The Real Life SolutionPrepaid by : Bhdresh KumbhaniMob no: +91 80002 58225
CHAROTAR UNIVERSITY OF SCIENCE AND TECHNOLOGY Department of Civil Engineering
INTRODUCTION
• India has one of the world's largest railway and roadway network transporting millions of people every year.
• India’s most of the road pavement are made up of bituminous material and failure occurs in the pavement due to different soil condition, temperature variation and material etc.
• In use bitumen material in road pavement so many problem in the road pavement potholes, shrinkage, many type of cracking
GENERAL CAUSES OF PAVMENT FAILURES
• Defects in the quality of materials used.
• Defects in construction method.
• Increase in the magnitude of wheel loads and the number of load repetition due to increase in traffic volume.
• Environmental factors including heavy rainfall, soil erosion, water table, snowfall, forest action, etc…
PROBLEM IN THE REAL LIFE
• Cracking in pavements
• Potholes in pavements
• Shrinkage in pavements
• Swelling in pavements
WHY THIS PROBLAMS OCCURS IN ROAD PAVEMENT
• In India has a most of road pavement are a flexible pavement and Rigid pavements so when the loads are apply on pavement in a few years load is properly and after pavement is failure.
FLEXIBLE PAVEMENTCOMPOSITION LAYERS OF FLEXIBLE PAVEMENT
• When the load apply in pavement, load is transfer to ground by safely.
• but a after few year lower sub grade is failure in ground.
LAYERS OF RIGID PAVEMENT RIGID PAVEMENT SLAB
• When the load apply in pavement, load is transfer to ground by safely.
• but a after some time lower sub grade is failure in ground.
LOAD DISTRIBUTION IN FLEXIBLE PAVEMENT LOAD DISTRIBUTION IN RIGID PAVEMENT
• As show in fig. when the load is apply in road pavement aggregate are secreted.
• That’s why in a road pavement upper layer is disturb so generated Cracking, Potholes, Shrinkage, Swelling etc…
WHAT IS THE SOLUTION IN THE REAL LIFE
• Use a geosynthetics material in a road pavement.
• The American Society for Testing and Materials (ASTM) has defined geosynthetics : “A planar product manufactured from polymeric material used with soil, rock, earth, or other geotechnical engineering related material as an integral part of a man-made project, structure, or system.”
• Common types of geosynthetics are geogrids, geotextiles, geocomposites, geonets, and geomembranes and our review would concentrate on geotextiles and geogrids
TYPES OF GEOSYNTHETIC MATERIAL
• Geogrids
• Geotextiles
• Geocomposites
• Geonets
• Geomembranes
• Geotextiles
• Geogrids
• The polymers used in the manufacture of geotextile fibers are made from polypropylene (83%), polyester (14%), polyethylene (2%) and polyamide, nylon (1%).
• The melt process accounts for most geotextile fibers; these include polyolefin, polyester, and nylon.
DIFFERENCE BETWEEN GEOSYNTHETICS AND WITHOUT GEOSYNTHETIC
CONTROL IN AGGREGATE LOSES BY GEOSYNTHETICS
In current time in Gujarat has a so many place use geosynthetic material in road pavement
• Surat bardoli highway Use Geotextile material
ADVANTAGE OF GEOSYNTETIC MATERIAL
• Easily accessible in market
• Life of road pavement is more
• It’s simple technic not hared
• Not require good skill person
• It is economic in financially condition
• It is less cost compeer to without geosyntetic material
DESCRIPTIONWITH
GEOSYNTHETICS(mm.)
WITHOUT GEOSYNTHETICS
(mm.)
TOTAL PAVEMENT THICKNESS 640 690
SURFACE COURSE 40 40
BINDER COURSE 90 100
GRANULAR BASE 250 250
GRANULAR SUB BASE 260 300
CALCULATE SOME DATA
• GRADE OF GEOGRID AMOUNT ( PR. SQ.MTR)
TGB-30 120/-
TGB-40 150/-
TGB-60 180/-
TGB-90 220/-
GRADE OF GEOTEXTILE AMOUNT (PR.SQ.MTR)
PR-15 32/-
PR-20 42/-
PR-25 55/-
PR-30 65/-
PR-40 85/-
• COST OF GEOGRIDS
• COST OF GEOTEXTILE
• COST OF ROAD (USING GEOSYNTHETIC)
• COST OF ROAD (WITHOUT USING GEOSYNTHETIC)SR NO.
DESCRIPTION UNIT RATE QTY.5%CBR
TOTAL AMOUNT5%CBR
1 SURFACE COURSE m3 6900/- 28 193200/-
2 BINDER COURSE m3 6500/- 70 455000/-
3 GRANULAR BASE m3 850/- 147.9 125715/-
5 GRANULAR SUB BASE
m3 400/- 352.8 141120/-
SR NO.
DESCRIPTION UNIT RATE QTY.6%CBR
TOTAL AMOUNT6%CBR
1 SURFACE COURSE m3 6900/- 28 193200/-
2 BINDER COURSE m3 6500/- 63 409500/-
3 GRANULAR BASE m3 850/- 127.14 108069/-
4 GEOSYNTHETIC MATERIAL
m3 700/- 263.5 184450/-
5 GRANULAR SUB BASE
m3 400/- 300 120000/-
1) TOTAL COST OF ROAD WITHOUT GEOSYNTHETIC:
1114465/-
TOTAL
1114465/-
2) TOTAL COST OF ROAD USING GEOSYNTHETIC
1026971/-
COST OF GEOSYNTHETIC MATERIAL USED
42000 + 16864
TOTAL
1085835/-
100m LENGTH (APP.)
REFERENCES
• “Method and design of flexible pavements and rigid pavements ” guide by asst. Professor, devang patel ( cspit civil dept.)
• S.K. Shukla “Functions and Installation of Paving Geosynthetics”
• Praveen Kumar “Case Studies on Failure of Bituminous Pavements”
• S.K. Khanna “highway engineering”
• Find the rate of material with help of internet
Prepaid by : Bhdresh Kumbhani
Mob no: +91 80002 58225