Page 1: Uraian Analisa Harga Satuan

URAIAN ANALISA HARGA SATUAN

TOWER CRANE

URAIAN PERALATAN

1. Jenis Peralatan : Tower Crane, type ST60/15 dengan radius 60 m Genset, dan standard mesin 150 KVA

2. Tenaga (Pw) : 150,0 HP

3. Kapasitas (Cp) : 15,0 ton

4. Umur Ekonomis (A) : 5,0 tahun ( Alat Baru )

5. Jam Operasi Dalam 1 Tahun (W) : 2.000 jam ( Alat Baru )

6. Harga Alat (B) : Rp 150.000.000 ( Alat Baru )

HARGA STANDAR

1. Tingkat Suku Bunga (i) : 20,00 % / Tahun

2. Upah Operator / Sopir (U1) : Rp 25.000,00 / Jam

3. Upah Pembantu Operator / Pmb.Sopir (U2) : Rp 20.000,00 / Jam

4. Bahan Bakar Bensin (Mb) : Rp 6.500,00 / Liter

5. Bahan Bakar Solar (Ms) : Rp 5.500,00 / Liter

6. Minyak Pelumas (Mp) : Rp 40.000,00 / Liter

Page 2: Uraian Analisa Harga Satuan

OWNING COST

1. Nilai Sisa Alat (C) = 10 % x Harga Alat Baru

= 10 % x Rp. 150.000.000

= Rp. 15.000.000

2. Faktor Angsuran Modal (D) = i×(1+i)A

(1+i)A−1

= 0,20× (1+0,20 )5

(1+0,20 )5−1

= 0,33438

3. Biaya Pasti per Jam :

a. Biaya Pengembalian Modal (E) = ( B - C ) x D

= (150.000.000 - 15.000.000) x 0,33438

= Rp. 45.141.300,00

b. Asuransi, dll (F) = 0,002×BW

=0,002×15 0.000 .000

2000

= Rp. 150,00

4. Biaya Pasti per Jam (G) = ( E + F )

= ( Rp. 45.141.300,00 + Rp. 150,00 )

= Rp. 45.141.450,00

Page 3: Uraian Analisa Harga Satuan

BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar (H) = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms

= (0.125-0.175 Ltr/HP/Jam) x 150 x Rp. 5.500,00

= Rp. 103.125,00

2. Pelumas (I) = (0.025-0.030 Ltr/HP/Jam) x Pw x Mp

= (0.025-0.030 Ltr/HP/Jam) x 150 x Rp. 40.000,00

= Rp. 150.000,00

3. Perawatan dan perbaikan (K) = (12,5 %−17,5 %)×B

W

= (12,5 %−17,5 %)×110.000.000

2000

= Rp 6.875,00

4. Operator (L) = ( 1 Orang / Jam ) x U1

= ( 1 Orang / Jam ) x 2.500,00

= Rp 2.500,00

5. Pembantu Operator (M) = ( 1 Orang / Jam ) x U2

= ( 1 Orang / Jam ) x 2.000,00

= Rp 2.000,00

6. Biaya Operasi per Jam (P) = ( H + I + K + L + M )

= (12.187,50 + 13.500,00 + 6.875,00 + 2.500,00 + 2.000,00)

= Rp 37.062,50

TOTAL BIAYA SEWA ALAT / JAM (S) = ( G + P )

Page 4: Uraian Analisa Harga Satuan

= (16.661,80 + 37.062 = Rp 53.724,30/ jam

ANALISA MASING – MASING HARGA SATUAN

PERKIRAAN HARGA JUMLAHNO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA

(Rp.) (Rp.)

A. PEKERJA

1. - - - -2. - - - -

B. BAHAN

1. - - - -2. - - - -

C. ALAT

1. CRANE 10-15 TON jam 1,0000 53.724,30 53.724,302. - jam - - -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 53.724,30E. OVERHEAD & PROFIT 10,0 % x D 5.372,43F. HARGA SATUAN PEKERJAAN ( D + E ) 59.096,72