Feasibility studies using GIS spatial data to determine areas lacking access

Fiber design efficiencies cost savings

Embed Size (px)

Citation preview

Feasibility studies using GIS spatial data to determine areas lacking access

Fiber Design Efficiencies cost savings

1. Drive teams dispatched to drive up and down streets in a target area to determine Aerial vs. Underground construction

2. Drive teams sketch proposed routes and send to CAD to create prelim field drawings, usually takes weeks to convert field notes to actual drawings for the field

3. After prelim route drawings created in CAD drive teams re dispatched to collect pole data & construction details for CDs

4. Field data collected sent in to complete pole applications, ROW permits and to the CAD Dept. to create a set of actual Construction Drawings

1. Aerial vs. Underground assessment completed via raster images embedded in GIS mapping takes days vs. weeks or months

2. Route drawings are created in mapping as part of the assessment process. A few clicks and you print scaled field drawings for survey teams.

3. The scaled GIS drawings go to the field so teams can collect pole data & verify underground constructability.

4. Field data can be collected and input electronically to create CDs. Mapping utilities can auto complete pole applications, determine municipalities to contacted for permits.

Traditional Method Our Approach

Aerial & Underground Fiber Build Cost Synopsis

Some communications providers have excess fiber strands. Fiber count in cables ranges from 6 to 24 near residences and individual businesses to more than 1,000 on backbone routes. The cost of a 6-count fiber cable is $2,000 per mile, while an 864-count cable is $50,000 per mile, implying a marginal cost of approximately $50 per fiber per mile. Actual costs for fiber purchase or lease, of course, reflect market costs and depend on the total availability of fiber over the route–and are thus, typically, considerably higher; however, fiber lease or purchase may be a serious consideration over routes where construction is difficult or costly and considerable fiber has already been installed (e.g., river crossings, tunnels).

Aerial Versus Underground Typical construction is a mixture of aerial and underground techniques. Aerial construction can be completed for $20,000 per mile. Aerial construction may be more expensive when poles are crowded or when the utility pole owner charges high rates for access. Worst-case costs can be $100,000 per mile (which usually would lead a network owner to build underground or over another route). Underground construction also has a wide cost range. In areas where restoration is not important and long continuous runs are possible (e.g., rural areas, in dirt, on the side of interstate roads), “plowing” the fiber into the ground is an inexpensive option— approximately $40,000 per mile. In more built-up areas, directional boring is necessary, because it is less destructive to the right-of-way and requires less restoration. Boring is more expensive, approximately $60,000 to $100,000 per mile. Boring also limits the amount of cable and conduit that can be built. (Two 2-inch conduit is a typical limit, corresponding to four medium-sized fiber optic cables.)

Drawings created in GIS mapping software. Right of Way, Geography and Demographic Spatial data is imported and analyzed to make the business case. Please note the

elaborate geocompression analytical tools in the drop down window A few clicks and we print scaled field drawings for teams to drive.

Aerial vs. Underground route assessments are completed using embedding Raster images translucently in the background of our GIS mapping software. Screen shot below shows a mile high view of a given target area. GIS designs eliminates the need for field teams driving every road in the area to see if poles exist on streets for aerial route planning. Red dots are poles for aerial placement, blue dots are

vault placements for underground routes (purple lines).

Screenshot below is zoomed into the center of previous mile high Raster imagery view. Designing in a virtual world significantly reduces overall engineering time and cost.

How we use imagery to find existing poles for aerial cable routing.

Screenshot below is zoomed into an underground portion to show level of detail available to accurately design UG paths and structure placement.

Using Raster images embedded translucently in ESRI GIS allows the drafter is able to see actual field conditions as they plan routes and placement of PON cabinets and underground structures. Traditionally this was done in CAD. All the drafter saw was black and white ROW & pavement lines. All too often these structures were drawn in middle of sidewalks or other places they couldn’t be installed. The ole “looks

good on paper” was not an efficient method of network drawing creation .

Below depicts how we use Google Earth or Bing street view feature to conduct a virtual survey of planned routes. In doing so we assess the extent of aerial make ready

and identify UG constructability issues. Note this street is very light make ready (only one cable attached) and has existing UG fiber. You can see the fiber optic

cable marker post.

Electronic pole data collection for aerial attachments. The attachments can be captured via (DMT) Digital Measuring Technology. We can import

electronic pole data to GIS using ESRI conversion tools.

Below is example of the Ocalc system Osmose developed for the RBOC ‘s.

Below is GE’s answer to the Osmose product offering

GIS data exported to auto populate pole sheets and attachment applications reducing field survey costs.

The data can be collected manually (shown below) or electronically . If collected manually we insert spreadsheet data to mapping via layer attributes.

GIS mapping utilities also determine municipalities, agencies and pole owners to be contacted for cable attachments, ROW, zoning and permitting.

Below is a sample Verizon Pole Application Below is a typical neighborhood demographic shown in spatial data

OSP Fiber Installation Tracking and Splicing Quality Control