PERHITUNGAN VOLUME GALIAN KIRI (Saluran) PERHITUNGAN VOLUME GALIAN KANAN (Saluran)
NO StaLUAS (m²)
PANJANG (m) NOSENDIRI RATA-RATA
1 0+000 0.9 1
0.9 100 902 0+100 0.9 2
0.9 100 903 0+200 0.9 3
0.9 100 904 0+300 0.9 4
0.9 100 905 0+400 0.9 5
0.9 100 906 0+500 0.9 6
0.9 100 907 0+600 0.9 7
0.9 100 908 0+700 0.9 8
0.9 100 909 0+800 0.9 9
0.9 100 9010 0+900 0.9 10
0.9 100 9011 1+000 0.9 11
0.9 100 9012 1+100 0.9 12
0.9 100 9013 1+200 0.9 13
0.9 100 9014 1+300 0.9 14
0.9 100 9015 1+400 0.9 15
0.9 100 9016 1+500 0.9 16
0.9 100 9017 1+600 0.9 17
0.9 100 9018 1+700 0.9 18
0.9 100 9019 1+800 0.9 19
0.9 100 9020 1+900 0.9 20
0.9 100 9021 2+000 0.9 21
0.9 100 9022 2+100 0.9 22
VOLUME (m³)
0.9 100 9023 2+200 0.9 23
0.9 100 9024 2+300 0.9 24
0.9 100 9025 2+400 0.9 25
0.9 100 9026 2+500 0.9 26
0.9 100 9027 2+600 0.9 27
0.9 100 9028 2+700 0.9 28
0.9 100 9029 2+800 0.9 29
0.9 100 9030 2+900 0.9 30
0.9 100 9031 3+000 0.9 31
TOTAL VOLUME GALIAN KIRI (Saluran) (m³) 2700 TOTAL VOLUME GALIAN KANAN (Saluran) (m³)
TOTAL KESELURUHAN GALIAN (Saluran) (m³)
PERHITUNGAN VOLUME GALIAN KANAN (Saluran)
StaLUAS (m²)
PANJANG (m)SENDIRI RATA-RATA
0+000 0.90.9 100 90
0+100 0.90.9 100 90
0+200 0.90.9 100 90
0+300 0.90.9 100 90
0+400 0.90.9 100 90
0+500 0.90.9 100 90
0+600 0.90.9 100 90
0+700 0.90.9 100 90
0+800 0.90.9 100 90
0+900 0.90.9 100 90
1+000 0.90.9 100 90
1+100 0.90.9 100 90
1+200 0.90.9 100 90
1+300 0.90.9 100 90
1+400 0.90.9 100 90
1+500 0.90.9 100 90
1+600 0.90.9 100 90
1+700 0.90.9 100 90
1+800 0.90.9 100 90
1+900 0.90.9 100 90
2+000 0.90.9 100 90
2+100 0.9
VOLUME (m³)
0.9 100 902+200 0.9
0.9 100 902+300 0.9
0.9 100 902+400 0.9
0.9 100 902+500 0.9
0.9 100 902+600 0.9
0.9 100 902+700 0.9
0.9 100 902+800 0.9
0.9 100 902+900 0.9
0.9 100 903+000 0.9
TOTAL VOLUME GALIAN KANAN (Saluran) (m³) 2700
TOTAL KESELURUHAN GALIAN (Saluran) (m³) 5400
PERHITUNGAN VOLUME LAPISAN AGREGAT KELAS A KIRI (LPB) PERHITUNGAN VOLUME LAPISAN AGREGAT KELAS A KANAN (LPB)
NO StaLUAS (m²)
PANJANG (m) NOSENDIRI RATA-RATA
1 0+000 0.5 1
0.5 100 502 0+100 0.5 2
0.5 100 503 0+200 0.5 3
0.5 100 504 0+300 0.5 4
0.5 100 505 0+400 0.5 5
0.5 100 506 0+500 0.5 6
0.5 100 507 0+600 0.5 7
0.5 100 508 0+700 0.5 8
0.5 100 509 0+800 0.5 9
0.5 100 5010 0+900 0.5 10
0.5 100 5011 1+000 0.5 11
0.5 100 5012 1+100 0.5 12
0.5 100 5013 1+200 0.5 13
0.5 100 5014 1+300 0.5 14
0.5 100 5015 1+400 0.5 15
0.5 100 5016 1+500 0.5 16
0.5 100 5017 1+600 0.5 17
0.5 100 5018 1+700 0.5 18
0.5 100 5019 1+800 0.5 19
0.5 100 5020 1+900 0.5 20
0.5 100 5021 2+000 0.5 21
0.5 100 5022 2+100 0.5 22
VOLUME (m³)
0.5 100 5023 2+200 0.5 23
0.5 100 5024 2+300 0.5 24
0.5 100 5025 2+400 0.5 25
0.5 100 5026 2+500 0.5 26
0.5 100 5027 2+600 0.5 27
0.5 100 5028 2+700 0.5 28
0.5 100 5029 2+800 0.5 29
0.5 100 5030 2+900 0.5 30
0.5 100 5031 3+000 0.5 31
TOTAL VOLUME LAPISAN AGREGAT KELAS B KIRI (m³) 1500 TOTAL VOLUME LAPISAN AGREGAT KELAS B KANAN (m³)
TOTAL KESELURUHAN LAPISAN AGREGAT KELAS B (m³)
0.5
PERHITUNGAN VOLUME LAPISAN AGREGAT KELAS A KANAN (LPB)
StaLUAS (m²)
PANJANG (m)SENDIRI RATA-RATA
0+000 0.50.5 100 50
0+100 0.50.5 100 50
0+200 0.50.5 100 50
0+300 0.50.5 100 50
0+400 0.50.5 100 50
0+500 0.50.5 100 50
0+600 0.50.5 100 50
0+700 0.50.5 100 50
0+800 0.50.5 100 50
0+900 0.50.5 100 50
1+000 0.50.5 100 50
1+100 0.50.5 100 50
1+200 0.50.5 100 50
1+300 0.50.5 100 50
1+400 0.50.5 100 50
1+500 0.50.5 100 50
1+600 0.50.5 100 50
1+700 0.50.5 100 50
1+800 0.50.5 100 50
1+900 0.50.5 100 50
2+000 0.50.5 100 50
2+100 0.5
VOLUME (m³)
0.5 100 502+200 0.5
0.5 100 502+300 0.5
0.5 100 502+400 0.5
0.5 100 502+500 0.5
0.5 100 502+600 0.5
0.5 100 502+700 0.5
0.5 100 502+800 0.5
0.5 100 502+900 0.5
0.5 100 503+000 0.5
TOTAL VOLUME LAPISAN AGREGAT KELAS B KANAN (m³) 1500
TOTAL KESELURUHAN LAPISAN AGREGAT KELAS B (m³) 3000
PERHITUNGAN VOLUME LAPISAN AGREGAT KELAS A KIRI (LPA) PERHITUNGAN VOLUME LAPISAN AGREGAT KELAS A KANAN (LPA)
NO StaLUAS (m²)
PANJANG (m) NOSENDIRI RATA-RATA
1 0+000 0.375 1
0.375 100 37.52 0+100 0.375 2
0.375 100 37.53 0+200 0.375 3
0.375 100 37.54 0+300 0.375 4
0.375 100 37.55 0+400 0.375 5
0.375 100 37.56 0+500 0.375 6
0.375 100 37.57 0+600 0.375 7
0.375 100 37.58 0+700 0.375 8
0.375 100 37.59 0+800 0.375 9
0.375 100 37.510 0+900 0.375 10
0.375 100 37.511 1+000 0.375 11
0.375 100 37.512 1+100 0.375 12
0.375 100 37.513 1+200 0.375 13
0.375 100 37.514 1+300 0.375 14
0.375 100 37.515 1+400 0.375 15
0.375 100 37.516 1+500 0.375 16
0.375 100 37.517 1+600 0.375 17
0.375 100 37.518 1+700 0.375 18
0.375 100 37.519 1+800 0.375 19
0.375 100 37.520 1+900 0.375 20
0.375 100 37.521 2+000 0.375 21
0.375 100 37.522 2+100 0.375 22
VOLUME (m³)
0.375 100 37.523 2+200 0.375 23
0.375 100 37.524 2+300 0.375 24
0.375 100 37.525 2+400 0.375 25
0.375 100 37.526 2+500 0.375 26
0.375 100 37.527 2+600 0.375 27
0.375 100 37.528 2+700 0.375 28
0.375 100 37.529 2+800 0.375 29
0.375 100 37.530 2+900 0.375 30
0.375 100 37.531 3+000 0.375 31
TOTAL VOLUME LAPISAN AGREGAT KELAS A KIRI (m³) 1125 TOTAL VOLUME LAPISAN AGREGAT KELAS A KANAN (m³)
TOTAL KESELURUHAN LAPISAN AGREGAT KELAS A (m³)
0.375
PERHITUNGAN VOLUME LAPISAN AGREGAT KELAS A KANAN (LPA)
StaLUAS (m²)
PANJANG (m)SENDIRI RATA-RATA
0+000 0.3750.375 100 37.5
0+100 0.3750.375 100 37.5
0+200 0.3750.375 100 37.5
0+300 0.3750.375 100 37.5
0+400 0.3750.375 100 37.5
0+500 0.3750.375 100 37.5
0+600 0.3750.375 100 37.5
0+700 0.3750.375 100 37.5
0+800 0.3750.375 100 37.5
0+900 0.3750.375 100 37.5
1+000 0.3750.375 100 37.5
1+100 0.3750.375 100 37.5
1+200 0.3750.375 100 37.5
1+300 0.3750.375 100 37.5
1+400 0.3750.375 100 37.5
1+500 0.3750.375 100 37.5
1+600 0.3750.375 100 37.5
1+700 0.3750.375 100 37.5
1+800 0.3750.375 100 37.5
1+900 0.3750.375 100 37.5
2+000 0.3750.375 100 37.5
2+100 0.375
VOLUME (m³)
0.375 100 37.52+200 0.375
0.375 100 37.52+300 0.375
0.375 100 37.52+400 0.375
0.375 100 37.52+500 0.375
0.375 100 37.52+600 0.375
0.375 100 37.52+700 0.375
0.375 100 37.52+800 0.375
0.375 100 37.52+900 0.375
0.375 100 37.53+000 0.375
TOTAL VOLUME LAPISAN AGREGAT KELAS A KANAN (m³) 1125
TOTAL KESELURUHAN LAPISAN AGREGAT KELAS A (m³) 2250
PERHITUNGAN VOLUME PRIME COAT KIRI PERHITUNGAN VOLUME PRIME COAT KANAN
NO StaLEBAR
PANJANG (m) NOSENDIRI RATA-RATA
1 0+000 2.5 1
2.5 100 212.52 0+100 2.5 2
2.5 100 212.53 0+200 2.5 3
2.5 100 212.54 0+300 2.5 4
2.5 100 212.55 0+400 2.5 5
2.5 100 212.56 0+500 2.5 6
2.5 100 212.57 0+600 2.5 7
2.5 100 212.58 0+700 2.5 8
2.5 100 212.59 0+800 2.5 9
2.5 100 212.510 0+900 2.5 10
2.5 100 212.511 1+000 2.5 11
2.5 100 212.512 1+100 2.5 12
2.5 100 212.513 1+200 2.5 13
2.5 100 212.514 1+300 2.5 14
2.5 100 212.515 1+400 2.5 15
2.5 100 212.516 1+500 2.5 16
2.5 100 212.517 1+600 2.5 17
2.5 100 212.518 1+700 2.5 18
2.5 100 212.519 1+800 2.5 19
2.5 100 212.520 1+900 2.5 20
2.5 100 212.521 2+000 2.5 21
2.5 100 212.522 2+100 2.5 22
VOLUME (LITER)
2.5 100 212.523 2+200 2.5 23
2.5 100 212.524 2+300 2.5 24
2.5 100 212.525 2+400 2.5 25
2.5 100 212.526 2+500 2.5 26
2.5 100 212.527 2+600 2.5 27
2.5 100 212.528 2+700 2.5 28
2.5 100 212.529 2+800 2.5 29
2.5 100 212.530 2+900 2.5 30
2.5 100 212.531 3+000 2.5 31
TOTAL PRIME COAT KIRI (LITER) 6375 TOTAL PRIME COAT KANAN (LITER)
TOTAL KESELURUHAN PRIME COAT (m³)
4250 2125
PERHITUNGAN VOLUME PRIME COAT KANAN
StaLEBAR
PANJANG (m)SENDIRI RATA-RATA
0+000 2.52.5 100 212.5
0+100 2.52.5 100 212.5
0+200 2.52.5 100 212.5
0+300 2.52.5 100 212.5
0+400 2.52.5 100 212.5
0+500 2.52.5 100 212.5
0+600 2.52.5 100 212.5
0+700 2.52.5 100 212.5
0+800 2.52.5 100 212.5
0+900 2.52.5 100 212.5
1+000 2.52.5 100 212.5
1+100 2.52.5 100 212.5
1+200 2.52.5 100 212.5
1+300 2.52.5 100 212.5
1+400 2.52.5 100 212.5
1+500 2.52.5 100 212.5
1+600 2.52.5 100 212.5
1+700 2.52.5 100 212.5
1+800 2.52.5 100 212.5
1+900 2.52.5 100 212.5
2+000 2.52.5 100 212.5
2+100 2.5
VOLUME (LITER)
2.5 100 212.52+200 2.5
2.5 100 212.52+300 2.5
2.5 100 212.52+400 2.5
2.5 100 212.52+500 2.5
2.5 100 212.52+600 2.5
2.5 100 212.52+700 2.5
2.5 100 212.52+800 2.5
2.5 100 212.52+900 2.5
2.5 100 212.53+000 2.5
TOTAL PRIME COAT KANAN (LITER) 6375
TOTAL KESELURUHAN PRIME COAT (m³) 12750
PERHITUNGAN VOLUME AC-BC KIRI PERHITUNGAN VOLUME AC-BC KANAN
NO StaLUAS (m²)
PANJANG (m) NOSENDIRI RATA-RATA
1 0+000 0.125 1
0.125 100 12.52 0+100 0.125 2
0.125 100 12.53 0+200 0.125 3
0.125 100 12.54 0+300 0.125 4
0.125 100 12.55 0+400 0.125 5
0.125 100 12.56 0+500 0.125 6
0.125 100 12.57 0+600 0.125 7
0.125 100 12.58 0+700 0.125 8
0.125 100 12.59 0+800 0.125 9
0.125 100 12.510 0+900 0.125 10
0.125 100 12.511 1+000 0.125 11
0.125 100 12.512 1+100 0.125 12
0.125 100 12.513 1+200 0.125 13
0.125 100 12.514 1+300 0.125 14
0.125 100 12.515 1+400 0.125 15
0.125 100 12.516 1+500 0.125 16
0.125 100 12.517 1+600 0.125 17
0.125 100 12.518 1+700 0.125 18
0.125 100 12.519 1+800 0.125 19
0.125 100 12.520 1+900 0.125 20
0.125 100 12.521 2+000 0.125 21
0.125 100 12.522 2+100 0.125 22
VOLUME (m³)
0.125 100 12.523 2+200 0.125 23
0.125 100 12.524 2+300 0.125 24
0.125 100 12.525 2+400 0.125 25
0.125 100 12.526 2+500 0.125 26
0.125 100 12.527 2+600 0.125 27
0.125 100 12.528 2+700 0.125 28
0.125 100 12.529 2+800 0.125 29
0.125 100 12.530 2+900 0.125 30
0.125 100 12.531 3+000 0.125 31
TOTAL AC-BC KIRI (m³) 375 TOTAL AC-BC KANAN (m³)
TOTAL KESELURUHAN AC-BC (m³)
PERHITUNGAN VOLUME AC-BC KANAN
StaLUAS (m²)
PANJANG (m)SENDIRI RATA-RATA
0+000 0.1250.125 100 12.5
0+100 0.1250.125 100 12.5
0+200 0.1250.125 100 12.5
0+300 0.1250.125 100 12.5
0+400 0.1250.125 100 12.5
0+500 0.1250.125 100 12.5
0+600 0.1250.125 100 12.5
0+700 0.1250.125 100 12.5
0+800 0.1250.125 100 12.5
0+900 0.1250.125 100 12.5
1+000 0.1250.125 100 12.5
1+100 0.1250.125 100 12.5
1+200 0.1250.125 100 12.5
1+300 0.1250.125 100 12.5
1+400 0.1250.125 100 12.5
1+500 0.1250.125 100 12.5
1+600 0.1250.125 100 12.5
1+700 0.1250.125 100 12.5
1+800 0.1250.125 100 12.5
1+900 0.1250.125 100 12.5
2+000 0.1250.125 100 12.5
2+100 0.125
VOLUME (m³)
0.125 100 12.52+200 0.125
0.125 100 12.52+300 0.125
0.125 100 12.52+400 0.125
0.125 100 12.52+500 0.125
0.125 100 12.52+600 0.125
0.125 100 12.52+700 0.125
0.125 100 12.52+800 0.125
0.125 100 12.52+900 0.125
0.125 100 12.53+000 0.125
TOTAL AC-BC KANAN (m³) 375
TOTAL KESELURUHAN AC-BC (m³) 750
PERHITUNGAN VOLUME TAKE COAT KIRI PERHITUNGAN VOLUME TAKE COAT KANAN
NO StaLEBAR
PANJANG (m) NOSENDIRI RATA-RATA
1 0+000 2.5 1
2.5 100 87.52 0+100 2.5 2
2.5 100 87.53 0+200 2.5 3
2.5 100 87.54 0+300 2.5 4
2.5 100 87.55 0+400 2.5 5
2.5 100 87.56 0+500 2.5 6
2.5 100 87.57 0+600 2.5 7
2.5 100 87.58 0+700 2.5 8
2.5 100 87.59 0+800 2.5 9
2.5 100 87.510 0+900 2.5 10
2.5 100 87.511 1+000 2.5 11
2.5 100 87.512 1+100 2.5 12
2.5 100 87.513 1+200 2.5 13
2.5 100 87.514 1+300 2.5 14
2.5 100 87.515 1+400 2.5 15
2.5 100 87.516 1+500 2.5 16
2.5 100 87.517 1+600 2.5 17
2.5 100 87.518 1+700 2.5 18
2.5 100 87.519 1+800 2.5 19
2.5 100 87.520 1+900 2.5 20
2.5 100 87.521 2+000 2.5 21
2.5 100 87.522 2+100 2.5 22
VOLUME (LITER)
2.5 100 87.523 2+200 2.5 23
2.5 100 87.524 2+300 2.5 24
2.5 100 87.525 2+400 2.5 25
2.5 100 87.526 2+500 2.5 26
2.5 100 87.527 2+600 2.5 27
2.5 100 87.528 2+700 2.5 28
2.5 100 87.529 2+800 2.5 29
2.5 100 87.530 2+900 2.5 30
2.5 100 87.531 3+000 2.5 31
TOTAL TAKE COAT KIRI (LITER) 2625 TOTAL TAKE COAT KANAN (LITER)
TOTAL KESELURUHAN TAKE COAT (m³)
1890 945
PERHITUNGAN VOLUME TAKE COAT KANAN
StaLEBAR
PANJANG (m)SENDIRI RATA-RATA
0+000 2.52.5 100 87.5
0+100 2.52.5 100 87.5
0+200 2.52.5 100 87.5
0+300 2.52.5 100 87.5
0+400 2.52.5 100 87.5
0+500 2.52.5 100 87.5
0+600 2.52.5 100 87.5
0+700 2.52.5 100 87.5
0+800 2.52.5 100 87.5
0+900 2.52.5 100 87.5
1+000 2.52.5 100 87.5
1+100 2.52.5 100 87.5
1+200 2.52.5 100 87.5
1+300 2.52.5 100 87.5
1+400 2.52.5 100 87.5
1+500 2.52.5 100 87.5
1+600 2.52.5 100 87.5
1+700 2.52.5 100 87.5
1+800 2.52.5 100 87.5
1+900 2.52.5 100 87.5
2+000 2.52.5 100 87.5
2+100 2.5
VOLUME (LITER)
2.5 100 87.52+200 2.5
2.5 100 87.52+300 2.5
2.5 100 87.52+400 2.5
2.5 100 87.52+500 2.5
2.5 100 87.52+600 2.5
2.5 100 87.52+700 2.5
2.5 100 87.52+800 2.5
2.5 100 87.52+900 2.5
2.5 100 87.53+000 2.5
TOTAL TAKE COAT KANAN (LITER) 2625
TOTAL KESELURUHAN TAKE COAT (m³) 5250
PERHITUNGAN VOLUME AC-WC KIRI PERHITUNGAN VOLUME AC-WC KANAN
NO Sta LEBAR (m) PANJANG (m) LUAS (m²) NO Sta
1 0+000 2.5 100 250 1 0+000
2 0+100 2.5 100 250 2 0+100
3 0+200 2.5 100 250 3 0+200
4 0+300 2.5 100 250 4 0+300
5 0+400 2.5 100 250 5 0+400
6 0+500 2.5 100 250 6 0+500
7 0+600 2.5 100 250 7 0+600
8 0+700 2.5 100 250 8 0+700
9 0+800 2.5 100 250 9 0+800
10 0+900 2.5 100 250 10 0+900
11 1+000 2.5 100 250 11 1+000
12 1+100 2.5 100 250 12 1+100
13 1+200 2.5 100 250 13 1+200
14 1+300 2.5 100 250 14 1+300
15 1+400 2.5 100 250 15 1+400
16 1+500 2.5 100 250 16 1+500
17 1+600 2.5 100 250 17 1+600
18 1+700 2.5 100 250 18 1+700
19 1+800 2.5 100 250 19 1+800
20 1+900 2.5 100 250 20 1+900
21 2+000 2.5 100 250 21 2+000
22 2+100 2.5 100 250 22 2+100
23 2+200 2.5 100 250 23 2+200
24 2+300 2.5 100 250 24 2+300
25 2+400 2.5 100 250 25 2+400
26 2+500 2.5 100 250 26 2+500
27 2+600 2.5 100 250 27 2+600
28 2+700 2.5 100 250 28 2+700
29 2+800 2.5 100 250 29 2+800
30 2+900 2.5 100 250 30 2+900
TOTAL AC-WC KIRI (m²) 7500 TOTAL AC-WC KANAN (m²)
TOTAL KESELURUHAN AC-WC (m²)
PERHITUNGAN VOLUME AC-WC KANAN
LEBAR (m) PANJANG (m) LUAS (m²)
2.5 100 250
2.5 100 250
2.5 100 250
2.5 100 250
2.5 100 250
2.5 100 250
2.5 100 250
2.5 100 250
2.5 100 250
2.5 100 250
2.5 100 250
2.5 100 250
2.5 100 250
2.5 100 250
2.5 100 250
2.5 100 250
2.5 100 250
2.5 100 250
2.5 100 250
2.5 100 250
2.5 100 250
2.5 100 250
2.5 100 250
2.5 100 250
2.5 100 250
2.5 100 250
2.5 100 250
2.5 100 250
2.5 100 250
2.5 100 250
TOTAL AC-WC KANAN (m²) 7500
TOTAL KESELURUHAN AC-WC (m²) 15000
PERHITUNGAN VOLUME LAPISAN AGREGAT KELAS A KIRI (LPA) PERHITUNGAN VOLUME LAPISAN AGREGAT KELAS A KANAN (LPA)
NO StaLUAS (m²)
PANJANG (m) NOSENDIRI RATA-RATA
1 0+000 0.48 1
0.48 100 482 0+100 0.48 2
0.48 100 483 0+200 0.48 3
0.48 100 484 0+300 0.48 4
0.48 100 485 0+400 0.48 5
0.48 100 486 0+500 0.48 6
0.48 100 487 0+600 0.48 7
0.48 100 488 0+700 0.48 8
0.48 100 489 0+800 0.48 9
0.48 100 4810 0+900 0.48 10
0.48 100 4811 1+000 0.48 11
0.48 100 4812 1+100 0.48 12
0.48 100 4813 1+200 0.48 13
0.48 100 4814 1+300 0.48 14
0.48 100 4815 1+400 0.48 15
0.48 100 4816 1+500 0.48 16
0.48 100 4817 1+600 0.48 17
0.48 100 4818 1+700 0.48 18
0.48 100 4819 1+800 0.48 19
0.48 100 4820 1+900 0.48 20
0.48 100 4821 2+000 0.48 21
0.48 100 4822 2+100 0.48 22
VOLUME (m³)
0.48 100 4823 2+200 0.48 23
0.48 100 4824 2+300 0.48 24
0.48 100 4825 2+400 0.48 25
0.48 100 4826 2+500 0.48 26
0.48 100 4827 2+600 0.48 27
0.48 100 4828 2+700 0.48 28
0.48 100 4829 2+800 0.48 29
0.48 100 4830 2+900 0.48 30
0.48 100 4831 3+000 0.48 31
TOTAL VOLUME LAPISAN AGREGAT KELAS A KIRI (m³) 1440 TOTAL VOLUME LAPISAN AGREGAT KELAS A KANAN (m³)
TOTAL KESELURUHAN LAPISAN AGREGAT KELAS A (m³)
0.375
PERHITUNGAN VOLUME LAPISAN AGREGAT KELAS A KANAN (LPA)
StaLUAS (m²)
PANJANG (m)SENDIRI RATA-RATA
0+000 0.480.48 100 48
0+100 0.480.48 100 48
0+200 0.480.48 100 48
0+300 0.480.48 100 48
0+400 0.480.48 100 48
0+500 0.480.48 100 48
0+600 0.480.48 100 48
0+700 0.480.48 100 48
0+800 0.480.48 100 48
0+900 0.480.48 100 48
1+000 0.480.48 100 48
1+100 0.480.48 100 48
1+200 0.480.48 100 48
1+300 0.480.48 100 48
1+400 0.480.48 100 48
1+500 0.480.48 100 48
1+600 0.480.48 100 48
1+700 0.480.48 100 48
1+800 0.480.48 100 48
1+900 0.480.48 100 48
2+000 0.480.48 100 48
2+100 0.48
VOLUME (m³)
0.48 100 482+200 0.48
0.48 100 482+300 0.48
0.48 100 482+400 0.48
0.48 100 482+500 0.48
0.48 100 482+600 0.48
0.48 100 482+700 0.48
0.48 100 482+800 0.48
0.48 100 482+900 0.48
0.48 100 483+000 0.48
TOTAL VOLUME LAPISAN AGREGAT KELAS A KANAN (m³) 1440
TOTAL KESELURUHAN LAPISAN AGREGAT KELAS A (m³) 2880
PETA LOKASI QUARRY
2 km
3 km AMP
1kmkm 108
km 107
3,5 km
km 106
km 105
LOKASI PEKERJAAN
TEMPAT PEMBUANGAN
MATERIAL
BASE CAMP
TEMPAT MATERIAL
Jarak Lokasi Pekerjaan ke Basecamp = 4,5 kmJarak Lokasi Pekerjaan ke tempat pembuangan material = 5 kmJarak Lokasi Pekerjaan ke tempat material = 4,5 km
HARGA SATUAN DASAR - UPAH
NO. PAKET KONTRAK :
NAMA PAKET : SANGATTA
No. Tenaga KerjaSatuan Biaya Satuan
Ket.Upah ( Rp )
1 Mandor jam 14,285.71
2 Pekerja jam 7,142.86
3 Tukang jam 11,428.57
4 Operator jam 10,000.00
5 Pembantu Operator jam 7,142.86
6 Sopir jam 11,428.57
7 Pembantu Sopir jam 7,142.86
8 Mekanik jam 12,857.14
9 Pembantu Mekanik jam 7,142.86
HARGA SATUAN DASAR - BAHAN
NOMOR PAKET KONTRAK :
NAMA PAKET : SANGATTA
No. Jenis BahanSatuan Harga Satuan
Ket.Volume ( Rp )
1 Agregat Halus Untuk ATB/AC 245,000.00
2 Agregat Kasar Untuk ATB/AC 245,000.00
3 Agregat Halus Untuk Pondasi 215,000.00
4 Agregat Kasar Untuk Pondasi 215,000.00
5 Agregat Kasar Untuk Beton 195,000.00
6 Agregat Kelas A 212,409.19
7 Agregat Kelas B 184,892.79
8 Agregat Kelas C1 -
9 Aspal Curah kg 16,000.00
10 Aspal Emulsi kg -
11 Batu Pecah 170,000.00
12 Batu Kali / Gunung 175,000.00
13 Bensin ltr 8,500.00
14 Filler kg 1,500.00
15 Kerosin ( Minyak Tanah ) ltr 10,000.00
16 Minyak Pelumas / Oli ltr 25,000.00
17 Pasir Biasa / Urug 100,000.00
18 Pasir Pasang 145,000.00 Base Camp
19 Plastik Filter -
20 Semen kg 1,000.00
21 Sirtu 133,125.00
22 Solar ltr 8,500.00
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m2
m3
1000005000080000700005000080000500009000050000
50000
HARGA SATUAN DASAR - PERALATAN
NOMOR PAKET KONTRAK :
NAMA PAKET : SANGATTA
Pemilikan & Operasional
No. Jenis PeralatanHarga Dasar Biaya per
KetPemilikan Satuan Satuan
(Rp)
1 Asphalt Finisher UNIPAVE ESP-05 980,000,000 Jam 249,958.71
2 Asphalt Mixing Plant TANAKA 800 1,600,000,000 Jam 1,174,688.15
3 Asphalt Sprayer ASP-1000 55,000,000 Jam 110,779.87
4 Bulldozer Komatsu D85Ess-2 950,000,000 Jam 347,785.03
5 Compressor 4000 - 5000 liter/menit 160,000,000 Jam 99,405.07
6 Concrete Mixer JZR350 36,260,000 Jam 51,047.16
7 221,000,000 Jam 110,763.52
9 Excavator Komatsu PC200-7 635,000,000 Jam 249,366.67
11 Generator Set OEM 97,804,000 Jam 130,654.80
12 Motor Grader Komatsu GD-GD510-1 810,000,000 Jam 315,261.92
13 Pneumatic Tire Roller HYC208P 588,000,000 Jam 170,428.80
14 Pompa Air 70 - 100 mm 13,500,000 Jam
15 Tandem Roller LUTONG LTC212 597,800,000 Jam 186,759.24
16 Water Tank Truck Isuzu 5000 L 176,000,000 Jam 111,450.93
17 Vibratory Roller XCMG XD121 784,000,000 Jam 211,450.01
18 Wheel Loader Komatsu WA350 3 m3 600,000,000 Jam 250,481.99
19
…………………. , …………………….. 200….
………………………..
Dump truck Hino Dutro 3 - 4 m3
URAIAN ANALISA ALAT
NO. PAKET KONTRAK :
NAMA PAKET : SANGATTA
NAMA ALAT : ASPHALT MIXING PLANT TANAKA 800
NO. U R A I A N KODE KOEF. SATUAN KET.
A URAIAN PERALATAN
1. Jenis Peralatan ASPHALT MIXING PLANT TANAKA 800
2. Tenaga Pw 150.00 HP
3. Kapasitas Cp 50.00 Ton/Jam
4. Alat Baru : a. Umur Ekonomis A 10.00 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,500.00 Jam
c. Harga Alat B 1,600,000,000.00 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 4.00 Tahun Alat Bekas
b. Jam Kerja Dalam 1 Tahun W' 1,500.00 Jam Alat Bekas
c. Harga Alat (*) B' 1,600,000,000.00 Rupiah Alat Bekas
B BIAYA PASTI PER JAM
1. Nilai Sisa Alat = 10 % x B' C 160,000,000.00 Rupiah
2. D 0.38629 -
3. Biaya Pasti Per Jam :
a. Biaya Pengembalian Modal = {( B'-C ) x D} / W' E 370,837.56 Rupiah
b. Asuransi, dll = ( 0,002 x B' ) / W' F 2,133.33 Rupiah
4. Biaya Pasti Per Jam = ( E + F ) G 372,970.89 Rupiah
C BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (0,125-0,175 Ltr/HP/Jam) x Pw x Ms 25,312.50 Rupiah
Bahan Bakar Pemanasan Material = 12x0,7CpxMs 567,000.00 Rupiah Khusus AMP
2. Pelumas = ( 0,01 - 0,02 Ltr/HP/Jam ) x Pw x Mp I 37,500.00 Rupiah
3. Perawatan dan = {(12,5% - 17,5%)xB'} / W' K 133,333.33 Rupiah
Perbaikan
4. OperatorL
10,000.00 Rupiah
5. Sopir 11,428.57 Rupiah
6.M
28,571.43 Rupiah
7. Pembantu Sopir 7,142.86 Rupiah
8. Biaya Operasi / Jam = ( H + I + K + L + M ) P 801,717.26 Rupiah
D TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 1,174,688.15 Rupiah
E LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 %/Tahun
2. Upah Operator 10,000.00 Rp./Jam
3. Upah Sopir 11,428.57 Rp./Jam
4. Upah Pembantu Operator 7,142.86 Rp./Jam
5. Upah Pembantu Sopir 7,142.86 Rp./Jam
6. Bahan Bakar Bensin Mb 8,500.00 Rp./Liter
7. Bahan Bakar Solar Ms 1,350.00 Rp./Liter
8. Minyak Pelumas Mp 25,000.00 Rp./Liter
9. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
Faktor Angsuran Modal = i x (1+i)A' / (1+i)A-1
H1
H2
= ( 1 Orang / Jam ) x U1
= ( 1 Orang / Jam ) x U2
Pembantu Operator = ( 4 Orang / Jam ) x U3
= ( 1 Orang / Jam ) x U4
U1
U2
U3
U4
URAIAN ANALISA ALAT
NO. PAKET KONTRAK :
NAMA PAKET : SANGATTA
NAMA ALAT : Asphalt Finisher UNIPAVE ESP-05
NO. U R A I A N KODE KOEF. SATUAN KET.
A URAIAN PERALATAN
1. Jenis Peralatan Asphalt Finisher UNIPAVE ESP-05
2. Tenaga Pw 105.00 HP
3. Kapasitas Cp 50.00 Ton/Jam
4. Alat Baru : a. Umur Ekonomis A 10.00 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 980,000,000.00 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 10.00 Tahun Alat Baru
b. Jam Kerja Dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat (*) B' 980,000,000.00 Rupiah Alat Baru
B BIAYA PASTI PER JAM
1. Nilai Sisa Alat = 10 % x B' C 98,000,000.00 Rupiah
2. D 0.23852 -
3. Biaya Pasti Per Jam :
a. Biaya Pengembalian Modal = {( B'-C ) x D} / W' E 105,188.54 Rupiah
b. Asuransi, dll = ( 0,002 x B' ) / W' F 980.00 Rupiah
4. Biaya Pasti Per Jam = ( E + F ) G 106,168.54 Rupiah
C BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (0,125-0,175 Ltr/HP/Jam) x Pw x Ms 17,718.75 Rupiah
2. Pelumas = ( 0,01 - 0,02 Ltr/HP/Jam ) x Pw x Mp I 26,250.00 Rupiah
3. Perawatan dan = {(12,5% - 17,5%)xB'} / W' K 61,250.00 Rupiah
Perbaikan
4. OperatorL
10,000.00 Rupiah
5. Sopir 11,428.57 Rupiah
6.M
28,571.43 Rupiah
7. Pembantu Sopir 7,142.86 Rupiah
8. Biaya Operasi / Jam = ( H + I + K + L + M ) P 143,790.18 Rupiah
D TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 249,958.71 Rupiah
E LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 %/Tahun
2. Upah Operator 10,000.00 Rp./Jam
3. Upah Sopir 11,428.57 Rp./Jam
4. Upah Pembantu Operator 7,142.86 Rp./Jam
5. Upah Pembantu Sopir 7,142.86 Rp./Jam
6. Bahan Bakar Bensin Mb 8,500.00 Rp./Liter
7. Bahan Bakar Solar Ms 1,350.00 Rp./Liter
8. Minyak Pelumas Mp 25,000.00 Rp./Liter
9. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
Faktor Angsuran Modal = i x (1+i)A' / (1+i)A-1
H1
= ( 1 Orang / Jam ) x U1
= ( 1 Orang / Jam ) x U2
Pembantu Operator = ( 4 Orang / Jam ) x U3
= ( 1 Orang / Jam ) x U4
U1
U2
U3
U4
URAIAN ANALISA ALAT
NO. PAKET KONTRAK :
NAMA PAKET : SANGATTA
NAMA ALAT : Asphalt Sprayer ASP-1000
NO. U R A I A N KODE KOEF. SATUAN KET.
A URAIAN PERALATAN
1. Jenis Peralatan Asphalt Sprayer ASP-1000
2. Tenaga Pw 150.00 HP
3. Kapasitas Cp 50.00 Ton/Jam
4. Alat Baru : a. Umur Ekonomis A 10.00 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 55,000,000.00 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 10.00 Tahun Alat Baru
b. Jam Kerja Dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat (*) B' 55,000,000.00 Rupiah Alat Baru
B BIAYA PASTI PER JAM
1. Nilai Sisa Alat = 10 % x B' C 5,500,000.00 Rupiah
2. D 0.23852 -
3. Biaya Pasti Per Jam :
a. Biaya Pengembalian Modal = {( B'-C ) x D} / W' E 5,903.44 Rupiah
b. Asuransi, dll = ( 0,002 x B' ) / W' F 55.00 Rupiah
4. Biaya Pasti Per Jam = ( E + F ) G 5,958.44 Rupiah
C BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (0,125-0,175 Ltr/HP/Jam) x Pw x Ms 25,312.50 Rupiah
2. Pelumas = ( 0,01 - 0,02 Ltr/HP/Jam ) x Pw x Mp I 37,500.00 Rupiah
3. Perawatan dan = {(12,5% - 17,5%)xB'} / W' K 3,437.50 Rupiah
Perbaikan
4. OperatorL
10,000.00 Rupiah
5. Sopir 11,428.57 Rupiah
6.M
28,571.43 Rupiah
7. Pembantu Sopir 7,142.86 Rupiah
8. Biaya Operasi / Jam = ( H + I + K + L + M ) P 104,821.43 Rupiah
D TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 110,779.87 Rupiah
E LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 %/Tahun
2. Upah Operator 10,000.00 Rp./Jam
3. Upah Sopir 11,428.57 Rp./Jam
4. Upah Pembantu Operator 7,142.86 Rp./Jam
5. Upah Pembantu Sopir 7,142.86 Rp./Jam
6. Bahan Bakar Bensin Mb 8,500.00 Rp./Liter
7. Bahan Bakar Solar Ms 1,350.00 Rp./Liter
8. Minyak Pelumas Mp 25,000.00 Rp./Liter
9. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
Faktor Angsuran Modal = i x (1+i)A' / (1+i)A-1
H1
= ( 1 Orang / Jam ) x U1
= ( 1 Orang / Jam ) x U2
Pembantu Operator = ( 4 Orang / Jam ) x U3
= ( 1 Orang / Jam ) x U4
U1
U2
U3
U4
URAIAN ANALISA ALAT
NO. PAKET KONTRAK :
NAMA PAKET : SANGATTA
NAMA ALAT : Bulldozer Komatsu D85Ess-2
NO. U R A I A N KODE KOEF. SATUAN KET.
A URAIAN PERALATAN
1. Jenis Peralatan Bulldozer Komatsu D85Ess-2
2. Tenaga Pw 200.00 HP
3. Kapasitas Cp 4.40 m3
4. Alat Baru : a. Umur Ekonomis A 10.00 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 950,000,000.00 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 4.00 Tahun Alat Bekas
b. Jam Kerja Dalam 1 Tahun W' 2,000.00 Jam Alat Bekas
c. Harga Alat (*) B' 950,000,000.00 Rupiah Alat Bekas
B BIAYA PASTI PER JAM
1. Nilai Sisa Alat = 10 % x B' C 95,000,000.00 Rupiah
2. D 0.38629 -
3. Biaya Pasti Per Jam :
a. Biaya Pengembalian Modal = {( B'-C ) x D} / W' E 165,138.60 Rupiah
b. Asuransi, dll = ( 0,002 x B' ) / W' F 950.00 Rupiah
4. Biaya Pasti Per Jam = ( E + F ) G 166,088.60 Rupiah
C BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (0,125-0,175 Ltr/HP/Jam) x Pw x Ms 33,750.00 Rupiah
2. Pelumas = ( 0,01 - 0,02 Ltr/HP/Jam ) x Pw x Mp I 50,000.00 Rupiah
3. Perawatan dan = {(12,5% - 17,5%)xB'} / W' K 59,375.00 Rupiah
Perbaikan
4. OperatorL
10,000.00 Rupiah
5. Sopir 11,428.57 Rupiah
6.M
28,571.43 Rupiah
7. Pembantu Sopir 7,142.86 Rupiah
8. Biaya Operasi / Jam = ( H + I + K + L + M ) P 181,696.43 Rupiah
D TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 347,785.03 Rupiah
E LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 %/Tahun
2. Upah Operator 10,000.00 Rp./Jam
3. Upah Sopir 11,428.57 Rp./Jam
4. Upah Pembantu Operator 7,142.86 Rp./Jam
5. Upah Pembantu Sopir 7,142.86 Rp./Jam
6. Bahan Bakar Bensin Mb 8,500.00 Rp./Liter
7. Bahan Bakar Solar Ms 1,350.00 Rp./Liter
8. Minyak Pelumas Mp 25,000.00 Rp./Liter
9. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
Faktor Angsuran Modal = i x (1+i)A' / (1+i)A-1
H1
= ( 1 Orang / Jam ) x U1
= ( 1 Orang / Jam ) x U2
Pembantu Operator = ( 4 Orang / Jam ) x U3
= ( 1 Orang / Jam ) x U4
U1
U2
U3
U4
URAIAN ANALISA ALAT
NO. PAKET KONTRAK :
NAMA PAKET : SANGATTA
NAMA ALAT : COMPRESSOR
NO. U R A I A N KODE KOEF. SATUAN KET.
A URAIAN PERALATAN
1. Jenis Peralatan COMPRESSOR
2. Tenaga Pw 80.00 HP
3. Kapasitas Cp 50.00 Ton/Jam
4. Alat Baru : a. Umur Ekonomis A 10.00 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 160,000,000.00 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 10.00 Tahun Alat Baru
b. Jam Kerja Dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat (*) B' 160,000,000.00 Rupiah Alat Baru
B BIAYA PASTI PER JAM
1. Nilai Sisa Alat = 10 % x B' C 16,000,000.00 Rupiah
2. D 0.23852 -
3. Biaya Pasti Per Jam :
a. Biaya Pengembalian Modal = {( B'-C ) x D} / W' E 17,173.64 Rupiah
b. Asuransi, dll = ( 0,002 x B' ) / W' F 160.00 Rupiah
4. Biaya Pasti Per Jam = ( E + F ) G 17,333.64 Rupiah
C BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (0,125-0,175 Ltr/HP/Jam) x Pw x Ms 13,500.00 Rupiah
2. Pelumas = ( 0,01 - 0,02 Ltr/HP/Jam ) x Pw x Mp I 20,000.00 Rupiah
3. Perawatan dan = {(12,5% - 17,5%)xB'} / W' K 10,000.00 Rupiah
Perbaikan
4. OperatorL
10,000.00 Rupiah
5. Sopir 11,428.57 Rupiah
6.M
28,571.43 Rupiah
7. Pembantu Sopir 7,142.86 Rupiah
8. Biaya Operasi / Jam = ( H + I + K + L + M ) P 82,071.43 Rupiah
D TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 99,405.07 Rupiah
E LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 %/Tahun
2. Upah Operator 10,000.00 Rp./Jam
3. Upah Sopir 11,428.57 Rp./Jam
4. Upah Pembantu Operator 7,142.86 Rp./Jam
5. Upah Pembantu Sopir 7,142.86 Rp./Jam
6. Bahan Bakar Bensin Mb 8,500.00 Rp./Liter
7. Bahan Bakar Solar Ms 1,350.00 Rp./Liter
8. Minyak Pelumas Mp 25,000.00 Rp./Liter
9. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
Faktor Angsuran Modal = i x (1+i)A' / (1+i)A-1
H1
= ( 1 Orang / Jam ) x U1
= ( 1 Orang / Jam ) x U2
Pembantu Operator = ( 4 Orang / Jam ) x U3
= ( 1 Orang / Jam ) x U4
U1
U2
U3
U4
URAIAN ANALISA ALAT
NO. PAKET KONTRAK :
NAMA PAKET : SANGATTA
NAMA ALAT : Concrete Mixer JZR350
NO. U R A I A N KODE KOEF. SATUAN KET.
A URAIAN PERALATAN
1. Jenis Peralatan Concrete Mixer JZR350
2. Tenaga Pw 15.00 HP
3. Kapasitas Cp 50.00 Ton/Jam
4. Alat Baru : a. Umur Ekonomis A 10.00 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 36,260,000.00 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 10.00 Tahun Alat Baru
b. Jam Kerja Dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat (*) B' 36,260,000.00 Rupiah Alat Baru
B BIAYA PASTI PER JAM
1. Nilai Sisa Alat = 10 % x B' C 3,626,000.00 Rupiah
2. D 0.23852 -
3. Biaya Pasti Per Jam :
a. Biaya Pengembalian Modal = {( B'-C ) x D} / W' E 3,891.98 Rupiah
b. Asuransi, dll = ( 0,002 x B' ) / W' F 36.26 Rupiah
4. Biaya Pasti Per Jam = ( E + F ) G 3,928.24 Rupiah
C BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (0,125-0,175 Ltr/HP/Jam) x Pw x Ms 2,531.25 Rupiah
2. Pelumas = ( 0,01 - 0,02 Ltr/HP/Jam ) x Pw x Mp I 3,750.00 Rupiah
3. Perawatan dan = {(12,5% - 17,5%)xB'} / W' K 2,266.25 Rupiah
Perbaikan
4. OperatorL
10,000.00 Rupiah
5. Sopir 11,428.57 Rupiah
6.M
28,571.43 Rupiah
7. Pembantu Sopir 7,142.86 Rupiah
8. Biaya Operasi / Jam = ( H + I + K + L + M ) P 47,118.93 Rupiah
D TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 51,047.16 Rupiah
E LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 %/Tahun
2. Upah Operator 10,000.00 Rp./Jam
3. Upah Sopir 11,428.57 Rp./Jam
4. Upah Pembantu Operator 7,142.86 Rp./Jam
5. Upah Pembantu Sopir 7,142.86 Rp./Jam
6. Bahan Bakar Bensin Mb 8,500.00 Rp./Liter
7. Bahan Bakar Solar Ms 1,350.00 Rp./Liter
8. Minyak Pelumas Mp 25,000.00 Rp./Liter
9. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
Faktor Angsuran Modal = i x (1+i)A' / (1+i)A-1
H1
= ( 1 Orang / Jam ) x U1
= ( 1 Orang / Jam ) x U2
Pembantu Operator = ( 4 Orang / Jam ) x U3
= ( 1 Orang / Jam ) x U4
U1
U2
U3
U4
URAIAN ANALISA ALAT
NO. PAKET KONTRAK :
NAMA PAKET : SANGATTA
NAMA ALAT : Dump truck Hino Dutro 3 - 4 m3
NO. U R A I A N KODE KOEF. SATUAN KET.
A URAIAN PERALATAN
1. Jenis Peralatan Dump truck Hino Dutro 3 - 4 m3
2. Tenaga Pw 130.00 HP
3. Kapasitas Cp 4.00 m3
4. Alat Baru : a. Umur Ekonomis A 10.00 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 221,000,000.00 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 10.00 Tahun Alat Baru
b. Jam Kerja Dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat (*) B' 221,000,000.00 Rupiah Alat Baru
B BIAYA PASTI PER JAM
1. Nilai Sisa Alat = 10 % x B' C 22,100,000.00 Rupiah
2. D 0.23852 -
3. Biaya Pasti Per Jam :
a. Biaya Pengembalian Modal = {( B'-C ) x D} / W' E 23,721.09 Rupiah
b. Asuransi, dll = ( 0,002 x B' ) / W' F 221.00 Rupiah
4. Biaya Pasti Per Jam = ( E + F ) G 23,942.09 Rupiah
C BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (0,125-0,175 Ltr/HP/Jam) x Pw x Ms 21,937.50 Rupiah
2. Pelumas = ( 0,01 - 0,02 Ltr/HP/Jam ) x Pw x Mp I 32,500.00 Rupiah
3. Perawatan dan = {(12,5% - 17,5%)xB'} / W' K 13,812.50 Rupiah
Perbaikan
4. OperatorL
10,000.00 Rupiah
5. Sopir 11,428.57 Rupiah
6.M
28,571.43 Rupiah
7. Pembantu Sopir 7,142.86 Rupiah
8. Biaya Operasi / Jam = ( H + I + K + L + M ) P 86,821.43 Rupiah
D TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 110,763.52 Rupiah
E LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 %/Tahun
2. Upah Operator 10,000.00 Rp./Jam
3. Upah Sopir 11,428.57 Rp./Jam
4. Upah Pembantu Operator 7,142.86 Rp./Jam
5. Upah Pembantu Sopir 7,142.86 Rp./Jam
6. Bahan Bakar Bensin Mb 8,500.00 Rp./Liter
7. Bahan Bakar Solar Ms 1,350.00 Rp./Liter
8. Minyak Pelumas Mp 25,000.00 Rp./Liter
9. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
Faktor Angsuran Modal = i x (1+i)A' / (1+i)A-1
H1
= ( 1 Orang / Jam ) x U1
= ( 1 Orang / Jam ) x U2
Pembantu Operator = ( 4 Orang / Jam ) x U3
= ( 1 Orang / Jam ) x U4
U1
U2
U3
U4
URAIAN ANALISA ALAT
NO. PAKET KONTRAK :
NAMA PAKET : SANGATTA
NAMA ALAT : Excavator Komatsu PC200-7
NO. U R A I A N KODE KOEF. SATUAN KET.
A URAIAN PERALATAN
1. Jenis Peralatan Excavator Komatsu PC200-7
2. Tenaga Pw 143.50 HP
3. Kapasitas Cp 50.00 Ton/Jam
4. Alat Baru : a. Umur Ekonomis A 10.00 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 635,000,000.00 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 4.00 Tahun Alat Bekas
b. Jam Kerja Dalam 1 Tahun W' 2,000.00 Jam Alat Bekas
c. Harga Alat (*) B' 635,000,000.00 Rupiah Alat Bekas
B BIAYA PASTI PER JAM
1. Nilai Sisa Alat = 10 % x B' C 63,500,000.00 Rupiah
2. D 0.38629 -
3. Biaya Pasti Per Jam :
a. Biaya Pengembalian Modal = {( B'-C ) x D} / W' E 110,382.12 Rupiah
b. Asuransi, dll = ( 0,002 x B' ) / W' F 635.00 Rupiah
4. Biaya Pasti Per Jam = ( E + F ) G 111,017.12 Rupiah
C BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (0,125-0,175 Ltr/HP/Jam) x Pw x Ms 24,215.63 Rupiah
2. Pelumas = ( 0,01 - 0,02 Ltr/HP/Jam ) x Pw x Mp I 35,875.00 Rupiah
3. Perawatan dan = {(12,5% - 17,5%)xB'} / W' K 39,687.50 Rupiah
Perbaikan
4. OperatorL
10,000.00 Rupiah
5. Sopir 11,428.57 Rupiah
6.M
28,571.43 Rupiah
7. Pembantu Sopir 7,142.86 Rupiah
8. Biaya Operasi / Jam = ( H + I + K + L + M ) P 138,349.55 Rupiah
D TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 249,366.67 Rupiah
E LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 %/Tahun
2. Upah Operator 10,000.00 Rp./Jam
3. Upah Sopir 11,428.57 Rp./Jam
4. Upah Pembantu Operator 7,142.86 Rp./Jam
5. Upah Pembantu Sopir 7,142.86 Rp./Jam
6. Bahan Bakar Bensin Mb 8,500.00 Rp./Liter
7. Bahan Bakar Solar Ms 1,350.00 Rp./Liter
8. Minyak Pelumas Mp 25,000.00 Rp./Liter
9. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
Faktor Angsuran Modal = i x (1+i)A' / (1+i)A-1
H1
= ( 1 Orang / Jam ) x U1
= ( 1 Orang / Jam ) x U2
Pembantu Operator = ( 4 Orang / Jam ) x U3
= ( 1 Orang / Jam ) x U4
U1
U2
U3
U4
URAIAN ANALISA ALAT
NO. PAKET KONTRAK :
NAMA PAKET : SANGATTA
NAMA ALAT : Generator Set OEM
NO. U R A I A N KODE KOEF. SATUAN KET.
A URAIAN PERALATAN
1. Jenis Peralatan Generator Set OEM
2. Tenaga Pw 180.00 HP
3. Kapasitas Cp 50.00 Ton/Jam
4. Alat Baru : a. Umur Ekonomis A 10.00 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 97,804,000.00 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 10.00 Tahun Alat Baru
b. Jam Kerja Dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat (*) B' 97,804,000.00 Rupiah Alat Baru
B BIAYA PASTI PER JAM
1. Nilai Sisa Alat = 10 % x B' C 9,780,400.00 Rupiah
2. D 0.23852 -
3. Biaya Pasti Per Jam :
a. Biaya Pengembalian Modal = {( B'-C ) x D} / W' E 10,497.82 Rupiah
b. Asuransi, dll = ( 0,002 x B' ) / W' F 97.80 Rupiah
4. Biaya Pasti Per Jam = ( E + F ) G 10,595.62 Rupiah
C BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (0,125-0,175 Ltr/HP/Jam) x Pw x Ms 30,375.00 Rupiah
2. Pelumas = ( 0,01 - 0,02 Ltr/HP/Jam ) x Pw x Mp I 45,000.00 Rupiah
3. Perawatan dan = {(12,5% - 17,5%)xB'} / W' K 6,112.75 Rupiah
Perbaikan
4. OperatorL
10,000.00 Rupiah
5. Sopir 11,428.57 Rupiah
6.M
28,571.43 Rupiah
7. Pembantu Sopir 7,142.86 Rupiah
8. Biaya Operasi / Jam = ( H + I + K + L + M ) P 120,059.18 Rupiah
D TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 130,654.80 Rupiah
E LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 %/Tahun
2. Upah Operator 10,000.00 Rp./Jam
3. Upah Sopir 11,428.57 Rp./Jam
4. Upah Pembantu Operator 7,142.86 Rp./Jam
5. Upah Pembantu Sopir 7,142.86 Rp./Jam
6. Bahan Bakar Bensin Mb 8,500.00 Rp./Liter
7. Bahan Bakar Solar Ms 1,350.00 Rp./Liter
8. Minyak Pelumas Mp 25,000.00 Rp./Liter
9. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
Faktor Angsuran Modal = i x (1+i)A' / (1+i)A-1
H1
= ( 1 Orang / Jam ) x U1
= ( 1 Orang / Jam ) x U2
Pembantu Operator = ( 4 Orang / Jam ) x U3
= ( 1 Orang / Jam ) x U4
U1
U2
U3
U4
URAIAN ANALISA ALAT
NO. PAKET KONTRAK :
NAMA PAKET : SANGATTA
NAMA ALAT : Motor Grader Komatsu GD-GD510-1
NO. U R A I A N KODE KOEF. SATUAN KET.
A URAIAN PERALATAN
1. Jenis Peralatan Motor Grader Komatsu GD-GD510-1
2. Tenaga Pw 124.70 HP
3. Kapasitas Cp 50.00 Ton/Jam
4. Alat Baru : a. Umur Ekonomis A 10.00 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 810,000,000.00 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 3.00 Tahun Alat Bekas
b. Jam Kerja Dalam 1 Tahun W' 2,000.00 Jam Alat Bekas
c. Harga Alat (*) B' 810,000,000.00 Rupiah Alat Bekas
B BIAYA PASTI PER JAM
1. Nilai Sisa Alat = 10 % x B' C 81,000,000.00 Rupiah
2. D 0.47473 -
3. Biaya Pasti Per Jam :
a. Biaya Pengembalian Modal = {( B'-C ) x D} / W' E 173,037.36 Rupiah
b. Asuransi, dll = ( 0,002 x B' ) / W' F 810.00 Rupiah
4. Biaya Pasti Per Jam = ( E + F ) G 173,847.36 Rupiah
C BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (0,125-0,175 Ltr/HP/Jam) x Pw x Ms 21,043.13 Rupiah
2. Pelumas = ( 0,01 - 0,02 Ltr/HP/Jam ) x Pw x Mp I 31,175.00 Rupiah
3. Perawatan dan = {(12,5% - 17,5%)xB'} / W' K 50,625.00 Rupiah
Perbaikan
4. OperatorL
10,000.00 Rupiah
5. Sopir 11,428.57 Rupiah
6.M
28,571.43 Rupiah
7. Pembantu Sopir 7,142.86 Rupiah
8. Biaya Operasi / Jam = ( H + I + K + L + M ) P 141,414.55 Rupiah
D TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 315,261.92 Rupiah
E LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 %/Tahun
2. Upah Operator 10,000.00 Rp./Jam
3. Upah Sopir 11,428.57 Rp./Jam
4. Upah Pembantu Operator 7,142.86 Rp./Jam
5. Upah Pembantu Sopir 7,142.86 Rp./Jam
6. Bahan Bakar Bensin Mb 8,500.00 Rp./Liter
7. Bahan Bakar Solar Ms 1,350.00 Rp./Liter
8. Minyak Pelumas Mp 25,000.00 Rp./Liter
9. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
Faktor Angsuran Modal = i x (1+i)A' / (1+i)A-1
H1
= ( 1 Orang / Jam ) x U1
= ( 1 Orang / Jam ) x U2
Pembantu Operator = ( 4 Orang / Jam ) x U3
= ( 1 Orang / Jam ) x U4
U1
U2
U3
U4
URAIAN ANALISA ALAT
NO. PAKET KONTRAK :
NAMA PAKET : SANGATTA
NAMA ALAT : Pneumatic Tire Roller HYC208P
NO. U R A I A N KODE KOEF. SATUAN KET.
A URAIAN PERALATAN
1. Jenis Peralatan Pneumatic Tire Roller HYC208P
2. Tenaga Pw 75.00 HP
3. Kapasitas Cp 50.00 Ton/Jam
4. Alat Baru : a. Umur Ekonomis A 10.00 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 588,000,000.00 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 10.00 Tahun Alat Baru
b. Jam Kerja Dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat (*) B' 588,000,000.00 Rupiah Alat Bekas
B BIAYA PASTI PER JAM
1. Nilai Sisa Alat = 10 % x B' C 58,800,000.00 Rupiah
2. D 0.23852 -
3. Biaya Pasti Per Jam :
a. Biaya Pengembalian Modal = {( B'-C ) x D} / W' E 63,113.12 Rupiah
b. Asuransi, dll = ( 0,002 x B' ) / W' F 588.00 Rupiah
4. Biaya Pasti Per Jam = ( E + F ) G 63,701.12 Rupiah
C BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (0,125-0,175 Ltr/HP/Jam) x Pw x Ms 12,656.25 Rupiah
2. Pelumas = ( 0,01 - 0,02 Ltr/HP/Jam ) x Pw x Mp I 18,750.00 Rupiah
3. Perawatan dan = {(12,5% - 17,5%)xB'} / W' K 36,750.00 Rupiah
Perbaikan
4. OperatorL
10,000.00 Rupiah
5. Sopir 11,428.57 Rupiah
6.M
28,571.43 Rupiah
7. Pembantu Sopir 7,142.86 Rupiah
8. Biaya Operasi / Jam = ( H + I + K + L + M ) P 106,727.68 Rupiah
D TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 170,428.80 Rupiah
E LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 %/Tahun
2. Upah Operator 10,000.00 Rp./Jam
3. Upah Sopir 11,428.57 Rp./Jam
4. Upah Pembantu Operator 7,142.86 Rp./Jam
5. Upah Pembantu Sopir 7,142.86 Rp./Jam
6. Bahan Bakar Bensin Mb 8,500.00 Rp./Liter
7. Bahan Bakar Solar Ms 1,350.00 Rp./Liter
8. Minyak Pelumas Mp 25,000.00 Rp./Liter
9. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
Faktor Angsuran Modal = i x (1+i)A' / (1+i)A-1
H1
= ( 1 Orang / Jam ) x U1
= ( 1 Orang / Jam ) x U2
Pembantu Operator = ( 4 Orang / Jam ) x U3
= ( 1 Orang / Jam ) x U4
U1
U2
U3
U4
URAIAN ANALISA ALAT
NO. PAKET KONTRAK :
NAMA PAKET : SANGATTA
NAMA ALAT : Tandem Roller LUTONG LTC212
NO. U R A I A N KODE KOEF. SATUAN KET.
A URAIAN PERALATAN
1. Jenis Peralatan Tandem Roller LUTONG LTC212
2. Tenaga Pw 110.00 HP
3. Kapasitas Cp 50.00 Ton/Jam
4. Alat Baru : a. Umur Ekonomis A 10.00 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 597,800,000.00 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 10.00 Tahun Alat Baru
b. Jam Kerja Dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat (*) B' 597,800,000.00 Rupiah Alat Baru
B BIAYA PASTI PER JAM
1. Nilai Sisa Alat = 10 % x B' C 59,780,000.00 Rupiah
2. D 0.23852 -
3. Biaya Pasti Per Jam :
a. Biaya Pengembalian Modal = {( B'-C ) x D} / W' E 64,165.01 Rupiah
b. Asuransi, dll = ( 0,002 x B' ) / W' F 597.80 Rupiah
4. Biaya Pasti Per Jam = ( E + F ) G 64,762.81 Rupiah
C BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (0,125-0,175 Ltr/HP/Jam) x Pw x Ms 18,562.50 Rupiah
2. Pelumas = ( 0,01 - 0,02 Ltr/HP/Jam ) x Pw x Mp I 27,500.00 Rupiah
3. Perawatan dan = {(12,5% - 17,5%)xB'} / W' K 37,362.50 Rupiah
Perbaikan
4. OperatorL
10,000.00 Rupiah
5. Sopir 11,428.57 Rupiah
6.M
28,571.43 Rupiah
7. Pembantu Sopir 7,142.86 Rupiah
8. Biaya Operasi / Jam = ( H + I + K + L + M ) P 121,996.43 Rupiah
D TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 186,759.24 Rupiah
E LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 %/Tahun
2. Upah Operator 10,000.00 Rp./Jam
3. Upah Sopir 11,428.57 Rp./Jam
4. Upah Pembantu Operator 7,142.86 Rp./Jam
5. Upah Pembantu Sopir 7,142.86 Rp./Jam
6. Bahan Bakar Bensin Mb 8,500.00 Rp./Liter
7. Bahan Bakar Solar Ms 1,350.00 Rp./Liter
8. Minyak Pelumas Mp 25,000.00 Rp./Liter
9. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
Faktor Angsuran Modal = i x (1+i)A' / (1+i)A-1
H1
= ( 1 Orang / Jam ) x U1
= ( 1 Orang / Jam ) x U2
Pembantu Operator = ( 4 Orang / Jam ) x U3
= ( 1 Orang / Jam ) x U4
U1
U2
U3
U4
URAIAN ANALISA ALAT
NO. PAKET KONTRAK :
NAMA PAKET : SANGATTA
NAMA ALAT : Water Tank Truck Isuzu 5000 L
NO. U R A I A N KODE KOEF. SATUAN KET.
A URAIAN PERALATAN
1. Jenis Peralatan Water Tank Truck Isuzu 5000 L
2. Tenaga Pw 150.00 HP
3. Kapasitas Cp 50.00 Ton/Jam
4. Alat Baru : a. Umur Ekonomis A 10.00 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 176,000,000.00 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 10.00 Tahun Alat Baru
b. Jam Kerja Dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat (*) B' 176,000,000.00 Rupiah Alat Baru
B BIAYA PASTI PER JAM
1. Nilai Sisa Alat = 10 % x B' C 17,600,000.00 Rupiah
2. D 0.23852 -
3. Biaya Pasti Per Jam :
a. Biaya Pengembalian Modal = {( B'-C ) x D} / W' E 18,891.00 Rupiah
b. Asuransi, dll = ( 0,002 x B' ) / W' F 176.00 Rupiah
4. Biaya Pasti Per Jam = ( E + F ) G 19,067.00 Rupiah
C BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (0,125-0,175 Ltr/HP/Jam) x Pw x Ms 25,312.50 Rupiah
2. Pelumas = ( 0,01 - 0,02 Ltr/HP/Jam ) x Pw x Mp I 37,500.00 Rupiah
3. Perawatan dan = {(12,5% - 17,5%)xB'} / W' K 11,000.00 Rupiah
Perbaikan
4. OperatorL
10,000.00 Rupiah
5. Sopir 11,428.57 Rupiah
6.M
28,571.43 Rupiah
7. Pembantu Sopir 7,142.86 Rupiah
8. Biaya Operasi / Jam = ( H + I + K + L + M ) P 92,383.93 Rupiah
D TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 111,450.93 Rupiah
E LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 %/Tahun
2. Upah Operator 10,000.00 Rp./Jam
3. Upah Sopir 11,428.57 Rp./Jam
4. Upah Pembantu Operator 7,142.86 Rp./Jam
5. Upah Pembantu Sopir 7,142.86 Rp./Jam
6. Bahan Bakar Bensin Mb 8,500.00 Rp./Liter
7. Bahan Bakar Solar Ms 1,350.00 Rp./Liter
8. Minyak Pelumas Mp 25,000.00 Rp./Liter
9. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
Faktor Angsuran Modal = i x (1+i)A' / (1+i)A-1
H1
= ( 1 Orang / Jam ) x U1
= ( 1 Orang / Jam ) x U2
Pembantu Operator = ( 4 Orang / Jam ) x U3
= ( 1 Orang / Jam ) x U4
U1
U2
U3
U4
URAIAN ANALISA ALAT
NO. PAKET KONTRAK :
NAMA PAKET : SANGATTA
NAMA ALAT : Vibratory Roller XCMG XD121
NO. U R A I A N KODE KOEF. SATUAN KET.
A URAIAN PERALATAN
1. Jenis Peralatan Vibratory Roller XCMG XD121
2. Tenaga Pw 93.00 HP
3. Kapasitas Cp 50.00 Ton/Jam
4. Alat Baru : a. Umur Ekonomis A 10.00 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 784,000,000.00 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 10.00 Tahun Alat Baru
b. Jam Kerja Dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat (*) B' 784,000,000.00 Rupiah Alat Baru
B BIAYA PASTI PER JAM
1. Nilai Sisa Alat = 10 % x B' C 78,400,000.00 Rupiah
2. D 0.23852 -
3. Biaya Pasti Per Jam :
a. Biaya Pengembalian Modal = {( B'-C ) x D} / W' E 84,150.83 Rupiah
b. Asuransi, dll = ( 0,002 x B' ) / W' F 784.00 Rupiah
4. Biaya Pasti Per Jam = ( E + F ) G 84,934.83 Rupiah
C BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (0,125-0,175 Ltr/HP/Jam) x Pw x Ms 15,693.75 Rupiah
2. Pelumas = ( 0,01 - 0,02 Ltr/HP/Jam ) x Pw x Mp I 23,250.00 Rupiah
3. Perawatan dan = {(12,5% - 17,5%)xB'} / W' K 49,000.00 Rupiah
Perbaikan
4. OperatorL
10,000.00 Rupiah
5. Sopir 11,428.57 Rupiah
6.M
28,571.43 Rupiah
7. Pembantu Sopir 7,142.86 Rupiah
8. Biaya Operasi / Jam = ( H + I + K + L + M ) P 126,515.18 Rupiah
D TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 211,450.01 Rupiah
E LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 %/Tahun
2. Upah Operator 10,000.00 Rp./Jam
3. Upah Sopir 11,428.57 Rp./Jam
4. Upah Pembantu Operator 7,142.86 Rp./Jam
5. Upah Pembantu Sopir 7,142.86 Rp./Jam
6. Bahan Bakar Bensin Mb 8,500.00 Rp./Liter
7. Bahan Bakar Solar Ms 1,350.00 Rp./Liter
8. Minyak Pelumas Mp 25,000.00 Rp./Liter
9. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
Faktor Angsuran Modal = i x (1+i)A' / (1+i)A-1
H1
= ( 1 Orang / Jam ) x U1
= ( 1 Orang / Jam ) x U2
Pembantu Operator = ( 4 Orang / Jam ) x U3
= ( 1 Orang / Jam ) x U4
U1
U2
U3
U4
URAIAN ANALISA ALAT
NO. PAKET KONTRAK :
NAMA PAKET : SANGATTA
NAMA ALAT : Wheel Loader Komatsu WA350 3 m3
NO. U R A I A N KODE KOEF. SATUAN KET.
A URAIAN PERALATAN
1. Jenis Peralatan Wheel Loader Komatsu WA350 3 m3
2. Tenaga Pw 166.00 HP
3. Kapasitas Cp 50.00 Ton/Jam
4. Alat Baru : a. Umur Ekonomis A 10.00 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 600,000,000.00 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 4.00 Tahun Alat Bekas
b. Jam Kerja Dalam 1 Tahun W' 2,000.00 Jam Alat Bekas
c. Harga Alat (*) B' 600,000,000.00 Rupiah Alat Bekas
B BIAYA PASTI PER JAM
1. Nilai Sisa Alat = 10 % x B' C 60,000,000.00 Rupiah
2. D 0.38629 -
3. Biaya Pasti Per Jam :
a. Biaya Pengembalian Modal = {( B'-C ) x D} / W' E 104,298.06 Rupiah
b. Asuransi, dll = ( 0,002 x B' ) / W' F 600.00 Rupiah
4. Biaya Pasti Per Jam = ( E + F ) G 104,898.06 Rupiah
C BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (0,125-0,175 Ltr/HP/Jam) x Pw x Ms 28,012.50 Rupiah
2. Pelumas = ( 0,01 - 0,02 Ltr/HP/Jam ) x Pw x Mp I 41,500.00 Rupiah
3. Perawatan dan = {(12,5% - 17,5%)xB'} / W' K 37,500.00 Rupiah
Perbaikan
4. OperatorL
10,000.00 Rupiah
5. Sopir 11,428.57 Rupiah
6.M
28,571.43 Rupiah
7. Pembantu Sopir 7,142.86 Rupiah
8. Biaya Operasi / Jam = ( H + I + K + L + M ) P 145,583.93 Rupiah
D TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 250,481.99 Rupiah
E LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 %/Tahun
2. Upah Operator 10,000.00 Rp./Jam
3. Upah Sopir 11,428.57 Rp./Jam
4. Upah Pembantu Operator 7,142.86 Rp./Jam
5. Upah Pembantu Sopir 7,142.86 Rp./Jam
6. Bahan Bakar Bensin Mb 8,500.00 Rp./Liter
7. Bahan Bakar Solar Ms 1,350.00 Rp./Liter
8. Minyak Pelumas Mp 25,000.00 Rp./Liter
9. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
Faktor Angsuran Modal = i x (1+i)A' / (1+i)A-1
H1
= ( 1 Orang / Jam ) x U1
= ( 1 Orang / Jam ) x U2
Pembantu Operator = ( 4 Orang / Jam ) x U3
= ( 1 Orang / Jam ) x U4
U1
U2
U3
U4
A N A L I S A B A H A N
NOMOR PAKET KONTRAK :
NAMA PAKET : SANGATTA
JENIS BAHAN : PENGADAAN AGREGAT KELAS A
SATUAN PENGUKURAN
No. U r a i a n Kode Koefisien Satuan Keterangan
I ASUMSI
1 Komposisi Campuran : - Agregat Kasar KAk 60.00 %
- Agregat Halus KAh 40.00 %
Untuk Agregat Halus sudah termasuk pasir sebanyak …. Kpsr 4.00 % 10% x KAh
2 Komposisi Produksi Stone Crusher ( Crusher Plant )
- Agregat Kasar %Ak 70.00 %
- Agregat Halus %Ah 30.00 %
3 Harga Satuan Batu Pecah ( Kasar/Halus ) HSBP 170,000.00
Harga Satuan Pasir di Base Camp Bpsr 145,000.00
4 Pencampuran dengan Wheel Loader
- Biaya Pemilikan dan Opersasi Awl 250,481.99 Rp/jam
- Kapasitas Cwl 3.20
- Faktor Efisiensi Alat Fwl 0.75 - Bekas
II PENCAMPURAN
1
a. Agr. Halus dari Stone Crusher = KAh - Kpsr %Ahsc 0.3600
b. Agr. Kasar dari Stone Crusher yang terproduksi :
= %Ak : %Ah x %Ahsc 0.8400
c. Jumlah Agregat Batu Pecah yang terproduksi Vbp 1.2000
2 Wheel Loader
- Cycle Time : Ct 1.50 menit
(menuang, mengumpulkan, mencampur, memindahkan dll)
- Produktivitas = Fwl x 60/Ct x Cwl Prwl 96.00
= Awl : Prwl HSwl 2,609.19
III HARGA SATUAN AGREGAT KELAS A
a. Agregat Batu Pecah = Vbp x HSBP 204,000.00
b. Pasir Tambahan = Kpsr x Bpsr 5,800.00
c. Biaya Pencampuran = HSwl 2,609.19
Btot 212,409.19
: M3
Rp/m3
Rp/m3
m3
Volume Agregat Kasar/Halus per 1 m3 Agregat Kelas A
m3
m3
m3
m3 / jam
- Biaya / m3 Rp / m3
Rp / m3
Rp / m3
Rp / m3
Rp / m3
A N A L I S A B A H A N
NOMOR PAKET KONTRAK :
NAMA PAKET : SANGATTA
JENIS BAHAN : PENGADAAN AGREGAT KELAS B
SATUAN PENGUKURAN
No. U r a i a n Kode Koefisien Satuan Keterangan
I ASUMSI
1 Komposisi Campuran : - Agregat Kasar KAk 65.00 %
- Agregat Halus KAh 35.00 %
Untuk Agregat Halus sudah termasuk pasir sebanyak …. Kpsr 3.60 % 10% x KAh
2 Komposisi Produksi Stone Crusher ( Crusher Plant )
- Agregat Kasar %Ak 70.00 %
- Agregat Halus %Ah 30.00 %
3 Harga Satuan Batu Pecah ( Kasar/Halus ) HSBP 170,000.00
Harga Satuan Pasir di Base Camp Bpsr 145,000.00
4 Pencampuran dengan Wheel Loader
- Biaya Pemilikan dan Opersasi Awl 250,481.99 Rp/jam
- Kapasitas Cwl 3.20
- Faktor Efisiensi Alat Fwl 0.75 - Bekas
II PENCAMPURAN
1
a. Agr. Halus dari Stone Crusher = KAh - Kpsr %Ahsc 0.3140
b. Agr. Kasar dari Stone Crusher yang terproduksi :
= %Ak : %Ah x %Ahsc 0.7327
c. Jumlah Agregat Batu Pecah yang terproduksi Vbp 1.0467
2 Wheel Loader
- Cycle Time : Ct 1.00 menit
(menuang, mengumpulkan, mencampur, memindahkan dll)
- Produktivitas = Fwl x 60/Ct x Cwl Prwl 144.00
= Awl : Prwl HSwl 1,739.46
III HARGA SATUAN AGREGAT KELAS B
a. Agregat Batu Pecah = Vbp x HSBP 177,933.33
b. Pasir Tambahan = Kpsr x Bpsr 5,220.00
c. Biaya Pencampuran = HSwl 1,739.46
Btot 184,892.79
: M3
Rp/m3
Rp/m3
m3
Volume Agregat Kasar/Halus per 1 m3 Agregat Kelas A
m3
m3
m3
m3 / jam
- Biaya / m3 Rp / m3
Rp / m3
Rp / m3
Rp / m3
Rp / m3
PROYEK PERENCANAAN TEKNIS JALAN ADI SUROSO CS
KEC. KAUBUN
SANGATTAKUTAI TIMUR
ENGINEER'S ESTIMATE( EE )
URAIAN ANALISA HARGA SATUANDIVISI - I
DRAINASE
URAIAN ANALISA HARGA SATUAN
ITEM PEMBAYARAN NO. :JENIS PEKERJAAN : GALIAN UNTUK DRAINASE, SELOKAN DAN SALURAN AIR
SATUAN PEMBAYARAN Analisa El - 21
NO U R A I A N KODE KOEF. SATUAN KET.
I ASUMSI1 Menggunakan alat berat ( cara mekanik )2 Lokasi Pekerjaan : sepanjang jalan3 Kondisi Jalan : sedang / baik4 Jam kerja efektif per - hari Tk 7.00 jam5 Faktor Pengembangan Bahan Fk 1.20 -
II URUTAN KERJA1 Penggalian dilakukan dengan menggunakan Excavator2 Excavator menuangkan hasil galian kedalam Dump Truck3 Dump Truck membuang hasil galian keluar lokasi jalan
sejauh ……. Km. L 5.00 Km4 Sekelompok pekerja akan merapikan hasil galian
III PEMAKAIAN BAHAN, ALAT DAN TENAGA
1 BAHANTidak ada bahan yang digunakan
2 ALAT2a. EXCAVATOR (E-10)
Kapasitas Bucket V 1.50Faktor Bucket Fb 0.90 -Faktor Efisiensi Alat Fa 0.75 -
Waktu Siklus Ts1- Menggali / memuat T1 0.50 menit- Lain - lain T2 0.50 menit
Ts1 1.00 menit
Kap. Prod./jam =V x Fb x Fa x 60
Q1 50.625Ts1 x Fk
(E-10) 0.0198 Jam
2b. DUMP TRUCK (E-08)
Kapasitas bak V 4.00Faktor Efisiensi Alat Fa 0.83 -Kecepatan rata-rata bermuatan v1 30.00 Km / JamKecepatan rata-rata kosong v2 50.00 Km / JamWaktu siklus : Ts2- Waktu tempuh isi = (L : v1) x 60 T1 10.00 menit- Waktu tempuh kosong = (L : v2) x 60 T2 6.00 menit- Muat = (V : Q1) x 60 T3 4.74 menit- Lain - lain T4 0.50 menit
Ts2 21.24 menit
Bersambung …
: M3
M3
M3 / jam
Koefisien Alat / M3 = 1 : Q1
M3
URAIAN ANALISA HARGA SATUAN
ITEM PEMBAYARAN NO. : JENIS PEKERJAAN : GALIAN UNTUK SALURAN
SATUAN PEMBAYARAN Analisa El - 21
NO U R A I A N KODE KOEF. SATUAN KET.
Kap. Prod./jam =V x Fa x 60
Q2 7.81517Ts2 x Fk
- 0.1280 Jam
2c. ALAT BANTUDipergunakan alat - alat kecil seperti :- Sekop- Keranjang + sapu
3. TENAGA
Produksi menentukan : EXCAVATOR Q1 50.63
Produksi galian / hari = Tk x Q1 Qt 354.375Kebutuhan tenaga :
- Pekerja P 6 orang- Mandor M 1 orang
- Pekerja = (Tk x P) : Qt (L01) 0.1185 Jam- Mandor = (Tk x M) : Qt (L03) 0.0198 Jam
4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALATLihat lampiran
5. ANALISA HARGA SATUAN PEKERJAANLihat perhitungan dalam Analisa Harga SatuanDidapat Harga Satuan Pekerjaan :
Rp. 27,750.14
6. WAKTU PELAKSANAAN YANG DIPERLUKANMasa Pelaksanaan : …………. Bulan
7. VOLUME PEKERJAAN YANG DIPERLUKAN
Volume Pekerjaan
: M3
M3 / jam
Koefisien Alat / M3 = 1 : Q2
M3 / jam
M3
Koefisien tenaga / M3 :
/ M3
m3
URAIAN ANALISA HARGA SATUAN
ITEM PEMBAYARAN NO. :JENIS PEKERJAAN : PASANGAN BATU DENGAN MORTAR
SATUAN PEMBAYARAN Analisa El - 22
NO U R A I A N KODE KOEF. SATUAN KET.
I ASUMSI1 Menggunakan alat ( cara mekanik )2 Lokasi Pekerjaan : sepanjang jalan / ruas3 Bahan dasar ( batu, pasir dan semen ) diterima seluruh-
nya di lokasi pekerjaan4 Jarak rata - rata Base Camp ke lokasi pekerjaan L 5.00 Km5 Jam kerja efektif per - hari Tk 7.00 jam6 Perbandingan pasir dan semen :
- semen PC 0.25 % 25%- pasir Psr 0.75 % 75%
7 Perbandingan batu dengan Mortar :- batu Bt 0.80 % 60%- mortar Mt 0.20 % 40%
8 Berat Jenis Bahan :
- Pas. Batu dengan mortar D1 2.40
- Batu kali D2 1.60
- Adukan / Mortar D3 1.80
- Pasir D4 1.67
- Semen (PC) D5 1.44
II URUTAN KERJA1 Semen, pasir dan air dicampur dan diaduk menjadi mortar
dengan menggunakan Concrete Mixer2 Batu dibersihlan dan dibasahi seluruh permukaannya
sebelum dipasang3 Penyelesaian dan perapihan setelah dipasang
III PEMAKAIAN BAHAN, ALAT DAN TENAGA
1 BAHAN
1.a Batu M-02 1.4400
1.b Semen M-12 100.800 Kg x {D5x1000}
1.c Pasir M-01 0.226347
2 ALAT2a. CONCRETE MIXER (E-10)
Kapasitas Alat V 350.00 LiterFaktor Efisiensi Alat Fa 0.83 -
Waktu Siklus Ts1- Memuat / mengisi T1 3.00 menit- Mengaduk T2 5.00 menit- Menuang T3 1.00 menit- Lain - lain ( menunggu, dsb ) T4 2.00 menit
Ts1 11.00 menit
Kap. Prod./jam =V x Fa x 60
Q1 1.5845451000 x Ts1
- 0.6311 Jam
Bersambung …
: M3
Ton/m3
Ton/m3
Ton/m3
Ton/m3
Ton/m3
: {(BtxD1x1M3) : D2} x 1,20 m3
: PC x {(MrxD1x1M3) : D3} x 1,05
: Psrx{(MrxD1x1M3) : D4} x 1,05 m3
M3 / jam
Koefisien Alat / M3 = 1 : Q1
URAIAN ANALISA HARGA SATUAN
ITEM PEMBAYARAN NO. : JENIS PEKERJAAN : PASANGAN BATU DENGAN MORTAR
SATUAN PEMBAYARAN Analisa El - 22
NO U R A I A N KODE KOEF. SATUAN KET.
2a. ALAT BANTUDipergunakan alat - alat seperti :- Sekop = 5 buah- Pacul = 5 buah- Sendok semen = 5 buah- Ember cor = 10 buah- Gerobak = 4 buah
3. TENAGA
Produksi menentukan : CONCRETE MIXER Q1 1.58
Produksi Pasangan Batu / hari = Tk x Q1 Qt 11.09182Kebutuhan tenaga :
- Pekerja P 2 orang- Tukang Batu Tb 2 orang- Mandor M 1 orang
- Pekerja = (Tk x P) : Qt L-01 1.262192 Jam- T. Batu = (Tk x Tb) : Qt L-02 1.262192 Jam- Mandor = (Tk x M) : Qt L-03 0.631096 Jam
4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALATLihat lampiran
5. ANALISA HARGA SATUAN PEKERJAANLihat perhitungan dalam Analisa Harga SatuanDidapat Harga Satuan Pekerjaan :
Rp. 455,106.74
6. WAKTU PELAKSANAAN YANG DIPERLUKANMasa Pelaksanaan : …………. Bulan
7. VOLUME PEKERJAAN YANG DIPERLUKAN
Volume Pekerjaan
: M3
M3 / jam
M3
Koefisien tenaga / M3 :
/ M3
m3
URAIAN ANALISA HARGA SATUAN
ITEM PEMBAYARAN NO. : JENIS PEKERJAAN : LAPIS PONDASI AGREGAT KELAS B
SATUAN PEMBAYARAN Analisa El - 412
NO U R A I A N KODE KOEF. SATUAN KET.
I ASUMSI1 Menggunakan alat berat ( cara mekanik )2 Pekerjaan dilaksanakan hanya pada daerah Galian3 Lokasi Pekerjaan : sepanjang jalan / ruas4 Kondisi jalan : jelek, sedang / baik5 Jam kerja efektif per - hari Tk 7.00 jam6 Jarak rata-rata Base Camp ke Lokasi Pekerjaan L 4.00 Km7 Tebal lapis Agregat Padat t 0.25 M8 Faktor Pengembangan Bahan Fk 1.209 Proporsi Campuran Agregat :
- Agregat Kasar Ak 59.00 %- Agregat Halus Ah 41.00 %
II URUTAN KERJA1 Agregat dimuat ke Dump Truck dengan Wheel Loader2 Agregat dihampar dengan Motor Grader3 Sebelum dipadatkan dengan Vibro Roller, terlebih dahulu
### disiram/dibasahi dengan Water Tank Truck4 Perapian tepi dan level permukaan dikerjakan oleh
sekelompok pekerja dengan Alat Bantu
III PEMAKAIAN BAHAN, ALAT DAN TENAGA1 BAHAN
- Agregat Kasar M-03 0.7080
- Agregat Halus M-04 0.4920
2 ALAT2a. WHEEL LOADER E-15
Kapasitas Bucket V 3.20Faktor Bucket b 0.90 -Faktor Efisiensi Alat Fa 0.75 -Waktu Siklus : Ts1- Muat T1 0.50 Menit- Lain - lain T2 0.50 Menit
Ts1 1.00 Menit
Kapasitas Produksi / Jam = (VxFbxFax60)/(FkxTs1) Q1 108.00
E-15 0.0093 Jam
2b. VIBRO ROLLER E - 19Kecepatan alat rata-rata ( saat operasi ) v 3.00 Km/JamLebar Efektif Pemadatan b 1.00 MJumlah lintasan n 8.00 KaliFaktor Efisiensi Alat Fa 0.83 -
Kapasitas Produksi / Jam = ( vx1000 ) x b x Fa / n Q2 311.25
E-19 0.0032 Jam
Bersambung …
: M3
= Ak x 1 m3 x Fk m3
= Ah x 1 m3 x Fk m3
m3
m3
Koefisien Alat / m3 = 1 : Q1
m3
Koefisien Alat / m2 = 1 : Q2
PROYEK PERENCANAAN TEKNIS JALAN ADI SUROSO CS
KEC. KAUBUN
SANGATTAKUTAI TIMUR
ENGINEER'S ESTIMATE( EE )
URAIAN ANALISA HARGA SATUANDIVISI - II
PEKERJAAN TANAH
URAIAN ANALISA HARGA SATUAN
ITEM PEMBAYARAN NO. : JENIS PEKERJAAN :
SATUAN PEMBAYARAN Analisa El - 412
NO U R A I A N KODE KOEF. SATUAN KET.
2c. WATER TANK TRUCK E-23
Volume Tangki Air V 4.00
Wc 0.07Pengisian Tangki / jam n 1.00 kaliFaktor Efisiensi Alat Fa 0.83 -
Kap. Produksi / Jam = ( V x n x Fa ) : Wc Q3 47.43
E-23 0.0211 jam
2d. DUMP TRUCK E - 08
Kapasitas Bak V 4.00Faktor Efisiensi Alat Fa 0.83 -Kecepatan rata-rata bermuatan v1 30.00 Km/JamKecepatan rata-rata kosong v2 50.00 Km/JamWaktu Siklus : Ts2 - Waktu Tempuh Isi = ( L : v1 ) x 60 T1 8.00 Menit - Waktu Tempuh Kosong = ( L : v2 ) x 60 T2 4.80 Menit - Waktu Lain - lain T4 3.00 Menit
Ts2 15.80 Menit
Kap. Produksi / Jam = ( V x Fa x 60 ) / ( Fk x Ts2 ) Q4 10.51
E - 08 0.0952 jam
2e. MOTOR GRADER E - 13Panjang hamparan Lh 50.00 MLebar efektif kerja blade b 2.40 MFaktor Efisiensi Alat Fa 0.83 -Kecepatan alat rata-rata v 4.00 Km/JamJumlah lintasan n 6.00 Kali 3 x ppWaktu Siklus : Ts3- Perataan 1 x lintasan = (Lh x 60) : (v x 1000 ) Ts1 0.75 Menit- Lain - lain Ts2 1.00 Menit
Ts3 1.75 Menit
Bersambung …
: M3
m3
Kebutuhan Air/m3 material padat m3
m3 / jam
Koefisien Alat / m3 = 1 : Q3
M3
m3 / jam
Koefisien Alat / m3 = 1 : Q4
URAIAN ANALISA HARGA SATUAN
ITEM PEMBAYARAN NO. : JENIS PEKERJAAN :
SATUAN PEMBAYARAN Analisa El - 412
NO U R A I A N KODE KOEF. SATUAN KET.
Kapasitas Produksi / Jam = (bxtxFax60)/(nxTs3) Q5 45.53
E-18 0.0220 Jam
2d. ALAT BANTUDiperlukan alat-alat bantu kecil - Sekop = 3 buah - Kereta Dorong = 2 buah - Garpu = 2 buah
3. TENAGA
Produksi menentukan : WHEEL LOADER Q1 108.00
Produksi Pekerjaan / hari = Tk x Q1 Qt 756.00Kebutuhan Tenaga :
- Pekerja P 7.00 orang- Tukang T 0.00 orang- Mandor M 1.00 orang
- Pekerja = (Tk x P ) : Qt 0.4537 Jam- Tukang = (Tk x T ) : Qt 0.0000 Jam- Mandor = (Tk x M ) : Qt 0.0093 Jam
4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALATLihat lampiran
5. ANALISA HARGA SATUAN PEKERJAANLihat perhitungan dalam Analisa Harga SatuanDidapat Harga Satuan Pekerjaan :
Rp. 278,365.42
6. WAKTU PELAKSANAAN YANG DIPERLUKANMasa Pelaksanaan : …………. Bulan
7. VOLUME PEKERJAAN YANG DIPERLUKAN
Volume Pekerjaan
: M3
M3
Koefisien Alat / m3 = 1 : Q5
m3 / jam
m3
Koefisien Tenaga / m3
/ m3
M3
URAIAN ANALISA HARGA SATUAN
ITEM PEMBAYARAN NO. :JENIS PEKERJAAN : LAPIS PONDASI AGREGAT KELAS A
SATUAN PEMBAYARAN Analisa El - 511
NO U R A I A N KODE KOEF. SATUAN KET.
I ASUMSI1 Menggunakan alat berat ( cara mekanik )2 Lokasi Pekerjaan : sepanjang jalan / ruas3 Kondisi jalan : jelek, sedang / baik4 Jam kerja efektif per - hari Tk 7.00 jam5 Jarak rata-rata Base Camp ke Lokasi Pekerjaan L 4.00 Km6 Tebal lapis Agregat Padat t 0.20 M7 Faktor Pengembangan Bahan Fk 1.208 Lebar rata-rata Bahu Jalan Lb 1.00 M9 Proporsi Campuran Agregat :
- Agregat Kasar Ak 64.00 %- Agregat Halus Ah 36.00 %
II URUTAN KERJA1 Wheel Loader mencampur dan memuat Agregat kedalam
Dump Truck di Base Camp.2 Agregat dihampar dengan Motor Grader3### Sebelum dipadatkan Agregat disiram / dibasahi dengan
Water Tank Truck.4 Pemadatan dilakukan dengan Vibro Roller5 Perapian tepi dan level permukaan dilakukan oleh pekerja
III PEMAKAIAN BAHAN, ALAT DAN TENAGA1 BAHAN
- Agregat Kasar M-03 0.7680
- Agregat Halus M-04 0.4320
2 ALAT2a. WHEEL LOADER E-15
Kapasitas Bucket V 3.20Faktor Bucket b 0.90 -Faktor Efisiensi Alat Fa 0.75 -Waktu Siklus : Ts1- Muat T1 2.50 Menit- Lain - lain T2 1.00 Menit
Ts1 3.50 Menit
Kapasitas Produksi / Jam = (VxFbxFax60)/(FkxTs1) Q1 30.86
E-15 0.0324 Jam
2b. VIBRO ROLLER E - 19Kecepatan alat rata-rata ( saat operasi ) v 3.00 Km/JamLebar Efektif Pemadatan b 1.20 MJumlah lintasan n 10.00 KaliFaktor Efisiensi Alat Fa 0.83 -
Bersambung …
: M3
= Ak x 1 m3 x Fk m3
= Ah x 1 m3 x Fk m3
m3
m3
Koefisien Alat / m3 = 1 : Q1
URAIAN ANALISA HARGA SATUAN
ITEM PEMBAYARAN NO. : JENIS PEKERJAAN : LAPIS PONDASI AGREGAT KELAS A
SATUAN PEMBAYARAN Analisa El - 511
NO U R A I A N KODE KOEF. SATUAN KET.
Kapasitas Produksi / Jam = ( vx1000 ) x b x Fa x t / n Q2 90.00
E-19 0.0111 Jam
2c. WATER TANK TRUCK E-23
Volume Tangki Air V 4.00
Wc 0.07Pengisian Tangki / jam n 1.00 kaliFaktor Efisiensi Alat Fa 0.83 -
Kap. Produksi / Jam = ( V x n x Fa ) : Wc Q3 47.43
E-23 0.0211 jam
2d. DUMP TRUCK E - 08
Kapasitas Bak V 4.00Faktor Efisiensi Alat Fa 0.83 -Kecepatan rata-rata bermuatan v1 30.00 Km/JamKecepatan rata-rata kosong v2 50.00 Km/JamWaktu Siklus : Ts2 - Waktu Tempuh Isi = ( L : v1 ) x 60 T1 14.00 Menit - Waktu Tempuh Kosong = ( L : v2 ) x 60 T2 4.80 Menit - Waktu Lain - lain T4 3.00 Menit
Ts2 21.80 Menit
Kap. Produksi / Jam = ( V x Fa x 60 ) / ( Fk x Ts2 ) Q4 7.61
E - 08 0.1313 jam
2e. MOTOR GRADER E - 13Panjang hamparan Lh 50.00 MLebar efektif kerja blade b 2.40 MFaktor Efisiensi Alat Fa 0.83 -Kecepatan alat rata-rata v 4.00 Km/JamJumlah lintasan n 6.00 Kali 3 x ppWaktu Siklus : Ts3- Perataan 1 x lintasan = (Lh x 60) : (v x 1000 ) Ts1 0.75 Menit- Lain - lain Ts2 1.00 Menit
Ts3 1.75 Menit
Bersambung …
: M3
m3
Koefisien Alat / m2 = 1 : Q2
m3
Kebutuhan Air/m3 material padat m3
m3 / jam
Koefisien Alat / m3 = 1 : Q3
M3
m3 / jam
Koefisien Alat / m3 = 1 : Q4
URAIAN ANALISA HARGA SATUAN
ITEM PEMBAYARAN NO. :JENIS PEKERJAAN : LAPIS PONDASI AGREGAT KELAS A
SATUAN PEMBAYARAN Analisa El - 511
NO U R A I A N KODE KOEF. SATUAN KET.
Kapasitas Produksi / Jam = (LhxbxtxFax60)/(nxTs3) Q5 113.83
E-18 0.0088 Jam
2f. ALAT BANTUDiperlukan alat-alat bantu kecil - Sekop = 3 buah - Kereta Dorong = 2 buah - Garpu = 2 buah
3. TENAGA
Produksi menentukan : WHEEL LOADER Q1 30.86
Produksi Pekerjaan / hari = Tk x Q1 Qt 216.00Kebutuhan Tenaga :
- Pekerja P 7.00 orang- Tukang T 0.00 orang- Mandor M 1.00 orang
- Pekerja = (Tk x P ) : Qt 1.5880 Jam- Tukang = (Tk x T ) : Qt 0.0000 Jam- Mandor = (Tk x M ) : Qt 0.0324 Jam
4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALATLihat lampiran
5. ANALISA HARGA SATUAN PEKERJAANLihat perhitungan dalam Analisa Harga SatuanDidapat Harga Satuan Pekerjaan :
Rp. 332,011.94
6. WAKTU PELAKSANAAN YANG DIPERLUKANMasa Pelaksanaan : …………. Bulan
7. VOLUME PEKERJAAN YANG DIPERLUKAN
Volume Pekerjaan
: M3
M3
Koefisien Alat / m3 = 1 : Q5
m3 / jam
m3
Koefisien Tenaga / m3
/ m3
M3
URAIAN ANALISA HARGA SATUAN
ITEM PEMBAYARAN NO. : JENIS PEKERJAAN : LAPIS RESAP PENGIKAT (PRIME COAT)SATUAN PEMBAYARAN : Liter Analisa El - 611
NO U R A I A N KODE KOEF. SATUAN KET.
I ASUMSI1 Menggunakan alat berat ( cara mekanik )2 Lokasi Pekerjaan : sepanjang jalan / ruas3 Jam kerja efektif per - hari Tk 7.00 jam4 Jarak rata-rata Base Camp ke Lokasi Pekerjaan L 5.00 Km5 Faktor Kehilangan Bahan Fh 1.106 Komposisi Campuran :
- Aspal AC-10 atau AC-20 As 56.00 % 100 bagian- Minyak Flux / pencair K 44.00 % 80 bagian
7 Berat Jenis Bahan :- Aspal AC-10 atau AC-20 D1 1.05 Kg/Liter- Minyak Flux / pencair D2 0.80 Kg/Liter
8 Bahan dasar ( aspal + minyak flux ) semuanya diterimadi lokasi pekerjaan
II URUTAN KERJA1 Aspal dan minyak flux dicampur dan dipanaskan sehingga
menjadi campuran aspal cair2 Permukaan yang akan dilapisi dibersihkan dari debu dan
### kotoran lainnya dengan Air Compressor3 Campuran aspal cair disemprotkan ke atas permukaan
yang bersih dengan Asphalt Sprayer4 Aspal dan minyak flux diangkut dengan Dump Truck
III PEMAKAIAN BAHAN, ALAT DAN TENAGA1 BAHAN
Untuk mendapatkan 1 liter Lapis Resap Pengikat,diperlukan : ( 1 Liter x Fh ) PC 1.1000 Liter CampuranAspal = As x PC x D1 M-10 0.6468 KgKerozen = K x PC M-11 0.4840 Liter
2 ALAT2a. ASPHALT SPRAYER E-03
Kapasitas Alat V 1000.00 LiterFaktor Efisiensi Alat Fa 0.83 -Waktu Siklus ( Termasuk Proses Pemanasan ) Ts 2.00 Jam
Kapasitas Produksi / Jam = ( V x Fa ) / Ts Q1 415.00 LiterKoefisien Alat / Ltr = 1 : Q1 E-03 0.0024 Jam
2b. AIR COMPRESSOR E-05
Kapasitas alat =====>> diambil V 400.00
Aplikasi Lapis Resap Pengikat rata-rata ( Spesifikasi ) Ap 0.80
Kapasitas Produksi / Jam = ( V x Ap ) Q2 320.00 LiterKoefisien Alat / Liter = 1 / Q2 E-05 0.0031 Jam
Bersambung …
m2 /Jam
Liter/m2
URAIAN ANALISA HARGA SATUAN
ITEM PEMBAYARAN NO. : JENIS PEKERJAAN : LAPIS RESAP PENGIKAT (PRIME COAT)SATUAN PEMBAYARAN : Liter Analisa El - 611
NO U R A I A N KODE KOEF. SATUAN KET.
2c. DUMP TRUCK E-08Sebagai alat pengangkut bahan ke lokasi pekerjaan.Dump Truck melayani Asphalt Sprayer
Kap. Produksi / Jam = Kapasitas Asphalt Sprayer Q3 415.00 LiterKoefisien Alat / Liter = 1 : Q3 E-08 0.0024 Jam
3. TENAGAProduksi menentukan : ASPHALT SPRAYER Q1 415.00 LiterProduksi Pekerjaan / hari = Tk x Q1 Qt 2905.00 LiterKebutuhan Tenaga :
- Pekerja P 10.00 orang- Tukang T 0.00 orang- Mandor M 2.00 orang
Koefisien Tenaga / Liter :- Pekerja = (Tk x P ) : Qt 0.0241 Jam- Tukang = (Tk x T ) : Qt 0.0000 Jam- Mandor = (Tk x M ) : Qt 0.0048 Jam
4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALATLihat lampiran
5. ANALISA HARGA SATUAN PEKERJAANLihat perhitungan dalam Analisa Harga SatuanDidapat Harga Satuan Pekerjaan :
Rp. 17,901.67 / Liter
6. WAKTU PELAKSANAAN YANG DIPERLUKANMasa Pelaksanaan : …………. Bulan
7. VOLUME PEKERJAAN YANG DIPERLUKANVolume Pekerjaan Liter
URAIAN ANALISA HARGA SATUAN
ITEM PEMBAYARAN NO. : JENIS PEKERJAAN : LAPIS PEREKAT (TAKE COAT)SATUAN PEMBAYARAN : Liter Analisa El - 612
NO U R A I A N KODE KOEF. SATUAN KET.
I ASUMSI1 Menggunakan alat berat ( cara mekanik )2 Lokasi Pekerjaan : sepanjang jalan / ruas3 Jam kerja efektif per - hari Tk 7.00 jam4 Jarak rata-rata Base Camp ke Lokasi Pekerjaan L 5.00 Km5 Faktor Kehilangan Bahan Fh 1.106 Komposisi Campuran :
- Aspal AC-10 atau AC-20 As 77.00 % 100 bagian- Minyak Flux / pencair K 23.00 % 80 bagian
7 Berat Jenis Bahan :- Aspal AC-10 atau AC-20 D1 1.05 Kg/Liter- Minyak Flux / pencair D2 0.80 Kg/Liter
8 Bahan dasar ( aspal + minyak flux ) semuanya diterimadi lokasi pekerjaan
II URUTAN KERJA1 Aspal dan minyak flux dicampur dan dipanaskan sehingga
menjadi campuran aspal cair2 Permukaan yang akan dilapisi dibersihkan dari debu dan
### kotoran lainnya dengan Air Compressor3 Campuran aspal cair disemprotkan ke atas permukaan
yang bersih dengan Asphalt Sprayer4 Aspal dan minyak flux diangkut dengan Dump Truck
III PEMAKAIAN BAHAN, ALAT DAN TENAGA1 BAHAN
Untuk mendapatkan 1 liter Lapis Resap Pengikat,diperlukan : ( 1 Liter x Fh ) PC 1.1000 Liter CampuranAspal = As x PC x D1 M-10 0.8894 KgKerozen = K x PC M-11 0.2530 Liter
2 ALAT2a. ASPHALT SPRAYER E-03
Kapasitas Alat V 1000.00 LiterFaktor Efisiensi Alat Fa 0.83 -Waktu Siklus ( Termasuk Proses Pemanasan ) Ts 2.00 Jam
Kapasitas Produksi / Jam = ( V x Fa ) / Ts Q1 415.00 LiterKoefisien Alat / Ltr = 1 : Q1 E-03 0.0024 Jam
2b. AIR COMPRESSOR E-05
Kapasitas alat =====>> diambil V 400.00
Aplikasi Lapis Resap Pengikat rata-rata ( Spesifikasi ) Ap 0.40
Kapasitas Produksi / Jam = ( V x Ap ) Q2 160.00 LiterKoefisien Alat / Liter = 1 / Q2 E-05 0.0063 Jam
Bersambung …
m2 /Jam
Liter/m2
URAIAN ANALISA HARGA SATUAN
ITEM PEMBAYARAN NO. : JENIS PEKERJAAN : LAPIS PEREKAT (TAKE COAT)SATUAN PEMBAYARAN : Liter Analisa El - 611
NO U R A I A N KODE KOEF. SATUAN KET.
2c. DUMP TRUCK E-08Sebagai alat pengangkut bahan ke lokasi pekerjaan.Dump Truck melayani Asphalt Sprayer
Kap. Produksi / Jam = Kapasitas Asphalt Sprayer Q3 415.00 LiterKoefisien Alat / Liter = 1 : Q3 E-08 0.0024 Jam
3. TENAGAProduksi menentukan : ASPHALT SPRAYER Q4 415.00 LiterProduksi Pekerjaan / hari = Tk x Q1 Qt 2905.00 LiterKebutuhan Tenaga :
- Pekerja P 10.00 orang- Tukang T 0.00 orang- Mandor M 2.00 orang
Koefisien Tenaga / Liter :- Pekerja = (Tk x P ) : Qt 0.1687 Jam- Tukang = (Tk x T ) : Qt 0.0000 Jam- Mandor = (Tk x M ) : Qt 0.0048 Jam
4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALATLihat lampiran
5. ANALISA HARGA SATUAN PEKERJAANLihat perhitungan dalam Analisa Harga SatuanDidapat Harga Satuan Pekerjaan :
Rp. 21,107.23 / Liter
6. WAKTU PELAKSANAAN YANG DIPERLUKANMasa Pelaksanaan : …………. Bulan
7. VOLUME PEKERJAAN YANG DIPERLUKANVolume Pekerjaan Liter
URAIAN ANALISA HARGA SATUAN
ITEM PEMBAYARAN NO. : JENIS PEKERJAAN : LAPISAN AC-BC
SATUAN PEMBAYARAN Analisa El - 633
NO U R A I A N KODE KOEF. SATUAN KET.
I ASUMSI1 Menggunakan alat berat ( cara mekanik )2 Lokasi Pekerjaan : sepanjang jalan / ruas3 Kondisi Existing Jalan : Sedang4 Jarak rata-rata Base Camp ke Lokasi Pekerjaan L 5.00 Km5 Tebal Lapis HRS - padat t 0.05 M6 Jam kerja efektif per - hari Tk 7.00 jam7 Faktor Kehilangan Bahan Fh - -
- Agregat Fh1 1.10 -- Aspal Fh2 1.05 -
6 Komposisi Campuran HRS ( Spesifikasi )- Coarse Agregat : 40 - 60 % CA 50.00 %- Fine Agregat : 26 - 49,5 % FA 38.00 %- Fraksi Filler : 4,5 - 7,5 % FF 5.50 %- Asphalt : Minimum 6,3 % As 6.50 %
7 Berat Jenis Bahan :
- HRS D1 2.30
- Coarse dan Fine Agregat D2 1.80
- Fraksi Filler D3 2.00
- Asphalt D4 1.03
II URUTAN KERJA1 Wheel Loader memuat Agregat dan Aspal kedalam
Cold Bin AMP2 Agregat dan Aspal dipanaskan dan dicampur ( Hot Bin )3 Dump Truck memuat HRS ke lokasi pekerjaan4 Campuran panas HRS, dihampar dengan Asphalt Finisher5 Pemadatan dengan Tandem Roller ( awal dan akhir ) dan
Pneumatic Tire Roller ( pemadatan antara )6 Perapian tepi dan permukaan dilakukan oleh pekerja
dengan Alat Bantu
III PEMAKAIAN BAHAN, ALAT DAN TENAGA1 BAHAN
Agregat Kasar M-03 0.7028
Agregat Halus M-04 0.5098
Filler M-05 139.1500 Kg
Aspal M-10 156.9750 Kg
2 ALAT2a. WHEEL LOADER E-15
Kapasitas Bucket V 3.20Faktor Bucket Fb 0.90 -Efisiensi Alat Fa 0.75 -Waktu Siklus Ts1
- Muat T1 1.50 Menit- Lain - lain T2 0.50 Menit
Ts1 2.00 Menit
Bersambung …
: M3
Ton/m3
Ton/m3
Ton/m3
Ton/m3
= (CAx(D1x m3)xFh1) : D2 M3
= (FAx(D1x m3)xFh1) : D2 M3
= (FFx(D1x m3)xFh1) x 1000
= (Asx(D1x m3)xFh2) x 1000
m3
URAIAN ANALISA HARGA SATUAN
ITEM PEMBAYARAN NO. : JENIS PEKERJAAN : LAPISAN AC-BC
SATUAN PEMBAYARAN Analisa El - 633
NO U R A I A N KODE KOEF. SATUAN KET.
Kapasitas Prod. / Jam = (D2xVxFbxFax60)/(D1xTs1) Q1 50.71
E-15 0.0197 Jam
2b. ASPHALT MIXING PLANT ( AMP ) E-01Kapasitas Produksi V 50.00 Ton/JamFaktor Efisiensi Alat Fa 0.75 -
Kapasitas Produksi / Jam = ( V x Fa ) / ( D1 ) Q2 16.30435
E-01 0.0613 Jam
2c. GENETAROR SET ( GENSET ) E-12
Kapasitas Produksi / Jam = AMP Q3 16.30435
E-12 0.0613 Jam
2c. DUMP TRUCK ( DT ) E-08Kapsitas Bak V 4.00 TonFaktor Efisiensi Alat Fa 0.83 -Kecepatan rata-rata bermuatan v1 30.00 Km / JamKecepatan rata-rata kosong v2 50.00 Km / JamKapasitas AMP / batch Q2b 0.50 TonWaktu menyiapkan 1 batch HRS Tb 1.00 MenitWaktu Siklus : Ts1- Mengisi Bak = ( V : Q2b ) x Tb T1 8.00 Menit- Angkut = ( L : v1 ) x 60 T2 10.00 Menit- Tunggu + dump + putar T3 15.00 Menit- Kembali = ( L : v2 ) x 60 T4 6.00 Menit
Ts1 39.00 Menit
Kap. Produksi / Jam = ( VxFax60) / ( D1 x Ts2 ) Q4 2.22
E-08 0.4503 Jam
2d. ASPHALT FINISHER E-02Kapasitas Produksi V 40.00 Ton/JamFaktor Efisiensi Alat Fa 0.83 -
Kapasitas Produlsi / Jam = ( V x Fa ) / ( D1 ) Q5 14.43
E-02 0.0693 Jam
2e. TANDEM ROLLER (TR) E-17Kecepatan alat rata-rata v 3.50 Km/JamLebar Efektif Pemadatan b 1.20 MJumlah Lintasan n 6.00 KaliFaktor Efisiensi Alat Fa 0.83 -
: M3
M3
Koefisien Alat / M3 = 1 : Q1
M2
Koefisien Alat / M2 = 1 : Q2
M3
Koefisien Alat / M3 = 1 : Q3
M3
Koefisien Alat / M3 = 1 : Q4
M3
Koefisien Alat / M3 = 1 : Q5
URAIAN ANALISA HARGA SATUAN
ITEM PEMBAYARAN NO. : JENIS PEKERJAAN : LAPISAN AC-BC
SATUAN PEMBAYARAN Analisa El - 633
NO U R A I A N KODE KOEF. SATUAN KET.
Kapasitas Prod. / Jam = ( v x 1000 x b x t x Fa )/ n Q6 29.05
E-15 0.0344 Jam
2f. PNEUMATIC TIRE ROLLER (PTR) E-18Kecepatan alat rata-rata v 5.00 Km/JamLebar Efektif Pemadatan b 1.50 MJumlah Lintasan n 8.00 KaliFaktor Efisiensi Alat Fa 0.83 -
Kapasitas Prod. / Jam = ( v x 1000 x b x Fa ) / n Q7 38.91
E-18 0.0257 Jam
3. ALAT BANTUDiperlukan alat bantu :- Kerete dorong = 2 buah- Sekop = 3 buah- Garpu = 2 buah- Tongkat Kontrol Ketebalan Hamparan
4. TENAGA
Produksi Menentukan = AMP Q2 16.30
Produksi HRS / hari = Tk x Q2 Qt 114.13Kebutuhan Tenaga :
- Pekerja P 7.00 Orang- Tukang T 0.00 Orang- Mandor M 1.00 Orang
- Pekerja = ( Tk x P ) / Qt L-01 0.4293 Jam- Tukang = ( Tk x T ) / Qt L-02 0.0000 Jam- Mandor = ( Tk x M ) / Qt L-03 0.0613 Jam
5. HARGA DASAR SATUAN UPAH, BAHAN DAN ALATLihat lampiran
6. ANALISA HARGA SATUAN PEKERJAANLihat perhitungan dalam Analisa Harga SatuanDidapat Harga Satuan Pekerjaan :
Rp. 3,508,296.62
7. WAKTU PELAKSANAAN YANG DIPERLUKANMasa Pelaksanaan : …………. Bulan
8. VOLUME PEKERJAAN YANG DIPERLUKAN
Volume Pekerjaan
: M3
M3
Koefisien Alat / M3 = 1 : Q6
M3
Koefisien Alat / M3 = 1 : Q7
M3 / Jam
M3
Koefisien Tenaga / M2 :
/ m3
M3
URAIAN ANALISA HARGA SATUAN
ITEM PEMBAYARAN NO. :JENIS PEKERJAAN : AC -WC
SATUAN PEMBAYARAN Analisa El - 634
NO U R A I A N KODE KOEF. SATUAN KET.
I ASUMSI1 Menggunakan alat berat ( cara mekanik )2 Lokasi Pekerjaan : sepanjang jalan / ruas3 Kondisi Existing Jalan : Sedang4 Jarak rata-rata Base Camp ke Lokasi Pekerjaan L 5.00 Km5 Tebal Lapis AC - padat t 0.04 M6 Jam kerja efektif per - hari Tk 7.00 jam7 Faktor Kehilangan Bahan Fh - -
- Agregat Fh1 1.10 -- Aspal Fh2 1.05 -
6 Komposisi Campuran AC ( Spesifikasi )- Coarse Agregat : 30 - 50 % CA 61.15 %- Fine Agregat : 39 - 59 % FA 27.00 %- Fraksi Filler : 4,5 - 7,5 % FF 4.85 %- Asphalt : Minimum 6,7 % As 7.00 %
7 Berat Jenis Bahan :
- AC D1 2.25
- Coarse dan Fine Agregat D2 1.80
- Fraksi Filler D3 2.00
- Asphalt D4 1.03
II URUTAN KERJA1 Wheel Loader memuat Agregat dan Aspal kedalam
Cold Bin AMP2 Agregat dan Aspal dipanaskan dan dicampur ( Hot Bin )3 Dump Truck memuat AC ke lokasi pekerjaan4 Campuran panas AC, dihampar dengan Asphalt Finisher5 Pemadatan dengan Tandem Roller ( awal dan akhir ) dan
Pneumatic Tire Roller ( pemadatan antara )6 Perapian tepi dan permukaan dilakukan oleh pekerja
dengan Alat Bantu
III PEMAKAIAN BAHAN, ALAT DAN TENAGA1 BAHAN
Agregat Kasar M-03 0.0336
Agregat Halus M-04 0.0149
Filler M-05 4.8015 Kg
Aspal M-10 6.6150 Kg
2 ALAT2a. WHEEL LOADER E-15
Kapasitas Bucket V 3.20Faktor Bucket Fb 0.90 -Efisiensi Alat Fa 0.83 -Waktu Siklus Ts1
- Muat T1 1.50 Menit- Lain - lain T2 0.50 Menit
Ts1 2.00 Menit
Bersambung …
: M2
Ton/m3
Ton/m3
Ton/m3
Ton/m3
= (CAx(D1xt m3)xFh1) : D2 M3
= (FAx(D1xt m3)xFh1) : D2 M3
= (FFx(D1xt m3)xFh1) x 1000
= (Asx(D1xt m3)xFh2) x 1000
m3
URAIAN ANALISA HARGA SATUAN
ITEM PEMBAYARAN NO. : JENIS PEKERJAAN : AC -WC
SATUAN PEMBAYARAN Analisa El - 634
NO U R A I A N KODE KOEF. SATUAN KET.
Kapasitas Prod. / Jam = (D2xVxFbxFax60)/(D1xtxTs1) Q1 1434.24
E-15 0.0007 Jam
2b. ASPHALT MIXING PLANT ( AMP ) E-01Kapasitas Produksi V 50.00 Ton/JamFaktor Efisiensi Alat Fa 0.75 -
Kapasitas Produksi / Jam = ( V x Fa ) / ( D1 x t ) Q2 416.6667
E-01 0.0024 Jam
2c. GENETAROR SET ( GENSET ) E-12
Kapasitas Produksi / Jam = AMP Q3 416.6667
E-12 0.0024 Jam
2c. DUMP TRUCK ( DT ) E-08
Kapsitas Bak V 4.00Faktor Efisiensi Alat Fa 0.83 -Kecepatan rata-rata bermuatan v1 30.00 Km / JamKecepatan rata-rata kosong v2 50.00 Km / JamKapasitas AMP / batch Q2b 0.50 TonWaktu menyiapkan 1 batch HRS Tb 1.00 MenitWaktu Siklus : Ts1- Mengisi Bak = ( V : Q2b ) x Tb T1 8.00 Menit- Angkut = ( L : v1 ) x 60 T2 0.00 Menit- Tunggu + dump + putar T3 15.00 Menit- Kembali = ( L : v2 ) x 60 T4 0.00 Menit
Ts1 23.00 Menit
Kap. Produksi / Jam = ( VxFax60) / ( D1 x t x Ts2 ) Q4 96.23
E-08 0.0104 Jam
2d. ASPHALT FINISHER E-02Kapasitas Produksi V 40.00 Ton/JamFaktor Efisiensi Alat Fa 0.83 -
Kapasitas Produlsi / Jam = ( V x Fa ) / ( D1 x t ) Q5 368.89
E-02 0.0027 Jam
2e. TANDEM ROLLER (TR) E-17Kecepatan alat rata-rata v 2.50 Km/JamLebar Efektif Pemadatan b 1.20 MJumlah Lintasan n 4.00 KaliFaktor Efisiensi Alat Fa 0.83 -
: M2
M2
Koefisien Alat / M2 = 1 : Q1
M2
Koefisien Alat / M2 = 1 : Q2
M2
Koefisien Alat / M2 = 1 : Q3
M3
M2
Koefisien Alat / M2 = 1 : Q4
M2
Koefisien Alat / M2 = 1 : Q5
URAIAN ANALISA HARGA SATUAN
ITEM PEMBAYARAN NO. : JENIS PEKERJAAN : AC -WC
SATUAN PEMBAYARAN Analisa El - 634
NO U R A I A N KODE KOEF. SATUAN KET.
Kapasitas Prod. / Jam = ( v x 1000 x b x Fa )/ n Q6 622.50
E-15 0.0016 Jam
2f. PNEUMATIC TIRE ROLLER ( PTR ) E-18Kecepatan alat rata-rata v 3.50 Km/JamLebar Efektif Pemadatan b 1.20 MJumlah Lintasan n 8.00 KaliFaktor Efisiensi Alat Fa 0.83 -
Kapasitas Prod. / Jam = ( v x 1000 x b x Fa ) / n Q7 435.75
E-18 0.0023 Jam
3. ALAT BANTUDiperlukan alat bantu :- Kerete dorong = 2 buah- Sekop = 3 buah- Garpu = 2 buah- Tongkat Kontrol Ketebalan Hamparan
4. TENAGA
Produksi Menentukan = AMP Q2 416.67
Produksi HRS / hari = Tk x Q2 Qt 2916.67Kebutuhan Tenaga :
- Pekerja P 10.00 Orang- Tukang T 0.00 Orang- Mandor M 1.00 Orang
- Pekerja = ( Tk x P ) / Qt L-01 0.0240 Jam- Tukang = ( Tk x T ) / Qt L-02 0.0000 Jam- Mandor = ( Tk x M ) / Qt L-03 0.0024 Jam
5. HARGA DASAR SATUAN UPAH, BAHAN DAN ALATLihat lampiran
6. ANALISA HARGA SATUAN PEKERJAANLihat perhitungan dalam Analisa Harga SatuanDidapat Harga Satuan Pekerjaan :
Rp. 149,548.72
7. WAKTU PELAKSANAAN YANG DIPERLUKANMasa Pelaksanaan : …………. Bulan
8. VOLUME PEKERJAAN YANG DIPERLUKAN
Volume Pekerjaan
: M2
M2
Koefisien Alat / M2 = 1 : Q6
M2
Koefisien Alat / M2 = 1 : Q7
M2/Jam
M2
Koefisien Tenaga / M2 :
/ m2
M2
A N A L I S A H A R G A S A T U A N
NO. PAKET KONTRAK :
NAMA PAKET :
NO. MATA PEMBAYARAN :
JENIS PEKERJAAN : GALIAN UNTUK DRAINASE, SELOKAN DAN SALURAN AIR
PERKIRAAN KUANTITAS :
SATUAN PEMBAYARAN : Meter Kubik TOTAL HARGA ( Rp ) :
% THDP BIAYA PROYEK :
No. U r a i a n SatuanPerkiraan Harga Satuan Jumlah Harga
Kuantitas (Rp) (Rp)
A TENAGA
1 Mandor (L03) jam 0.0198 14,285.71 282.19
2 Tukang (L02) jam 0.0000 11,428.57 0.00
3 Pekerja (L01) jam 0.1185 7,142.86 846.56
JUMLAH HARGA TENAGA 1,128.75
B BAHAN
( Tidak ada bahan yang digunakan )
JUMLAH HARGA BAHAN 0.00
C PERALATAN
1 Alat Bantu LS 1.0000 5,000.00 5,000.00
2 Excavator jam 0.0198 249,366.67 4,925.76
3 Dump Truck jam 0.1280 110,763.52 14,172.89
JUMLAH HARGA PERALATAN 24,098.65
D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 25,227.40
E BIAYA UMUM DAN KEUNTUNGAN ( 10% x D ) 2,522.74
F HARGA SATUAN PEKERJAAN ( D + E ) 27,750.14
1. Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, vulume dan / atau ukuran berat -
untuk bahan - bahan.
2. Kuantitas satuan adalah perkiraan dari setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran
3. Biaya Satuan untuk peralatan sudah termasuk bahan bakar, bahan habis terpakai oleh operator
4. Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang harus dibayar dari kontrak ) dan biaya - biaya lainnya.
A N A L I S A H A R G A S A T U A N
NO. PAKET KONTRAK :
NAMA PAKET :
NO. MATA PEMBAYARAN :
JENIS PEKERJAAN : PASANGAN BATU DENGAN MORTAR
PERKIRAAN KUANTITAS :
SATUAN PENGUKURAN : Meter Kubik TOTAL HARGA ( Rp ) :
% THDP BIAYA PROYEK :
No. U r a i a n SatuanPerkiraan Harga Satuan Jumlah Harga
Kuantitas (Rp) (Rp)
A TENAGA
1 Mandor (L03) jam 0.6311 14,285.71 9,015.65
2 Tukang (L02) jam 1.2622 11,428.57 14,425.05
3 Pekerja (L01) jam 1.2622 7,142.86 9,015.65
JUMLAH HARGA TENAGA 32,456.36
B BAHAN
1 Batu Kali 1.4400 175,000.0 252,000.00
2 Semen PC kg 100.8000 1,000.0 100,800.00
3 Pasir Pasangan 0.2263 100,000.0 22,634.73
JUMLAH HARGA BAHAN 375,434.73
C PERALATAN
1 Alat Bantu LS 1.0000 15,000.0 15,000.00
2 Concrete Mixer jam 0.6311 51,047.2 32,215.65
JUMLAH HARGA PERALATAN 47,215.65
D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 455,106.74
E BIAYA UMUM DAN KEUNTUNGAN ( 10% x D )
F HARGA SATUAN PEKERJAAN ( D + E ) 455,106.74
1. Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, vulume dan / atau ukuran berat -
untuk bahan - bahan.
2. Kuantitas satuan adalah perkiraan dari setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran
3. Biaya Satuan untuk peralatan sudah termasuk bahan bakar, bahan habis terpakai oleh operator
4. Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang harus dibayar dari kontrak ) dan biaya - biaya lainnya.
m3
m3
A N A L I S A H A R G A S A T U A N
NO. PAKET KONTRAK :
NAMA PAKET :
NO. MATA PEMBAYARAN :
JENIS PEKERJAAN : LAPIS PONDASI AGREGAT KELAS B
PERKIRAAN KUANTITAS :
SATUAN PENGUKURAN : Meter Kubik TOTAL HARGA ( Rp ) :
% THDP BIAYA PROYEK :
No. U r a i a n SatuanPerkiraan Harga Satuan Jumlah Harga
Kuantitas (Rp) (Rp)
A TENAGA
1 Mandor (L03) jam 0.0093 14,285.71 132.28
2 Tukang (L02) jam 0.0000 11,428.57 0.00
3 Pekerja (L01) jam 0.4537 7,142.86 3,240.74
JUMLAH HARGA TENAGA 3,373.02
B BAHAN
1 Agregat Kelas B 1.2000 184,892.79 221,871.35
JUMLAH HARGA BAHAN 221,871.35
C PERALATAN
1 Alat Bantu LS 1.0000 5,000.00 5,000.00
2 Wheel Loader jam 0.0093 250,481.99 2,319.28
3 Motor Grader jam 0.0220 315,261.92 6,924.05
4 Vibro Roller jam 0.0032 211,450.01 679.36
5 Water Tank Truck jam 0.0211 111,450.93 2,349.87
6 Dump Truck jam 0.0952 110,763.52 10,542.55
JUMLAH HARGA PERALATAN 27,815.11
D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 253,059.47
E BIAYA UMUM DAN KEUNTUNGAN ( 10% x D ) 25,305.95
F HARGA SATUAN PEKERJAAN ( D + E ) 278,365.42
1. Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, vulume dan / atau ukuran berat -
untuk bahan - bahan.
2. Kuantitas satuan adalah perkiraan dari setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran
3. Biaya Satuan untuk peralatan sudah termasuk bahan bakar, bahan habis terpakai oleh operator
4. Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang harus dibayar dari kontrak ) dan biaya - biaya lainnya.
m3
A N A L I S A H A R G A S A T U A N
NO. PAKET KONTRAK :
NAMA PAKET :
NO. MATA PEMBAYARAN :
JENIS PEKERJAAN : LAPIS PONDASI AGREGAT KELAS A
PERKIRAAN KUANTITAS :
SATUAN PENGUKURAN : Meter Kubik TOTAL HARGA ( Rp ) :
% THDP BIAYA PROYEK :
No. U r a i a n SatuanPerkiraan Harga Satuan Jumlah Harga
Kuantitas (Rp) (Rp)
A TENAGA
1 Mandor (L03) jam 0.0324 14,285.71 462.96
2 Tukang (L02) jam 0.0000 11,428.57 0.00
3 Pekerja (L01) jam 1.5880 7,142.86 11,342.59
JUMLAH HARGA TENAGA 11,805.56
B BAHAN
1 Agregat Kelas A 1.2000 212,409.19 254,891.02
JUMLAH HARGA BAHAN 254,891.02
C PERALATAN
1 Alat Bantu LS 1.0000 5,000.00 5,000.00
2 Wheel Loader jam 0.0324 250,481.99 8,117.47
3 Motor Grader jam 0.0088 315,261.92 2,769.62
4 Vibratory Roller jam 0.0111 211,450.01 2,349.44
6 Water Tank Truck jam 0.0211 111,450.93 2,349.87
7 Dump Truck jam 0.1313 110,763.52 14,546.05
JUMLAH HARGA PERALATAN 35,132.46
D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 301,829.04
E BIAYA UMUM DAN KEUNTUNGAN ( 10% x D ) 30,182.90
F HARGA SATUAN PEKERJAAN ( D + E ) 332,011.94
1. Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, vulume dan / atau ukuran berat -
untuk bahan - bahan.
2. Kuantitas satuan adalah perkiraan dari setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran
3. Biaya Satuan untuk peralatan sudah termasuk bahan bakar, bahan habis terpakai oleh operator
4. Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang harus dibayar dari kontrak ) dan biaya - biaya lainnya.
m3
A N A L I S A H A R G A S A T U A N
NO. PAKET KONTRAK :
NAMA PAKET :
NO. MATA PEMBAYARAN :
JENIS PEKERJAAN : LAPIS RESAP PENGIKAT (PRIME COAT)
PERKIRAAN KUANTITAS :
SATUAN PENGUKURAN : Liter TOTAL HARGA ( Rp ) :
% THDP BIAYA PROYEK :
No. U r a i a n SatuanPerkiraan Harga Satuan Jumlah Harga
Kuantitas (Rp) (Rp)
A TENAGA
1 Mandor (L03) jam 0.0048 14,285.71 68.85
2 Tukang (L02) jam 0.0000 11,428.57 0.00
3 Pekerja (L01) jam 0.0241 7,142.86 172.12
JUMLAH HARGA TENAGA 240.96
B BAHAN
1 Aspal kg 0.6468 16,000.00 10,348.80
2 Minyak Tanah ltr 0.4840 10,000.00 4,840.00
JUMLAH HARGA BAHAN 15,188.80
C PERALATAN
1 Asphalt Sprayer jam 0.0024 110,779.87 266.94
2 Compressor jam 0.0031 99,405.07 310.64
3 Dump Truck jam 0.0024 110,763.52 266.90
JUMLAH HARGA PERALATAN 844.48
D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 16,274.24
E BIAYA UMUM DAN KEUNTUNGAN ( 10% x D ) 1,627.42
F HARGA SATUAN PEKERJAAN ( D + E ) 17,901.67
1. Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, vulume dan / atau ukuran berat -
untuk bahan - bahan.
2. Kuantitas satuan adalah perkiraan dari setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran
3. Biaya Satuan untuk peralatan sudah termasuk bahan bakar, bahan habis terpakai oleh operator
4. Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang harus dibayar dari kontrak ) dan biaya - biaya lainnya.
A N A L I S A H A R G A S A T U A N
NO. PAKET KONTRAK :
NAMA PAKET :
NO. MATA PEMBAYARAN :
JENIS PEKERJAAN : LAPIS PEREKAT (TAKE COAT)
PERKIRAAN KUANTITAS :
SATUAN PENGUKURAN : Liter TOTAL HARGA ( Rp ) :
% THDP BIAYA PROYEK :
No. U r a i a n SatuanPerkiraan Harga Satuan Jumlah Harga
Kuantitas (Rp) (Rp)
A TENAGA
1 Mandor (L03) jam 0.0048 14,285.71 68.85
2 Tukang (L02) jam 0.0000 11,428.57 0.00
3 Pekerja (L01) jam 0.1687 7,142.86 1,204.82
JUMLAH HARGA TENAGA 1,273.67
B BAHAN
1 Aspal kg 0.8894 16,000.00 14,229.60
2 Minyak Tanah ltr 0.2530 10,000.00 2,530.00
JUMLAH HARGA BAHAN 16,759.60
C PERALATAN
1 Asphalt Sprayer jam 0.0024 110,779.87 266.94
2 Compressor jam 0.0063 99,405.07 621.28
3 Dump Truck jam 0.0024 110,763.52 266.90
JUMLAH HARGA PERALATAN 1,155.12
D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 19,188.39
E BIAYA UMUM DAN KEUNTUNGAN ( 10% x D ) 1,918.84
F HARGA SATUAN PEKERJAAN ( D + E ) 21,107.23
1. Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, vulume dan / atau ukuran berat -
untuk bahan - bahan.
2. Kuantitas satuan adalah perkiraan dari setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran
3. Biaya Satuan untuk peralatan sudah termasuk bahan bakar, bahan habis terpakai oleh operator
4. Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang harus dibayar dari kontrak ) dan biaya - biaya lainnya.
A N A L I S A H A R G A S A T U A N
NO. PAKET KONTRAK :
NAMA PAKET :
NO. MATA PEMBAYARAN :
JENIS PEKERJAAN : AC BC
PERKIRAAN KUANTITAS :
SATUAN PENGUKURAN : M 3 TOTAL HARGA ( Rp ) :
% THDP BIAYA PROYEK :
No. U r a i a n SatuanPerkiraan Harga Satuan Jumlah Harga
Kuantitas (Rp) (Rp)
A TENAGA
1 Mandor (L03) jam 0.0613 14,285.71 876.19
2 Tukang (L02) jam 0.0000 11,428.57 0.00
3 Pekerja (L01) jam 0.4293 7,142.86 3,066.67
JUMLAH HARGA TENAGA 3,942.86
B BAHAN
1 Agregat Kasar 0.7028 245,000.00 172,180.56
2 Agregat Halus 0.5098 245,000.00 124,909.17
3 Filler kg 139.1500 1,500.00 208,725.00
4 Aspal kg 156.9750 16,000.00 2,511,600.00
JUMLAH HARGA BAHAN 3,017,414.72
C PERALATAN
1 Alat Bantu LS 1.0000 5,000.00 5,000.00
2 Wheel Loader jam 0.0197 250,481.99 4,939.20
3 Asphalt Mixing Plant ( AMP ) jam 0.0613 1,174,688.15 72,047.54
4 Generator Set jam 0.0613 130,654.80 8,013.49
5 Asphalt Finisher jam 0.0693 249,958.71 17,316.42
6 Pneumatic Tire Roller jam 0.0257 170,428.80 4,380.50
7 Tandem Roller jam 0.0344 186,759.24 6,428.89
8 Dump Truck jam 0.4503 110,763.52 49,876.95
JUMLAH HARGA PERALATAN 168,002.99
D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 3,189,360.57
E BIAYA UMUM DAN KEUNTUNGAN ( 10% x D ) 318,936.06
F HARGA SATUAN PEKERJAAN ( D + E ) 3,508,296.62
1. Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, vulume dan / atau ukuran berat -
untuk bahan - bahan.
2. Kuantitas satuan adalah perkiraan dari setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran
3. Biaya Satuan untuk peralatan sudah termasuk bahan bakar, bahan habis terpakai oleh operator
4. Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang harus dibayar dari kontrak ) dan biaya - biaya lainnya.
m3
m3
A N A L I S A H A R G A S A T U A N
NO. PAKET KONTRAK :
NAMA PAKET :
NO. MATA PEMBAYARAN :
JENIS PEKERJAAN : AC WC
PERKIRAAN KUANTITAS :
SATUAN PENGUKURAN : M 2 TOTAL HARGA ( Rp ) :
% THDP BIAYA PROYEK :
No. U r a i a n SatuanPerkiraan Harga Satuan Jumlah Harga
Kuantitas (Rp) (Rp)
A TENAGA
1 Mandor (L03) jam 0.0024 14,285.71 34.29
2 Tukang (L02) jam 0.0000 11,428.57 0.00
3 Pekerja (L01) jam 0.0240 7,142.86 171.43
JUMLAH HARGA TENAGA 205.71
B BAHAN
1 Agregat Kasar 0.0336 245,000.00 8,239.96
2 Agregat Halus 0.0149 245,000.00 3,638.25
3 Filler kg 4.8015 1,500.00 7,202.25
4 Aspal kg 6.6150 16,000.00 105,840.00
JUMLAH HARGA BAHAN 124,920.46
C PERALATAN
1 Alat Bantu LS 1.0000 5,000.00 5,000.00
2 Wheel Loader jam 0.0007 250,481.99 174.64
3 Asphalt Mixing Plant ( AMP ) jam 0.0024 1,174,688.15 2,819.25
4 Generator Set jam 0.0024 130,654.80 313.57
5 Asphalt Finisher jam 0.0027 249,958.71 677.60
6 Pneumatic Tire Roller jam 0.0023 170,428.80 391.12
7 Tandem Roller jam 0.0016 186,759.24 300.01
8 Dump Truck jam 0.0104 110,763.52 1,151.01
JUMLAH HARGA PERALATAN 10,827.20
D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 135,953.38
E BIAYA UMUM DAN KEUNTUNGAN ( 10% x D ) 13,595.34
F HARGA SATUAN PEKERJAAN ( D + E ) 149,548.72
1. Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, vulume dan / atau ukuran berat -
untuk bahan - bahan.
2. Kuantitas satuan adalah perkiraan dari setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran
3. Biaya Satuan untuk peralatan sudah termasuk bahan bakar, bahan habis terpakai oleh operator
4. Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang harus dibayar dari kontrak ) dan biaya - biaya lainnya.
m3
m3
DAFTAR HARGA PEKERJAAN
No. Paket Kontrak :
Nama Paket
Prop / Kab / Kodya
Nama Peserta Lelang :
Harga Satuan Jumlah HargaNo Uraian Satuan Kuantitas
( Rp ) ( Rp )
a b c d e f = ( d x e )
1 Galian Saluran m 3 5,400.00 27,750.14 149,850,729.72
2 Pasangan Batu dan Mortar m 3 2,880.00 455,106.74 1,310,707,406.10
3 Pek. LPB m 3 3,000.00 278,365.42 835,096,258.22
4 Pek. LPA m 3 2,250.00 332,011.94 747,026,869.98
5 Pek. Lapis Pengikat (Prime Coat) Liter 12,750.00 17,901.67 228,246,274.46
6 Pek. Lapis AC-BC m 3 750.00 3,508,296.62 2,631,222,467.55
7 Pek. Lapis Perekat (Take Coat) Liter 5,250.00 21,107.23 110,812,936.31 `
8 Pek. Lapis AC-WC m 2 15,000.00 149,548.72 2,243,230,777.61
REKAPITULASIDAFTAR KUANTITAS DAN HARGA
No. Paket Kontrak :
Nama Kontrak : SANGATTA
Prop / Kab / Kodya :
Nama Peserta Lelang :
NoJ u m l a h
U r a i a n Harga Penawaran
Divisi ( Rp )
1 Galian Saluran 149,850,729.72
2 Pasangan Batu dan Mortar 1,310,707,406.10
3 Pek. LPB 835,096,258.22
4 Pek. LPA 747,026,869.98
5 Pek. Lapis Pengikat (Prime Coat) 228,246,274.46
6 Pek. Lapis AC-BC 2,631,222,467.55
7 Pek. Lapis Perekat (Take Coat) 110,812,936.31
8 Pek. Lapis AC-WC 2,243,230,777.61
(A) Jumlah Harga ( Termasuk Biaya Umum dan Keuntungan ) 8,256,193,719.96
(B) Pajak Pertambahan Nilai (PPN) = 10 % x (A) 825,619,372.00
(C) JUMLAH TOTAL HARGA = (A) + (B) 9,081,813,091.95
(D) JUMLAH TOTAL HARGA DIBULATKAN 9,081,813,000.00
Terbilang : Sembilan Milyar Delapan Puluh Satu Juta -
Delapan Ratus Tiga Belas Ribu Rupiah.-