NECESSITY OF GEOTECHNICALINSTRUMENTATION
FINDING OUT THE ENGINEERING PROPERTIES OF THE
SOIL.
MODIFYING THE ENGINEERING PROPERTIES OF THE SOIL
TO THE DESIRED LEVEL.
DESIGN OF THE STRUCTURE BASED ON THE PROPERTIES.
MONITORING THE GEOTECHNICAL CONDITIONS OR
BEHAVIOR OF THE STRUCTURE DURING THE
CONSTRUCTION PROCESS.
CHANGES IN THE DESIGN BASED ON THE BEHAVIOR.2
SOU
RABH
JAIN
IMPORTANCE OF MONITERING INSTRUMENTS
TO OBSERVE THE BEHAVIOR OF THE STRUCTURE
MONITORING INSTRUMENTS ARE REQUIRED .
INSTRUMENTATION IS A TOOL TO ASSIST WITH THESE
OBSERVATIONS. THEY ARE OUR EYES AND EARS INSIDE
THE ROCK.
INSTRUMENTATION IS USED TO MEASURE THE RESPONSE
(DEFORMATION, STRESS ETC.) OF SOIL OR ROCK TO
CHANGES IN LOADING OR SUPPORT ARRANGEMENTS,
AND FROM THE MEASUREMENTS TAKEN, THE NEED FOR
MODIFICATIONS TO THE LOADING OR SUPPORT
ARRANGEMENTS IS DETERMINED.3
SOU
RABH
JAIN
PURPOSE OF GOOD INSTRUMENTATION
SITE INVESTIGATION.
DESIGN VERIFICATION
CONSTRUCTION CONTROL
SAFETY
LEGAL PROTECTION
PERFORMANCE
4
SOU
RABH
JAIN
SITE INVESTIGATION.
Instruments are used to characterize and determine initial site
conditions.
Common parameters of interest in a site investigation are pore
pressure, permeability of soil, slope stability etc.
5
SOU
RABH
JAIN
DESIGN VERIFICATION
Instruments are used to verify design assumptions.
Instrumentation data from the initial stage of a project may show the
need or provide the opportunity to modify the design in later stages.
For example, data obtained from NATM shotcrete cells in the initial
stretch of tunnel is used to revise the thickness of shotcrete in the
later stages.
6
SOU
RABH
JAIN
CONSTRUCTION CONTROL
Instruments are installed to monitor the effects of construction.
Instrument data helps the engineer to determine how fast
construction can proceed without adverse effects on the foundation
soil and construction materials used.
For example, in tunnel construction, the data obtained from the load
cells helps the geotechnical engineer to know if the stresses in the
excavated tunnel have been stabilized and how fast he can proceed
with further excavation.
7
SOU
RABH
JAIN
SAFETY
Instruments can provide early warning of impending failure.
In case of metro railway tunnels instruments provide early
warning through real time monitoring systems available on the
internet for any excessive and undue ground movements
affecting the adjoining premises, structure and utilities like the
railways, power lines, water lines etc.
within the zone of influence of the excavations or tunnels. This
allows for implementation of preventive remedial actions well
within time.8
SOU
RABH
JAIN
LEGAL PROTECTION
Instruments provide designers and contractors the basis of a
legal defence should resident and owners of adjacent properties
blame construction for damage to their property and life.
This aspect gains prominence in constructions in populated
areas such as for underground metro railways
9
SOU
RABH
JAIN
PERFORMANCE
Instruments are used to monitor the in-service performance of
a structure.
For example, monitoring leakage, pore water pressure and
deformation can provide an indication of the perform bolts and
movements within a tunnel can provide an indication of the
stability of tunnel.
10
SOU
RABH
JAINMONITERING EQUIPMENTS
11
SOU
RABH
JAIN
ROOF TO FLOOR CONVERGENCE MEASUREMENT
Used to measure deformation in tunnels by measuring contraction ( or elongation )Procedure : Measurements are taken by simply stretching the telescopic rodbetween the reference points, and reading the graduations on the rod. Theseindicators are useful for understanding the roof to floor closure in the advancegalleries at various stages of extraction.
TELESCOPICCONVERGENCE ROD
12
SOU
RABH
JAIN
Chart Type Convergence Recorder
13
SOU
RABH
JAIN
REMOTE CONVERGENCEINDICATOR
• For monitoring convergence in roof
• Sensor – Vibrating wire type or Potentiometric type
• Needs laying of wire from instrument location to measurement site
• Fails immediately with the failure of immediate roof
14
SOU
RABH
JAIN
STRATA MONITORING BY TELL TALES
• Tell tale is strata – extensometer. • It provides pre-emptive warning of roof-falling. • The dual-height tell tale provides an immediate visible
warning, distinguishing between movement above and below rock-bolted height.
TYPES• Single height tell tale• Dual height tell tale• Three point tell tale• Four point tell tale• Rotary tell tale
15
SOU
RABH
JAIN
SINGLE HEIGHT TELL TALE
• It comprises a strata movement indicator usually with color bands and/or graduations.
• a mechanical tell tale consists of a strata movement indicator positioned in the mouth of a drilled hole and attached to an anchor installed up the hole
16
SOU
RABH
JAIN
Dual height tell tale
• Dual Height tell tale is designed to be installed for monitoring the bolted strata. • They have two versions –
one for dry drill holes and the other for watery drill holes. • This is designed to be
installed following the installation of roof bolt reinforcement. 17
SOU
RABH
JAIN
SAFETY MONITORING
18
SOU
RABH
JAIN
ACTION LEVELS• GREEN 0 - 25 mm• YELLOW 25 - 50 mm• RED 50 mm +ACTIONS• GREEN No action required, continue routine monitoring• YELLOW Identify height of softening [HOS]. If HOS is above bolts, install longer reinforcement. If below top of bolts, install additional standard length reinforcement to increase density of support.• RED Restrict access. Investigate. Install longer reinforcement 19
SOU
RABH
JAIN
Rotary Tell tale Extensometer
• It is useful where the conventional method of Roof support system is not convenient or possible.
• Movement of the strata is indicated with a magnification of 1:15.• It gives visual indication to a workman regarding the status of
Roof stability.• Rapid and simple to install.• Rotary type are useful for variable depth.
20
SOU
RABH
JAIN
MAGNET EXTENSOMETER
• The Magnet Extensometer consists of a series of magnets that are installed with an access pipe.
• The magnets are anchored at specified depths.
• Measurements are taken by lowering a probe through the access pipe to detect the depth of the magnets.
21
SOU
RABH
JAIN
VIBRATING WIRE LOAD CELLS• The load cell is a transducer working
on vibrating-wire principle.• It has three stretched wires housed in
a metal cylinder, which are plucked by an electric pulse of high energy.
• Changes in the load exerted on the cell cause changes in the length of the wire, resulting in variations of frequency of vibration of the wire.
• As the load increases the frequency decreases accordingly and vice-versa.
• This frequency is measured by a digital read-out unit, and is converted into load using calibration charts. Efficacy and adequacy of the support system can be inferred on the basis of these load cells. 22
SOU
RABH
JAIN
ROCKBOLT LOAD CELL
• The load cell is a transducer working on vibrating-wire principle.
• The load cells should be installed under the roof bolts using specially prepared steel seating arrangement .
• The load cells should be installed at the junctions to understand the change in load over the roof bolt during the operation.
23
SOU
RABH
JAIN
Mechanical Load Cell
• Load cell consists of an elastic disc element sandwiched between two plates.
• The disc deflects under load and changes distance between plates.
• The deflection is measured with a dial gauge or suitable electronic transduced.
• It has limited application due to nonlinear calibration curve and restricted application.
24
SOU
RABH
JAIN
STRESS CELL
• Principle : These are used for measuring unidirectional stress change in the pillar. It consists essentially of a wire tensioned across a steel cylinder (38 mm diameter). As the stress within the rock/coal changes, the cylinder deforms, causing tension in the wire to change.
• Procedure : A bore hole of 38 mm diameter is required for installing the stress meters, preferably at mid height of the pillar either horizontally or slightly rising/dipping according to dip of the seam. The stress meter along with wedge and platen assembly is set in the borehole with the help of special installation tools, at a depth of about 4 to 9 m. 25
SOU
RABH
JAINSafety aspects
26
SOU
RABH
JAIN
Scope and application
The rule applies to construction of underground tunnels, shafts,chambers, and passageways. It also applies to cut-and-coverexcavations, both those physically connected to tunnels and those thatcreate conditions characteristic of underground construction. Hazardscommon to such work include reduced natural ventilation and light,difficult or limited access and egress, exposure to air contaminants,fire, and explosion
27
SOU
RABH
JAIN
Provisions of the standard• The standard gives employers the flexibility to select from a variety
of appropriate and effective methods of controlling workplace hazards
• In underground construction. It includes a safety program focusing on instructing workers in topics appropriate to specific jobsites
• And it gives specific duties and responsibilities to a “competent person.”
28
SOU
RABH
JAIN
Competent person
• A “competent person” is one capable of identifying existing and predictable workplace hazards who is authorized to take corrective
• action to eliminate them• Duties of competent person
• Monitoring air • Inspecting the work area for ground stability • Inspecting all drilling equipment prior to each use • Inspecting hauling equipment before each shift and visually checking all hoisting machinery, equipment, anchorages, and rope at the beginning of each shift and during hoisting
29
SOU
RABH
JAIN
Safety instruction• Employers must ensure that workers are instructed on
the recognition• and avoidance of hazards associated with underground
construction.• Instruction must include the following topics that are
appropriate to• each jobsite:
• Air monitoring • Ventilation and illumination • Communications • Flood control • Mechanical and personal protective equipment • Explosives: fire prevention and protection • Emergency procedures: evacuation plans and check-in/check- out procedures
30
SOU
RABH
JAIN
Access and egress
• Employers must provide safe access to and egress from all
workstations and prevent unauthorized underground entry. Completed
• Unused sections of an underground work area must be barricaded.
• Unused openings must be covered, fenced off, or posted with warning
• signs indicating “Keep Out” or other appropriate language
31
SOU
RABH
JAIN
Check-in/check-out• Employers must maintain a check-in/check-out procedure that
ensures above-ground personnel can maintain an accurate
count of people who are underground, in case of an emergency.
At least one
• Designated person must be on duty at the surface whenever
anyone is working underground. That person is responsible for
securing
• Immediate aid in case of an emergency
32
SOU
RABH
JAIN
Gassy operations• • Using more-stringent ventilation requirements
• • Using only diesel equipment approved for use in gassy operations
• • Posting each entrance with warning signs and prohibiting
smoking and personal sources of ignition
• • Maintaining a fire watch when hot work is performed
• • Suspending all operations in the affected area until all special
requirements are met or the operation is declassified
• Additional air monitoring is also required during gassy conditions
33
SOU
RABH
JAIN
SPECIAL AIR MONITORING REQUIREMENTS
• The employer must assign a "competent person" to perform air
monitoring. If this individual determines that air contaminants may
present a danger to life at any time, the employer must
immediately take all necessary precautions and post a notice at all
entrances to the underground site about the hazardous condition
and his responsible for checking air quality
test for oxygen first
testing for methane and other flammable gases
hydrogen sulfide levels34
SOU
RABH
JAIN
Illumination• As in all construction operations, the rule requires that proper
illumination be provided during tunneling operations, as
specified
• When explosives are being handled, acceptable portable
lighting equipment must be used within 50 feet of any
underground heading
35
SOU
RABH
JAIN
Fire prevention and control
• open flames and fires are prohibited in all underground
construction activities, except for hot-work operations.
• Smoking is allowed only in areas free of fire and explosion hazards.
• Employers must post signs prohibiting smoking and open flames
where such hazards exist
• Gases such as acetylene, liquefied petroleum, and methyl acetylene
propadiene (stabilized), may be used underground only for hot-
work operations.
• Leaks and spills of flammable or combustible fluids must be
cleaned up immediately.36
SOU
RABH
JAIN
Safety provisions• —IS: 4756:- 1978 – Safety Code for Tunnelling work• —IS: 3764 –1966 – Safety Code for Excavation work• —IS: 4081-1986 – Safety Code for Blasting and Related drilling
operations• —IS: 4138-1977 – Safety Code for Working on Compressed Air• —IS: 7293-1974 – Safety Code for Working with Construction
Machinery• —IS: 5878 (Various parts) – Codes of practices relating to
tunnelling and underground excavations• —Indian Explosive Act -1988• —Indian Explosive Rules -1983
37
SOU
RABH
JAIN
Lighting:
38
SOU
RABH
JAIN
• Minimum 50 lux at headings during drilling, mucking 70 m.and scaling.
• Minimum 30 lux for trolley track working area.• Minimum 10 lux for other areas inside the tunnel or on
approach cut/roads.• Emergency lights (battery operated) at the working faces and
at regular interval along the tunnel.• Proper earthling and grounding of all electrical apparatus.
39
SOU
RABH
JAIN
Medical facilities:• First Aid box with experienced first aid attendant with his
distinguishing badge on each shift.• Stretchers in every shift at portal.
40
SOU
RABH
JAIN
Protective wear:• Helmet, steel tow safety shop, gum boots for each worker. • Sign boards 1x1.5m in size to be displayed at the approach
“Construction AREA, HELMET required beyond this point”
41
SOU
RABH
JAIN
Notices and signs:
42
SOU
RABH
JAIN
Telephone System:
• For communication between control locations inside tunnel and portal (when more than 500m)
43
SOU
RABH
JAIN
Ventilation• Essential to make working space safe for workers by keeping
the air fresh and repairable and by eliminating harmful and obnoxious dust, dynamite fumes and other gases. Mechanical ventilation must be used for long tunnels.
44
SOU
RABH
JAIN
• It is essential to ensure • Temp < 40 C dry and < 29 C wet at the working place.• Concentration of gases in side the tunnel by volume a) Oxygen not less than 19.5% b) Carbon monoxide not more than 0.005% c) Carbon Dioxide not more than 0.5% d) Hydrogen Sulphide not more than 0.001%
45
SOU
RABH
JAIN
Sanitation and Drinking Water
• Sanitation - Unless the worksite is within 500 m of the portal of the tunnel, sanitation facilities shall be provided close by.• Drinking Water- Drinking water, at least 5 litre per person employed in the shift, shall he provided near the portal and
also inside the longer tunnels.• Washing and cleaning facilities shall be provided for all
workers near the portal.
46
SOU
RABH
JAIN
Risk register
47
SOU
RABH
JAIN
Emergency Planning & Mitigation of Risk
• to ensure safety of tunnel workers and other stakeholders• A culture of safety can be enhanced by in-house training,
communication through toolbox meetings and display of procedures and escape plans on notice boards.
• table top exercise and regular drills shall be conducted once in every six months.
• Accountability for safety performance must be appropriately allocated through the entire safety management process, in particular to the emergency plan
48
SOU
RABH
JAIN
49
SOU
RABH
JAIN
50
SOU
RABH
JAIN
Safety measures for blasting• Based on IS :4081- 1986.• No metals except approved metal truck bodies shall be
allowed to come in contact with cases of explosives. • Blasting caps, electric blasting caps or primers shall not be
stored in the same box, container or room with other explosives.
• Smoking shall be prohibited in the storage area of explosives and in its vicinity.
• Packages containing explosives shall not be allowed to remain in the sun.
• Explosives shall not be carried in the pockets or folds of clothing by any person. 51
SOU
RABH
JAIN
• All electrical wiring and equipment of storage area shall be adequately insulated and protected against mechanical damage to prevent short-circuiting.
• Children and unauthorized or unnecessary persons shall not be present where explosives are being handled or used.
52
SOU
RABH
JAIN
Safety measures for drilling• No drilling shall be started until previous holes in the blasted
area are flushed with air and water. • While planning drilling operations for blasting purposes,
consideration must be given to the nature of stratum and the overburden with a view to avoiding the possibilities of land-slides after blasting.
• The position of all holes to be drilled shall be marked out with white paint.
• The face of rock shall be carefully examined before drilling, to determine the possible presence of unfired explosive.
• The diameter of the bore of each hole shall be greater than the outside diameter of the cartridges of explosive. 53
SOU
RABH
JAIN
• explosives shall not be forced down a bore hole or on obstruction in a bore hole.
• A bore hole near another hole loaded with explosives shall not be sprung.
• No holes shall be loaded except those to be fired on the next round of blasting and after blasting.
• Drilling shall not be resumed after blasts have been fired until a thorough examination has been made.