URAIAN ANALISA HARGA SATUAN
TOWER CRANE
URAIAN PERALATAN
1. Jenis Peralatan : Tower Crane, type ST60/15 dengan radius 60 m Genset, dan standard mesin 150 KVA
2. Tenaga (Pw) : 150,0 HP
3. Kapasitas (Cp) : 15,0 ton
4. Umur Ekonomis (A) : 5,0 tahun ( Alat Baru )
5. Jam Operasi Dalam 1 Tahun (W) : 2.000 jam ( Alat Baru )
6. Harga Alat (B) : Rp 150.000.000 ( Alat Baru )
HARGA STANDAR
1. Tingkat Suku Bunga (i) : 20,00 % / Tahun
2. Upah Operator / Sopir (U1) : Rp 25.000,00 / Jam
3. Upah Pembantu Operator / Pmb.Sopir (U2) : Rp 20.000,00 / Jam
4. Bahan Bakar Bensin (Mb) : Rp 6.500,00 / Liter
5. Bahan Bakar Solar (Ms) : Rp 5.500,00 / Liter
6. Minyak Pelumas (Mp) : Rp 40.000,00 / Liter
OWNING COST
1. Nilai Sisa Alat (C) = 10 % x Harga Alat Baru
= 10 % x Rp. 150.000.000
= Rp. 15.000.000
2. Faktor Angsuran Modal (D) = i×(1+i)A
(1+i)A−1
= 0,20× (1+0,20 )5
(1+0,20 )5−1
= 0,33438
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal (E) = ( B - C ) x D
= (150.000.000 - 15.000.000) x 0,33438
= Rp. 45.141.300,00
b. Asuransi, dll (F) = 0,002×BW
=0,002×15 0.000 .000
2000
= Rp. 150,00
4. Biaya Pasti per Jam (G) = ( E + F )
= ( Rp. 45.141.300,00 + Rp. 150,00 )
= Rp. 45.141.450,00
BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar (H) = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms
= (0.125-0.175 Ltr/HP/Jam) x 150 x Rp. 5.500,00
= Rp. 103.125,00
2. Pelumas (I) = (0.025-0.030 Ltr/HP/Jam) x Pw x Mp
= (0.025-0.030 Ltr/HP/Jam) x 150 x Rp. 40.000,00
= Rp. 150.000,00
3. Perawatan dan perbaikan (K) = (12,5 %−17,5 %)×B
W
= (12,5 %−17,5 %)×110.000.000
2000
= Rp 6.875,00
4. Operator (L) = ( 1 Orang / Jam ) x U1
= ( 1 Orang / Jam ) x 2.500,00
= Rp 2.500,00
5. Pembantu Operator (M) = ( 1 Orang / Jam ) x U2
= ( 1 Orang / Jam ) x 2.000,00
= Rp 2.000,00
6. Biaya Operasi per Jam (P) = ( H + I + K + L + M )
= (12.187,50 + 13.500,00 + 6.875,00 + 2.500,00 + 2.000,00)
= Rp 37.062,50
TOTAL BIAYA SEWA ALAT / JAM (S) = ( G + P )
= (16.661,80 + 37.062 = Rp 53.724,30/ jam
ANALISA MASING – MASING HARGA SATUAN
PERKIRAAN HARGA JUMLAHNO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. PEKERJA
1. - - - -2. - - - -
B. BAHAN
1. - - - -2. - - - -
C. ALAT
1. CRANE 10-15 TON jam 1,0000 53.724,30 53.724,302. - jam - - -