39
NO. KOEF. SAT. JUMLAH PEKERJAAN PERSIAPAN 1 m2 - Pembersihan Lokasi 1 Pekerja 0.0500 hr 55.000.00 2.750.00 2 Mandor 0.0100 hr 70.000.00 700.00 JUMLAH 3.450.00 DIBULATKAN 3.450.00 1 bh - Papan nama proyek Multipleks 122 x 244, 9 mm 0.5000 lbr 103.360.00 51.680.00 Cat kayu/besi 1.1000 kg 25.840.00 28.424.00 Kaso kayu meranti 0.0280 m3 2.876.860.00 80.552.08 Penulisan 1.0000 ls 56.000.00 56.000.00 Ongkos pasang 1.0000 ls 32.000.00 32.000.00 JUMLAH 248.656.08 DIBULATKAN 248.656.00 1 m2 - Direksikeet (lantai plesteran) 1 Pasir pasang 0.2500 m3 150.000.00 37.500.00 2 Pasir beton 0.0517 m3 150.000.00 7.755.00 3 Batu bata merah 25.0000 bh 700.00 17.500.00 4 Semen PC 50 kg 0.2500 zak 60.000.00 15.000.00 5 Kayu kaso meranti 0.0300 m3 2.876.860.00 86.305.80 6 Triplek 122 x 244 x 4 mm 1.0000 lbr 50.000.00 50.000.00 7 Engsel pintu uk 3 " 0.1667 bh 25.080.00 4.180.84 8 Asbes semen gelombang 250x92 x 0. 5 cm 0.5000 lbr 40.130.00 20.065.00 9 Kaca polos 5 mm 0.2917 m2 102.600.00 29.928.42 10 Rangka teralis nako 0.2917 bh 9.120.00 2.660.30 11 Paku segala ukuran ( rata-rata) 0.5000 kg 15.000.00 7.500.00 12 Kunci gembok kecil 0.0834 bh 10.260.00 855.68 13 Pekerja 0.4000 hr 48.000.00 19.200.00 14 Tukang batu 0.0834 hr 55.000.00 4.587.00 15 Tukang kayu 0.3340 hr 55.000.00 18.370.00 16 Mandor 0.0200 hr 70.000.00 1.400.00 JUMLAH 322.808.04 DIBULATKAN 322.808.00 1 m1 - Pengukuran & pemasangan bouwplank 1 Kayu Kaso terentang 5/7-400 cm 0.0040 m3 1.197.100.00 4.788.40 2 Kayu Papan terentang 2/20- 400 cm 0.0060 m3 1.197.100.00 7.182.60 3 Paku segala ukuran 0.0200 kg 15.000.00 300.00 4 Pekerja 0.0500 hr 55.000.00 2.750.00 5 Tukang Kayu 0.0500 hr 55.000.00 2.750.00 6 Mandor 0.0050 hr 70.000.00 350.00 JUMLAH 18.121.00 ANALISA HARGA SATUAN PEKERJAAN DINAS TATA KOTA - KOTA BANDUNG HARGA SATUAN URAIAN

Analisa Harga Satuan Pekerjaan

Embed Size (px)

DESCRIPTION

contoh analisa harga satuan pekerjaan

Citation preview

Page 1: Analisa Harga Satuan Pekerjaan

NO. KOEF. SAT. JUMLAH

PEKERJAAN PERSIAPAN

1 m2 - Pembersihan Lokasi

1 Pekerja 0.0500 hr 55.000.00 2.750.00

2 Mandor 0.0100 hr 70.000.00 700.00

JUMLAH 3.450.00

DIBULATKAN 3.450.00

1 bh - Papan nama proyek

Multipleks 122 x 244, 9 mm 0.5000 lbr 103.360.00 51.680.00

Cat kayu/besi 1.1000 kg 25.840.00 28.424.00

Kaso kayu meranti 0.0280 m3 2.876.860.00 80.552.08

Penulisan 1.0000 ls 56.000.00 56.000.00

Ongkos pasang 1.0000 ls 32.000.00 32.000.00

JUMLAH 248.656.08

DIBULATKAN 248.656.00

1 m2 - Direksikeet (lantai plesteran)

1 Pasir pasang 0.2500 m3 150.000.00 37.500.00

2 Pasir beton 0.0517 m3 150.000.00 7.755.00

3 Batu bata merah 25.0000 bh 700.00 17.500.00

4 Semen PC 50 kg 0.2500 zak 60.000.00 15.000.00

5 Kayu kaso meranti 0.0300 m3 2.876.860.00 86.305.80

6 Triplek 122 x 244 x 4 mm 1.0000 lbr 50.000.00 50.000.00

7 Engsel pintu uk 3 " 0.1667 bh 25.080.00 4.180.84

8 Asbes semen gelombang 250x92 x 0. 5 cm 0.5000 lbr 40.130.00 20.065.00

9 Kaca polos 5 mm 0.2917 m2 102.600.00 29.928.42

10 Rangka teralis nako 0.2917 bh 9.120.00 2.660.30

11 Paku segala ukuran ( rata-rata) 0.5000 kg 15.000.00 7.500.00

12 Kunci gembok kecil 0.0834 bh 10.260.00 855.68

13 Pekerja 0.4000 hr 48.000.00 19.200.00

14 Tukang batu 0.0834 hr 55.000.00 4.587.00

15 Tukang kayu 0.3340 hr 55.000.00 18.370.00

16 Mandor 0.0200 hr 70.000.00 1.400.00

JUMLAH 322.808.04

DIBULATKAN 322.808.00

1 m1 - Pengukuran & pemasangan bouwplank

1 Kayu Kaso terentang 5/7-400 cm 0.0040 m3 1.197.100.00 4.788.40

2 Kayu Papan terentang 2/20- 400 cm 0.0060 m3 1.197.100.00 7.182.60

3 Paku segala ukuran 0.0200 kg 15.000.00 300.00

4 Pekerja 0.0500 hr 55.000.00 2.750.00

5 Tukang Kayu 0.0500 hr 55.000.00 2.750.00

6 Mandor 0.0050 hr 70.000.00 350.00

JUMLAH 18.121.00

ANALISA HARGA SATUAN PEKERJAANDINAS TATA KOTA - KOTA BANDUNG

HARGA SATUAN URAIAN

Page 2: Analisa Harga Satuan Pekerjaan

DIBULATKAN 18.121.00

1 m1 - Pagar Pengaman Proyek

1 Pasir Beton 0.0012 m³ 150.000.00 180.00

2 Batu kali 0.0048 m³ 160.000.00 768.00

3 Semen PC ( 50 kg ) 0.0170 zak 60.000.00 1.020.00

4 Kaso Meranti Jambi Basah uk. 5 x 10 x 400 cm 0.0360 m³ 2.876.860.00 103.566.96

5 Seng Gelombang BJLS 28 (90x180) cm 1.4300 lbr 40.660.00 58.143.80

6 Paku Kayu Segala uk. 0.0200 kg 15.000.00 300.00

7 Pekerja 0.3000 hr 55.000.00 16.500.00

8 Tukang Batu 0.3750 hr 55.000.00 20.625.00

9 Tukang Kayu 0.1500 hr 55.000.00 8.250.00

10 Mandor 0.0150 hr 70.000.00 1.050.00

JUMLAH 210.403.76

DIBULATKAN 210.403.00

1 m1 - Pagar BRC tinggi 90 cm

1 BRC t = 0.9 m Ø 6 0.4340 lbr 167.210.00 72.569.14

2 Pekerja 0.0420 hr 55.000.00 2.310.00

3 Tukang Kayu 0.0420 hr 55.000.00 2.310.00

4 Kepala Tukang Kayu 0.0040 hr 55.000.00 220.00

5 Mandor 0.0020 hr 70.000.00 140.00

JUMLAH 77.549.14

DIBULATKAN 77.549.00

PEKERJAAN TANAH

1 m3 - Perataan Tanah

1 Pekerja 0.0400 hr 55.000.00 2.200.00

2 Mandor 0.0040 hr 70.000.00 280.00

3 Alat bantu 0.6000 set 700.00 420.00

JUMLAH 2.900.00

DIBULATKAN 2.900.00

1 m3 - Galian Tanah Biasa Kedalaman 1 m

1 Pekerja 0.7500 hr 55.000.00 41.250.00

2 Mandor 0.0250 hr 70.000.00 1.750.00

3 Alat bantu 0.6000 set 700.00 420.00

JUMLAH 43.420.00

DIBULATKAN 43.420.00

1 m3 - Galian Tanah Biasa Kedalaman 1 m - 2 m

1 Pekerja 0.9000 m3 55.000.00 49.500.00

2 Mandor 0.0325 hr 70.000.00 2.275.00

3 Alat bantu 0.6000 set 700.00 420.00

JUMLAH 52.195.00

DIBULATKAN 52.195.00

1 m3 - Galian Tanah Biasa Kedalaman 2 m - 3 m

1 Pekerja 0.9350 hr 55.000.00 51.425.00

2 Mandor 0.0730 hr 70.000.00 5.110.00

3 Alat bantu 0.6000 set 700.00 420.00

JUMLAH 56.955.00

DIBULATKAN 56.955.00

1 m3 - Galian Tanah Biasa Kedalaman 3 m - 4 m

Page 3: Analisa Harga Satuan Pekerjaan

1 Pekerja 0.9400 hr 55.000.00 51.700.00

2 Mandor 0.0940 hr 70.000.00 6.580.00

3 Alat bantu 0.6000 set 700.00 420.00

JUMLAH 58.700.00

DIBULATKAN 58.700.00

1 m3 - Galian tanah kedalaman 1 - 5 m dengan alat besar

1 Pekerja 0.2000 hr 55.000.00 11.000.00

2 Mandor 0.0020 hr 70.000.00 140.00

3 Excavator kap. 80 - 120 HP 0.1000 jam 211.400.00 21.140.00

4 Alat bantu 0.3000 hr 700.00 210.00

JUMLAH 32.490.00

DIBULATKAN 32.490.00

1 m3 - Galian Tanah Keras

1 Pekerja 0.9650 hr 55.000.00 53.075.00

2 Mandor 0.0350 hr 70.000.00 2.450.00

3 Alat bantu 0.6000 set 700.00 420.00

JUMLAH 55.945.00

DIBULATKAN 55.945.00

1 m3 - Galian Tanah Berbatu

1 Pekerja 1.9600 hr 55.000.00 107.800.00

2 Mandor 0.0323 hr 70.000.00 2.261.00

3 Alat bantu 0.6000 set 700.00 420.00

JUMLAH 110.481.00

DIBULATKAN 110.481.00

1 m3 - Galian Tanah Lumpur

1 Pekerja 0.9750 hr 55.000.00 53.625.00

2 Mandor 0.0325 hr 70.000.00 2.275.00

3 Alat bantu 0.6000 set 700.00 420.00

JUMLAH 56.320.00

DIBULATKAN 56.320.00

1 m3 - Galian Tanah Sumuran Kedalaman Max. 10 m

1 Pekerja 1.2000 hr 55.000.00 66.000.00

2 Mandor 0.0500 hr 70.000.00 3.500.00

3 Alat bantu 0.6000 set 700.00 420.00

JUMLAH 69.920.00

DIBULATKAN 69.920.00

1 m3 - Angkutan Galian Jarak Max. 30 m

1 Pekerja 0.2480 hr 55.000.00 13.640.00

2 Mandor 0.0080 hr 70.000.00 560.00

3 Alat bantu 0.6000 set 700.00 420.00

JUMLAH 14.620.00

DIBULATKAN 14.620.00

1 m3 - Urugan Kembali Galian Tanah

1 Pekerja 0.3000 hr 55.000.00 16.500.00

2 Mandor 0.0100 hr 70.000.00 700.00

3 Alat bantu 0.6000 set 700.00 420.00

JUMLAH 17.620.00

DIBULATKAN 17.620.00

Page 4: Analisa Harga Satuan Pekerjaan

1 m3 - Urugan Tanah bahan dari luar dipadatkan dg stamper tiap 20 cm (tanah biasa)

1 Tanah Urug 1.2000 m3 50.000.00 60.000.00

2 Pekerja 0.1240 hr 55.000.00 6.820.00

3 Mandor 0.0040 hr 70.000.00 280.00

4 Stamper, 5 HP, Kap. 0.17 ton 0.8000 jam 43.000.00 34.400.00

5 Alat bantu 0.3000 set 700.00 210.00

JUMLAH 101.710.00

DIBULATKAN 101.710.00

1 m3 - Urugan Tanah bahan dari luar pakai alat besar ( tiap 20 cm ) tanah biasa

1 Tanah Urug 1.2000 m3 50.000.00 60.000.00

2 Pekerja 0.1240 hr 55.000.00 6.820.00

3 Mandor 0.0040 hr 70.000.00 280.00

4 Buldozer kap. 100 - 150 HP 0.1000 jam 313.200.00 31.320.00

5 Alat bantu 0.3000 set 700.00 210.00

JUMLAH 98.630.00

DIBULATKAN 98.630.00

1 m3 - Urugan tanah bahan dari luar pakai alat besar ( tiap 20 cm) tanah berbatu

1 Tanah Urug 1.2000 m3 50.000.00 60.000.00

2 Pekerja 0.1500 hr 55.000.00 8.250.00

3 Mandor 0.0050 hr 70.000.00 350.00

4 Buldozer kap. 100 - 150 HP 0.1500 jam 313.200.00 46.980.00

5 Alat bantu 0.3000 set 700.00 210.00

JUMLAH 115.790.00

DIBULATKAN 115.790.00

1 m3 - Urugan pasir bawah lantai & pondasi

1 Pasir Urug 1.2000 m3 100.000.00 120.000.00

2 Pekerja 0.3000 hr 55.000.00 16.500.00

3 Mandor 0.0100 hr 70.000.00 700.00

4 Alat bantu 0.6000 set 700.00 420.00

JUMLAH 137.620.00

DIBULATKAN 137.620.00

1 m3 - Urugan Sirtu

1 Sirtu 1.2000 m3 140.000.00 168.000.00

2 Pekerja 0.5000 hr 55.000.00 27.500.00

3 Mandor 0.0200 hr 70.000.00 1.400.00

4 Alat bantu 0.6000 set 700.00 420.00

JUMLAH 197.320.00

DIBULATKAN 197.320.00

1 m3 - Pemadatan Tanah ( tiap 20 cm ) dengan stamper

1 Pekerja 0.3000 hr 55.000.00 16.500.00

2 Mandor 0.0050 hr 70.000.00 350.00

3 Stamper 0.9000 jam 43.000.00 38.700.00

4 Alat bantu 0.6000 set 700.00 420.00

JUMLAH 55.970.00

DIBULATKAN 55.970.00

PEKERJAAN PONDASI

1 m3 - Lantai kerja, mutu fc = 7.4 MPa (K.100)

Page 5: Analisa Harga Satuan Pekerjaan

1 Pasir beton 0.6200 m3 144.410.00 89.534.20

2 Split pecah mesin 2/3 0.7400 m3 164.000.00 121.360.00

3 Semen PC ( 50 kg ) 4.9400 zak 54.000.00 266.760.00

4 Pekerja 1.6500 hr 55.000.00 90.750.00

5 Tukang batu 0.2500 hr 52.000.00 13.000.00

6 Kepala Tukang 0.0250 hr 56.000.00 1.400.00

7 Mandor 0.0800 hr 70.000.00 5.600.00

8 Sewa molen 0.4000 jam 43.000.00 17.200.00

JUMLAH 605.604.20

DIBULATKAN 605.604.00

1 m3 - Pas.Pondasi batu kali 1 : 2

1 Pasir Pasang 0.4300 m3 144.410.00 62.096.30

2 Batu Kali 1.2000 m3 140.000.00 168.000.00

3 Semen PC ( 50 kg ) 5.2000 zak 54.000.00 280.800.00

4 Pekerja 1.6500 hr 55.000.00 90.750.00

5 Tukang Batu 0.5775 hr 52.000.00 30.030.00

6 Mandor 0.0495 hr 70.000.00 3.465.00

7 Alat Bantu 2.0000 set 700.00 1.400.00

JUMLAH 636.541.30

DIBULATKAN 636.541.00

1 m3 - Pas.Pondasi batu kali 1 : 3

1 Pasir Pasang 0.4560 m3 144.410.00 65.850.96

2 Batu Kali 1.2000 m3 140.000.00 168.000.00

3 Semen PC ( 50 kg ) 4.0000 zak 54.000.00 216.000.00

4 Pekerja 1.6500 hr 55.000.00 90.750.00

5 Tukang Batu 0.5775 hr 52.000.00 30.030.00

6 Mandor 0.0495 hr 70.000.00 3.465.00

7 Alat Bantu 2.0000 set 700.00 1.400.00

JUMLAH 575.495.96

DIBULATKAN 575.495.00

1 m3 - Pas.Pondasi batu kali 1 : 4

1 Pasir Pasang 0.3910 m3 144.410.00 56.464.31

2 Batu Kali 1.2000 m3 140.000.00 168.000.00

3 Semen PC ( 50 kg ) 3.5280 zak 54.000.00 190.512.00

4 Pekerja 1.6500 hr 55.000.00 90.750.00

5 Tukang Batu 0.8000 hr 52.000.00 41.600.00

6 Mandor 0.2000 hr 70.000.00 14.000.00

7 Alat Bantu 2.0000 set 700.00 1.400.00

JUMLAH 562.726.31

DIBULATKAN 562.726.00

1 m3 - Pas.Pondasi batu kali 1 : 5

1 Pasir Pasang 0.5600 m3 144.410.00 80.869.60

2 Batu Kali 1.2000 m3 140.000.00 168.000.00

3 Semen PC ( 50 kg ) 2.8640 zak 54.000.00 154.656.00

4 Pekerja 1.6500 hr 55.000.00 90.750.00

5 Tukang Batu 0.5775 hr 52.000.00 30.030.00

6 Mandor 0.0495 hr 70.000.00 3.465.00

7 Alat Bantu 2.0000 set 700.00 1.400.00

JUMLAH 529.170.60

Page 6: Analisa Harga Satuan Pekerjaan

DIBULATKAN 529.170.00

1 m3 - Pas.Batu kosong

1 Batu Kali 1.2000 m3 140.000.00 168.000.00

2 Pekerja 1.1240 hr 55.000.00 61.820.00

3 Mandor 0.0560 hr 70.000.00 3.920.00

4 Alat Bantu 2.0000 set 700.00 1.400.00

JUMLAH 235.140.00

DIBULATKAN 235.140.00

1 m2 - Pas. Cerucuk Dolken sedalam 3 m jarak tiap 50 cm

1 Dolken Ø 8-10 x 350-400 cm 4.0000 btg 20.520.00 82.080.00

2 Pekerja 0.7500 hr 55.000.00 41.250.00

3 Tukang Kayu 0.2625 hr 52.000.00 13.650.00

4 Mandor 2.0000 hr 70.000.00 140.000.00

JUMLAH 276.980.00

DIBULATKAN 276.980.00

1 m2 - Pas. Cerucuk Dolken sedalam 3 m jarak tiap 50 cm

1 Dolken Ø 8-10 x 350-400 cm 4.0000 btg 20.520.00 82.080.00

2 Pekerja 0.7500 hr 55.000.00 41.250.00

3 Tukang Kayu 0.2625 hr 52.000.00 13.650.00

4 Mandor 2.0000 hr 70.000.00 140.000.00

JUMLAH 276.980.00

DIBULATKAN 276.980.00

PEKERJAAN BETON

1 m3 - Cor beton K.125 ( manual )

1 Pasir beton 0.5070 m3 144.410.00 73.215.87

2 Split pecah mesin 2/3 0.7160 m3 164.000.00 117.424.00

3 Semen PC ( 50 kg ) 5.0000 zak 54.000.00 270.000.00

4 Pekerja 1.8000 hr 55.000.00 99.000.00

5 Tukang batu 0.4750 hr 52.000.00 24.700.00

6 Mandor 0.2858 hr 70.000.00 20.006.00

7 Alat bantu 2.5000 set 700.00 1.750.00

JUMLAH 606.095.87

DIBULATKAN 606.095.00

1 m3 - Cor beton K.175 ( manual )

1 Pasir beton 0.5070 m3 144.410.00 73.215.87

2 Split pecah mesin 2/3 0.7160 m3 164.000.00 117.424.00

3 Semen PC ( 50 kg ) 9.0000 zak 54.000.00 486.000.00

4 Pekerja 1.8000 hr 55.000.00 99.000.00

5 Tukang batu 0.4858 hr 52.000.00 25.261.60

6 Mandor 0.2608 hr 70.000.00 18.256.00

7 Alat bantu 2.5000 set 700.00 1.750.00

JUMLAH 820.907.47

DIBULATKAN 820.907.00

1 m3 - Cor beton K.225 ( manual )

1 Pasir beton 0.5070 m3 144.410.00 73.215.87

2 Split pecah mesin 2/3 0.7160 m3 164.000.00 117.424.00

3 Semen PC ( 50 kg ) 11.0000 zak 54.000.00 594.000.00

4 Pekerja 1.8000 hr 55.000.00 99.000.00

Page 7: Analisa Harga Satuan Pekerjaan

5 Tukang batu 0.2608 hr 52.000.00 13.561.60

6 Mandor 0.5858 hr 70.000.00 41.006.00

7 Alat bantu 2.5000 set 700.00 1.750.00

JUMLAH 939.957.47

DIBULATKAN 939.957.00

1 m3 - Cor beton K.250 ( manual )

1 Pasir beton 0.4000 m3 144.410.00 57.764.00

2 Split pecah mesin 2/3 0.7400 m3 164.000.00 121.360.00

3 Semen PC ( 50 kg ) 11.8000 zak 54.000.00 637.200.00

4 Pekerja 1.8000 hr 55.000.00 99.000.00

5 Tukang batu 0.2620 hr 52.000.00 13.624.00

6 Mandor 0.6270 hr 70.000.00 43.890.00

7 Alat bantu 2.5000 set 700.00 1.750.00

JUMLAH 974.588.00

DIBULATKAN 974.588.00

1 m3 - Cor beton K.125 dengan readymix

1 Beton readymix K.125 1.0000 m3 402.830.00 402.830.00

2 Pekerja 0.5508 hr 55.000.00 30.294.00

3 Tukang batu 0.1377 hr 52.000.00 7.160.40

4 Mandor 0.0688 hr 70.000.00 4.816.00

5 Concrete vibrator 0.4819 jam 39.500.00 19.035.05

6 Alat bantu 2.5000 set 700.00 1.750.00

JUMLAH 465.885.45

DIBULATKAN 465.885.00

1 m3 - Cor beton K.225 dengan readymix

1 Beton readymix K.225 1.0000 m3 620.000.00 620.000.00

2 Pekerja 0.6885 hr 55.000.00 37.867.50

3 Tukang batu 0.1377 hr 55.000.00 7.573.50

4 Mandor 0.0688 hr 70.000.00 4.816.00

5 Concrete vibrator 0.4819 jam 39.500.00 19.035.05

6 Alat bantu 2.5000 set 700.00 1.750.00

JUMLAH 691.042.05

DIBULATKAN 691.042.00

1 m3 - Cor beton K.250 dengan readymix

1 Beton readymix K.250 1.0000 m3 550.000.00 550.000.00

2 Pekerja 0.6885 hr 55.000.00 37.867.50

3 Tukang batu 0.1377 hr 55.000.00 7.573.50

4 Mandor 0.0688 hr 70.000.00 4.816.00

5 Concrete vibrator 0.4819 jam 39.500.00 19.035.05

6 Alat bantu 2.5000 set 700.00 1.750.00

JUMLAH 621.042.05

DIBULATKAN 621.042.00

1 m3 - Cor beton K.300 dengan readymix

1 Beton readymix K.300 1.0000 m3 532.040.00 532.040.00

2 Pekerja 0.6885 hr 55.000.00 37.867.50

3 Tukang batu 0.1377 hr 55.000.00 7.573.50

4 Mandor 0.0688 hr 70.000.00 4.816.00

5 Concrete vibrator 0.4819 jam 42.000.00 20.239.80

Page 8: Analisa Harga Satuan Pekerjaan

6 Alat bantu 2.5000 set 700.00 1.750.00

JUMLAH 604.286.80

DIBULATKAN 604.286.00

1 m3 - Cor beton K.350 dengan readymix

1 Beton readymix K.350 1.0000 m3 650.000.00 650.000.00

2 Pekerja 0.6885 hr 55.000.00 37.867.50

3 Tukang batu 0.1377 hr 55.000.00 7.573.50

4 Mandor 0.0688 hr 70.000.00 4.816.00

5 Concrete vibrator 0.4819 jam 42.000.00 20.239.80

6 Alat bantu 2.5000 set 700.00 1.750.00

JUMLAH 722.246.80

DIBULATKAN 722.246.00

1 m3 - Cor beton K.400 dengan readymix

1 Beton readymix K.400 1.0000 m3 700.000.00 700.000.00

2 Pekerja 0.6885 hr 55.000.00 37.867.50

3 Tukang batu 0.1377 hr 55.000.00 7.573.50

4 Mandor 0.0688 hr 70.000.00 4.816.00

5 Concrete vibrator 0.4819 jam 42.000.00 20.239.80

6 Alat bantu 2.5000 set 700.00 1.750.00

JUMLAH 772.246.80

DIBULATKAN 772.246.00

1 kg - Pembesian ( besi polos )

1 Kawat beton 0.0200 kg 11.400.00 228.00

2 Besi beton polos 1.1000 kg 8.000.00 8.800.00

3 Pekerja 0.0150 hr 55.000.00 825.00

4 Tukang besi 0.0050 hr 55.000.00 275.00

5 Mandor 0.0050 hr 70.000.00 350.00

6 Alat bantu 2.5000 set 700.00 1.750.00

JUMLAH 12.228.00

DIBULATKAN 12.228.00

1 kg - Pembesian ( besi ulir )

1 Kawat beton 0.0200 kg 11.400.00 228.00

2 Besi beton ulir 1.1000 kg 9.000.00 9.900.00

3 Pekerja 0.0150 hr 55.000.00 825.00

4 Tukang besi 0.0050 hr 55.000.00 275.00

5 Mandor 0.0050 hr 70.000.00 350.00

6 Alat bantu 2.5000 set 700.00 1.750.00

JUMLAH 13.328.00

DIBULATKAN 13.328.00

1 m2 - Bekisting dengan papan + bongkaran dan penyiraman

1 Kayu Papan terentang 2/20-400 cm 0.0240 m3 1.197.100.00 28.730.40

2 Kayu Kaso terentang 5/7-400 cm 0.0280 m3 1.197.100.00 33.518.80

3 Paku 0.2500 kg 15.000.00 3.750.00

4 Pekerja 0.1650 hr 55.000.00 9.075.00

5 Tukang kayu 0.3940 hr 55.000.00 21.670.00

6 Mandor 0.0270 hr 70.000.00 1.890.00

7 Alat bantu 2.5000 set 700.00 1.750.00

JUMLAH 100.384.20

Page 9: Analisa Harga Satuan Pekerjaan

DIBULATKAN 100.384.00

1 m2 - Bekisting dengan triplex 9 mm + bongkaran dan penyiraman

1 Kayu Kaso terentang 5/7-400 cm 0.0280 m3 1.197.100.00 33.518.80

2 Triplex 9 mm 0.3500 lbr 103.360.00 36.176.00

3 Paku 0.2500 kg 15.000.00 3.750.00

4 Pekerja 0.1650 bh 55.000.00 9.075.00

5 Tukang kayu 0.3940 hr 55.000.00 21.670.00

6 Mandor 0.0270 hr 70.000.00 1.890.00

7 Alat bantu 2.5000 set 700.00 1.750.00

JUMLAH 107.829.80

DIBULATKAN 107.829.00

1 m3 - Bekisting kolom beton struktur

1 Kayu Kaso terentang 5/7-400 cm 0.2520 m3 1.197.100.00 301.669.20

2 Triplex 9 mm 3.1500 lbr 103.360.00 325.584.00

3 Paku 2.2500 kg 15.000.00 33.750.00

4 Pekerja 1.4850 hr 55.000.00 81.675.00

5 Tukang kayu 3.5440 hr 55.000.00 194.920.00

6 Mandor 0.2430 hr 70.000.00 17.010.00

7 Alat bantu 2.5000 set 700.00 1.750.00

JUMLAH 956.358.20

DIBULATKAN 956.358.00

1 m3 - Bekisting balok beton struktur

1 Kayu Kaso terentang 5/7-400 cm 0.1870 m3 1.197.100.00 223.857.70

2 Triplex 9 mm 2.3500 lbr 103.360.00 242.896.00

3 Paku 1.6680 kg 15.000.00 25.020.00

4 Pekerja 1.1010 hr 55.000.00 60.555.00

5 Tukang kayu 2.6260 hr 55.000.00 144.430.00

6 Mandor 0.1800 hr 70.000.00 12.600.00

7 Alat bantu 2.5000 set 700.00 1.750.00

JUMLAH 711.108.70

DIBULATKAN 711.108.00

1 m3 - Bekisting lantai beton

1 Kayu Kaso terentang 5/7-400 cm 0.2320 m3 1.197.100.00 277.727.20

2 Triplex 9 mm 2.9050 lbr 103.360.00 300.260.80

3 Paku 2.0750 kg 15.000.00 31.125.00

4 Pekerja 1.3700 hr 55.000.00 75.350.00

5 Tukang kayu 3.2685 hr 55.000.00 179.767.50

6 Mandor 0.2245 hr 70.000.00 15.715.00

7 Alat bantu 2.5000 set 700.00 1.750.00

JUMLAH 881.695.50

DIBULATKAN 881.695.00

1 m2 - Perancah kayu / stoot werk - tinggi s/d 2 m

1 Kayu Kaso terentang 5/7-400 cm 0.0608 m3 1.197.100.00 72.783.68

2 Paku 0.3000 kg 15.000.00 4.500.00

3 Pekerja 0.6000 hr 55.000.00 33.000.00

4 Tukang kayu 0.4200 hr 55.000.00 23.100.00

5 Mandor 0.0300 hr 70.000.00 2.100.00

6 Alat bantu 2.5000 set 700.00 1.750.00

Page 10: Analisa Harga Satuan Pekerjaan

JUMLAH 137.233.68

DIBULATKAN 137.233.00

1 m2 - Perancah kayu / stoot werk - tinggi s/d 3 m

1 Kayu Kaso terentang 5/7-400 cm 0.0851 m3 1.197.100.00 101.873.21

2 Paku 0.4200 kg 15.000.00 6.300.00

3 Pekerja 0.8400 hr 55.000.00 46.200.00

4 Tukang kayu 0.5880 hr 55.000.00 32.340.00

5 Mandor 0.0420 hr 70.000.00 2.940.00

6 Alat bantu 3.5000 set 700.00 2.450.00

JUMLAH 192.103.21

DIBULATKAN 192.103.00

1 m2 - Perancah kayu / stoot werk - tinggi s/d 4 m

1 Kayu Kaso terentang 5/7-400 cm 0.1094 m3 1.197.100.00 130.962.74

2 Paku 0.5400 kg 15.000.00 8.100.00

3 Pekerja 1.0800 hr 55.000.00 59.400.00

4 Tukang kayu 0.7560 hr 55.000.00 41.580.00

5 Mandor 0.0540 hr 70.000.00 3.780.00

6 Alat bantu 4.5000 set 700.00 3.150.00

JUMLAH 246.972.74

DIBULATKAN 246.972.00

1 m2 - Perancah kayu / stoot werk - tinggi s/d 5 m

1 Kayu Kaso terentang 5/7-400 cm 0.1398 m3 1.197.100.00 167.354.58

2 Paku 0.6900 kg 15.000.00 10.350.00

3 Pekerja 1.3800 hr 55.000.00 75.900.00

4 Tukang kayu 0.9660 hr 55.000.00 53.130.00

5 Mandor 0.0690 hr 70.000.00 4.830.00

6 Alat bantu 5.7500 set 700.00 4.025.00

JUMLAH 315.589.58

DIBULATKAN 315.589.00

1 m3 - Balok beton praktis K.175

1 Adukan beton K.175 ( konvensional ) 1.0000 m3 820.907.00 820.907.00

2 Pembesian besi polos 120.0000 kg 12.228.00 1.467.360.00

3 Bekisting dengan papan 5.0000 m2 100.384.00 501.920.00

4 Alat bantu 4.2000 set 700.00 2.940.00

JUMLAH 2.793.127.00

DIBULATKAN 2.793.127.00

1 m3 - Kolom beton praktis K.175

1 Adukan beton K.175 ( konvensional ) 1.0000 m3 820.907.00 820.907.00

2 Pembesian besi polos 156.8622 kg 12.228.00 1.918.111.25

3 Bekisting dengan papan 5.0000 m2 100.384.00 501.920.00

4 Alat bantu 4.2000 set 700.00 2.940.00

JUMLAH 3.243.878.25

DIBULATKAN 3.243.878.00

1 m3 - Pondasi beton setapak K.225

1 Adukan beton K.225 ( konvensional ) 1.0000 m3 939.957.00 939.957.00

2 Pembesian besi polos 160.0000 kg 12.228.00 1.956.480.00

3 Bekisting triplek 9 mm 2.6670 m2 107.829.00 287.579.94

JUMLAH 3.184.016.94

Page 11: Analisa Harga Satuan Pekerjaan

DIBULATKAN 3.184.016.00

1 m3 - Sloof beton 20/35 K-225 ( SL1 )

1 Adukan beton K-225 (Konvensional) 1.0000 m3 939.957.00 939.957.00

2 Pembesian 158.9524 kg 12.228.00 1.943.669.71

3 Bekisting balok struktur 1.0000 m3 711.108.00 711.108.00

JUMLAH 3.594.734.71

DIBULATKAN 3.594.734.00

1 m3 - Sloof beton 20/40 K.225 ( SL2 )

1 Adukan beton K.225 ( konvensional ) 1.0000 m3 939.957.00 939.957.00

2 Pembesian besi polos 162.5000 kg 12.228.00 1.987.050.00

3 Bekisting balok struktur 1.0000 m3 711.108.00 711.108.00

JUMLAH 3.638.115.00

DIBULATKAN 3.638.115.00

1 m3 - Kolom beton 30/40 K-225 ( K1 )

1 Adukan beton K-225 (ready-mixl) 1.0000 m3 691.042.00 691.042.00

2 Pembesian 213.0000 kg 12.228.00 2.604.564.00

3 Bekisting Kolom 1.0000 m3 930.903.00 930.903.00

JUMLAH 4.226.509.00

DIBULATKAN 4.226.509.00

1 m3 - Sloof beton 15/20 K.175

1 Adukan beton K.175 ( konvensional ) 1.0000 m3 820.907.00 820.907.00

2 Pembesian besi polos 187.1111 kg 12.228.00 2.287.994.67

3 Bekisting balok struktur 1.0000 m3 711.108.00 711.108.00

JUMLAH 3.820.009.67

DIBULATKAN 3.820.009.00

1 m3 - Kolom beton 30/30 K-225 ( K1 )

1 Adukan beton K-225 (ready-mixl) 1.0000 m3 691.042.00 691.042.00

2 Pembesian 259.5556 kg 12.228.00 3.173.845.33

3 Bekisting Kolom 1.0000 m3 930.903.00 930.903.00

JUMLAH 4.795.790.33

DIBULATKAN 4.795.790.00

1 m3 - Kolom beton 30/30 K.225 ( K2)

1 Adukan beton K.225 ( ready - mix ) 1.0000 m3 691.042.00 691.042.00

2 Pembesian besi polos 189.3333 kg 12.228.00 2.315.168.00

3 Bekisting kolom 1.0000 m3 930.903.00 930.903.00

JUMLAH 3.937.113.00

DIBULATKAN 3.937.113.00

1 m3 - Kolom beton 25/25 K.225

1 Adukan beton K.225 ( ready - mix ) 1.0000 m3 691.042.00 691.042.00

2 Pembesian besi polos 155.0000 kg 12.228.00 1.895.340.00

3 Bekisting kolom 1.0000 m2 930.903.00 930.903.00

JUMLAH 3.517.285.00

DIBULATKAN 3.517.285.00

1 m3 - Kolom beton 15/30 K.225

1 Adukan beton K.225 ( ready - mix ) 1.0000 m3 691.042.00 691.042.00

2 Pembesian besi polos 170.0000 kg 12.228.00 2.078.760.00

3 Bekisting kolom 1.0000 m3 930.903.00 930.903.00

JUMLAH 3.700.705.00

Page 12: Analisa Harga Satuan Pekerjaan

DIBULATKAN 3.700.705.00

1 m3 - Balok beton 30/50 K-225

1 Adukan beton K-225 (ready-mixl) 1.0000 m3 691.042.00 691.042.00

2 Pembesian 154.0000 kg 12.228.00 1.883.112.00

3 Perancah kayu / stoot werk - tinggi s/d 4 m 2.0000 m2 246.972.00 493.944.00

4 Bekisting Balok 1.0000 m3 711.108.00 711.108.00

JUMLAH 3.779.206.00

DIBULATKAN 3.779.206.00

1 m3 - Balok beton 25/50 K.225 ( B1 )

1 Adukan beton K.225 ( ready - mix ) 1.0000 m3 691.042.00 691.042.00

2 Pembesian besi polos 181.3600 kg 12.228.00 2.217.670.08

3 Perancah kayu / stoot werk - tinggi s / d 4 m 1.6675 m2 246.972.00 411.825.81

4 Bekisting balok 1.0000 m3 711.108.00 711.108.00

JUMLAH 4.031.645.89

DIBULATKAN 4.031.645.00

1 m3 - Balok beton 25/45 K-225

1 Adukan beton K-225 (ready-mixl) 1.0000 m3 691.042.00 691.042.00

2 Pembesian 170.0000 kg 12.228.00 2.078.760.00

3 Perancah kayu / stoot werk - tinggi s/d 4 m 2.2200 m2 246.972.00 548.277.84

4 Bekisting Balok 1.0000 m3 711.108.00 711.108.00

JUMLAH 4.029.187.84

DIBULATKAN 4.029.187.00

1 m3 - Balok beton 25/35 K.225

1 Adukan beton K.225 ( ready - mix ) 1.0000 m3 691.042.00 691.042.00

2 Pembesian besi polos 170.0000 kg 12.228.00 2.078.760.00

3 Perancah kayu / stoot werk - tinggi s / d 4 m 2.8575 m2 246.972.00 705.722.49

4 Bekisting balok 1.0000 m3 711.108.00 711.108.00

JUMLAH 4.186.632.49

DIBULATKAN 4.186.632.00

1 m3 - Balok beton 20/40 K-225 ( B2 )

1 Adukan beton K-225 (ready-mixl) 1.0000 m3 691.042.00 691.042.00

2 Pembesian 162.5000 kg 12.228.00 1.987.050.00

3 Perancah kayu / stoot werk - tinggi s/d 4 m 1.6675 m2 246.972.00 411.825.81

4 Bekisting balok 1.0000 m3 711.108.00 711.108.00

JUMLAH 3.801.025.81

DIBULATKAN 3.801.025.00

1 m3 - Balok beton 20/30 K-225 ( B3 )

1 Adukan beton K-225 (ready-mixl) 1.0000 m3 691.042.00 691.042.00

2 Pembesian 180.5556 kg 12.228.00 2.207.833.33

3 Perancah kayu / stoot werk - tinggi s/d 4 m 1.6675 m2 246.972.00 411.825.81

4 Bekisting Balok 1.0000 m3 711.108.00 711.108.00

JUMLAH 4.021.809.14

DIBULATKAN 4.021.809.00

1 m3 - Balok beton 15/30 K.225 ( B4 )

1 Adukan beton K.225 ( ready - mix ) 1.0000 m3 691.042.00 691.042.00

2 Pembesian besi polos 199.1111 kg 12.228.00 2.434.730.67

3 Perancah kayu / stoot werk - tinggi s / d 4 m 1.6675 m2 246.972.00 411.825.81

4 Bekisting balok 1.0000 m3 711.108.00 711.108.00

Page 13: Analisa Harga Satuan Pekerjaan

JUMLAH 4.248.706.48

DIBULATKAN 4.248.706.00

1 m3 - Balok beton 15/60 K.225

1 Adukan beton K.225 ( ready - mix ) 1.0000 m3 691.042.00 691.042.00

2 Pembesian besi polos 120.0000 kg 12.228.00 1.467.360.00

3 Perancah kayu / stoot werk - tinggi s / d 4 m 1.6665 m2 246.972.00 411.578.84

4 Bekisting balok 1.0000 m3 711.108.00 711.108.00

JUMLAH 3.281.088.84

DIBULATKAN 3.281.088.00

1 m3 - Plat lantai & tangga beton K.225

1 Adukan beton K.225 ( ready - mix ) 1.0000 m3 691.042.00 691.042.00

2 Pembesian besi polos 105.0000 kg 12.228.00 1.283.940.00

3 Perancah kayu / stoot werk - tinggi s / d 4 m 6.2475 m2 246.972.00 1.542.957.57

4 Bekisting plat lantai 1.0000 m3 881.695.00 881.695.00

JUMLAH 4.399.634.57

DIBULATKAN 4.399.634.00

1 m3 - Plat listplank beton K.225

1 Adukan beton K.225 ( ready - mix ) 1.0000 m3 691.042.00 691.042.00

2 Pembesian besi polos 100.0000 kg 12.228.00 1.222.800.00

3 Perancah kayu / stoot werk - tinggi s / d 4 m 1.0000 m2 246.972.00 246.972.00

4 Bekisting balok 1.0000 m3 711.108.00 711.108.00

JUMLAH 2.871.922.00

DIBULATKAN 2.871.922.00

1 m3 - Beton Plat Canopy atas jendela t = 10 cm - K.225

1 Adukan beton K-225 (ready-mixl) 1.0000 m3 691.042.00 691.042.00

2 Pembesian 75.0000 kg 12.228.00 917.100.00

3 Perancah kayu / stoot werk - tinggi s/d 4 m 1.0000 m2 246.972.00 246.972.00

4 Bekisting pelat lantai 1.0000 m3 881.695.00 881.695.00

JUMLAH 2.736.809.00

DIBULATKAN 2.736.809.00

1 m3 - Beton slab, T=10cm, + wiremesh M- 8

1 Adukan beton K.225 ( ready - mix ) 1.0000 m3 691.042.00 691.042.00

2 Wiremesh M - 8 0.8818 lbr 323.020.00 284.850.09

3 Pembesian besi polos 51.0000 kg 12.228.00 623.628.00

JUMLAH 1.599.520.09

DIBULATKAN 1.599.520.00

1 m2 - Pas.Batu bata, t = 1 / 2 bata ad. 1 : 2

1 Pasir pasang 0.0380 m3 144.410.00 5.487.58

2 Bata merah 75.0000 bh 400.00 30.000.00

3 Semen PC ( 50 kg ) 0.4700 zak 54.000.00 25.380.00

4 Pekerja 0.3600 hr 55.000.00 19.800.00

5 Tukang batu 0.1875 hr 55.000.00 10.312.50

6 Mandor 0.0155 hr 70.000.00 1.085.00

7 Alat bantu 4.0000 set 700.00 2.800.00

JUMLAH 94.865.08

DIBULATKAN 94.865.00

1 m2 - Pas.Batu bata, t = 1 / 2 bata ad. 1 : 3

1 Pasir pasang 0.0430 m3 144.410.00 6.209.63

Page 14: Analisa Harga Satuan Pekerjaan

2 Bata merah 75.0000 bh 400.00 30.000.00

3 Semen PC ( 50 kg ) 0.3600 zak 54.000.00 19.440.00

4 Pekerja 0.3600 hr 55.000.00 19.800.00

5 Tukang batu 0.1875 hr 55.000.00 10.312.50

6 Mandor 0.0155 hr 70.000.00 1.085.00

7 Alat bantu 4.0000 set 700.00 2.800.00

JUMLAH 89.647.13

DIBULATKAN 89.647.00

1 m2 - Pas.Batu bata, t = 1 / 2 bata ad. 1 : 4

1 Pasir pasang 0.0460 m3 144.410.00 6.642.86

2 Bata merah 75.0000 bh 400.00 30.000.00

3 Semen PC ( 50 kg ) 0.2900 zak 54.000.00 15.660.00

4 Pekerja 0.3600 hr 55.000.00 19.800.00

5 Tukang batu 0.1875 hr 55.000.00 10.312.50

6 Mandor 0.0155 hr 70.000.00 1.085.00

7 Alat bantu 4.0000 set 700.00 2.800.00

JUMLAH 86.300.36

DIBULATKAN 86.300.00

1 m2 - Pas.Batu bata, t = 1 / 2 bata ad. 1 : 5

1 Pasir pasang 0.0480 m3 144.410.00 6.931.68

2 Bata merah 75.0000 bh 400.00 30.000.00

3 Semen PC ( 50 kg ) 0.2400 zak 54.000.00 12.960.00

4 Pekerja 0.3600 hr 55.000.00 19.800.00

5 Tukang batu 0.1875 hr 55.000.00 10.312.50

6 Mandor 0.0155 hr 70.000.00 1.085.00

7 Alat bantu 4.0000 set 700.00 2.800.00

JUMLAH 83.889.18

DIBULATKAN 83.889.00

1 m2 - Pas.Batako beton ad. 1 : 2

1 Pasir pasang 0.0130 m3 144.410.00 1.877.33

2 Batako beton 20 / 40 13.0000 bh 7.300.00 94.900.00

3 Semen PC ( 50 kg ) 0.1570 zak 54.000.00 8.478.00

4 Pekerja 0.2900 hr 55.000.00 15.950.00

5 Tukang batu 0.1500 hr 55.000.00 8.250.00

6 Mandor 0.0300 hr 70.000.00 2.100.00

7 Alat bantu 2.0000 set 700.00 1.400.00

JUMLAH 132.955.33

DIBULATKAN 132.955.00

1 m2 - Pas.Batako beton ad. 1 : 3

1 Pasir pasang 0.0140 m3 144.410.00 2.021.74

2 Batako beton 20 / 40 13.0000 bh 7.300.00 94.900.00

3 Semen PC ( 50 kg ) 0.1000 zak 54.000.00 5.400.00

4 Pekerja 0.2900 hr 55.000.00 15.950.00

5 Tukang batu 0.1500 hr 55.000.00 8.250.00

6 Mandor 0.0300 hr 70.000.00 2.100.00

7 Alat bantu 2.0000 set 700.00 1.400.00

JUMLAH 130.021.74

DIBULATKAN 130.021.00

1 m2 - Pas.Batako beton ad. 1 : 4

Page 15: Analisa Harga Satuan Pekerjaan

1 Pasir pasang 0.0150 m3 144.410.00 2.166.15

2 Batako beton 20 / 40 13.0000 bh 7.300.00 94.900.00

3 Semen PC ( 50 kg ) 0.1000 zak 54.000.00 5.400.00

4 Pekerja 0.2900 hr 55.000.00 15.950.00

5 Tukang batu 0.1500 hr 55.000.00 8.250.00

6 Mandor 0.0300 hr 70.000.00 2.100.00

7 Alat bantu 2.0000 set 700.00 1.400.00

JUMLAH 130.166.15

DIBULATKAN 130.166.00

1 m2 - Pas.Batako beton ad. 1 : 5

1 Pasir pasang 0.0160 m3 144.410.00 2.310.56

2 Batako beton 20 / 40 13.0000 bh 7.300.00 94.900.00

3 Semen PC ( 50 kg ) 0.0800 zak 54.000.00 4.320.00

4 Pekerja 0.2900 hr 55.000.00 15.950.00

5 Tukang batu 0.1500 hr 55.000.00 8.250.00

6 Mandor 0.0300 hr 70.000.00 2.100.00

7 Alat bantu 2.0000 set 700.00 1.400.00

JUMLAH 129.230.56

DIBULATKAN 129.230.00

1 m2 - Pas. Bata Ringan (Silicon) beton ad. 1 : 3

1 Pasir pasang 0.0070 m3 144.410.00 1.010.87

2 Batako beton 20 / 40 8.3300 bh 7.300.00 60.809.00

3 Semen PC ( 50 kg ) 0.1000 zak 54.000.00 5.400.00

4 Pekerja 0.2000 hr 55.000.00 11.000.00

5 Tukang batu 0.1500 hr 55.000.00 8.250.00

6 Mandor 0.0300 hr 70.000.00 2.100.00

7 Alat bantu 2.0000 set 700.00 1.400.00

JUMLAH 89.969.87

DIBULATKAN 89.969.00

1 m2 - Pas. Bata Ringan (Silicon) beton ad. 1 : 5

1 Pasir pasang 0.0060 m3 144.410.00 866.46

2 Batako beton 20 / 40 8.3300 bh 7.300.00 60.809.00

3 Semen PC ( 50 kg ) 0.0800 zak 54.000.00 4.320.00

4 Pekerja 0.2000 hr 55.000.00 11.000.00

5 Tukang batu 0.1500 hr 55.000.00 8.250.00

6 Mandor 0.0300 hr 70.000.00 2.100.00

7 Alat bantu 2.0000 set 700.00 1.400.00

JUMLAH 88.745.46

DIBULATKAN 88.745.00

1 m2 - Plesteran & acian tebal 1,5 cm ad. 1 : 2

1 Pasir pasang 0.0180 m3 144.410.00 2.599.38

2 Semen PC ( 50 kg ) 0.2130 zak 54.000.00 11.502.00

3 Pekerja 0.3000 hr 55.000.00 16.500.00

4 Tukang batu 0.1575 hr 55.000.00 8.662.50

5 Mandor 0.0115 hr 70.000.00 805.00

6 Alat bantu 2.0000 set 700.00 1.400.00

JUMLAH 41.468.88

DIBULATKAN 41.468.00

Page 16: Analisa Harga Satuan Pekerjaan

1 m2 - Plesteran & acian tebal 1,5 cm ad. 1 : 3

1 Pasir pasang 0.0210 m3 144.410.00 3.032.61

2 Semen PC ( 50 kg ) 0.1920 zak 54.000.00 10.368.00

3 Pekerja 0.3000 hr 55.000.00 16.500.00

4 Tukang batu 0.1575 hr 55.000.00 8.662.50

5 Mandor 0.0115 hr 70.000.00 805.00

6 Alat bantu 2.0000 set 700.00 1.400.00

JUMLAH 40.768.11

DIBULATKAN 40.768.00

1 m2 - Plesteran & acian tebal 1,5 cm ad. 1 : 4

1 Pasir pasang 0.0230 m3 144.410.00 3.321.43

2 Semen PC ( 50 kg ) 0.1570 zak 54.000.00 8.478.00

3 Pekerja 0.3000 hr 55.000.00 16.500.00

4 Tukang batu 0.1575 hr 55.000.00 8.662.50

5 Mandor 0.0115 hr 70.000.00 805.00

6 Alat bantu 2.0000 set 700.00 1.400.00

JUMLAH 39.166.93

DIBULATKAN 39.166.00

1 m2 - Plesteran & acian tebal 1,5 cm ad. 1 : 5

1 Pasir pasang 0.0240 m3 144.410.00 3.465.84

2 Semen PC ( 50 kg ) 0.1240 zak 54.000.00 6.696.00

3 Pekerja 0.3000 hr 55.000.00 16.500.00

4 Tukang batu 0.1575 hr 55.000.00 8.662.50

5 Mandor 0.0115 hr 70.000.00 805.00

6 Alat bantu 2.0000 set 700.00 1.400.00

JUMLAH 37.529.34

DIBULATKAN 37.529.00

1 m2 - Pek.Acian

1 Semen PC ( 50 kg ) 0.0800 zak 54.000.00 4.320.00

2 Pekerja 0.1430 hr 55.000.00 7.865.00

3 Tukang batu 0.1123 hr 55.000.00 6.176.50

4 Mandor 0.0063 hr 70.000.00 441.00

5 Alat bantu 2.0000 set 700.00 1.400.00

JUMLAH 20.202.50

DIBULATKAN 20.202.00

1 m2 - Pasang Dinding Rooster / Terawang, Natural, uk. 12x11x24 cm, Ad. 1Pc : 4Ps

1 Rooster 36.0000 bh 4.600.00 165.600.00

2 Pasir pasang 0.0350 m3 144.410.00 5.054.35

3 Semen PC ( 50 kg ) 0.2560 zak 54.000.00 13.824.00

4 Pekerja 0.3000 hr 55.000.00 16.500.00

5 Tukang Batu 0.1000 hr 55.000.00 5.500.00

6 Kepala Tukang Batu 0.0100 hr 56.000.00 560.00

7 Mandor 0.0150 hr 70.000.00 1.050.00

JUMLAH 208.088.35

DIBULATKAN 208.088.00

1 m2 - Pas. Dinding glass block uk. 20x20x10 cm , ad. 1 PC : 4 psr

1 Glass Block 20 x 20 (Kedawung) 25.0000 bh 31.000.00 775.000.00

2 Pasir pasang 0.0350 m3 144.410.00 5.054.35

Page 17: Analisa Harga Satuan Pekerjaan

3 Semen PC ( 50 kg ) 0.2560 zak 54.000.00 13.824.00

4 Pekerja 0.3000 hr 55.000.00 16.500.00

5 Tukang Batu 0.1000 hr 55.000.00 5.500.00

6 Kepala Tukang Batu 0.0100 hr 56.000.00 560.00

7 Mandor 0.0150 hr 70.000.00 1.050.00

JUMLAH 817.488.35

DIBULATKAN 817.488.00

1 m2 - Pasang Dinding Batu Tempel Palimanan Kuning, 20 x 20 cm Texture Kasar

1 Batu Tempel Palimanan 1.0500 m2 60.800.00 63.840.00

2 Pasir pasang 0.0350 m3 144.410.00 5.054.35

3 Semen PC ( 50 kg ) 0.2350 zak 54.000.00 12.690.00

4 Pekerja 0.6200 hr 55.000.00 34.100.00

5 Tukang batu 0.3500 hr 55.000.00 19.250.00

6 Kepala Tukang Batu 0.0350 hr 56.000.00 1.960.00

7 Mandor 0.0300 hr 70.000.00 2.100.00

JUMLAH 138.994.35

DIBULATKAN 138.994.00

PEKERJAAN ATAP

1 m3 - Kuda - kuda kayu kamper kruing

1 Kayu balok kamper kruing 1.1000 m3 4.408.400.00 4.849.240.00

2 Paku 8 - 12 3.0000 kg 13.680.00 41.040.00

3 Besi pengikat kuda - kuda 15.0000 kg 7.600.00 114.000.00

4 Pekerja 5.0000 hr 55.000.00 275.000.00

5 Tukang kayu 15.7500 hr 55.000.00 866.250.00

6 Mandor 1.0000 hr 70.000.00 70.000.00

JUMLAH 6.215.530.00

DIBULATKAN 6.215.530.00

1 m3 - Kuda - kuda kayu kamper banjar

1 Kayu balok kamper banjar 1.1000 m3 4.408.400.00 4.849.240.00

2 Paku 8 - 12 3.0000 kg 13.680.00 41.040.00

3 Besi pengikat kuda - kuda 15.0000 kg 7.600.00 114.000.00

4 Pekerja 5.0000 hr 55.000.00 275.000.00

5 Tukang kayu 15.7500 hr 55.000.00 866.250.00

6 Mandor 1.0000 hr 70.000.00 70.000.00

JUMLAH 6.215.530.00

DIBULATKAN 6.215.530.00

1 m3 - Kuda - kuda kayu meranti

1 Kayu meranti 1.1000 m3 2.876.860.00 3.164.546.00

2 Paku 8 - 12 3.0000 kg 13.680.00 41.040.00

3 Besi pengikat kuda - kuda 15.0000 kg 7.600.00 114.000.00

4 Pekerja 5.0000 hr 55.000.00 275.000.00

5 Tukang kayu 15.7500 hr 55.000.00 866.250.00

6 Mandor 1.0000 hr 70.000.00 70.000.00

JUMLAH 4.530.836.00

DIBULATKAN 4.530.836.00

1 m2 - Rangka atap ( kaso 5/7 dan reng 3/4 ) kayu meranti

1 Kayu meranti 0.0180 m3 2.876.860.00 51.783.48

2 Paku 8 - 12 0.1500 kg 13.680.00 2.052.00

Page 18: Analisa Harga Satuan Pekerjaan

3 Pekerja 0.1000 hr 55.000.00 5.500.00

4 Tukang kayu 0.1000 hr 55.000.00 5.500.00

5 Mandor 0.0150 hr 70.000.00 1.050.00

JUMLAH 65.885.48

DIBULATKAN 65.885.00

1 m' - Listplank 3 / 30 + 3 / 15 kayu kamper banjar

1 Papan kayu kamper banjar 0.0150 m3 4.651.620.00 69.774.30

2 Paku 8 - 12 0.8000 kg 13.680.00 10.944.00

3 Pekerja 0.2800 hr 55.000.00 15.400.00

4 Tukang kayu 0.5600 hr 55.000.00 30.800.00

5 Mandor 0.0720 hr 70.000.00 5.040.00

JUMLAH 131.958.30

DIBULATKAN 131.958.00

1 m' - Listplank 3 / 30 kayu kamper banjar

1 Papan kayu kamper banjar 0.0100 m3 4.651.620.00 46.516.20

2 Paku 8 - 12 0.0500 kg 13.680.00 684.00

3 Pekerja 0.1430 hr 55.000.00 7.865.00

4 Tukang kayu 0.2850 hr 55.000.00 15.675.00

5 Mandor 0.0360 hr 70.000.00 2.520.00

JUMLAH 73.260.20

DIBULATKAN 73.260.00

1 m2 - Atap genteng morando glasuur

1 Genteng morando Glazur 18.0000 bh 3.040.00 54.720.00

2 Pekerja 0.1500 hr 55.000.00 8.250.00

3 Tukang kayu 0.0790 hr 55.000.00 4.345.00

4 Mandor 0.0120 hr 70.000.00 840.00

JUMLAH 68.155.00

DIBULATKAN 68.155.00

1 m' - Karpusan genteng morando glasuur

1 Pasir pasang 0.0320 m3 144.410.00 4.621.12

2 Semen PC ( 50 kg ) 0.2200 zak 54.000.00 11.880.00

3 Genteng bubungan / nok 3.5000 bh 5.700.00 19.950.00

4 Pekerja 0.3000 hr 55.000.00 16.500.00

5 Tukang batu 0.1575 hr 55.000.00 8.662.50

6 Mandor 0.0225 hr 70.000.00 1.575.00

JUMLAH 63.188.62

DIBULATKAN 63.188.00

1 m2 - Atap genteng beton (polos)

1 Genteng beton polos 18.0000 bh 3.800.00 68.400.00

2 Pekerja 0.1500 hr 55.000.00 8.250.00

3 Tukang kayu 0.0790 hr 55.000.00 4.345.00

4 Mandor 0.0120 hr 70.000.00 840.00

JUMLAH 81.835.00

DIBULATKAN 81.835.00

1 m' - Karpusan genteng beton

1 Pasir pasang 0.0320 m3 144.410.00 4.621.12

2 Semen PC ( 50 kg ) 0.2200 zak 54.000.00 11.880.00

3 Genteng bubungan / nok 3.5000 bh 5.240.00 18.340.00

Page 19: Analisa Harga Satuan Pekerjaan

4 Pekerja 0.3000 hr 55.000.00 16.500.00

5 Tukang batu 0.1575 hr 55.000.00 8.662.50

6 Mandor 0.0225 hr 70.000.00 1.575.00

JUMLAH 61.578.62

DIBULATKAN 61.578.00

1 m2 - Pasang atap asbes gelombang 5 mm

1 Asbes Gelombang 5 mm (180x108)cm 0.9000 lbr 40.280.00 36.252.00

2 Paku asbes / kg 0.1200 kg 13.680.00 1.641.60

3 Pekerja 0.1400 hr 55.000.00 7.700.00

4 Tukang Kayu 0.0750 hr 55.000.00 4.125.00

5 Kepala Tukang Kayu 0.0080 hr 56.000.00 448.00

6 Mandor 0.0080 hr 70.000.00 560.00

JUMLAH 50.726.60

DIBULATKAN 50.726.00

1 m1 - Pasang bubungan/nok stel 1.05 m

1 Asbes Nok Stel 2.1000 lbr 15.730.00 33.033.00

2 Paku Kayu Segala uk. 6.0000 kg 13.680.00 82.080.00

3 Pekerja 0.0840 hr 55.000.00 4.620.00

4 Tukang Kayu 0.1250 hr 55.000.00 6.875.00

5 Kepala Tukang Kayu 0.0130 hr 56.000.00 728.00

6 Mandor 0.0040 hr 70.000.00 280.00

JUMLAH 127.616.00

DIBULATKAN 127.616.00

1 kg - Konstruksi baja H - beam / WF ( termasuk plat simpul,las & zinkchromate )

1 Zinkcchromate 0.0400 m2 760.00 30.40

2 Besi WF ex. DN SII 1.0500 kg 11.020.00 11.571.00

3 Pekerja 0.0600 hr 55.000.00 3.300.00

4 Tukang besi 0.0045 hr 55.000.00 247.50

5 Mandor 0.0025 hr 70.000.00 175.00

6 Erection 1.0000 kg 800.00 800.00

JUMLAH 16.123.90

DIBULATKAN 16.123.00

1 kg - Konstruksi besi siku ( termasuk plat simpul,las & zinkchromate )

1 Zinkcchromate 0.0400 m2 760.00 30.40

2 Besi siku ex. DN SII 1.0500 kg 11.400.00 11.970.00

3 Pekerja 0.0600 hr 55.000.00 3.300.00

4 Tukang besi 0.0045 hr 55.000.00 247.50

5 Mandor 0.0025 hr 70.000.00 175.00

6 Erection 1.0000 kg 800.00 800.00

JUMLAH 16.522.90

DIBULATKAN 16.522.00

1 kg - Konstruksi gording besi ( termasuk plat simpul,las & zinkchromate )

1 Zinkcchromate 0.0400 m2 760.00 30.40

2 Gording besi 1.0200 kg 11.020.00 11.240.40

3 Pekerja 0.0600 hr 55.000.00 3.300.00

4 Tukang besi 0.0045 hr 55.000.00 247.50

5 Mandor 0.0025 hr 70.000.00 175.00

6 Erection 1.0000 kg 800.00 800.00

Page 20: Analisa Harga Satuan Pekerjaan

JUMLAH 15.793.30

DIBULATKAN 15.793.00

1 m2 - Alumunium foil

1 Alumunium foil 1.0500 m2 14.440.00 15.162.00

2 Pekerja 0.0330 hr 55.000.00 1.815.00

3 Tukang kayu 0.0330 hr 55.000.00 1.815.00

4 Mandor 0.0050 hr 70.000.00 350.00

JUMLAH 19.142.00

DIBULATKAN 19.142.00

1 m' - Talang datar / jurai seng tebal 0.3 mm

1 Papan kayu meranti Oven 0.0096 m3 2.622.230.00 25.173.41

2 Plat seng lebar 90 cm, tebal 0.30 mm 0.5000 m' 25.760.00 12.880.00

3 Paku 0.0150 kg 13.680.00 205.20

4 Pekerja 0.0500 hr 55.000.00 2.750.00

5 Tukang kayu 0.1200 hr 55.000.00 6.600.00

6 Mandor 0.0120 hr 70.000.00 840.00

JUMLAH 48.448.61

DIBULATKAN 48.448.00

1 m2 - Pasangan Atap Zincalume + Glasswall+Alumunium Foil + Roofmesh

1 Atap Zincalume 1.0000 m2 112.110.00 112.110.00

2 Glasswall 1.0000 m2 11.400.00 11.400.00

3 Alumunium Foil 1.0500 m2 19.142.00 20.099.10

4 Roofmesh 1.0000 m2 13.300.00 13.300.00

5 Paku Pengikat Atap metal/zincalume 0.1750 kg 13.680.00 2.394.00

6 Sealent 0.0650 kg 20.440.00 1.328.60

7 Pekerja 0.0695 hr 55.000.00 3.822.50

8 Tukang Besi 0.1225 hr 55.000.00 6.737.50

9 Mandor 0.0067 hr 70.000.00 469.00

JUMLAH 171.660.70

DIBULATKAN 171.660.00

1 m' - Pasangan Nok Zincalume + Glasswall+Alumunium Foil + Roofmesh

1 Atap Zincalume 0.3500 m2 112.110.00 39.238.50

2 Paku Pengikat Atap metal/zincalume 0.1550 kg 13.680.00 2.120.40

3 Sealent 0.0250 kg 20.440.00 511.00

4 Pekerja 0.0693 hr 55.000.00 3.811.50

5 Tukang Besi 0.1213 hr 55.000.00 6.671.50

6 Mandor 0.0067 hr 70.000.00 469.00

JUMLAH 52.821.90

DIBULATKAN 52.821.00

PEKERJAAN KAYU

1 m3 - Kusen kayu kamper samarinda

1 Kayu balok kamper samarinda Oven 1.1000 m3 5.875.330.00 6.462.863.00

2 Paku 3.0000 kg 13.680.00 41.040.00

3 Angkur 10.5600 kg 7.600.00 80.256.00

4 Pekerja 7.2000 hr 55.000.00 396.000.00

5 Tukang kayu 25.2000 hr 55.000.00 1.386.000.00

6 Mandor 1.5600 hr 70.000.00 109.200.00

JUMLAH 8.475.359.00

Page 21: Analisa Harga Satuan Pekerjaan

DIBULATKAN 8.475.359.00

1 m3 - Kusen kayu kamper banjar

1 Kayu balok kamper banjar 1.1000 m3 5.875.330.00 6.462.863.00

2 Paku 3.0000 kg 13.680.00 41.040.00

3 Angkur 10.5600 kg 7.600.00 80.256.00

4 Pekerja 7.2000 hr 55.000.00 396.000.00

5 Tukang kayu 25.2000 hr 55.000.00 1.386.000.00

6 Mandor 1.5600 hr 70.000.00 109.200.00

JUMLAH 8.475.359.00

DIBULATKAN 8.475.359.00

1 m3 - Kusen kayu kamper kruing

1 Kayu balok kamper kruing 1.1000 m3 4.408.400.00 4.849.240.00

2 Paku 3.0000 kg 13.680.00 41.040.00

3 Angkur 10.5600 kg 7.600.00 80.256.00

4 Pekerja 7.2000 hr 55.000.00 396.000.00

5 Tukang kayu 25.2000 hr 55.000.00 1.386.000.00

6 Mandor 1.5600 hr 70.000.00 109.200.00

JUMLAH 6.861.736.00

DIBULATKAN 6.861.736.00

1 m3 - Kusen kayu meranti

1 Kayu balok meranti 1.1000 m3 2.876.860.00 3.164.546.00

2 Paku 3.0000 kg 13.680.00 41.040.00

3 Angkur 10.5600 kg 7.600.00 80.256.00

4 Pekerja 7.2000 hr 55.000.00 396.000.00

5 Tukang kayu 25.2000 hr 55.000.00 1.386.000.00

6 Mandor 1.5600 hr 70.000.00 109.200.00

JUMLAH 5.177.042.00

DIBULATKAN 5.177.042.00

1 m2 - Daun pintu double teakwood

1 Rangka papan kamper banjar 0.0400 m3 4.408.400.00 176.336.00

2 Teakwood 4 mm ukuran pintu 1.0000 lbr 75.200.00 75.200.00

3 Lem putih 0.3000 kg 12.540.00 3.762.00

4 Paku triplek 0.0300 kg 13.680.00 410.40

5 Pekerja 0.4800 hr 55.000.00 26.400.00

6 Tukang kayu 1.6000 hr 55.000.00 88.000.00

7 Mandor 0.1840 hr 70.000.00 12.880.00

JUMLAH 382.988.40

DIBULATKAN 382.988.00

1 m2 - Daun pintu double teakwood lapis formika ( untuk KM/WC )

1 Rangka papan kamper banjar 0.0400 m3 4.408.400.00 176.336.00

2 Teakwood 4 mm ukuran pintu 1.0000 lbr 75.200.00 75.200.00

3 Formika 0.5000 lbr 66.700.00 33.350.00

4 Lem putih 0.8000 kg 12.540.00 10.032.00

5 Paku triplek 0.0300 kg 13.680.00 410.40

6 Pekerja 0.4800 hr 55.000.00 26.400.00

7 Tukang kayu 1.6000 hr 55.000.00 88.000.00

8 Mandor 0.1840 hr 70.000.00 12.880.00

JUMLAH 422.608.40

Page 22: Analisa Harga Satuan Pekerjaan

DIBULATKAN 422.608.00

1 m2 - Daun pintu kaca polos

1 Rangka papan kamper banjar 0.0300 m3 4.408.400.00 132.252.00

2 Lem putih 0.4000 kg 12.540.00 5.016.00

3 Paku 0.0300 kg 13.680.00 410.40

4 Kaca polos 5 mm 0.9000 m2 102.600.00 92.340.00

5 Pekerja 0.8000 hr 55.000.00 44.000.00

6 Tukang kayu 2.0000 hr 55.000.00 110.000.00

7 Mandor 0.2400 hr 70.000.00 16.800.00

JUMLAH 400.818.40

DIBULATKAN 400.818.00

1 m2 - Daun pintu kaca rayben

1 Rangka papan kamper banjar 0.0300 m3 4.408.400.00 132.252.00

2 Lem putih 0.4000 kg 12.540.00 5.016.00

3 Paku 0.0300 kg 13.680.00 410.40

4 Kaca rayben 5 mm 0.9000 m2 106.100.00 95.490.00

5 Pekerja 0.8000 hr 55.000.00 44.000.00

6 Tukang kayu 2.0000 hr 55.000.00 110.000.00

7 Mandor 0.2400 hr 70.000.00 16.800.00

JUMLAH 403.968.40

DIBULATKAN 403.968.00

1 m2 - Daun pintu kaca es

1 Rangka papan kamper banjar 0.0300 m3 4.408.400.00 132.252.00

2 Lem putih 0.4000 kg 12.540.00 5.016.00

3 Paku 0.0300 kg 13.680.00 410.40

4 Kaca es 5 mm 0.9000 m2 144.030.00 129.627.00

5 Pekerja 0.8000 hr 55.000.00 44.000.00

6 Tukang kayu 2.0000 hr 55.000.00 110.000.00

7 Mandor 0.2400 hr 70.000.00 16.800.00

JUMLAH 438.105.40

DIBULATKAN 438.105.00

1 m2 - Daun pintu panel kayu samarinda

1 Rangka papan kamper samarinda Oven 0.0440 m3 5.738.520.00 252.494.88

2 Lem putih 0.4000 kg 12.540.00 5.016.00

3 Pekerja 1.2150 hr 55.000.00 66.825.00

4 Tukang kayu 2.4300 hr 55.000.00 133.650.00

5 Mandor 0.2590 hr 70.000.00 18.130.00

JUMLAH 476.115.88

DIBULATKAN 476.115.00

1 m2 - Daun pintu panel kayu banjar

1 Rangka papan kamper banjar 0.0440 m3 4.408.400.00 193.969.60

2 Lem putih 0.4000 kg 12.540.00 5.016.00

3 Pekerja 1.2150 hr 55.000.00 66.825.00

4 Tukang kayu 2.4300 hr 55.000.00 133.650.00

5 Mandor 0.2590 hr 70.000.00 18.130.00

JUMLAH 417.590.60

DIBULATKAN 417.590.00

1 m2 - Daun pintu panel kayu meranti

Page 23: Analisa Harga Satuan Pekerjaan

1 Rangka papan kamper meranti 0.0440 m3 2.876.860.00 126.581.84

2 Lem putih 0.4000 kg 12.540.00 5.016.00

3 Pekerja 1.2150 hr 55.000.00 66.825.00

4 Tukang kayu 2.4300 hr 55.000.00 133.650.00

5 Mandor 0.2590 hr 70.000.00 18.130.00

JUMLAH 350.202.84

DIBULATKAN 350.202.00

1 m2 - Daun pintu / jendela krepyak ( jalusi ) kamper samarinda

1 Rangka papan kamper samarinda 0.0420 m3 5.738.520.00 241.017.84

2 Lem putih 0.2000 kg 12.540.00 2.508.00

3 Pekerja 1.0000 hr 55.000.00 55.000.00

4 Tukang kayu 3.0000 hr 55.000.00 165.000.00

5 Mandor 0.3500 hr 70.000.00 24.500.00

JUMLAH 488.025.84

DIBULATKAN 488.025.00

1 m2 - Daun pintu / jendela krepyak ( jalusi ) kamper banjar

1 Rangka papan kamper banjar 0.0420 m3 4.408.400.00 185.152.80

2 Lem putih 0.2000 kg 12.540.00 2.508.00

3 Pekerja 1.0000 hr 55.000.00 55.000.00

4 Tukang kayu 3.0000 hr 55.000.00 165.000.00

5 Mandor 0.3500 hr 70.000.00 24.500.00

JUMLAH 432.160.80

DIBULATKAN 432.160.00

PEKERJAAN LANTAI

1 m2 - Rabat beton 7 cm + plester dan acian

1 Pasir pasang 0.0030 m3 144.410.00 433.23

2 Pasir beton 0.0330 m3 144.410.00 4.765.53

3 Kerikil / split 0.0650 m3 164.000.00 10.660.00

4 Semen PC ( 50 kg ) 0.2760 zak 54.000.00 14.904.00

5 Pekerja 0.1150 hr 55.000.00 6.325.00

6 Tukang batu 0.0120 hr 55.000.00 660.00

7 Mandor 0.0060 hr 70.000.00 420.00

JUMLAH 38.167.76

DIBULATKAN 38.167.00

1 m2 - Lantai keramik 20 x 20 ad.1 : 3

1 Pasir pasang 0.0300 m3 144.410.00 4.332.30

2 Semen PC ( 50 kg ) 0.0337 zak 54.000.00 1.819.80

3 Semen warna ( cor nat ) 0.0125 kg 10.600.00 132.50

4 Keramik 20 x 20 standar Kw 1 1.0500 m2 40.050.00 42.052.50

5 Pekerja 0.2816 hr 55.000.00 15.488.00

6 Tukang batu 0.1320 hr 55.000.00 7.260.00

7 Mandor 0.0203 hr 70.000.00 1.421.00

8 Alat bantu 0.6000 set 700.00 420.00

JUMLAH 72.926.10

DIBULATKAN 72.926.00

1 m2 - Lantai keramik 30 x 30 ad.1 : 3

1 Pasir pasang 0.0300 m3 144.410.00 4.332.30

2 Semen PC ( 50 kg ) 0.0337 zak 54.000.00 1.819.80

Page 24: Analisa Harga Satuan Pekerjaan

3 Semen warna ( cor nat ) 0.0125 kg 10.600.00 132.50

4 Keramik 30 x 30 standar 40 x 40 1.0500 m2 33.820.00 35.511.00

5 Pekerja 0.2816 hr 55.000.00 15.488.00

6 Tukang batu 0.1320 hr 55.000.00 7.260.00

7 Mandor 0.0203 hr 70.000.00 1.421.00

8 Alat bantu 0.6000 set 700.00 420.00

JUMLAH 66.384.60

DIBULATKAN 66.384.00

1 m2 - Lantai keramik 40 x 40 ad.1 : 3

1 Pasir pasang 0.0300 m3 144.410.00 4.332.30

2 Semen PC ( 50 kg ) 0.0337 zak 54.000.00 1.819.80

3 Semen warna ( cor nat ) 0.0125 kg 10.600.00 132.50

4 Keramik 40 x 40 standar 1.0500 m2 42.940.00 45.087.00

5 Pekerja 0.2816 hr 55.000.00 15.488.00

6 Tukang batu 0.1320 hr 55.000.00 7.260.00

7 Mandor 0.0203 hr 70.000.00 1.421.00

8 Alat bantu 0.6000 set 700.00 420.00

JUMLAH 75.960.60

DIBULATKAN 75.960.00

1 m2 - Keramik dinding 20 x 20

1 Pasir pasang 0.0380 m3 144.410.00 5.487.58

2 Semen PC ( 50 kg ) 0.0340 zak 54.000.00 1.836.00

3 Semen warna ( cor nat ) 0.0125 kg 10.600.00 132.50

4 Keramik 20 x 20 standar 1.0500 m2 40.050.00 42.052.50

5 Pekerja 0.2620 hr 55.000.00 14.410.00

6 Tukang batu 0.2760 hr 55.000.00 15.180.00

7 Mandor 0.0263 hr 70.000.00 1.841.00

8 Alat bantu 0.6000 set 700.00 420.00

JUMLAH 81.359.58

DIBULATKAN 81.359.00

1 m2 - Keramik dinding 20x25

1 Pasir pasang 0.0380 m3 144.410.00 5.487.58

2 Semen PC ( 50 kg ) 0.0340 zak 54.000.00 1.836.00

3 Semen warna ( cor nat ) 0.0125 kg 10.600.00 132.50

4 Keramik 20/25 Kw 1 1.0500 m2 39.140.00 41.097.00

5 Pekerja 0.2620 hr 55.000.00 14.410.00

6 Tukang batu 0.2760 hr 55.000.00 15.180.00

7 Mandor 0.0263 hr 70.000.00 1.841.00

8 Alat bantu 0.6000 set 700.00 420.00

JUMLAH 80.404.08

DIBULATKAN 80.404.00

1 m1 - Plint keramik standar

1 Pasir pasang 0.0030 m3 144.410.00 433.23

2 Semen PC ( 50 kg ) 0.0353 zak 54.000.00 1.906.20

3 Plint keramik standar 0.1100 m2 5.850.00 643.50

4 Semen warna ( cor nat ) 0.0500 kg 10.600.00 530.00

5 Pekerja 0.4000 hr 55.000.00 22.000.00

6 Tukang batu 0.1300 hr 55.000.00 7.150.00

7 Mandor 0.0260 hr 70.000.00 1.820.00

Page 25: Analisa Harga Satuan Pekerjaan

8 Alat bantu 0.6000 set 700.00 420.00

JUMLAH 34.902.93

DIBULATKAN 34.902.00

1 m1 - Plint kayu standar

1 Rangka papan kamper banjar 0.0016 m3 4.408.400.00 7.053.44

2 Paku segala ukuran 0.1000 kg 18.000.00 1.800.00

3 Pekerja 0.4000 hr 55.000.00 22.000.00

4 Tukang kayu 0.1300 hr 55.000.00 7.150.00

5 Mandor 0.0260 hr 70.000.00 1.820.00

6 Alat bantu 0.6000 set 700.00 420.00

JUMLAH 40.243.44

DIBULATKAN 40.243.00

1 m' - Plint keramik 10x20 dinding Kamar mandi

1 Pasir pasang 0.0030 m3 144.410.00 433.23

2 Semen PC ( 50 kg ) 0.0353 zak 54.000.00 1.906.20

3 Plint keramik standar 5.0000 bh 5.850.00 29.250.00

4 Semen warna ( cor nat ) 0.0500 kg 10.600.00 530.00

5 Pekerja 0.0400 hr 55.000.00 2.200.00

6 Tukang batu 0.0130 hr 55.000.00 715.00

7 Mandor 0.0026 hr 70.000.00 182.00

8 Alat bantu 0.0600 set 700.00 42.00

JUMLAH 35.258.43

DIBULATKAN 35.258.00

1 m' - Border 7x20 / Plint keramik dinding Kamar mandi

1 Pasir pasang 0.0030 m3 144.410.00 433.23

2 Semen PC ( 50 kg ) 0.0353 zak 54.000.00 1.906.20

3 Border Keramik Dinding 7/20 1.0000 m' 31.350.00 31.350.00

4 Semen warna ( cor nat ) 0.0500 kg 10.600.00 530.00

5 Pekerja 0.0400 hr 55.000.00 2.200.00

6 Tukang batu 0.0130 hr 55.000.00 715.00

7 Mandor 0.0026 hr 70.000.00 182.00

8 Alat bantu 0.0600 set 700.00 42.00

JUMLAH 37.358.43

DIBULATKAN 37.358.00

PEKERJAAN PLAFOND

1 m2 - Rangka plafond gird 60 x 60 cm ( Rangka Hollow )

1 Hollow 20X40X0,7 mm 0.4500 btg 29.000.00 13.050.00

2 Hollow 40X40X0,7 mm 0.2250 btg 17.100.00 3.847.50

3 Wall Angle 0.2400 btg 15.200.00 3.648.00

4 Suspention Road 4 mm 0.9750 unit 12.160.00 11.856.00

5 Paku Riffet 0.0180 dos 18.240.00 328.32

6 Gypsumboard 9 mm 0.4320 lbr 40.280.00 17.400.96

7 Drywall Screw 0.0400 dos 57.000.00 2.280.00

8 Cornice Adhesive 0.0340 zak 64.600.00 2.196.40

9 Catton Tape 0.0520 roll 10.030.00 521.56

10 Tukang 0.3980 hr 55.000.00 21.890.00

11 Pekerja 0.3740 hr 55.000.00 20.570.00

12 Mandor 0.0700 hr 70.000.00 4.900.00

JUMLAH 102.488.74

Page 26: Analisa Harga Satuan Pekerjaan

DIBULATKAN 102.488.00

1 m2 - Rangka plafond gird 60 x 60 cm ( Rangka Hollow )

1 Hollow 20X40X0,7 mm 0.4500 btg 29.000.00 13.050.00

2 Hollow 40X40X0,7 mm 0.2250 btg 17.100.00 3.847.50

3 Wall Angle 0.2400 btg 15.200.00 3.648.00

4 Suspention Road 4 mm 0.9750 unit 12.160.00 11.856.00

5 Paku Riffet 0.0180 dos 18.240.00 328.32

6 GRC Board t=6 mm 0.4320 lbr 152.010.00 65.668.32

7 Drywall Screw 0.0400 dos 57.000.00 2.280.00

8 Cornice Adhesive 0.0340 zak 64.600.00 2.196.40

9 Catton Tape 0.0520 roll 10.030.00 521.56

10 Tukang 0.3980 hr 55.000.00 21.890.00

11 Pekerja 0.3740 hr 55.000.00 20.570.00

12 Mandor 0.0700 hr 70.000.00 4.900.00

JUMLAH 150.756.10

DIBULATKAN 150.756.00

1 m2 - Rangka plafond gird 50 x 100 cm ( kayu kamper banjar )

1 Kayu kamper banjar Oven 0.0080 m3 4.408.400.00 35.267.20

2 Paku 0.1400 kg 18.000.00 2.520.00

3 Pekerja 0.1700 hr 55.000.00 9.350.00

4 Tukang kayu 0.2800 hr 55.000.00 15.400.00

5 Mandor 0.0370 hr 70.000.00 2.590.00

6 Alat bantu 0.6000 set 700.00 420.00

JUMLAH 65.547.20

DIBULATKAN 65.547.00

1 m2 - Plafond asbes 5 mm + rangka kayu meranti

1 Kayu meranti 0.0080 m3 2.876.860.00 23.014.88

2 Plat asbes semen 100 x 100 cm, t = 6 mm 1.0250 lbr 21.430.00 21.965.75

3 Paku 0.1750 kg 18.000.00 3.150.00

4 Pekerja 0.2200 hr 55.000.00 12.100.00

5 Tukang kayu 0.3500 hr 55.000.00 19.250.00

6 Mandor 0.0460 hr 70.000.00 3.220.00

7 Alat bantu 1.0000 set 700.00 700.00

JUMLAH 83.400.63

DIBULATKAN 83.400.00

1 m2 - Plafond gysum 9 mm + rangka kayu meranti

1 Kayu meranti 0.0080 m3 2.876.860.00 23.014.88

2 Gypsum 9 mm 0.5800 lbr 40.280.00 23.362.40

3 Paku 0.1750 kg 18.000.00 3.150.00

4 Pekerja 0.2200 hr 55.000.00 12.100.00

5 Tukang kayu 0.3500 hr 55.000.00 19.250.00

6 Mandor 0.0460 hr 70.000.00 3.220.00

7 Alat bantu 1.0000 set 700.00 700.00

JUMLAH 84.797.28

DIBULATKAN 84.797.00

1 m2 - Plafond triplek 4 mm + rangka kayu meranti

1 Kayu meranti 0.0080 m3 2.876.860.00 23.014.88

2 Triplek 4 mm 0.3750 lbr 75.200.00 28.200.00

3 Paku 0.1750 kg 18.000.00 3.150.00

Page 27: Analisa Harga Satuan Pekerjaan

4 Pekerja 0.2200 hr 55.000.00 12.100.00

5 Tukang kayu 0.3500 hr 55.000.00 19.250.00

6 Mandor 0.0460 hr 70.000.00 3.220.00

7 Alat bantu 1.0000 set 700.00 700.00

JUMLAH 89.634.88

DIBULATKAN 89.634.00

1 m2 - Plafond asbes 5 mm + rangka kayu meranti

1 Kayu meranti 0.0080 m3 2.876.860.00 23.014.88

2 Asbes 5 mm 0.3750 lbr 40.280.00 15.105.00

3 Paku 0.1750 kg 18.000.00 3.150.00

4 Pekerja 0.2200 hr 55.000.00 12.100.00

5 Tukang kayu 0.3500 hr 55.000.00 19.250.00

6 Mandor 0.0460 hr 70.000.00 3.220.00

7 Alat bantu 1.0000 set 700.00 700.00

JUMLAH 76.539.88

DIBULATKAN 76.539.00

1 m2 - Plafond GRC + rangka kayu meranti

1 Kayu meranti 0.0080 m3 2.876.860.00 23.014.88

2 GRC Board 0.5800 lbr 152.010.00 88.165.80

3 Paku 0.1750 kg 18.000.00 3.150.00

4 Pekerja 0.2200 hr 55.000.00 12.100.00

5 Tukang kayu 0.3500 hr 55.000.00 19.250.00

6 Mandor 0.0460 hr 70.000.00 3.220.00

7 Alat bantu 1.0000 set 700.00 700.00

JUMLAH 149.600.68

DIBULATKAN 149.600.00

1 m1 - List Plafond Kayu Kamper Samarinda 5 cm

1 List Profil Kamper 5 cm 1.1000 m1 12.160.00 13.376.00

2 Paku 0.0100 kg 18.000.00 180.00

3 Pekerja 0.0500 hr 55.000.00 2.750.00

4 Tukang kayu 0.0500 hr 55.000.00 2.750.00

5 Kepala Tukang Kayu 0.0050 hr 56.000.00 280.00

6 Mandor 0.0030 hr 70.000.00 210.00

JUMLAH 19.546.00

DIBULATKAN 19.546.00

PEKERJAAN CAT

1 m2 - Cat dinding dalam ( ICI )

1 Cat setara ICI - interior 0.2800 kg 29.300.00 8.204.00

2 Roll cat + bak 0.0100 bh 16.300.00 163.00

3 Plamur / dempul tembok 0.1600 kg 12.380.00 1.980.80

4 Ampelas 0.5000 lbr 2.600.00 1.300.00

5 Tukang cat 0.2950 hr 65.000.00 19.175.00

6 Mandor 0.0250 hr 80.000.00 2.000.00

JUMLAH 32.822.80

DIBULATKAN 32.822.00

1 m2 - Cat dinding dalam ( Jotun )

1 Cat setara jotun 0.2800 kg 19.900.00 5.572.00

2 Roll cat + bak 0.0100 bh 16.300.00 163.00

Page 28: Analisa Harga Satuan Pekerjaan

3 Plamur / dempul tembok 0.1600 kg 12.380.00 1.980.80

4 Ampelas 0.5000 lbr 2.600.00 1.300.00

5 Tukang cat 0.2950 hr 65.000.00 19.175.00

6 Mandor 0.0250 hr 80.000.00 2.000.00

JUMLAH 30.190.80

DIBULATKAN 30.190.00

1 m2 - Cat dinding luar dengan ( ICI Weathershield )

1 Cat setara ICI Weathershield ) 0.2800 kg 47.100.00 13.188.00

2 Roll cat + bak 0.0100 bh 16.300.00 163.00

3 Plamur / dempul tembok 0.1600 kg 12.380.00 1.980.80

4 Ampelas 0.5000 lbr 2.600.00 1.300.00

5 Tukang cat 0.2950 hr 65.000.00 19.175.00

6 Mandor 0.0250 hr 80.000.00 2.000.00

JUMLAH 37.806.80

DIBULATKAN 37.806.00

1 m2 - Cat dinding dengan Vinilex

1 Cat setara Vinilex 0.2800 kg 16.500.00 4.620.00

2 Roll cat + bak 0.0100 bh 16.300.00 163.00

3 Plamur / dempul tembok 0.1600 kg 12.380.00 1.980.80

4 Ampelas 0.5000 lbr 2.600.00 1.300.00

5 Tukang cat 0.2950 hr 65.000.00 19.175.00

6 Mandor 0.0250 hr 80.000.00 2.000.00

JUMLAH 29.238.80

DIBULATKAN 29.238.00

1 m2 - Cat dinding dengan Metrolith

1 Cat setara Metrolith 0.2800 kg 12.900.00 3.612.00

2 Roll cat + bak 0.0100 bh 16.300.00 163.00

3 Plamur / dempul tembok 0.1600 kg 12.380.00 1.980.80

4 Ampelas 0.5000 lbr 2.600.00 1.300.00

5 Tukang cat 0.2950 hr 65.000.00 19.175.00

6 Mandor 0.0250 hr 80.000.00 2.000.00

JUMLAH 28.230.80

DIBULATKAN 28.230.00

1 m2 - Cat plafond setara ICI

1 Cat setara ICI 0.3000 kg 29.300.00 8.790.00

2 Roll cat + bak 0.0500 bh 16.300.00 815.00

3 Plamur / dempul tembok 0.0450 kg 12.380.00 557.10

4 Ampelas 0.2000 lbr 2.600.00 520.00

5 Tukang cat 0.3150 hr 65.000.00 20.475.00

6 Mandor 0.0250 hr 80.000.00 2.000.00

JUMLAH 33.157.10

DIBULATKAN 33.157.00

1 m2 - Cat plafond setara Jotun

1 Cat setara jotun 0.3000 kg 19.900.00 5.970.00

2 Roll cat + bak 0.0500 bh 16.300.00 815.00

3 Plamur / dempul tembok 0.0450 kg 12.380.00 557.10

4 Ampelas 0.2000 lbr 2.600.00 520.00

5 Tukang cat 0.3150 hr 65.000.00 20.475.00

Page 29: Analisa Harga Satuan Pekerjaan

6 Mandor 0.0250 hr 80.000.00 2.000.00

JUMLAH 30.337.10

DIBULATKAN 30.337.00

1 m2 - Cat besi memakai kuas

1 Cat besi / kayu setara F - Talit 0.2000 kg 38.700.00 7.740.00

2 Kuas 3" 0.0500 bh 12.920.00 646.00

3 Minyak cat / thiner 0.1500 lt 12.540.00 1.881.00

4 Meni besi 0.1675 kg 19.760.00 3.309.80

5 Ampelas 0.4000 lbr 4.560.00 1.824.00

6 Tukang cat 0.3150 hr 65.000.00 20.475.00

7 Mandor 0.0250 hr 80.000.00 2.000.00

JUMLAH 37.875.80

DIBULATKAN 37.875.00

1 m2 - Cat kayu memakai kuas

1 Cat besi / kayu setara F - Talit 0.2000 kg 38.700.00 7.740.00

2 Kuas 3" 0.0500 bh 12.920.00 646.00

3 Plamir kayu 0.0630 kg 12.380.00 779.94

4 Meni kayu 0.1670 kg 20.140.00 3.363.38

5 Ampelas 0.4000 lbr 2.600.00 1.040.00

6 Minyak cat / thiner 0.1500 lt 12.540.00 1.881.00

7 Tukang cat 0.3150 hr 65.000.00 20.475.00

8 Mandor 0.0250 hr 80.000.00 2.000.00

JUMLAH 37.925.32

DIBULATKAN 37.925.00

PEKERJAAN SANITER

1 unit - Closet jongkok standar

1 Pasir pasang 0.1500 m3 144.410.00 21.661.50

2 Semen PC ( 50 kg ) 0.1000 zak 54.000.00 5.400.00

3 Closet jongkok standar 1.0000 bh 222.390.00 222.390.00

4 Pekerja 0.3000 hr 55.000.00 16.500.00

5 Tukang batu 0.2500 hr 55.000.00 13.750.00

6 Mandor 0.1800 hr 70.000.00 12.600.00

JUMLAH 292.301.50

DIBULATKAN 292.301.00

1 unit - Bak air fiber glass kap. 200 ltr

1 Pasir pasang 0.1500 m3 144.410.00 21.661.50

2 Semen PC ( 50 kg ) 0.1000 zak 54.000.00 5.400.00

3 Bak air fiber glass kap. 200 ltr 1.0000 bh 248.540.00 248.540.00

4 Pekerja 0.3000 hr 55.000.00 16.500.00

5 Tukang batu 0.2500 hr 55.000.00 13.750.00

6 Mandor 0.1800 hr 70.000.00 12.600.00

JUMLAH 318.451.50

DIBULATKAN 318.451.00

1 bh - Floor drain

1 Floor drain kuningan 1.0000 bh 25.460.00 25.460.00

2 Pekerja 0.0100 hr 55.000.00 550.00

3 Tukang batu 0.1000 hr 55.000.00 5.500.00

4 Mandor 0.0050 hr 70.000.00 350.00

Page 30: Analisa Harga Satuan Pekerjaan

JUMLAH 31.860.00

DIBULATKAN 31.860.00

1 bh - Kran air 1/2"

1 Kran air 1/2 ex toto 1.0000 bh 91.960.00 91.960.00

2 Seal tape 0.0250 roll 2.280.00 57.00

3 Lem pipa PVC 0.1250 tube 6.840.00 855.00

4 Pekerja 0.0100 hr 55.000.00 550.00

5 Tukang batu 0.1000 hr 55.000.00 5.500.00

6 Mandor 0.0050 hr 70.000.00 350.00

JUMLAH 99.272.00

DIBULATKAN 99.272.00

1 unit - Pompa air jet pump + Instalasi dan pengeboran

1 Pompa air jet pump 1.0000 bh 2.299.200.00 2.299.200.00

2 Pipa PVC 1 " 40.0000 m' 5.850.00 234.000.00

3 Pipa PVC 4 " 16.0000 m' 34.480.00 551.680.00

4 Bocht LL-D 1" (lokal) 6.0000 bh 20.980.00 125.880.00

5 Water moer 2.0000 bh 50.580.00 101.160.00

6 Ongkos pengeboran 1.0000 ls 1.200.000.00 1.200.000.00

JUMLAH 4.511.920.00

DIBULATKAN 4.511.920.00

1 unit - Water tower rangka besi siku

1 Konstruksi besi siku 175.0000 kg 16.522.00 2.891.350.00

2 Pondasi beton tapak K. 175 0.7665 m3 820.907.00 629.225.22

3 Pekerja 2.5000 hr 55.000.00 137.500.00

4 Tukang besi 3.0000 hr 55.000.00 165.000.00

5 Tukang batu 3.0000 hr 55.000.00 165.000.00

6 Mandor 0.3000 hr 70.000.00 21.000.00

JUMLAH 4.009.075.22

DIBULATKAN 4.009.075.00

1 bh - Tangki air kapasitas 1 m3

1 Tangki air kapasitas 1 m3 1.0000 bh 1.320.990.00 1.320.990.00

2 Pekerja 0.1000 hr 55.000.00 5.500.00

3 Tukang batu 0.2500 hr 55.000.00 13.750.00

4 Mandor 0.0250 hr 70.000.00 1.750.00

JUMLAH 1.341.990.00

DIBULATKAN 1.341.990.00

1 unit - Septictank & Rembesan + Instalasi

1 Pas batu bata, t = 1/2 bata ad 1 : 2 12.5000 m2 86.300.00 1.078.750.00

2 Pasir urug unt rembesan 0.3000 m3 100.000.00 30.000.00

3 Koral beton unt. rembesan 1.5080 m3 133.800.00 201.770.40

4 Plesteran dan acian trasraam ad. 1 : 3 11.3400 m2 40.768.00 462.309.12

5 Plat beton penutup t = 12 cm (beton site mix K. 175) 0.3600 m3 820.907.00 295.526.52

6 Besi beton polos 47.4000 kg 12.228.00 579.607.20

7 Pipa PVC 1 " 0.5000 m' 5.850.00 2.925.00

8 Pipa porous 4 " 3.0000 m' 34.480.00 103.440.00

9 Ijuk 30.0000 ikt 6.840.00 205.200.00

10 Pekerja 2.5000 hr 55.000.00 137.500.00

11 Tukang batu 3.0000 hr 55.000.00 165.000.00

12 Mandor 0.0500 hr 70.000.00 3.500.00

Page 31: Analisa Harga Satuan Pekerjaan

JUMLAH 3.265.528.24

DIBULATKAN 3.265.528.00

PEKERJAAN ASESORIS

1 bh - Pasang Engsel pintu nilon 4"

1 Engsel nilon 4" 1.0000 bh 28.040.00 28.040.00

2 Pekerja 0.0150 hr 55.000.00 825.00

3 Tukang kayu 0.1500 hr 55.000.00 8.250.00

4 Mandor 0.0075 hr 70.000.00 525.00

JUMLAH 37.640.00

DIBULATKAN 37.640.00

1 bh - Pasang Engsel jendela

1 Engsel nilon 3" 1.0000 bh 25.080.00 25.080.00

2 Pekerja 0.0100 hr 55.000.00 550.00

3 Tukang kayu 0.1000 hr 55.000.00 5.500.00

4 Mandor 0.0050 hr 70.000.00 350.00

JUMLAH 31.480.00

DIBULATKAN 31.480.00

1 bh - Pasang hak angin

1 Hak angin 1.0000 bh 11.170.00 11.170.00

2 Pekerja 0.0100 hr 55.000.00 550.00

3 Tukang kayu 0.1000 hr 55.000.00 5.500.00

4 Mandor 0.0050 hr 70.000.00 350.00

JUMLAH 17.570.00

DIBULATKAN 17.570.00

1 bh - Pasang slot jendela

1 Slot jendela 1.0000 bh 17.480.00 17.480.00

2 Pekerja 0.0100 hr 55.000.00 550.00

3 Tukang kayu 0.1000 hr 55.000.00 5.500.00

4 Mandor 0.0050 hr 70.000.00 350.00

JUMLAH 23.880.00

DIBULATKAN 23.880.00

1 bh - Pasang kunci double slaag (SOLID)

1 Kunci double slaag (SOLID) 1.0000 bh 202.630.00 202.630.00

2 Pekerja 0.0500 hr 55.000.00 2.750.00

3 Tukang kayu 0.2500 hr 55.000.00 13.750.00

4 Mandor 0.0100 hr 70.000.00 700.00

JUMLAH 219.830.00

DIBULATKAN 219.830.00

1 Titik - Instalasi Lampu (kabel NYM 3x2,5 mm)

1 Kabel NYM 3x2.5 mm 5.0000 m 11.020.00 55.100.00

2 Klem kabel 1.0000 dus 2.410.00 2.410.00

3 Pipa PVC AW 1/2" 2.0000 m 5.850.00 11.700.00

4 Pembantu Instalator 0.3715 hr 56.000.00 20.804.00

5 Instalator 0.1050 hr 64.000.00 6.720.00

6 Mandor 0.0050 hr 70.000.00 350.00

JUMLAH 97.084.00

DIBULATKAN 97.084.00

1 Titik - Instalasi Saklar/Stop Kontak (kabel NYM 3x2,5 mm)

Page 32: Analisa Harga Satuan Pekerjaan

1 Kabel NYM 3x2.5 mm 5.0000 m 11.020.00 55.100.00

2 Klem kabel 1.0000 dus 2.410.00 2.410.00

3 Pipa PVC AW 1/2" 2.0000 m 5.850.00 11.700.00

4 Pembantu Instalator 0.3715 hr 56.000.00 20.804.00

5 Instalator 0.1050 hr 64.000.00 6.720.00

6 Mandor 0.0050 hr 70.000.00 350.00

JUMLAH 97.084.00

DIBULATKAN 97.084.00

1 Bh - Pasang Saklar Tunggal

1 Saklar tunggal 1.0000 bh 13.300.00 13.300.00

2 Pembantu Instalator 0.2500 hr 56.000.00 14.000.00

3 Instalator 0.1500 hr 64.000.00 9.600.00

4 Mandor 0.0050 hr 70.000.00 350.00

JUMLAH 37.250.00

DIBULATKAN 37.250.00

1 Bh - Pasang Saklar Ganda

1 Saklar ganda 1.0000 bh 16.990.00 16.990.00

2 Pembantu Instalator 0.2500 hr 56.000.00 14.000.00

3 Instalator 0.1500 hr 64.000.00 9.600.00

4 Mandor 0.0050 hr 70.000.00 350.00

JUMLAH 40.940.00

DIBULATKAN 40.940.00

1 Bh - Pasang Stop Kontak

1 Stop Kontak 1.0000 bh 14.060.00 14.060.00

2 Pembantu Instalator 0.2500 hr 56.000.00 14.000.00

3 Instalator 0.1500 hr 64.000.00 9.600.00

4 Mandor 0.0050 hr 70.000.00 350.00

JUMLAH 38.010.00

DIBULATKAN 38.010.00

1 Bh - Lampu TL 2 x 18 watt setara philips (inbouw) termasuk bahan komplit

1 Lampu TL 2 x 18 watt, armatur, komplit philips 1.0000 bh 136.810.00 136.810.00

2 Pekerja 0.3132 hr 48.000.00 15.033.60

3 Tukang listrik 0.1045 hr 64.000.00 6.688.00

4 Mandor 0.0050 hr 70.000.00 350.00

5 Alat bantu 0.3000 set 700.00 210.00

JUMLAH 159.091.60

DIBULATKAN 159.091.00

1 Bh - Lampu SL 18 watt setara philips (inbouw) termasuk bahan komplit

1 Lampu SL 18 watt, komplit philips 1.0000 bh 36.570.00 36.570.00

2 Fitting keramik 1.0000 bh 23.240.00 23.240.00

3 Pekerja 0.3132 hr 48.000.00 15.033.60

4 Tukang listrik 0.1045 hr 64.000.00 6.688.00

5 Mandor 0.0050 hr 70.000.00 350.00

6 Alat bantu 0.3000 set 700.00 210.00

JUMLAH 82.091.60

DIBULATKAN 82.091.00

PEKERJAAN SARANA LUAR

1 m' - Saluran buis beton 1/2 dia. 20 cm

Page 33: Analisa Harga Satuan Pekerjaan

1 Buis beton 1/2 dia. 20 cm 1.0250 m' 28.350.00 29.058.75

2 Pasir urug 0.1200 m3 100.000.00 12.000.00

3 Pasir pasang 0.0540 m3 144.410.00 7.798.14

4 Semen PC ( 50 kg ) 0.0270 zak 54.000.00 1.458.00

5 Pekerja 0.0750 hr 48.000.00 3.600.00

6 Tukang batu 0.0500 hr 52.000.00 2.600.00

7 Mandor 0.0125 hr 70.000.00 875.00

JUMLAH 57.389.89

DIBULATKAN 57.389.00

1 m2 - Paving block t = 6 cm

1 Paving block t = 6 cm K.250 1.0250 m2 43.000.00 44.075.00

2 Pasir pasang 0.0250 m3 144.410.00 3.610.25

3 Pekerja 0.1500 hr 48.000.00 7.200.00

4 Tukang batu 0.0500 hr 52.000.00 2.600.00

5 Mandor 0.0030 hr 70.000.00 210.00

JUMLAH 57.695.25

DIBULATKAN 57.695.00

1 m2 - Paving block t = 8 cm

1 Paving block t = 8 cm K.250 1.0250 m2 49.800.00 51.045.00

2 Pasir beton 0.0250 m3 144.410.00 3.610.25

3 Pekerja 0.1500 hr 48.000.00 7.200.00

4 Tukang batu 0.0500 hr 52.000.00 2.600.00

5 Mandor 0.0030 hr 70.000.00 210.00

JUMLAH 64.665.25

DIBULATKAN 64.665.00

1 m' - Kanstin abu - abu 10.20.40 - K.175

1 Kanstin abu - abu 10.20.40 - K.175 1.0000 m2 26.400.00 26.400.00

2 Adukan 0.0100 m3 606.095.00 6.060.95

3 Pekerja 0.0500 hr 48.000.00 2.400.00

4 Tukang batu 0.0175 hr 52.000.00 910.00

5 Mandor 0.00875 hr 70.000.00 612.50

JUMLAH 36.383.45

DIBULATKAN 36.383.00

1 m' - Pagar beton precat t = 2.00 m

1 Galian tanah pondasi 0.1200 m3 43.420.00 5.210.40

2 Pasir beton 0.0150 m3 144.410.00 2.166.15

3 Batu pecah 3/4 0.0290 m3 164.000.00 4.756.00

4 Semen 0.2250 zak 54.000.00 12.150.00

5 Tinggi pagar 5 panel/ 2 m, panjang kolom 3 m, mutu beton K2251.0000 m 167.970.00 167.970.00

6 Pekerja 0.6000 hr 48.000.00 28.800.00

7 Tukang batu 0.3500 hr 52.000.00 18.200.00

8 Mandor 0.0350 hr 70.000.00 2.450.00

JUMLAH 241.702.55

DIBULATKAN 241.702.00

1 m' - Pagar beton precat t = 2.40 m

1 Galian tanah pondasi 0.1200 m3 43.420.00 5.210.40

2 Pasir beton 0.0150 m3 144.410.00 2.166.15

3 Batu pecah 3/4 0.0290 m3 164.000.00 4.756.00

Page 34: Analisa Harga Satuan Pekerjaan

4 Semen 0.2250 zak 54.000.00 12.150.00

5 Tinggi pagar 6 panel/ 2.4 m, pjang kolom 3.5 m, mutu beton K2251.0000 m 197.610.00 197.610.00

6 Pekerja 0.6000 hr 48.000.00 28.800.00

7 Tukang batu 0.3500 hr 52.000.00 18.200.00

8 Mandor 0.0350 hr 70.000.00 2.450.00

JUMLAH 271.342.55

DIBULATKAN 271.342.00

1 m' - Pas.Pagar Tralis Besi

1 Galian Tanah Pondasi 0.1000 m3 43.420.00 4.342.00

2 Urugan Tanah Kembali 0.0250 m3 17.620.00 440.50

3 Pas. Batu Kali 1 : 5 0.1875 m3 529.170.00 99.219.38

4 Sloof beton 15/20 K.175 0.0300 m3 3.820.009.00 114.600.27

5 Kolom beton 25/25 K.225 0.0354 m3 3.263.329.00 115.576.24

6 Kepala pagar dengan beton K.225 0.0167 m3 3.263.329.00 54.388.82

7 Pas.Batu bata 1 : 5 0.5000 m2 83.889.00 41.944.50

8 Plester + Acian 1.5200 m2 37.529.00 57.044.08

9 Pas. Batu Tempel 1.0000 m2 133.424.00 133.424.00

10 Pengecetan Kolom 1.5200 m2 32.822.00 49.889.44

11 Besi Beton Polos dia..16 9.8000 kg 12.228.00 119.834.40

12 Besi Beton Polos dia..10 2.2200 kg 12.228.00 27.146.16

13 Besi siku L.40.40.4 4.8333 kg 11.400.00 55.100.00

14 Tombak Beton 7.0000 bh 5.700.00 39.900.00

15 Pengelasan & Pengecetan 1.0000 ls 44.000.00 44.000.00

16 Ongkos pasang Pagar Besi 1.0000 ls 8.000.00 8.000.00

JUMLAH 964.849.78

DIBULATKAN 964.849.00

1 m' - Pas.Pintu Pagar Tralis Besi

1 Besi Beton Polos dia..16 18.0000 kg 12.228.00 220.104.00

2 Besi Beton Polos dia..10 4.9950 kg 12.228.00 61.078.86

3 Besi Galvanis dia. 2" 4.5000 m1 45.600.00 205.200.00

4 Tombak Beton 54.0000 bh 5.700.00 307.800.00

5 Pengelasan & Pengecetan 1.0000 ls 44.000.00 44.000.00

6 Roda Pagar 0.7500 bh 11.400.00 8.550.00

7 Kunci Pagar 0.2500 bh 38.000.00 9.500.00

8 Rel Besi 1.3000 kg 7.600.00 9.880.00

9 Ongkos pasang Pagar Besi 1.0000 ls 8.000.00 8.000.00

JUMLAH 874.112.86

DIBULATKAN 874.112.00

1 m' - Ralling Tangga Kayu

1 Catur kayu kamper 4.0000 bh 38.000.00 152.000.00

2 Hand Ralling 1.1000 m' 22.990.00 25.289.00

3 Melamin 0.2000 m2 6.680.00 1.336.00

4 Dyna Bolt 6.0000 bh 4.180.00 25.080.00

5 Pekerja 0.3550 hr 48.000.00 17.040.00

6 Tukang 0.8875 hr 52.000.00 46.150.00

7 Mandor 0.0533 hr 70.000.00 3.727.50

8 Alat bantu 1.0000 set 700.00 700.00

JUMLAH 271.322.50

DIBULATKAN 271.322.00

Page 35: Analisa Harga Satuan Pekerjaan

PEKERJAAN PARTISI

1 M2 Rangka partisi besi hollow, modul 60X60 CM

1 Hollow 40X40X0,7 mm 1.1000 btg 17.100.00 18.810.00

2 Paku Riffet 6.0000 bj 1.000.00 6.000.00

3 Tukang 0.2260 org/hr 48.000.00 10.848.00

4 Pekerja 0.2160 org/hr 52.000.00 11.232.00

5 Mandor 0.0250 org/hr 70.000.00 1.750.00

JUMLAH 48.640.00

DIBULATKAN 48.600.00

1 M2 Partisi gypsumboard 9 MM

1 Gypsumboard 9 mm 0.4320 lbr 40.280.00 17.400.96

2 Drywall Screw 0.0400 dos 57.000.00 2.280.00

3 Cornice Adhesive 0.0340 zak 64.600.00 2.196.40

4 Catton Tape 0.0520 roll 10.030.00 521.56

5 Tukang 0.1220 org/hr 48.000.00 5.856.00

6 Pekerja 0.1080 org/hr 52.000.00 5.616.00

7 Mandor 0.0250 org/hr 70.000.00 1.750.00

JUMLAH 35.620.92

DIBULATKAN 35.600.00

1 M2 Mengerjakan dinding kisi-kisi / sunshading besi hollow

1 Besi holllow 40X40x1,8 mm 0.5000 btg 60.800.00 30.400.00

2 Besi holllow 40X20x1,8 mm 4.0000 btg 41.800.00 167.200.00

3 Aksesories dan perlengkapan 0.2500 hrg 51.300.00 12.825.00

4 Upah potong besi 1.0000 m2 4.000.00 4.000.00

5 Upah las dan pasang 1.0000 m2 4.000.00 4.000.00

JUMLAH 218.425.00

DIBULATKAN 218.400.00

Mengerjakan dinding partisi type - PR1

1 Rangka hollow 4/4 2.0720 m2 48.600.00 100.699.20

2 Gypsumboard 9 mm 4.1440 m2 45.000.00 186.480.00

3 Papan kayu 3X10 cm 1.4800 m' 19.000.00 28.120.00

4 List profil kayu 2X4 cm 2.9600 m' 12.160.00 35.993.60

5 Plint kayu 1,5/10 5.9200 m' 17.100.00 101.232.00

6 Paku 0.1000 kg 13.680.00 1.368.00

JUMLAH 453.892.80

DIBULATKAN 453.800.00

Mengerjakan dinding partisi type - PR2

1 Rangka hollow 4/4 3.4300 m2 48.600.00 166.698.00

2 Gypsumboard 9 mm 6.8600 m2 45.000.00 308.700.00

3 Papan kayu 3X10 cm 2.4500 m' 19.000.00 46.550.00

4 List profil kayu 2X4 cm 4.9000 m' 12.160.00 59.584.00

5 Plint kayu 1,5/10 9.8000 m' 17.100.00 167.580.00

6 Paku 0.1500 kg 13.680.00 2.052.00

JUMLAH 751.164.00

DIBULATKAN 751.100.00

Mengerjakan dinding partisi type - PR3

1 Rangka hollow 4/4 6.6920 m2 48.600.00 325.231.20

2 Gypsumboard 9 mm 13.3840 m2 45.000.00 602.280.00

Page 36: Analisa Harga Satuan Pekerjaan

3 Papan kayu 3X10 cm 4.7800 m' 19.000.00 90.820.00

4 List profil kayu 2X4 cm 9.5600 m' 12.160.00 116.249.60

5 Plint kayu 1,5/10 19.1200 m' 17.100.00 326.952.00

6 Paku 0.2500 kg 13.680.00 3.420.00

JUMLAH 1.464.952.80

DIBULATKAN 1.464.900.00

` Mengerjakan dinding partisi type - PR4

1 Rangka hollow 4/4 4.4800 m2 48.600.00 217.728.00

2 Gypsumboard 9 mm 8.9600 m2 45.000.00 403.200.00

3 Papan kayu 3X10 cm 3.2000 m' 19.000.00 60.800.00

4 List profil kayu 2X4 cm 6.4000 m' 12.160.00 77.824.00

5 Plint kayu 1,5/10 12.8000 m' 17.100.00 218.880.00

6 Paku 0.2000 kg 13.680.00 2.736.00

JUMLAH 981.168.00

DIBULATKAN 981.100.00

` Mengerjakan dinding partisi type - PR5

1 Rangka hollow 4/4 3.2620 m2 48.600.00 158.533.20

2 Gypsumboard 9 mm 6.5240 m2 45.000.00 293.580.00

3 Papan kayu 3X10 cm 2.3300 m' 19.000.00 44.270.00

4 List profil kayu 2X4 cm 4.6600 m' 12.160.00 56.665.60

5 Plint kayu 1,5/10 9.3200 m' 17.100.00 159.372.00

6 Paku 0.1500 kg 13.680.00 2.052.00

JUMLAH 714.472.80

DIBULATKAN 714.400.00

` Mengerjakan dinding partisi type - PR6

1 Rangka hollow 4/4 5.1520 m2 48.600.00 250.387.20

2 Gypsumboard 9 mm 10.3040 m2 45.000.00 463.680.00

3 Papan kayu 3X10 cm 3.6800 m' 19.000.00 69.920.00

4 List profil kayu 2X4 cm 7.3600 m' 12.160.00 89.497.60

5 Plint kayu 1,5/10 14.7200 m' 17.100.00 251.712.00

6 Paku 0.2000 kg 13.680.00 2.736.00

JUMLAH 1.127.932.80

DIBULATKAN 1.127.900.00

` Mengerjakan dinding partisi type - PR7 / PR7a

1 Rangka hollow 4/4 3.5420 m2 48.600.00 172.141.20

2 Gypsumboard 9 mm 7.0840 m2 45.000.00 318.780.00

3 Papan kayu 3X10 cm 2.5300 m' 19.000.00 48.070.00

4 List profil kayu 2X4 cm 5.0600 m' 12.160.00 61.529.60

5 Plint kayu 1,5/10 10.1200 m' 17.100.00 173.052.00

6 Paku 0.1500 kg 13.680.00 2.052.00

JUMLAH 775.624.80

DIBULATKAN 775.600.00

` Mengerjakan dinding partisi type - PR8

1 Rangka hollow 4/4 10.9760 m2 48.600.00 533.433.60

2 Gypsumboard 9 mm 21.9520 m2 45.000.00 987.840.00

3 Plint kayu 1,5/10 6.8600 m' 17.100.00 117.306.00

4 Paku 0.3000 kg 13.680.00 4.104.00

JUMLAH 1.642.683.60

Page 37: Analisa Harga Satuan Pekerjaan

DIBULATKAN 1.642.600.00

` Mengerjakan dinding partisi type - PR9

1 Rangka hollow 4/4 4.3520 m2 48.600.00 211.507.20

2 Gypsumboard 9 mm 8.7040 m2 45.000.00 391.680.00

3 Plint kayu 1,5/10 2.7200 m' 17.100.00 46.512.00

4 Paku 0.2000 kg 13.680.00 2.736.00

JUMLAH 652.435.20

DIBULATKAN 652.400.00

1 UNIT PK

No Vol Sat Harga Jumlah Harga

1 Pintu Kaca+kaca Frameless Tempered 12mm 8.30 m2 850.000.00 7.055.000.00

2 Floor Hings, Ex. Dexon 2.00 Set 2.150.000.00 4.300.000.00

3 Pasang Fitch Fitting Komplit, Ex. Dexon 1.00 Set 2.350.000.00 2.350.000.00

4 Handle Stainless 2.00 Psg 350.000.00 700.000.00

5 pasang "u" aluminium 18.64 m1 60.000.00 1.118.400.00

6 Upah kerja + pasang 1.00 Unit 750.000.00 750.000.00

Jumlah 16.273.400.00

Dibulatkan 16.273.400.00

1 UNIT P1

1 Kusen kayu kamper samarinda 0.04 m3 8.475.359.00 375.034.64

2 Daun pintu panel kayu samarinda 1.71 m2 476.115.00 814.156.65

3 Pas. Double Multipleks 6 mm + Teakwood 0.20 m2 382.988.00 76.597.60

4 Pasang Engsel pintu nilon 4" 3.00 Bh 28.040.00 84.120.00

5 Pasang kunci standar (SOLID) 1.00 Bh 202.630.00 202.630.00

6 Handle Stailess Steel (Decksen) 2.00 Bh 275.000.00 550.000.00

7 Kaca Es 5mm 0.17 m2 144.030.00 24.485.10

Jumlah 2.127.023.99

Dibulatkan 2.127.000.00

1 UNIT P2

1 Kusen kayu kamper samarinda 0.04 m3 8.475.359.00 375.034.64

2 Daun pintu panel kayu samarinda 1.50 m2 476.115.00 714.172.50

3 Pas. Double Multipleks 6 mm + Teakwood 0.20 m2 382.988.00 76.597.60

4 Pasang Engsel pintu nilon 4" 3.00 Bh 28.040.00 84.120.00

5 Pasang kunci standar (SOLID) 1.00 Bh 202.630.00 202.630.00

6 Handle Stailess Steel (Decksen) 2.00 Bh 275.000.00 550.000.00

7 Kaca Es 5mm 0.17 m2 144.030.00 24.485.10

Jumlah 2.027.039.84

Dibulatkan 2.027.000.00

1 UNIT P6

1 Kusen kayu kamper samarinda 0.10 m3 8.475.359.00 847.535.90

2 Daun pintu panel kayu samarinda 1.71 m2 476.115.00 814.156.65

3 Pas. Double Multipleks 6 mm + Teakwood 0.75 m2 382.988.00 287.241.00

4 Pasang Engsel pintu nilon 4" 3.00 Bh 28.040.00 84.120.00

5 Pasang Engsel jendela nilon 3" - Bh 25.080.00 -

6 Handle Stailess Steel (Decksen) 2.00 Bh 275.000.00 550.000.00

6 GRENDEL TANAM - set 44.230.00 -

7 Kaca Es 5mm 1.65 m2 144.030.00 237.649.50

Jumlah 2.820.703.05

Dibulatkan 2.820.700.00

Uraian

Page 38: Analisa Harga Satuan Pekerjaan

1 UNIT P4

1 Pintu PVC 1.00 Bh 266.020.00 266.020.00

2 Upah Pasang 1.51 m2 13.301.00 20.084.51

Jumlah 286.104.51

Dibulatkan 286.100.00

1 UNIT P3

1 Kusen kayu kamper samarinda 0.03 m3 8.475.359.00 286.043.37

2 Daun pintu panel kayu samarinda 1.30 m2 476.115.00 618.949.50

3 Pas. Double Multipleks 6 mm + Teakwood - m2 382.988.00 -

4 Pasang Engsel pintu nilon 4" 3.00 Bh 28.040.00 84.120.00

5 Pasang Engsel jendela nilon 3" - Bh 25.080.00 -

6 Pasang kunci standar (SOLID) 1.00 Ps 202.630.00 202.630.00

7 Handle Stailess Steel (Decksen) 2.00 Bh 275.000.00 550.000.00

8 Kaca Es 5mm 0.12 m2 144.030.00 17.283.60

Jumlah 1.759.026.47

Dibulatkan 1.759.000.00

1 UNIT JENDELA J2

1 Kusen Alumunium warna ukuran 4" x 1 3/4" 13.00 m' 88.540.00 1.151.020.00

2 Pasangan kaca polos, t= 8 mm 3.60 m2 109.440.00 393.984.00

3 Fisher 12.00 bh 500.00 6.000.00

4 Upah potong kaca 3.60 m2 5.000.00 18.000.00

5 Upah pasang + aksesories 1.00 Unit 75.000.00 75.000.00

Jumlah 1.644.004.00

Dibulatkan 1.644.000.00

1 UNIT JENDELA J5

1 Kusen Alumunium warna ukuran 4" x 1 3/4" 5.40 m' 88.540.00 478.116.00

2 Pasangan kaca polos, t= 5 mm 0.98 m2 102.600.00 100.548.00

3 Fisher 6.00 bh 500.00 3.000.00

4 Upah potong kaca 0.98 m2 5.000.00 4.900.00

5 Upah pasang + aksesories 1.00 Unit 75.000.00 75.000.00

Jumlah 661.564.00

Dibulatkan 661.500.00

1 UNIT JENDELA J1

1 Kusen Alumunium warna ukuran 4" x 1 3/4" 4.40 m' 88.540.00 389.576.00

2 Bingkai jendela aluminium 4.00 m' 109.520.00 438.080.00

3 Pasangan kaca polos, t= 5 mm 0.65 m2 102.600.00 66.690.00

4 Engsel jendela casemen 16" 1.00 set 39.520.00 39.520.00

5 Karet dan silent 4.00 m' 1.920.00 7.680.00

6 Fisher 4.00 bh 500.00 2.000.00

7 ramp buncis 1.00 bh 15.000.00 15.000.00

8 Upah potong kaca 0.65 m2 5.000.00 3.250.00

9 Upah pasang + aksesories 1.00 Unit 75.000.00 75.000.00

Jumlah 1.036.796.00

Dibulatkan 1.036.700.00

1 UNIT JENDELA J6/J6a

1 Kusen Alumunium warna ukuran 4" x 1 3/4" 9.10 m' 88.540.00 805.714.00

2 Pasangan kaca polos, t= 8 mm 2.88 m2 109.440.00 315.187.20

3 Fisher 10.00 bh 500.00 5.000.00

4 Upah potong kaca 2.25 m2 5.000.00 11.250.00

Page 39: Analisa Harga Satuan Pekerjaan

5 Upah pasang + aksesories 1.00 Unit 75.000.00 75.000.00

Jumlah 1.212.151.20

Dibulatkan 1.212.100.00

1 UNIT JENDELA J3

1 Kaca Es 5mm 0.35 m2 144.030.00 50.410.50

2 pasangan "u" aluminium 3.36 m' 60.000.00 201.600.00

3 Upah kerja 1.00 Unit 75.000.00 75.000.00

4 Upah potong kaca 0.35 m2 5.000.00 1.750.00

Jumlah 328.760.50

Dibulatkan 328.700.00

1 UNIT JENDELA J4

1 Kusen Alumunium warna ukuran 4" x 1 3/4" 2.20 m' 88.540.00 194.788.00

3 Kaca Es 5mm 0.30 m2 144.030.00 43.209.00

6 Upah potong kaca 0.30 m2 5.000.00 1.500.00

7 Upah pasang + aksesories 1.00 Unit 75.000.00 75.000.00

Jumlah 314.497.00

Dibulatkan 314.400.00

1 UNIT JENDELA J4a

1 pasangan "u" aluminium 2.00 m' 60.000.00 120.000.00

3 Kaca Es 5mm 0.26 m2 144.030.00 37.447.80

6 Upah potong kaca 0.26 m2 5.000.00 1.300.00

7 Upah pasang + aksesories 1.00 Unit 75.000.00 75.000.00

Jumlah 233.747.80

Dibulatkan 233.700.00

1 M2 Mengerjakan dinding kisi-kisi / sunshading besi hollow

1 Besi holllow 40X40x1,8 mm 0.50 m' 60.800.00 30.400.00

2 Besi holllow 40X20x1,8 mm 4.00 m2 41.800.00 167.200.00

3 Aksesories dan perlengkapan 0.25 m2 300.000.00 75.000.00

4 Upah Potong besi 1.00 m2 4.000.00 4.000.00

5 Upah Las dan Pasang 1.00 m2 4.000.00 4.000.00

Jumlah 280.600.00

Dibulatkan 280.600.00

Pek. Kosen Pintu besi R. pompa (Type P5)

Termasuk Pengadaan bahan dan pemasangan, lengkap unit set,

sesuai gambar untuk itu, dengan rincian & spesifikasi sbb. :

- Kosen dari besi Canal CNP-10, finish cat 4.50 m' 175.000.00 787.500.00

- Pintu dbl plat & tralis besi, rangka hollow 40.40.2 1.26 m2 525.000.00 661.500.00

- Finishing cat duco kosen besi 0.90 m2 85.000.00 76.500.00

- Finishing cat pintu 2.52 m2 37.925.00 95.571.00

- Engsel dari engsel bubut 3.00 bh 100.000.00 300.000.00

- Handle, Lockcase & Cylinder Cisa, khusus pintu besi. 1.00 unit 800.000.00 800.000.00

Jumlah 2.721.071.00

Dibulatkan 2.721.000.00