Upload
aditya-shah
View
91
Download
2
Embed Size (px)
Citation preview
POST TENSIONED FLOOR SYSTEM Prepared byAditya Shah (M.Tech CPM)
Building Construction System
INTRODUCTION
Post-tensioning is
simply a method of producing
prestressed concrete,
masonry, and other
structural elements
process of introducing
internal stress into a concrete
during the construction
process in order to counteract the external loads applied
when the structure is put
into use
Internal forces are applied by
tensioning HS steel
WORKING OF PT FLOOR
EXECUTIONMETHODOLOGY
Construction of post-tensioned slabs on grade is very similar to using reinforcing steel, except for the tensioning step. Step wise construction of post tension floor is given below.
1. Form work setup 2. Placing of bottom reinforcement 3. Fixing of bar chair for PT tendon 4. Placing PT tendon 5. Fixing anchorage burstling reinforcement 6. Placing of top reinforcement 7. Placing anchorage pocket former and grout vent 8. Fixing slab edge formwork with pocket former 9. Concreting of slab
10. Removal of slab edge formwork 11. Remove pocket former 12. Placing anchor head and wedge in position 13. Stressing 14. Cutting end of strand 15. Capping stressing recess with cement mortar 16. Grouting 17. Repeat for next floor slab
COMPONENTS
ADVANTAGES OF PT FLOOR
Lighter and Slender
members are
possible.
remains un-cracked
under Service load.
improves serviceabili
ty
Fast constructio
n can achieved
Flat soffit reduces
shuttering, plastering
and painting
cost.
Reduces building height
DISADVANTAGES
Chances of corrosion are high
Complexity of work
Lead to accidents
ECONOMICS
• Post-tensioned
should be considered as a possible economic alternative for most structures when spans exceed 7.0 meters.
ECONOMICS
P-T reduces the concrete volume by 10 to 20%.
Cost of PT is typically 20 to 30% less as compared to conventional reinforced structure.
For flat slab in 8m x 8m or 9m x 9m Grid, P-T costs approximately Rs. 40 to 50 per sq. ft. with any kind of desired geometry availed better than R.C.C.
Since the reinforcement is protected, P-T reinforced structures have lower annual maintenance costs overtime
SPEED OF CONSTRUCTION
The comparison of PT and RCC slab is carried out on Strata SE1 project located in center London. The building is a residential high-rise 147 meters in height with 41 post-tensioned flat slabs.
The average area of the slab is 630 sqm.
The floor cycle estimates using the same criteria for PT and RCC are respectively 5 and 6.5.
This yields a total increase of 60 working days between PT and RCC.
Time saving on the PT option is due to less material and hence less installation time and labor, to stressing of the tendons and consequently early deshoring.
The actual floor-cycle achieved on the PT slab was 4.5 days on average.
REFERENCES
[1] “POST-TENSIONING IN BUILDING STRUCTURES”, Ed Cross1 BE, Grad.Dip(Tech.Mgt), MIEAust, CPEng.
[2] POST-TENSIONED SLABS, PUBLISHED BY VSL INTERNATIONAL LTD.
[3] Sanfield (India) LTD., PT Slab brochure. [4] “A PROJECT-BASED COMPARISON BETWEEN
REINFORCED AND POST-TENSIONED STRUCTURES FROM A SUSTAINABILITY PERSPECTIVE.”, Carol Hayek & Saleem Kalil.
[5] www.concreteconstruction.net
Thank you