Upload
gilberto-mejia
View
211
Download
9
Embed Size (px)
Citation preview
Insulation Coordination Studies“The Selection of Insulation Strength”
March 25, 2014Adam Sparacino
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES
Definition of Insulation Coordination1
• Insulation Coordination (IEEE)– The selection of insulation strength consistent with expected
overvoltages to obtain an acceptable risk of failure.– The procedure for insulation coordination consists of (a)
determination of the voltage stresses and (b) selection of theinsulation strength to achieve the desired probability of failure.
– The voltage stresses can be reduced by the application of surge‐protective devices, switching device insertion resistors and controlledclosing, shield wires, improved grounding, etc.
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 2
(1) IEEE Std 1313.1‐1996 “IEEE Standard for Insulation Coordination ‐ Definitions, Principles, and Rules.
Four Basic Considerations
• Understanding Insulation Stresses• Understanding Insulation Strength• Designing Methods for Controlling Stresses• Designing Insulation Systems
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 3
Four Basic Considerations
• Understanding Insulation Stresses• Understanding Insulation Strength• Designing Methods for Controlling Stresses• Designing Insulation Systems
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 4
Definition of Overvoltages
• Overvoltage– Abnormal voltage between two points of a system that is greater than
the highest value appearing between the same two points undernormal service conditions.2
• Overvoltages are the primary “metric” for “measuring” and“quantifying” power system transients and thus insulationstress.
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 5
(2) IEEE Std C62.22‐1991 ‐ IEEE Guide for the Application of Metal‐Oxide Surge Arresters for Alternating‐CurrentSystems, 1991.
Vocabulary of Voltage
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 6
Peak line‐ground VoltageRMS Voltage line‐ground = (Vpeak/√2)
Peak Voltage line‐ground = VL‐L_rms√2/√3
Illustration of Overvoltages
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 7
Four Basic Considerations
• Understanding Insulation Stresses• Understanding Insulation Strength• Designing Methods for Controlling Stresses• Designing Insulation Systems
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 8
Electrical Insulation
• Insulation can be expressed as a dielectric with a function topreserve the electrical integrity of the system.– The insulation can be “internal” (solid, liquid, or gaseous), which is
protected from the effects of atmospheric conditions (e.g.,transformer windings, cables, gas‐insulated substations, oil circuitbreakers, etc.).
– The insulation can be “external” (in air), which is exposed toatmospheric conditions (e.g., bushings, bus support insulators,disconnect switches, line insulators, air itself [tower windows, phasespacing], etc.).
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 9
Insulation Strength
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 10
Source: IEEE Std 62.22-1997, IEEE Guide for the Application of Metal-Oxide Surge Arresters for AC Systems
Typical Volt Time Curve for Insulation Withstand Strength for Liquid Filled Transformers
Insulation Strength
• Example for Transformers Windings– Normal system operating voltage
• 345 kVL‐L_RMS (1.00 p.u.)
– Maximum continuous operating voltage (MCOV)• 362 kVL‐L_RMS (1.05 p.u.)
– Basic switching impulse insulation level (BSL)• 745/870/975 kVL‐N_Peak
– Basic lightning impulse insulation level (BSL)• 900/1050/1175 kVL‐N_Peak
– Chopped wave withstand (CWW)• 1035/1205/1350 kVL‐N_Peak
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 11
Frequency of Different Events
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 12
Transients& Surges
Power System Control& Dynamics
milliseconds microsecondsseconds10-20 minutes Power
Frequency
Four Basic Considerations
• Understanding Insulation Stresses• Duty and Magnitude of applied voltage
• Understanding Insulation Strength• Ability to withstand applied stress
• Designing Methods for Controlling Stresses• Designing Insulation Systems
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 13
Potential Overvoltage Mitigation
1. Surge Arresters– Need to be sized and located properly to “clip” overvoltages.
2. Pre‐Insertion Resistors/Inductors– Need to be sized according to equipment being switched (only help
during breaker operation) to prevent excessive overvoltages frombeing initiated.
3. Synchronous‐Close/Open Control– Need to use independent pole operated (IPO) breakers and program
controller based on equipment being switched (only help duringbreaker operation) to prevent excessive overvoltages from beinginitiated.
4. Surge Capacitors– Need to be sized and located to “slow” the front of incoming surges
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 14
Four Basic Considerations
• Understanding Insulation Stresses• Duty and Magnitude of applied voltage
• Understanding Insulation Strength• Ability to withstand applied stress
• Designing Methods for Controlling Stresses• Designing Insulation Systems
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 15
Insulation Coordination Process
1. Specify the equipment insulation strength, the BIL and BSL ofall equipment.
2. Specify the phase‐ground and phase‐phase clearances thatshould be considered.
3. Specify the need for, location, rating, and number of surgearresters.
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 16
Insulation Coordination Studies
1. Very Fast Transients (VFT) Analysis (nanoseconds time frame)– GIS disconnected switching.– Quantify the overvoltages throughout the substation.– Primary intent of determining location and number of surge arresters
within the substation.2. Lightning Surge Analysis (microseconds time frame)
– Quantify the overvoltages throughout the substation.– Primary intent of determining location and number of surge arresters
within the substation.3. Switching Overvoltage Analysis (milliseconds time frame)
– Quantify the overvoltages and surge arrester energy duties associatedwith switching events and fault/clear operations.
– Primary intent is to verify that transient overvoltage mitigating devices(e.g., surge arresters, pre‐insertion resistors, synchronous close control)are adequate to protect electrical equipment.
– Capacitor, Shunt Reactor, Transformer, and Line Switching Studies.
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 17
Insulation Coordination Studies (cont.)
4. Temporary Overvoltage Analysis (seconds time frame)– Quantify the overvoltages and surge arrester energy duties as produced
by faults, resonance conditions, etc.– Primary intent is to verify conditions that cause problems within the
system and develop the necessary mitigation.– Fault/Clear, load rejection, ferroresonance studies.
5. Steady State Analysis (minutes to hours time frame)– Quantify voltage during various system configurations.– Power flow/stability studies.
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 18
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 19
EXAMPLE APPLICATIONSTUDY FOR INSULATION COORDINATION
LIGHTNING SURGE ANALYSIS
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 20
EAST 500 kV BUS
WEST 500 kV BUS
CB CB CB CB CB CB CB CB CB
DUMMY BUS (POSITION FOR FUTURE BREAKER)
GML00
G762W
G762E
GEB06
G752E
G752W
G3A00
B3A01
B3A00
G952E
G952W
GWB06
G962W
G962E
G972W
G972E
GLU00
G872W
BLU01
BLU00
G872E
G4A00
G772W
G772E
B4A01
B4A00
la = 30.70lb = 25.66lc = 21.76
la = 21.19lb = 20.74lc = 23.64
la = 70.62lb = 76.69lc = 82.77
la = 70.15lb = 76.25lc = 82.30
la = 26.42lb = 25.51lc = 24.59
la = 23.47lb = 22.56lc = 21.64
la = 23.47lb = 22.56lc = 20.64
la = 26.42lb = 25.51lc = 24.59
la,b,c = 8.323
la,b,c = 19.59la = 12.47lb = 11.55lc = 10.64
la,b,c = 19.59
la,b,c = 8.323
la = 9.518lb = 8.603lc = 7.689
la,b,c = 8.323
la,b,c = 5.634
la,b,c = 5.634
la,b,c = 8.323
BML00
BML01
500 kV LINE 500 kV LINE
Refer to Figure 2 for details of line terminations.
Refer to Figure 2 for details of line terminations.
XFMR Refer to Figure 3 for details of XFMR
terminations.
Refer to Figure 3 for details of XFMR
terminations.
XFMR
All lengths shown in meters.
Example for Line/XFMR Termination
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 21
Notes(1) Line traps only on phase A and C for 500 kV lines. In
EMTP model, phase B has a 2.53 m section of conductor modeled in place of line trap.
550 kV GIS
To GIS Bay #6
Line Trap1
CCVT
Gas-to-Air
Bushing
Surge Arrester
500 kV Line
350 MCM Ground Lead
(38’)
550 kV GIS
To GIS Bay
Gas-to-Air Bushing
Surge Arrester
To Transformer
350 MCM Ground
Lead (38’)
Approach for Evaluation the Insulation Coordination of the 550 kV Gas‐Insulated Substation
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 22
Step 1: A severe voltage surge was injected into the substation for variousoperating configurations to screen for maximum potential overvoltages.
Step 2: The resulting overvoltages were compared to the Basic Lightning ImpulseInsulation Level (BIL) of the equipment and the protective margin1 for theequipment was calculated.
Step 3: If overvoltages resulted in less than a 20% protective margin in the initialscreening analysis for cases with the full system in or N‐1 contingencies, a moredetailed analysis was performed to identify the protective margins resulting from areasonable upper bounds lightning surge based on the configuration of thesubstation and connected transmission lines.– For the detailed analysis, specific details of the transmission lines such as conductor
characteristics, shielding design, ground resistivity, keraunic level, etc. are considered todetermine a reasonable upper bounds to place on the lightning surge impinging on thesubstation.
(1) Protective Margin = [ BIL / Vmaximum_peak – 1] x 100%
Screen
ing An
alysis
Detailed An
alysis
Lightning Surge Incoming From 500 kV LinePhase‐to‐Ground Voltage of Incoming Lightning Surge
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 23
0
1000
2000
3000
4000
0 5 10 15 20
MLFULL_halfSRC>MLSRCA(Type 1)
Vol
tage
(kV
)
Time (us)
Peak = 3264 kV (1.2 x 2720 kV CFO)Time-to-peak = 0.5 microseconds.
Lightning surge impinges substation from 500 kV Line.
Lightning surge initiated at 1.0 microseconds.
Lightning Surge Incoming From 500 kV LineHighest Phase‐to‐Ground Voltage Observed in GIS
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 24
0
500
1000
1500
2000
0 5 10 15 20
MLFULLB>G752WB(Type 1)
Vol
tage
(kV
)
Time (us)
Peak overvoltage = 1109 kV.
GIS Basic Impulse Insulation Level (BIL) = 1550 kV
Protective Margin = 40% ([1550/1109 – 1] x 100%)
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 25
EXAMPLE APPLICATIONSTUDY FOR INSULATION COORDINATION
TRANSMISSION LINE SWITCHING ANALYSIS
Transmission Line Switching Analysis
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 26
• Excessive Transient Overvoltages and the Possibility of a Flashover During Energizing or Re‐Closing
• Overvoltages Exceeding Guidelines Used to Develop Line Clearances
Potential Equipment Concerns
Transmission line is energized (normal energizing or re-closing).
• Synchronous‐Close Control• Pre‐Insertion Resistors/Inductors• Surge Arresters• Shunt Reactors
Potential Mitigation Techniques
• Basic Switching Impulse Level (BSL)• Probability of Flashovers
Applicable Criteria
Statistical Switching Methodology
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 27
Tclose
Three poles closing centered around closing
time (Tclose)
3 = ¼ cycle ÷ 2 = 2.08 ms
Sliding ¼ cycle window for pole closing shifted over a half cycle
timeframe using a uniform distribution
Each pole can close at anytime within the ¼ cycle window centered around the closing time (Tclose) for
each energization. Random closing times based on a normal (Gaussian)
distribution
¼ cycle window
Source-Side Voltage
Case simulated with 200-400 energizations
Electro‐Geometric Line ModelExample 345 kV Transmission Line
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 28
14.5’ 14.5’
27’
B C A
27’
54’(24’ at midpoint)
78’ (63’ at midpoint)
CenterLine Line Length (total) = 85 mi
UntransposedGround resistivity = 37 Ohm‐m
Phase Conductor:ACSR Lapwing2/c Bundle 18” spacingOutside diameter = 1.504”RDC = 0.059 Ohm/miThick/Diam = 0.375
Shield Wire:Alumoweld 7#8Outside diameter = 0.385”RDC = 2.40 Ohm/mi
Statistical Switching Overvoltage Strength Characteristics and SOV densities of the line
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 29
Statistical Distr. Of Overvoltages Along 500 kV Line with NO Surge Arresters
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 30
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
110%
1.00 1.50 2.00 2.50 3.00 3.50 4.00
Prob
ability to
Exceed Overvoltage (%
)
Peak Overvoltage (Per Unit on a 500 kV Base)
Statistical Distribution of Overvoltages Along Line
Sending End
1/4 Point
1/2 Point
3/4 Point
Remote End
Example CFO
Estimated insulation withstand for the
transmission line: CFO = 3.53 p.u., f/CFO =5%.
E2 is the value in which the overvoltages exceed 2% of the
switching operations.
Highest overvoltage at the remote end of the line = 2.75
p.u. (1123 kV).
98% of the overvoltages along the line are ≤ 2.62 p.u. (1070
kV).
Statistical distribution based on
the case‐peak method from IEEE Std 1313.2‐1999.
Statistical Distr. Of Overvoltages Along 500 kV Line withLine End Surge Arresters
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 31
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
110%
1.00 1.50 2.00 2.50 3.00 3.50 4.00
Prob
ability to
Exceed Overvoltage (%
)
Peak Overvoltage (Per Unit on a 500 kV Base)
Statistical Distribution of Overvoltages Along Line
Sending End
1/4 Point
1/2 Point
3/4 Point
Remote End
Example CFO
Estimated insulation withstand for the
transmission line: CFO = 3.53 p.u., f/CFO =5%.
E2 is the value in which the overvoltages exceed 2% of the
switching operations.
Highest overvoltage along the line = 2.21 p.u. (902 kV).
98% of the overvoltages along the line are ≤ 2.16 p.u. (882
kV).
Statistical distribution based on
the case‐peak method from IEEE Std 1313.2‐1999.
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 32
EXAMPLE APPLICATIONSTUDY FOR INSULATION COORDINATION
SHUNT CAPACITOR SWITCHING ANALYSIS
Shunt Capacitor Switching Analysis
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 33
• Contact Wear from Excessive Inrush Current Duty
• Excessive Transient Overvoltages• Induced Voltages and Currents in
Control Circuits• Step and Touch Potentials During
Switching
Potential Equipment Concerns
Capacitor bank is energized and transient inrush currents flow through capacitor bank breaker and voltage surges propagate into the system.
• Current‐Limiting Reactors• Synchronous‐Close Control• Pre‐Insertion Resistors/Inductors• Surge Arresters
Potential Mitigation Techniques
• ANSI/IEEE Inrush Current Limits• Basic Switching Impulse Level (BSL)• Breaker Capability Beyond Standards• IEEE Std 80 for grounding
Applicable Criteria
Capacitor Bank Re‐StrikeDuring De‐Energization
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 34
Current Through Switching Device Voltage on Each Side of Switching Device
Current is interrupted
First restrike occurs and current is re‐established
High frequency current is interrupted
Second restrike occurs and current is re‐established
Voltage on capacitor bank side of
switching device (DC trapped charge)
Voltage on system side of switching
device
Peak overvoltage from 1st restrike
Peak overvoltage from 2nd restrike
Voltage Magnification
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 35
• When a shunt capacitor bank is energized with a nearbycapacitor at a lower voltage, the potential for voltagemagnification may exist when the following condition is true:
1 1 2 2
• Furthermore, when C1>>C2, and L1<<L2 the condition can be exaggerated
Voltage Magnification (Cont.)
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 36
Example 1.95 p.u. overvoltage at HV bus when capacitor bank is switched.
Example 4.39 p.u. overvoltage at LV bus when capacitor bank is switched.
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 37
EXAMPLE APPLICATIONSTUDY FOR INSULATION COORDINATION
SHUNT REACTOR SWITCHING ANALYSIS
Shunt Reactor Switching Analysis
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 38
• Excessive Inrush Currents from Energizing
• Transient and Temporary Overvoltages from Resonance Conditions
• Generation of Harmonics• Resonance from Parallel Lines
Potential Equipment Concerns
Shunt reactor is energized and inrush current flows through the
system and circuit breaker.
• Synchronous‐Close Control• Surge Arresters• Appropriate Relay Settings• Operational Limitations
Potential Mitigation Techniques
• Equipment Insulation Levels• Voltage Sag/Dip Criteria• Harmonic Distortion
Applicable Criteria
Resonance Overvoltages
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 39
345 kV Substation
Voltage Measured on Energized Line
Line in service (breakers closed at both ends)
Line out of service (breakers open at both ends)
345 kV Substation
345 kV Substation 345 kV Substation
Resonance Overvoltages
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 40
Peak overvoltage = 2.94 p.u.
It is anticipated that the line equipment would be capable of withstanding at
least 1.5 p.u. for 100 ms.
Line breakers open to trip the line at 200 ms.
The shunt reactors should be tripped within 550 ms of the line breakers
tripping to avoid excessive overvoltages for this case.
Anticipated temporary overvoltage (TOV) capability (1.5 p.u. for 100 ms).
Summary
• Insulation Coordination is the selection of insulation strength.• Determine maximum insulation stress.• Determine the minimum insulation strength with margin taking into
account stress reducers (surge arresters, pre‐insertion resistors,synchronous close control, etc.) that can withstand the maximumstress.
• Studies help in quantifying the maximum anticipated stressand determining the rating/location of overvoltage mitigatingdevices.
• A key component of insulation coordination is pairing thecorrect strength to the correct stress.• As a rule of thumb, the shorter the time the overvoltage is applied to
the insulation the greater the magnitude of overvoltage the insulationcan withstand before failure.
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 41
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES 42
THANK YOU FOR YOU ATTENTION