixer- at site, used for small road construction2. Continuous mixer- Continuous mixer used for large construction . if distance is more from site , mix concrete transported at site within setting time.

Page 22: RIGID PAVEMENT -ANIL GUPTA (P.W.D)

22

Page 23: RIGID PAVEMENT -ANIL GUPTA (P.W.D)

23

Laying of polyethylene sheet over DLC

Page 24: RIGID PAVEMENT -ANIL GUPTA (P.W.D)

24

Page 25: RIGID PAVEMENT -ANIL GUPTA (P.W.D)

25

Two methods generally used in placing of concrete-1. Alternate bay method- Placed the concrete on both side of road alternatively like as1,3,5… part at one side and 2,4,6… part other side . 1st side 2nd sideThis method have slow process due to road traffic problems.

Page 26: RIGID PAVEMENT -ANIL GUPTA (P.W.D)

26

2. Continuous bay method- construct one side of road regularly, if completed some part of first side than construct other side. this method have fast process without no obstruction of traffic

Page 27: RIGID PAVEMENT -ANIL GUPTA (P.W.D)

27

7. Compaction

Purpose of compaction is that to pull out air from void and make concrete harden. Compaction done by- 1.mechanically surface vibrator 2. manually hand tempers

Page 28: RIGID PAVEMENT -ANIL GUPTA (P.W.D)

28

8. Finishing of surface

1.Floating- For levelling the surface use floating, scree-ding , power trowel. So that there is no acceptable more than 3mm variation in concrete level surface.2.Belting- For making surface clean used belting process. Belt is nothing but a 15-30cm thick sheets of canvass which have more length than road.

Page 29: RIGID PAVEMENT -ANIL GUPTA (P.W.D)

29

Page 30: RIGID PAVEMENT -ANIL GUPTA (P.W.D)

30

3. Brooming- Brooming is the process in which we made rough surface parallel to road by brush. It useful in avoiding slip & comfortable travelling on road . the depth of line on road no more than 1.5mm.

Page 31: RIGID PAVEMENT -ANIL GUPTA (P.W.D)

31

Texturing of finished surface by texturing machine

Page 32: RIGID PAVEMENT -ANIL GUPTA (P.W.D)

32

9. Curing

Curing is the name of increasing the hydration process of cement. after setting the concrete , curing process done till 14-28days.

Page 33: RIGID PAVEMENT -ANIL GUPTA (P.W.D)

33

Some method of curing are-1.Shading concrete works2. Covering with hessian & gunny bags3. Sprinkling of water4.By ponding5. Membrane curing6. Steam curing

Page 34: RIGID PAVEMENT -ANIL GUPTA (P.W.D)

34

CURING

Page 35: RIGID PAVEMENT -ANIL GUPTA (P.W.D)

35

10. Filling joint

After drying road, clean the joints and fill the shelling compound or hot bitumen . also bitumen fill road bank.

Page 36: RIGID PAVEMENT -ANIL GUPTA (P.W.D)

36

11. Edging

To protect damaging the sides of concrete pavements used over burnt brick work. in place of brick, provided kerb of pre mix concrete.

Page 37: RIGID PAVEMENT -ANIL GUPTA (P.W.D)

37

12. OPEN TO TRAFFIC

Generally after a month, road should be open to traffic. If used rapid hardening cement it take 7 days to open traffic.

Page 38: RIGID PAVEMENT -ANIL GUPTA (P.W.D)

38

Advantages of Concrete Road

• Durability and maintenance free life• Vehicles consume less fuel• Resistant to automobile fuel spillage and

extreme weather• Greener process• Saving of natural resources• Eco friendly process