16
POST TENSIONED FLOOR SYSTEM Prepared by Aditya Shah (M.Tech CPM) Building Construction System

Post tension Floor System

Embed Size (px)

Citation preview

Page 1: Post tension Floor System

POST TENSIONED FLOOR SYSTEM Prepared byAditya Shah (M.Tech CPM)

Building Construction System

Page 2: Post tension Floor System

INTRODUCTION

Post-tensioning is

simply a method of producing

prestressed concrete,

masonry, and other

structural elements

process of introducing

internal stress into a concrete

during the construction

process in order to counteract the external loads applied

when the structure is put

into use

Internal forces are applied by

tensioning HS steel

Page 3: Post tension Floor System

WORKING OF PT FLOOR

Page 4: Post tension Floor System

EXECUTIONMETHODOLOGY

Construction of post-tensioned slabs on grade is very similar to using reinforcing steel, except for the tensioning step. Step wise construction of post tension floor is given below.

1. Form work setup 2. Placing of bottom reinforcement 3. Fixing of bar chair for PT tendon 4. Placing PT tendon 5. Fixing anchorage burstling reinforcement 6. Placing of top reinforcement 7. Placing anchorage pocket former and grout vent 8. Fixing slab edge formwork with pocket former 9. Concreting of slab

Page 5: Post tension Floor System

10. Removal of slab edge formwork 11. Remove pocket former 12. Placing anchor head and wedge in position 13. Stressing 14. Cutting end of strand 15. Capping stressing recess with cement mortar 16. Grouting 17. Repeat for next floor slab

Page 6: Post tension Floor System

COMPONENTS

Page 7: Post tension Floor System
Page 8: Post tension Floor System

ADVANTAGES OF PT FLOOR

Lighter and Slender

members are

possible.

remains un-cracked

under Service load.

improves serviceabili

ty

Fast constructio

n can achieved

Flat soffit reduces

shuttering, plastering

and painting

cost.

Reduces building height

Page 9: Post tension Floor System
Page 10: Post tension Floor System

DISADVANTAGES

Chances of corrosion are high

Complexity of work

Lead to accidents

Page 11: Post tension Floor System

ECONOMICS

• Post-tensioned

should be considered as a possible economic alternative for most structures when spans exceed 7.0 meters.

Page 12: Post tension Floor System

ECONOMICS

P-T reduces the concrete volume by 10 to 20%.

Cost of PT is typically 20 to 30% less as compared to conventional reinforced structure.

For flat slab in 8m x 8m or 9m x 9m Grid, P-T costs approximately Rs. 40 to 50 per sq. ft. with any kind of desired geometry availed better than R.C.C.

Since the reinforcement is protected, P-T reinforced structures have lower annual maintenance costs overtime

Page 13: Post tension Floor System

SPEED OF CONSTRUCTION

The comparison of PT and RCC slab is carried out on Strata SE1 project located in center London. The building is a residential high-rise 147 meters in height with 41 post-tensioned flat slabs.

The average area of the slab is 630 sqm.

The floor cycle estimates using the same criteria for PT and RCC are respectively 5 and 6.5.

This yields a total increase of 60 working days between PT and RCC.

Page 14: Post tension Floor System

Time saving on the PT option is due to less material and hence less installation time and labor, to stressing of the tendons and consequently early deshoring.

The actual floor-cycle achieved on the PT slab was 4.5 days on average.

Page 15: Post tension Floor System

REFERENCES

[1] “POST-TENSIONING IN BUILDING STRUCTURES”, Ed Cross1 BE, Grad.Dip(Tech.Mgt), MIEAust, CPEng.

[2] POST-TENSIONED SLABS, PUBLISHED BY VSL INTERNATIONAL LTD.

[3] Sanfield (India) LTD., PT Slab brochure. [4] “A PROJECT-BASED COMPARISON BETWEEN

REINFORCED AND POST-TENSIONED STRUCTURES FROM A SUSTAINABILITY PERSPECTIVE.”, Carol Hayek & Saleem Kalil.

[5] www.concreteconstruction.net

Page 16: Post tension Floor System

Thank you