35
DSLIP 2015 Final Report DCC-SU-LAU Internship Program Joanna Ding

DSLIP 2015 Technical Report

Embed Size (px)

Citation preview

 

DSLIP 2015 Final Report DCC-SU-LAU Internship Program

Joanna Ding

  2

ABSTRACT

The Dubai Contracting Company was founded in 1962 by the late

Hasan Abdallah Yabroudi. The company specializes in residential,

commercial, mixed-use buildings along with hospitality and leisure

complexes. The DCC-SU-LAU Internship Program started in 2008 in

honor of Dr. Samuel P. Clemence and Dr. James A. Mandel by DCC

CEO Mr. Abdallah Yabroudi. The internship brings together aspiring

civil engineers from Syracuse University and Lebanese American

University for a valuable learning experience in the booming city of

Dubai. In the summer of 2015, the DSLIP interns visited seven (7) DCC

project sites and ten (10) relevant offices/plants. This report will cover

all sites in descriptive and observational details in order to reflect

lessons learned from each visit.

  3

Table of Contents JUMEIRAH VILLAGE RESIDENTIAL BUILDING .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5

INTRODUCTION .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5 PROJECT DETAILING . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6 OUTSTANDING ISSUES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7

FAREED TOWER .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8

INTRODUCTION .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8 PROJECT DETAILING . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9 SPECIAL FEATURES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10 HANDS-ON ACTIVITY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11

BRIGHT START HOTEL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12

INTRODUCTION .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12 PROJECT DETAILING . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13 SPECIAL FEATURES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14 HANDS-ON ACTIVITY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15

PRIVATE VILLA – PALM JUMEIRAH .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16

INTRODUCTION .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16 PROJECT DETAILING . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17 SPECIAL FEATURES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18

KHALFAN VILLA .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19

INTRODUCTION .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19 PROJECT DETAILING . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20 SPECIAL FEATURES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21 HANDS-ON ACTIVITY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21

FOUR SEASONS HOTEL AND RESORT .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22

INTRODUCTION .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22 PROJECT DETAILING . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23 SPECIAL FEATURES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24 OUTSTANDING ISSUES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26

  4

BURJ AL SALAM .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27

INTRODUCTION .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27 PROJECT DETAILING . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28 SPECIAL FEATURES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29 OUTSTANDING ISSUES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30

ERGA PROGRESS ENGINEERING CONSULTANTS .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31

ROLEX TOWER .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31

READY MIX BETON .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32

EXOVA .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33

ALBONIAN INTERNATIONAL .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33

E.CONSTRUCT .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34

DCC WORKSHOP .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 35

  5

Jumeirah Village Residential Building

Introduction

The Jumeirah Village Residential Building is a mid-rise residential building located in Al

Barsha South 4th, Dubai, U.A.E. The design-build project is developed by Rambyk

Properties Limited and designed by Erga Progress Engineering Consultants. The

original contract is valued at AED 53,543,000. The total plot area for the development

is 2,377 m2, and the total built-up area is 10,880.40 m2. The construction process will

last 16 months and be completed in July of 2016. Delays due to unwarranted

dewatering are expected to push back the completion date.

The B+G+5+R residential building consists of the following elements:

• Parking areas on the basement and ground level

• Retail areas on ground floor

• 61 apartments with balcony space from ground to 5th floor, including 31 one-

bedroom apts. and 30 two-bedroom apts.

• Two (2) passenger elevators

• One (1) gymnasium on 5th floor

• One (1) swimming pool with leisure deck at roof level

Figure 1. Jumeriah Vil lage Res identia l Building Rendering

  6

Project Detailing

Construction

The project is currently in

the mobilization stage with a

complete shoring system in

place. The shallow

excavation done within

demarcation points is

entirely surrounded by steel

I-beams spaced 2-m apart,

filled with reinforced

concrete planks. This system

will be removed once the

ground floor slab is set.

Subsequently, a block wall

will be constructed within the shoring perimeter and steel shutters will be set up inside.

A concrete wall will then be poured between the two installments. As a final precaution

to prevent cracks, the space between the concrete wall and the shoring wall will be

filled with sand. Dewatering pumps are set up to extract ground water. However, the

dewatering process has been suspended due to insufficient capacity determined by

the Dubai municipality.

Structural Details

The building is supported by a framework of reinforced concrete ground beams tied to

and stabilized by isolated footings, above which a 150-mm thick reinforced concrete

ground floor slab is constructed. The slab is connected to the level above by reinforced

concrete columns to make the complete structure a continuous frame. All slabs, beams,

and parapets are made of suspended post-tensioned concrete or reinforced concrete.

Figure 2. On site of excavat ion

  7

Finishes

On the exterior, the structure is clad in thermal insulated blocks finished in plaster with

paint, aluminum window frames, doors and louvres pre-finished in paint, as well as

tempered glass in tinted and hermetically sealed double glazed units up to 34-mm

thick. The roofs are layered from concrete tiles, insulation, screed, down to the bottom

waterproofing membrane. Balcony balustrading is tempered-laminated glass and

pergola is galvanized steel on powder-coated aluminum cladding.

On the interior, standard concrete block construction with plaster finish constitutes the

internal partitioning system. Gypsum board suspended ceilings are adopted with

ceiling voids finished in Gypsum plaster to conceal all MEP services. Floors are

generally covered in tiles resting on the cement screed base.

Outstanding Issues

The unexpected halt to dewatering and the resulting delay in overall project

completion time has been the most

outstanding issue on the project site. The

project cannot be moved forward without

the enabling works fully finished and idle

labor is kept on the contractor’s payroll.

However, the nature of the delay dictates

that the contractor has the right to file for an

EOT or extension of time.

Figure 3. Excavat ion reveal ing water table level

  8

Fareed Tower Introduction

The Fareed Tower is a high-rise luxury

residential building located in Business Bay,

Dubai, U.A.E. The building project is

developed by National Trading & Developing

Est. and carried out in design by dxb.Lab

Architecture as well as Erga Progress

Engineering Consultants. The original

contract is valued at AED 109,000,000. This

development consists of a total plot area of

2,141 m2 and a total built-up area of 18,119

m2. The construction is planned to take place

over a period of 22 months and to be

completed in April of 2016.

The 3B+G+22+R luxury residential building consists of the following elements:

• Parking areas on the three basement levels

• 20 apartments located on 20 separate levels

• One (1) smaller apartment on level 12 (including a technical area)

• Two (2) car lifts operating between the ground level and all three basement

levels

• One (1) swimming pool at roof level

• One (1) gymnasium on level 2

Figure 4. Fareed Tower Rendering

  9

Project Detailing

Construction

The project is currently in the concrete works stage with a complete substructure and a

superstructure in progress. The dewatering process has been completed and the

structure is erected up to the 8th level. Plastering is in progress Due to project capacity

demand, the concrete used for cast-in-place columns are double pumped to higher

elevations.

Structural Details

In an effort to highlight the individuality of the

building design, the below-ground structures—

including the basement, podium, and canopy—

form a 5-sided plot shape while the tower itself is

rectangular. This is done primarily to suit end use

and lower the development cost without

diminishing the project’s originality.

The tower rests on a raft foundation and standard

shoring piles. The piles are only installed on

three of the five sides of the plot due to existing

ground levels and the project’s close proximity to

the road. Reinforced concrete retaining walls are

constructed at the basement level. The concrete

columns in the superstructure are made from

reinforced concrete and are constructed with

corbels to support the 200-mm thick precast

concrete floor slabs topped by a 6-mm layer of wire

mesh and a 75-mm layer of concrete. The columns

are integrated into the façade, providing sufficient

vertical structural support on the perimeter to

optimize the span of unobstructed internal space.

Core columns and shear walls have been poured to resist seismic and wind loads.

Figure 6. Steel reinforcing bars for precast concrete slabs

Figure 5. Shear walls in construction

  10

Finishes

On the exterior, the façade is consisted of a curtain walling system from ground to

second floor level, above which individual glazing panels will be installed. Additional

aluminum features and integrated lighting are to be used to soften its appearance. The

materials used to finish entrance doors, vertical louvres, and balcony railings are

tempered glass and powder coated aluminum.

On the interior, all concrete block walls are to be constructed with autoclaved aerated

concrete (AAC) lightweight blocks to reduce the overall dead load. The block wall

finishes are standard plastering and painting. Standard gypsum boards are used for the

suspended ceilings with a 3.85-m story height to conceal all MEP services. Floors are in

engineered solid wood parquet with walnut joinery finishes to match the doors,

skirting, and cupboards. Common areas such as the lifts and the entrance lobby will be

enhanced with dimmed lighting and marble flooring. Basement floors will be layered

with traffic deck coating. Reflective pool features, glass partitions, and stone clad

walling will also be installed in the lobby. In the apartments, the bathrooms will have

high-end fixtures with marble finished walls and floors, while the kitchens will be

equipped with Siemens appliances and European cupboards, work-tops, and

accessories.

Special Features

While on site, the closely spaced concrete

columns become one of the most prominent

features. From a structural standpoint, the size

and amount of the concrete columns as vertical

support seem excessive for any type of dead or

live load. Instead, these columns act as distinct

architectural elements on the building façade as

cut-off points for window units. This particular

feature is unique in that it shifts the function of

traditionally structural elements like concrete

columns to an architectural one. Figure 7. Tightly knitted column perimeter

  11

The use of car lifts in lieu of traditional car ramps is another special feature employed in

the building construction. The innovative car lifts are designed to maximize parking

spaces by eliminating the use of intra-level ramps that are traditionally used for vehicles

to travel between different basement levels. These hydraulic lifts used to raise or lower

cars directly onto different floor levels are both time and space efficient and are

beneficial to both the developer and the residents. The additional automatic

gatekeeping security system makes this development a prime example of IT

connectivity’s increasingly significant role in civil construction projects.

Hands-on Activity

Concrete block work

For a first-hand experience in construction of a building project, the interns were given

the opportunity of laying block work with lightweight AAC blocks on site. In order to

satisfy all standards, the process requires a specific set of techniques—marking,

preparing mortar, and fixing blocks. Reference points marked on site by surveyors were

set up and aligned with fishing lines to guide the intern’s block work. The markings are

transcribed from the construction

drawings are pivotal in precise

placement of block walls. Bags of mortar

consisted of cement and sand is poured

along with enough water to create a

workable mix. The mix should have an

even consistency and smoothly fill in the

100-mm wide gaps between the

concrete blocks. Once the mortar is set

and an entire row of blocks is placed,

inspection and adjustment of the block

alignment is carried out before placing the next layer.

Figure 8. DSLIP intern laying block work

  12

Bright Start Hotel

 

Introduction

The Bright Start, Four Seasons Hotel is a hotel situated within a previously completed

building structure located in DIFC, Dubai, U.A.E. The building project is developed by

Bright Start L.L.C. and designed by Erga Progress Engineering Consultants and interior

designer Tihany Design New York. The original contract is valued at AED 171,000,000.

This project has a total plot area of 1,590 m2 and a total built-up area of 15,128 m2. The

construction will last 20 months and be completed in November of 2015. Due to MEP

service delays, the project is now expected to finish in January of 2016.

The 5B+G+8+HC hotel compound consists of the following elements:

• Parking from B2 to B5

• Staff changing, laundry, washing and refuse areas on level B5

• Two (2) Lobbies on level B2 and the podium level

• 106 guest rooms from level 1 to level 7

• One (1) swimming pool, one (1) gymnasium, and a health spa on level 7

• A sky bar, a cigar lounge and terraces on level 8 and level 8M

Figure 9. Br ight Start Hotel Rendering

  13

• Restaurants, bars, and coffee lounges on the podium level

• Meeting rooms on level B2

• Staff changing, laundry, washing and refuse areas on level B5

• Mechanical/technical rooms and staff areas on the hypocaust level

Project Detailing

Construction

Due to the unique nature of the project, the

construction sequence is different from a

traditional project. Since the beginning of

2015, the initial demolition and concrete

repair works have been complete. The tasks

currently undertaken are internal partitions

and fitting out, façade lighting, as well as lift

works. The recent focus has been put on

MEP services in terms of installation,

concealing, and obtaining sufficient overhead clearance after installation.

Structural Details

The existing structure is a reinforced insitu concrete framed superstructure originally

designed as an apartment complex. The structure is supported on a reinforced

concrete raft and pile caps on bearing piles, with shoring piles for the depth of the

basement levels. The new development has modified the structural components by

creating new openings, demolishing certain parts of the existing building, as well as

providing for additional support. The extra structural strengthening for the added loads

is done mainly with carbon fiber, steel plates, and column jacketing. The weight of the

additional support is then compensated for by stiffening the raft foundation.

Finishes

On the exterior, the existing glass and aluminum façade will be removed and replaced

with a new tempered glass and powder coated aluminum curtain walling system.

Figure 10. Partially constructed building façade

  14

On the interior, all AAC lightweight block walls are to be finished with plaster and

paint. The block walls finishes are standard plastering and painting. Ceilings are

suspended plain gypsum board ceilings finished with emulsion paint to conceal all MEP

services. Carpet flooring is used in guest rooms and corridors (some rooms are also to

receive parquet flooring with marine plywood backing), while Novelda cream limestone

is used in the bathrooms and marble in the main lobbies. The guest room walls are to

be finished in plaster under a layer of stucco, and finally covered in fabric wall covering;

bathrooms use the same cream limestone; and the corridors will receive vinyl

wallpapers.

Special Features

In order to reduce noise traveling between adjacent guest

rooms, insulation panels made of soft rubber material are

inserted between two 100-mm thick lightweight AAC block to

make up the soundproofing walls separating all guest rooms.

This insulation process is also done in the flooring panels to

muffle noises created by rapid movements. This unique feature

is included to specifically suit the building’s need as a hotel.

The finished look of a standard guest room is demonstrated

through an extensively decorated and neatly arranged mock up

room. The mock up room serves as a model unit showcasing the

materials and finishes to the client and the designer while

simultaneously providing as a sample for future construction and layout.

Figure 11. Insulat ion layer between block

wall panels

Figure 12. Mock-up room display

  15

Hands-on Activity

Tiling

The interns were instructed to place tiles on a previously

plastered bathroom wall. The process is consisted of

several steps. First, the mortar mix is placed on the wall

and a trowel is used to create grooves in the paste for

better adhesion. The tiles are rested against the

mortared wall, aligned and spaced from existing tiles

with spacers. Excess mortar will be removed and the

tiles are left to set in place. Normally, the grouting

procedure is carried out after all tiling works are set, but

the interns were given the opportunity to do so as a part

of the learning experience. The grouting mix is carefully

placed between tiles to fill in the void and left to set. A

final clean up of the tile surface with wet sponges is done to complete the work.

Wall Finishing

The interns were separated into two groups to simultaneously carry out stucco and

paint finishes on a plastered bedroom wall. Through the activity, the interns learned

that the usual wall finish sequence on top of the plaster, in order, is stucco, sanding,

additional stucco layers if needed, and finally a layer of paint.

Figure 13. DSLIP intern placing mortar on the wall

Figure 14. DSLIP intern troweling stucco

  16

Private Villa – Palm Jumeirah

 

Introduction

The private villa is a single family dwelling situated on Frond N of the Palm Jumeirah in

Jumeirah 381, Dubai, U.A.E. The turnkey project is built for Mr. Abdul Hamied Ahmed

Qassim Seddiqi and designed by AS.Architecture-Studio and Erga Progress

Engineering Consultants. The original contract is valued at AED 27,500,000. This

development consists of a total plot area of 1,581.21 m2 and a total built-up area of

1177.3 m2 with 153 m2 of service/garage areas. The construction will take place for 18

months and be completed in October of 2015.

The G+1 villa consists of the following units:

• Two (2) living rooms on the ground level

• One (1) guest bedroom and one (1) children’s room on the ground level

• One (1) dining room on the ground level

• One (1) maid’s room with WC, shower, and kitchen on the ground level

• One (1) master suite with dressing room and library on level one

Figure 15. Palm Jumeirah Private Vil la Render ing

  17

• Four (4) bedroom suites on level one

• One (1) family room and a gallery area on level one

• One (1) passenger lift with a six-passenger load capacity

• A two-car garage on the ground level

• A roof terrace and technical room on roof level

• A private beach, terracing/patio areas, and landscaping on the ground level

• Perimeter walling, gates, and fencing

Project Detailing

Construction

The project construction is in the façade and finishing stage with all concrete works in

place.

Structural Details

The villa rests on a 150-mm thick reinforced concrete ground floor slab supported by a

framework of reinforced concrete ground beams. The ground beams are tied into and

stabilized by pile cap foundations on 48 500-mm diameter piles driven to a depth of 16

meters. All floor and roof slabs, beams, and parapets are post-tensioned and

reinforced concrete, supported between the levels by reinforced concrete columns to

make the complete structure a continuous frame. The technical room on the roof is in

structural steel and concrete.

Façade Details

The building façade is consisted of

thermal insulated blocks finished in

limestone panels that are fluted in

the living room pod to create a

checker-board effect, aluminum

window frames, doors, and louvres

finished in baked on paint, and glass

up to 34-mm thick hermetically

sealed double glazed units tempered and tinted to meet highest performance Figure 16. Vil la façade

  18

standards. The use of full-height glass panels connects the building’s interior

seamlessly to the outside environment. Roofs are concrete tiled on a layer of insulation

on a layer of screed on a layer of waterproofing membrane to provide protection

against both foot traffic and heat transference. Balcony balustrading is monolithic

tempered-laminated glass up to 19-mm thick.

Finishes

Internal partitioning is concrete block

construction with a plaster finish. The

walls in the formal living room are clad in

oakwood, while the casual living room is

finished in walnut. Ceilings on the interior

are gypsum board suspended ceilings

with bulkhead returns to facilitate the full

height external glazing. External ceilings are finished with calcium silicate for moisture

resistance. Floors have cement screed bases.

Stainless steel is used between different

finishes and marble finishes are

bookmatched. Waterproofing treatment is

applied to the ground floor as a safety

precaution against flooding.

Special Features

The villa is equipped with an Otis gearless passenger lift that has a load capacity of 450

kilograms, the equivalent of approximately 6 passengers. The cabin will be finished

with brush stainless steel for the walls and front return, safety glass framed in brush

stainless steel for the door, round type stainless steel finish for the handrail, Grigio vagli

scuro honed tiles for the floor, and walnut wood veneer with LED strip light and

spotlight for the ceiling.

Figure 17. Marble bookmatching

Figure 18. Shear resistant gypsum board ceil ing

  19

Khalfan Villa

 

Figure 19. Rendering of Khalfan Vil la

Introduction

The Khalfan villa is a single family dwelling situated in Umm Suqeim, Dubai, U.A.E. The

project is built for Mr. Osama Ibrahim Ahmad Seddiqi and designed by Erga Progress

Engineering Consultants. The original contract is valued at AED 4,275,000. The villa

has a total plot area of 1393.5 m2 and a total built-up area of 505.9 m2 with 40.7 m2 of

service/garage areas. Project construction will last 12 months and is expected to finish

in November of 2015. Due to efficient planning and execution, the project will be

completed in June of 2015, nearly four months ahead of the predetermined schedule.

The G+1 villa consists of the following units:

• One (1) double height living room on the ground level

• One (1) foyer/office on the ground level

• One (1) kitchen and one (1) dining room on the ground level

• One (1) maid’s room with WC, shower, and kitchen on the ground level

• One (1) master suite with dressing room on level one

• Three (3) bedroom suites on level one

• One (1) family room on level one

• One (1) passenger lift with a six-passenger load capacity

• One (1) two-car garage on the ground level

  20

• One (1) swimming pool and a roof terrace on external ground level

• Landscaping on the ground level

• Roof deck on the roof level

• Perimeter walling, gates, and fencing

Project Detailing

Construction

The project is currently in the finishing stage of façade, internal finishes, and external

works such as painting, grouting, and

pool waterproofing. Repairing works

are in progress for minor cracking and

thermal expansion/shrinkage of the

structure since the A/C began

operating.

Structural Details

The villa rests on a 150-mm thick reinforced concrete ground floor slab supported by a

framework of reinforced concrete ground beams. The ground beams are tied into and

stabilized by isolated footings. All floor and roof slabs, beams, and parapets are

reinforced concrete, supported between the levels by reinforced concrete columns to

make the complete structure a continuous frame.

Façade Details

The building façade is consisted of

thermal insulated blocks finished in

plaster with paint, aluminum window

frames, doors, and louvres finished in

baked on paint, and glass up to 34-

mm thick hermetically sealed double

glazed units tempered and tinted to

meet highest performance standards. Figure 6. Vil la façade

Figure 20. External works

  21

The roofs are concrete tiled on a layer of insulation on a layer of screed on a layer of

waterproofing membrane to provide protection against both foot traffic and heat

transference.

Internal Finishes

Internal partitioning is concrete block construction with a plaster finish. Ceilings are

gypsum board suspended ceilings with bulkhead returns to facilitate the full height

external glazing. Floors have cement screed bases. Door frames and doors are lime

oak. The staircase and the first story corridor have

glass balustrading. The extensive use of glass on

the interior required installation of floor plugs.

Kitchens are equipped with white quartz

countertops, laminate cabinets with internal

lighting, and high-end Siemens appliances. The

bedrooms are finished with parquet flooring and

skirting. Wardrobes have white lacquer doors and

internal sensor lights. The side roof deck is lined

with calcium silica for insulation.

Special Features

The Khalfan Villa is built as an exact replica of the private villa located in Al Barsha as a

means of value engineering to expedite the completion of the project and eliminate

design complications. The villa is constructed for lease by the client and employs

neutral construction elements to suit a wide variety of interest. The garage door is also

removed due to existing perimeter fencing as a part of the contractor’s commitment to

value engineering.

Hands-on Activity

The interns were instructed to make a list of snags and outstanding works from each

room in the villa.    

Figure 21. Inter ior glass finishes

  22

Four Seasons Hotel and Resort

 

Figure 22. Outdoor view of the resort

Introduction

The luxurious beach resort comprised of a five-star hotel and ancillary buildings is

located on Jumeirah Beach Road, Dubai, U.A.E. The project is developed by H.H.

Investment and Development, operated by Bright Start L.L.C., and designed by DSA

Architects International along with Hyder Consulting Middle East Ltd. The original

contract is valued at AED 354,000,000, with AEW 187,000,000 being provisional sums

under the client’s control. This development consists of a total built-up area of 60,000

m2. The construction process takes place over a period of 25 months and is expected

to be complete in March 2014 according to the program of works. Due to various

changes of order for both construction material and landscaping design along with

sub-contractor inefficiencies, the project was delayed by 6 months. However, the hotel

operation commenced in December as scheduled.

The resort consists of the following units:

• 223 guest rooms including two (2) presidential suites and one (1) royal suite

• In-house restaurants, bars, and lounges

• Three (3) swimming pools including two (2) outdoors and on (1) in-house

• One (1) pool restaurant

  23

• Three (3) ballrooms including one (1) in separate compound and two (2) in-house

• Cabanas and super-cabanas for hotel guest access only

• Private beach for hotel guest use only

• Outdoor facilities include lounge areas, grass areas, and tennis courts

• Underground car park

Project Detailing

Structural Details

The foundation of the main V-shaped hotel building consists of 939 piles, each 750 mm

in diameter and 22 m in length. The foundation is topped with pile caps and floor slabs

on grade under all wings of the compound. The structure is made of reinforced

concrete throughout, with the exception of the ball room in the North wing. Steel is

used in the ball room to increase its span and provide for a sizable space for large scale

events. The underground car park is formed on a 450-mm thick reinforced concrete raft

foundation. Retaining walls that support the basement area are cast-in-place reinforced

concrete.

Façade Details

The façade of the structure

is cavity-wall construction

with a plaster finish made

from glass reinforced

concrete (GRC) and carved

plaster. The GRC columns

are non-structural and are

constructed to give the

project a distinct theme.

The flat roof areas are

insulated with waterproofing membrane underneath a layer of aggregate. The pitched

roof areas are covered in themed roof tiles for aesthetic purposes. Other elements such

as special cast-aluminum balconies with paint finish and aluminum windows also reflect

the antiqued theme. Solar neutral glass is installed to reduce heat transference into the

building. Acoustic treatment is also done to minimize external noise distractions.

Figure 23. Bui lding façade and soft landscaping

  24

Internal Finishes

All internal walls are plaster finished solid block construction, with the exception of the

ball room in the North wing. The steel structure is finished with high performance

insulation to provide the facility with a sound acoustic environment. Entrance finishes

include marble, themed carpets, and mosaics on the floor, polished plaster and

wallpaper on the walls, and gypsum and paint on the ceiling. Public areas throughout

the hotel have a combination of marble and carpet flooring, decorative paint finish and

timber paneling on the walls, and painted gypsum

ceiling with decorative mouldings.

Lifts are finished with marble flooring and timber

paneling on the walls. Flooring around the indoor

pool consists of black absolute granite specially

treated to be anti-slippery. Public bathrooms are

clad in anti-fungus and fire-rated vinyl wallpaper

for maintenance and safety purposes. Kitchens

are finished in vinyl with no 90° corners to suit the

maintenance needs of the facility. Wall guards are

installed to protect the kitchen walls from heavy

moving equipment.

In the guest rooms, flooring consists of themed

carpeting, marbled wet areas, and ceramic tiles on

the balconies. Wall finishes are paint, wallpaper, timber paneling, and marble. False

ceilings installed to conceal MEP services are finished in paint and trimmed with

decorative gypsum and timber cornices. The doors, wardrobes, wall paneling, and

vanity units are all timber with a factory applied paint finish.

Special Features

Upon entrance, guests encounter a full height glass window made of a 2-ton glass

panel from Belgium leading out to the beach area. The weight of the glass panel

required additional reinforcement in the surrounding wall.

Figure 24. Finishes in lobby area

  25

Marble columns are installed in the lobby area in

hexagonal shapes with book matching to appear 3-

dimensional. The columns are mechanically fixed, and

stand open-jointed with no grouting.

Gold elements are extensively used throughout the hotel

as a recurring theme. 30cm x 30cm mosaic sheets plated

with 24-karat gold are used as wall decorations; gold

flakes filled man-made glass is used as staircase

balustrading; gold tiling can also be found in the indoor

swimming pool.

The renovation of the presidential suite on the South wing added luxurious features

such as a private gym, a water feature, use of frosted glass, as well as a comprehensive

security system to provide for the highest level of confidential entry and personal

protection. The private gym is constructed on the tail of the hotel’s South wing and

overlooks the entire resort. The gym runs on a separate A/C unit and is a stand-alone

structure accessible only from the roof deck through a narrow bridge connecting it to

the suite. Frosted glass is used on two of the four sides of full-height glass façades to

obstruct the view onto the neighboring Dubai Ladies Club. A water feature is installed

directly in the entrance area to be mirrored on both sides of the full-height glass

Figure 25. Bookmatched marble columns

Figure 26. Gold wall, gold flakes in balustrading, and gold mosaic t i les

  26

window. Considering the temperature difference on the two sides of the glass window,

the cutout glass panel design around the full

water feature is eliminated. Instead, a full glass

panel is installed and the water feature is cut in

half and aligned as one. Access to the corridor

outside the suite is restricted. The guest has the

option of bypassing public entrance and

entering through a private lift that leads out to a

private passageway directly opening up to the

suite through an aluminum sliding door.

Outstanding issues

The landscaping work on the exterior retaining walls constituted a major problem in

the later stages of construction. According to the

program of works, approximately 600 m2 of stones was

required to be put up each day and there was neither

sufficient stone supply nor labor force to fill the quota.

In order to resolve the issue, plaster mortar/concrete

mix was poured and molded into irregular stone

shapes and the “stones” were finished with spray paint

to create natural color tones. The solution not only met

the client’s specifications and reduced the time of

installation, but also proved to be very cost efficient.

Figure 27. Pr ivate gym in presidentia l suite

Figure 28. Spray painted concrete "stones"

  27

Burj Al Salam Introduction

The mixed-use development comprised of

three adjoined towers and a separate car

park building is located in Trade Centre First,

Dubai, U.A.E. The project is developed by

Abdul Salam Al Rafi Group and designed by

Erga Progress Engineering Consultants along

with Meinhardt Consulting Engineers. The

original contract is valued at AED

849,992,250. The towers consist of a total

plot area of 6,283 m2 and a total built-up

area of 292,144 m2 while the car park has a

plot area of 3,025 m2 and a built-up area of

44,695 m2. The construction process takes

place over a period of 930 days and is

expected to be complete in March 2013

according to the program of works. Due to the employer’s subsequent agreement with

the hotel operator on structural alteration works and finishes, both the value and the

duration of the project have been prolonged. While the residential and the office

towers were finished on time, the hotel tower was delayed for approximately 20

months and began operation in December 2014.

The mixed-use development consists of the following units:

• Three (3) 4B+G+54 building towers

• One (1) 4B+12 car park structure connected to main building by foot and

vehicular bridges

• One (1) pool and one (1) gym on the roof of parking structure

• 54 stories of 510 apartments in the residential tower

• 50 stories of 281 offices in the office tower

• 54 stories of 483 guest rooms and 180 serviced apartments in the hotel tower

• 48 lifts in total in the main tower building

Figure 29. Rendering of Burj Al Salam

  28

• Technical floors on level 30 and level 54 in all three towers

• One (1) swimming pool, one (1) gymnasium, and one (1) play area in the hotel

tower

• Four (4) basement and two (2) podium parking levels with 798 parking spaces

• Additional 1,170 parking spaces are offered in the car park structure

Project Detailing

Structural Details

Both the main tower building and the car park structure are supported by a raft

foundation on piles with reinforced concrete retaining walls at the basement levels. The

building superstructure is reinforced concrete, with post-tensioned slabs from level 7 to

the roof level for additional head room. The car park building has a structural steel

framed superstructure with steel decking topped by 7-cm concrete screed. Due to the

existing 6-story structure, steel reinforcement and carbon fiber strengthening are done

on the structure.

Façade Details

Unitized curtain walling glass in high

performance aluminum framed glazing and

travertine stone paneling is used for the

building façade. Distinctive features include

stainless steel louvers and LED lighting

boxes. The car park structure is clad in

precast concrete with 7-cm concrete screed

covered in fireproofing paint. Stainless steel,

glass, and powder coated aluminum is used

for entrance doors, vertical louvers, link

bridges, balcony partitions and balustrades.

Internal Finishes

All internal walls are lightweight block work with plaster and a layer of decorative paint

on top. In enclosed public areas, ceilings are suspended gypsum and floors are

Figure 30. Bui lding façade

  29

typically porcelain with mosaic tiling in wet areas. The

residential lobby area has book-matched Calcutta

marble on the floor and the countertops. The partition

wall and decorative wall paneling in the entrance area

are white onyx with backlight with surrounding crown-

cut walnut veneer walls. Crown-cut walnut veneer

finish is also used on doors, wardrobes, vanities and

kitchen cabinets. The apartments are supplied with

high-end Siemens kitchen appliances and lift-and-slide

balcony doors for safety reasons.

Typical flooring in the office tower consists of

timber, plywood, acoustic material for

soundproofing, 50 mm of screed, and epoxy

and waterproofing treatment. The office lobby is

clad in gray marquina marble and decorated

with titanium paint finished steel water features.

Mirrors are used in certain ceiling areas to create

a sense of large open space. All doors are fire

rated at 60 minutes throughout the towers as a

safety precaution. In the technical room, all

pipes ducts resting on the floor are on elevated

grounds to control vibration from MEP services.

The floor on the technical level is acoustically

treated for the same consideration.

Special Features

Although the building is a continuous structure operating under a central building

manager, it is divided into three towers of different end uses. The division required

additional civil works on top of the 6-story existing structure, careful planning of MEP

services, as well as safety precautions such as intricate evacuation route designation.

The lift system used in the tower is designed in Switzerland and employs the

Destination Floor Reservation System (DFRS) where passengers are grouped into

different lifts by the floor level they indicate as their destination. The office portion of

Figure 31. Backli t onyx

Figure 32. Water feature

  30

the project is delivered as “shell and core” to allow

for customization of the interior space and reduce

the work load for the main contractor. Due to

utility lines running under the building, trees and

other natural green features were not permitted.

Instead, green walls are installed at the entrance of

the residential tower as aesthetically pleasing and

sustainable soft landscaping.

Outstanding issues

Complaints from neighboring hotel about falling objects were one of the main

concerns during the construction process. Although precautions were taken for the

neighboring pool to be covered, the follow-up repair for damages and clean-up work

delayed the project for one (1) month.

 

Figure 33. Green wal l feature

  31

Erga Progress Engineering Consultants Erga Progress Engineering Consultants is a consultancy, design and supervision

oriented firm originally founded in 1982 in Beirut, Lebanon. The company expanded to

establish its Dubai office in 2003 by Mr. Joseph Sawaya at the request of DCC CEO Mr.

Abdallah Yabroudi. The company has since completed over 380 projects in the U.A.E.,

90% of which are in collaboration with DCC. Although Erga Progress has established

itself as a reputable consultancy company over the greater Middle East region, their

most eminent projects are located in Dubai in collaboration with DCC, which include

the O14 Tower, the Rolex Tower, as well as the Burj Al Salam. During the visit, Mr. Elio

Gebrayel gave a short lecture on

industry standard procurement

strategy and contract selection. It

was particularly interesting to note

that he pinpointed the design-build

procurement strategy, where the

contractor and the designer are

selected as one, as the key to the

company’s successful business

relationship with DCC.

Rolex Tower The Rolex Tower is a mixed-use residential/commercial building completed in 2010

with collaborative effort from DCC, Skidmore, Owings & Merrill Architects and Erga

Progress. The owner of the tower is the largest local Rolex watch distributor Seddiqi &

Sons. The tower is very unique in that it is one of very few residential buildings in the

world that offer data connectivity through built-in services preinstalled by the owner.

As the founder of IT Works Mr. Amir Kolahzadeh explained, the IT industry has matured

thus far that connectivity is becoming the 4th utility and provides added value for

building structures. The tour of the tower showcased many of the building’s most

innovative IT infrastructure including the POP (Point of Presence), the IDF (Intermediate

Distribution Frame) on every two floors, the BMS (Building Management System), the

CCTV (Closed-Circuit Television), the RFID (Radio-Frequency Identification) Security

Figure 34. DSLIP interns at Erga Progress office

  32

System, as well as an advanced intercom system. These components all come together

to provide recognition intelligence and connectivity, giving the residents a unique and

quality living experience.

Ready Mix Beton Ready Mix Beton is a concrete batch plant founded back in 1975 that keeps a close

business relationship with DCC as its main concrete supplier. Mainly using Type I and V

concrete, RMB is able to produce mixes with

compressive strength reaching 100MPa. During

the visit, Mr. Abel William took the time to

identify and discuss different cementitious

materials that are added to the mixes to improve

concrete performance while reducing

environmental impact. Some of the most

commonly used materials, aside from the OPC

(Ordinary Portland Cement) and the SRC (Sulfate

Resistance Cement), include fly ash, GGBS (Ground Granulated Blast Slag), and micro-

silica fume. Fly ash and GGBS are both known for their role in reducing the heat

dissipation and increasing the overall durability of the mix. Fly ash is typically used to

avoid thermal cracks and increase concrete

workability particularly in the process of

pumping. Microsilica also plays a significant

role in boosting durability. Concrete durability

is generally measured with four tests—Water

Absorption Test, RCP (Rapid Chloride

Permeability), Water Permeability Test, and the

ISAT (Initial Surface Absorption Test). Testing is

normally done on 150mm x 150mm cubes and

six (6) cubes are removed for testing at a time.

Additional additives include admixtures such as super plasticizers to generate

workability and ice flakes to reduce temperature. The plant produces a maximum of

100 m3 of concrete mix per hour, and up to 2500 m3 per day.

Figure 36. Standard concrete test ing cubes

Figure 35. Additive materials on display

  33

Exova Exova is a global material testing laboratory that provides test results on the

performance, strength,

durability, and corrosion

resistance of materials. In the

civil laboratory, standard

concrete cubes are used in

grading, PI (Plastic Index), CBR

(California Bearing Ratio), and

vibration testings to measure

performance and durability.

Concrete cubes are kept in

curing tanks with water

temperature at around 20°C

before being removed for testing. In events of coring sampling and MEP works, cover

meters are used to locate the steel rebars before the drilling takes place. The chemistry

lab is responsible for water quality monitoring and testing, namely BOD, COD, and

alkalinity values. In addition, the company also specializes in façade testing where non-

loadbearing exteriors are replicated from real projects and tested against shear loads

and fire hazard. Addition performance testing for façades include air linkage, water

linkage, acoustics, and thermal testing.

Albonian International Albonian International was first established in Lebanon in 1987. It is currently

headquartered in Al Quoz Estate 3, Dubai and operates as the main MEP

subcontractor for DCC. During the office visit, Mr. Amir Rushdy and Mr. Ali Hammad

gave an informative presentation on how MEP services are installed and used in a

construction project and its sustainability aspect. The lecture familiarized the interns

with the how basic components of the MEP system such as electrical, mechanical,

plumbing, and the HVAC systems function in relation to building spaces. Mr. Rushdy

explained how these basic concepts translate to larger topics in civil engineering

projects such as fire protection, water supply, electricity distribution, and energy

Figure 37. Curing tanks in the civi l laboratory

  34

efficient solar heating systems in order for civil engineers to thoroughly carry out

construction projects. A tour around the Bright Start Business Hotel was given later in

the day on MEP features such as distribution boards, A/C units, and water supply

pumps to help the interns visualize the lecture material.

e.Construct e.Construct is an international structural engineering consulting company that

specializes in structural design and value engineering. The interns were given a lecture

on precast conrete, prestressed concrete, as well as GFRC (Glass Fiber Reinforced

Concrete) by Mr. Jack Kara’a, Mr. Musa Alawneh, and Mr. Nasr Yahia, respectively. The

basic design, fabrication, and construction use of each type of concrete is explained

along with their advantages and disadvantages. A

case study was done on the precast bridge in the Abu

Dhabi Airport and one was done on the One

Thousand Museum in Miami, Florida. The precast

bridge is constructed with precaste concrete slabs

and beams to support large loads expected on the

decking. The One thousand Museum employs GFRC

cladding and permanent formwork as non-structural

elements that are innovatively integrated into the final

product. The

interns took a

visit to the

Arabian Profile GRC/GRP plant after the lectures

to witness the production process, and mock-up

products, and testing procedures of the material.

GRC/GRP are primarily used as decorative

façade elements and don’t serve any structural

functions.

Figure 38. GRP moulding

Figure 39. GRC façade display

  35

DCC Workshop The DCC workshop is

situated in 22000 m2 of

storage area in Jebel Ali

for assorted crane

materials and mobile

units. DCC constructed

cranes have an average

freestanding height of 50

meters and lift from 1.5

tons to 6 tons of weight.

Storage manager Mr.

Bennet guided the interns

through the workshop,

which included working

areas for carpentry and

metal fabrication. The workshop is responsible for a variety of site facilities such as site

fencing, signage, offices, as well as scaffolding. The interns were given a demonstration

of the hydraulic mobile crane operation as well as a tour around the garage, where

construction vehicles for smaller working areas like backhoes and telehandlers were

closely examined.

Figure 40. Standard DCC tower crane