Transcript
  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    1/160

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    2/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy

    Copyright 2014

    Developed by Plankton Investment Private Limited for the Low Emission Climate ResilientDevelopment Programme (LECRED) and commissioned by United Nations Development

    Programme in the Maldives

    All rights reserved. The document or extracts from this publication may, however, be freely

    reviewed, quoted, reproduced or translated, in part or in full, provided the source is given

    due acknowledgement. The views expressed in this publication are those of the author(s) and

    do not necessarily represent those of the United Nations, including UNDP, or their Member

    States.

    Published by: United Nations Development Programme in the Maldives

    Cover and Layout design by: Plankton Investment Private Limited

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    3/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 1

    Table of contents

    EXECUTIVE SUMMARY 4

    ABBREVIATION 6

    1 BACKGROUND 8

    2 MALDIVES POWER SECTOR 10

    2.1 ENERGY SECTOR INSTITUTIONAL FRAMEWORK 10

    2.2 POLICY, LEGAL AND REGULATORY CONTEXT 11

    2.2.1 MALDIVES NATIONAL ENERGY POLICY AND STRATEGY 2010 11

    2.2.2 LEGAL AND REGULATORY BACKGROUND 11

    2.2.3 ELECTRICITY TARIFF STRUCTURE 122.3 ENERGY SUPPLY 13

    3 THE PROJECT 14

    3.1 PROJECT LOCATION 14

    3.2 METHODOLOGY 15

    4 SOCIO-ECONOMIC CONTEXT OF THE PROJECT LOCATION 16

    4.1 GANISLAND 194.2 FONADHOO ISLAND 20

    5 EXISTING POWER SYSTEMS 21

    5.1 POWER SYSTEM OF GAN 21

    5.2 POWER SYSTEM OF THUNDI 21

    5.3 POWER SYSTEM OF MAAHINNA 22

    5.4 POWER SYSTEM OF MATHIMARADHOO 23

    5.5 POWER SYSTEM OF MUKURIMAGU 24

    5.6 POWER SYSTEM OF FONADHOO 255.7 OTHER POWER PRODUCERS 26

    6 LOAD FORECAST AND AVAILABLE CAPACITY 28

    7 DEMAND FOR ELECTRICAL ENERGY 33

    7.1 ELECTRICITY DEMAND PATTERN 33

    8 RENEWABLE ENERGY OPTIONS 35

    8.1 WIND ENERGY 35

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    4/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 2

    8.2 OCEAN ENERGY 37

    8.3 WASTE HEAT RECOVERY 39

    8.4 BIOMASS 40

    8.5 WASTE TO ENERGY 41

    8.6 SOLAR ENERGY 42

    9 PROPOSED POWER SYSTEM FOR GAN FONADHOO 45

    10 ENVIRONMENTAL CONSIDERATIONS 48

    10.1 POWER PLANT LOCATION AND CLIMATE 48

    10.2 ENVIRONMENTAL ASPECTS OF DIESEL POWER PLANT 48

    10.3 EXHAUST EMISSION TO THE AIR 49

    10.4 IDENTIFYING AND ASSESSING THE IMPACTS 51

    10.5 ENVIRONMENTAL ASPECTS TO CONSIDER FOR THE PROJECT 51

    10.6 POSSIBLE ENVIRONMENTAL IMPACTS BY THE PROJECT 5210.6.1 MOBILIZATION 52

    10.6.2 FUEL MANAGEMENT 52

    10.6.3 COOLING WATER DISCHARGE 53

    10.6.4 ATMOSPHERIC EMISSIONS 53

    10.6.5 NOISE POLLUTION 54

    10.7 IMPACT ON MARINE ENVIRONMENT 54

    10.8 WAYS TO MINIMIZE IMPACTS 54

    10.8.1 MITIGATION ACTIONS DURING CONSTRUCTION 55

    10.8.2 MITIGATION ACTIONS DURING THE OPERATION 55

    10.9 MONITORING AND MAINTENANCE OF THE SYSTEM 55

    11 FINANCIAL AND ECONOMIC ANALYSIS 57

    11.1 INITIAL INVESTMENT BUDGET 57

    11.2 OPERATION COSTS 57

    11.3 SENSITIVITY TO THE CHANGES IN TARIFF 60

    11.4 USE OF SOLAR PHOTOVOLTAIC (PV) WITH THE NEW SYSTEM 61

    11.5 AVOIDANCE OF CO2 62

    12 RISK ANALYSIS 63

    13 PROJECT MANAGEMENT AND PROCUREMENT 64

    13.1 SCOPE OF BID 64

    13.2 SOURCE OF FUND 64

    13.3 ELIGIBLE BIDDERS 65

    13.4 INSTRUCTION TO BIDDERS 65

    13.5 GENERAL CONDITION OF THE CONTRACT 66

    13.6 GENERAL TECHNICAL REQUIREMENT 66

    13.7 CIVIL WORKS 67

    13.8 MECHANICAL WORKS 67

    13.9 ELECTRICAL WORKS 6813.10 INSTRUMENT AND CONTROL (I&C) 68

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    5/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 3

    14 PROPOSED ORGANIZATIONAL STRUCTURE FOR CPS 69

    14.1 ADMINISTRATIVE DEPARTMENT 69

    14.2 FINANCE AND ACCOUNTS DEPARTMENT 70

    14.3 POWER GENERATION AND DISTRIBUTION DEPARTMENT 70

    15 STAFF COMPETENCY AND TRAINING REQUIREMENT 71

    15.1 SITE TRAINING FOR POWER GENERATION AND DISTRIBUTION DEPARTMENT STAFF 71

    15.2 SPECIFIC TRAINING AT SITE FOR ELECTRICAL UNIT STAFF: 72

    15.3 SPECIFIC TRAINING AT FACTORY 72

    15.4 ADDITIONAL TRAINING AT SITE 73

    16 CONCLUSION 74

    ANNEX I

    ANNEX II

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    6/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 4

    Executive Summary

    The supply of quality electricity to the citizens of the Maldives is one of the top priorities of

    the Government of Maldives (GoM). In this regard, the Government of Maldives (GoM) is

    exploring the feasibility of constructing a Central Power System (CPS) in Laamu Atoll wherethe islands are connected by land. Under the Low Emission and Climate Resilient

    Development (LECReD) program, the project focuses on constructing a single CPS for

    providing power to all citizens ofGan-Fonadhoo in Laamu Atoll.

    The objective of this feasibility study is to assess the technical, institutional, regulatory,

    economic, financial and environmental aspects of the proposed central power station and

    distribution network to feed the local LV networks and intake of energy from appropriate

    renewable energy sources.

    Gan-Fonadhoo stretch consists of four districts of Gan Island, Fonadhoo Island, Maandhoo

    Island where a fish processing factory is operated and managed by Horizon Fisheries Private

    Limited and Kadhdhoo Islandwhere a domestic airport is operated by the Regional Airports.

    The power systems developed in the districts ofGan and Fonadhoo were developed as need

    based and in an ad-hoc manner. As a result, the power systems in these wards were not

    properly equipped, and the installed generator systems are poorly designed and engineered,

    leading to reduced life span of the power systems. The powerhouses and the equipment are

    not to the current standards and regulations of the Maldives. Existing facilities are undersized,

    inefficient and overloaded.

    Despite the poor quality of the power generation and distribution systems that exist in the

    stretch the demand for electricity has grown rapidly in the Gan-Fonadhoo stretch over the

    past years. The data indicates that there is a combined peak demand of 3.28 MW among all

    the islands.

    As the land stretch has potential for industrial activities within the stretch like demand for

    construction of guesthouses and related businesses, it is anticipated that the demand for the

    electricity will be increased considerably in the near future.

    The proposed central power station would provide reliable electricity to current and future

    electricity need within the stretch. The proposed generating capacity of 16MW (4 x 4 MW)

    and the medium voltage distribution network will enable power producer to relieve the

    present shortage and meet the anticipated increase in demand for electricity in Gan-

    Fonadhoo stretch. The new power station will also help to enhance the quality of supply

    through greater rehabilitation of LV network with improved efficiency.

    The new power station would be located on reclaimed land adjacent to the fish factory inLaamu Atoll. When commissioned it will take over as the base load station and will make

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    7/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 5

    possible to shut down the existing powerhouses located in the middle of the wards amidst

    commercial and residential properties. The new power station is expected to be in operation

    in 2018 and will be capable for extension to accommodate more generating units to meet

    future load increase. Additionally, the new power station will be designed to feed renewable

    energy. Therefore, cleaner energy production will occur within the scope of the project sideby side.

    The project will bring positive socio-economic and environmental benefits to the

    communities of Gan-Fonadhoo stretch. The introduction of solar energy for power

    generation will reduce the amount of emissions from diesel generators, which would

    contribute to a cleaner environment and less pollution. With oil prices continually rising and

    volatile, the reduction in specific consumption of diesel may lead to lower electricity costs in

    the long term.

    The total cost of the project without renewable component is estimated to be USD 29.50

    million. However, when the system is in operational this system will give an annual saving of

    MVR 5.9 million and it is expected to payback the investment in 9 years.

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    8/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 6

    Abbreviations

    Unit Description

    AC Alternating Current

    CCTV Closed Circuit TelevisionCHP Combined Heat and Power

    CO Carbon monoxide

    CO2 Carbon dioxide

    CPS Central Power Station

    CUF Capacity Utilization Factor

    dB(A) Sound Power in Decibels

    DC Direct Current

    ED Energy Department

    EIA Environmental Impact Assessment

    EPA Environmental Protection AgencyEPC Engineering, Procurement and Construction

    GDP Gross Domestic Product

    GoM Government of Maldives

    HSE Health, Safety and Environment

    IFC International Finance Corporation

    IPP Independent Power Provider

    IRR Internal Rate of Return

    JICA Japan International Corporation Agency

    kV Kilo Volt

    kW KilowattkWh Kilowatt hour

    LECReD Low Emission and Climate Resilient Development

    LED Light Emitting Diode

    LV Low Voltage

    MEA Maldives Energy Authority

    MED Multi Effect Distillation

    MEE Ministry of Environment and Energy

    MNDF Maldives National Defense Force

    MV Medium Voltage

    MVC Mechanical Vapor Compression

    MW Megawatt

    MWSC Male Water and Sewerage Company

    NEP National Energy Policy

    NMHC Non-Methane Hydrocarbons

    NO2 Nitrogen dioxide

    NOx Nitrogen oxides

    NREL National Renewable Energy Laboratory

    OTEC Ocean Thermal Energy Conversion

    O3

    Ozone

    Pb Lead

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    9/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 7

    PLC Programmable Logic Controller

    PV Photovoltaic

    RE Renewable Energy

    RMU Ring Main Unit

    SCADA Supervisory Control and Data Acquisition

    SIDS Small Island Developing States

    SO2 Sulphur dioxide

    SREP Scaling up Renewable Energy Program

    TFT Thin Film Transistor

    THC Total Hydrocarbons

    TVC Thermal Vapor Compression

    UPS Uninterrupted Power Supply

    VA Voltage Ampere

    VOC Volatile Organic Compound

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    10/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 8

    1 Background

    Maldives is an archipelago with 1,192 island1 and out of which only 188 islands are

    inhabited with a total population of 341,256. Out of total population 44.9% that is

    153,379 people live in the capital Male2. The development of infrastructure on localislands has been an urgent task for the government to alleviate this issue. Tourism and

    fisheries are two most important sectors of the economy. Tourism sectors contribute

    about 47.8% of the countrys gross domestic product (GDP)3. Given the low lying nature

    of the country Maldives are regularly exposed to multiple natural hazards such as

    storms, heavy rain, high waves and extended dry season.

    The Maldives contribution to greenhouse gas (GHG) at global level is very insignificant.

    Total carbon emissions in 2009 was 1.3 million tons of CO2 equivalent (tCO2)4. However,

    Maldives is one of the active country working on reducing negative impacts of climatechange and it has an objective to make the country develop on a low carbon economy.

    In this regard, Maldives is working to achieve energy security through a low carbon

    development path for climate change mitigation. To achieve the said objective,

    Maldives will use energy efficiency and indigenous renewable energy resources

    available in the country.

    In that respect, GoM has implemented and are implementing several projects. The first

    is on the use of renewable energy and energy efficiency to reduce carbon emissions

    from electricity generation.

    In Maldives each island have its own electric power generation and distribution system.

    The total installed power generation capacity in the country is around 245 megawatts5.

    Most of the installed capacity is in the resort islands, followed by the capital Male and

    surrounding islands. The remaining capacity is installed in the outer islands and in

    commercial islands.

    At present there are only few islands with renewable energy installations and as a result

    electricity is almost entirely generated using imported diesel. This poses the countrys

    energy security at threat and exposes it to high price volatility in the international

    market forcing government to provide subsidies on electricity.

    The Gan Island consist of four wards namely Thundi, Mathimaradhoo, Mukurimagu and

    Maahinna. In between Gan and Fonadhoo there is Kadhdhoo Island, where domestic

    airport is operated. Gan, Fonadhoo and Kadhdhoo are connected via causeway.

    1 Maldives Energy Outlook for Inhabited Islands, 2013

    2 Population and Housing Census, Preliminary Results, 20143 Travel & Tourism Economic Impact, 2014, Maldives4 Energy Supply and Demand Study, 20145 Maldives SREP Investment Plan, 2013-2017

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    11/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 9

    Fonadhoo is the atoll capital and one of the largest populated among the Islands in the

    atoll. Current population of the stretch is around 6,840 people about 1,094 of which are

    people working on resorts and industrial Islands.

    Provision of power supply for all inhabited Islands in Gan-Fonadhoo stretch is the

    responsibility of FENAKA Corporation Limited, which is a hundred percent government

    owned company. The utility, established in June 2012, is responsible for providing

    power, water and sewerage service for outer Atolls including the entire population of

    the stretch. Electricity generation in Gan-Fonadhoo stretch is supplied from diesel

    generators with total installed capacities of 6,450 kilowatts (kW).

    The cost of electricity supply in Gan-Fonadhoo stretch is high at around US$ 0.30/kWh.

    Fuel prices likely to continue to be on the rise, and coupled with an expected fuel

    surcharge which would be added to electricity consumers, solar electricity generation

    has been found to be an economically attractive option for Gan-Fonadhoo stretch

    together with energy efficiency measures.

    Alternative energy options in Gan-Fonadhoo stretch are limited. The most dominant

    indigenous renewable energy resource is solar which is available on a relatively uniform

    basis throughout the year. Average solar insolation for the Maldives is around 5.4

    kWh/m2 per day6.

    6 Modelling of Renewable Energy Systems in the Maldives, 2004

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    12/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 10

    2 Maldives Power Sector

    In the Maldives electricity is available for twenty four hours in each inhabited Island,

    tourist resorts and commercial Islands. Each of these Islands has its own power

    generation and distribution systems. Almost 99.2% of electricity is generated by usingdiesel and about 0.8% of electricity is generated from renewable sources. At present,

    the total installed capacity in inhabited islands of Maldives is around 140 MW from 191

    powerhouses7. The lack of any interconnection between islands means there is no

    opportunity yet to generate electricity on one island and supply to another.

    2.1 Energy Sector Institutional Framework

    Maldives has the most simplistic institutional framework in the energy sector. The sectorhas three main bodies, namely policy guiding body, regulatory body and service

    providing body.

    The policy guidance is primarily provided by the government ministry mandated with

    energy sector. In this regard, currently the mandate lies within the Ministry of

    Environment and Energy (MEE). The Energy Department (ED) within the ministry is

    responsible for formulating and implementing policies and appropriate legislations

    when required. In addition to this, MEE is also responsible for implementing projects

    and programs related to energy sector in the Maldives.

    The Maldives Energy Authority (MEA) is the regulatory body, which is mandated to

    standardize the energy sector in the Maldives. MEA is an independent authority loosely

    attached to MEE. However, the technical decisions of MEA is taken by the Governing

    Board of MEA. MEA is the institutional platform where both the policy guiding body

    (MEE) and service providing body meet.

    The service providing bodies are the utility companies. State Electricity Company

    Limited (STELCO) and FENAKA Corporation Limited are the two largest utility service

    providers in the Maldives. These two state owned companies provide electricity and

    other utility services to the residents and in some cases to the industrial islands or zones.

    However, it is to be noted that these two utilities do not compete to provide services

    and each has been given almost a geographical monopoly to provide public utility

    services for their assigned regions.

    7 Maldives Energy Outlook for Inhabited Islands 2013

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    13/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 11

    2.2 Policy, Legal and Regulatory Context

    The government has formulated a number of policy decisions, including the Maldives

    National Energy Policy & Strategy (2010), National Energy Action Plan (2009-2013) and

    Renewable Energy Investment Framework (2011) that have been adopted to guide thedevelopment of the energy sector in the Maldives. The country has also been designated

    for the Scaling up Renewable Energy Program (SREP).

    2.2.1 Maldives National Energy Policy and Strategy 2010

    The 2010 National Energy Policy (NEP) has been formulated by the Government of

    Maldives with the strategic objective of developing and diversifying its energy sector to

    build an affordable, sustainable, energy secure electricity sector. The strategies of the

    NEP includes:

    Enhancing national energy security,

    Diversifying the fuel technologies and reducing over-reliance of the energy sector

    on fossil fuels thereby encouraging and adoption of low carbon technologies and

    local energy resources,

    Ensuring compliance of energy sector utility companies/energy service providers

    with safety standards issued by Maldives Energy Authority as well as

    environmental standards stipulated by the Environmental Protection Agency,

    Promoting energy conservation and energy efficiency in both the supply side and

    demand side and encouraging private participation to provide impetus to thesame,

    Facilitating the implementation of a nationwide electricity grid to ensure parity in

    prices and quality of power,

    Promoting the use of indigenously and abundant available renewable energy

    resources for energy generation,

    Strengthening the Institutional and Legal Framework for the Energy Sector

    towards achieving the above mentioned targets.

    2.2.2 Legal and Regulatory Background

    Re-organization of the state-owned electricity utility responsible for power supply in

    Mal and nearby islands and restructuring of power sector and mandate of FENAKA

    corporation ltd were some of the significant changes in this sector which paved the way

    for immediate development of appropriate regulations. This also led to capacity building

    of MEA to regulate the sector.

    The Maldives Energy Authority is the lead agency for the overall regulatory framework

    for power sector in Maldives. The regulations of MEA are designed towards tariff setting,

    power quality and safety measures. Currently, MEA is coming up with the followingregulations (including draft phase):

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    14/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 12

    The Engineers Licensing Regulation which is designed to cover the following

    aspects:

    - Responsibilities of the Licensees;

    - Civil and criminal responsibilities of Licensees;

    - Licensing process;

    - Examination Board;

    - Code of Professional Conduct for Licensees

    Installation Standards Regulations for Electrical Installations & Standards for

    Generating Stations

    - Guideline for Grid connected PV System (2013)

    Investment Approval Regulations for Generation Licensees including IPPs,

    Transmission Licensees & Distribution Licensees

    The Electricity (Applications for Licenses and Exemptions) Regulations

    Metering Regulations:

    - Manual for PV Grid (connection application)

    The Service Providers will develop the following Aspects

    - Requirements for Service Provider License Insurance

    - Requirements for Generating Stations

    - Distribution Network Operation and Maintenance

    - Distribution Network Planning

    - Connection to the Distribution Network

    - Commercial Aspects & Disputes

    Acts and regulations like the formulation of Maldives Energy Act, a Maldives

    Hydrocarbon Exploration Act, Maldives Energy Standards and incorporation of energy

    efficiency and conservation measures is absent from the energy sector. Regulations

    related to environmental protection is enforced by the EPA.

    2.2.3 Electricity Tariff Structure

    In the Maldives, any set of principles or regulations to define the tariff setting

    mechanism for the utilities is not available and the cost recovery approach is followed

    when determining the tariff for utilities. However, in order to ensure that the utilities

    are not cash strapped and have resources for carrying out their business, a cost plus

    approach shall be considered for utilities. The aforementioned approach shall provide

    adequate returns to the utilities and help the utilities in carrying out their business in

    viable fashion. It is also to be noted that at present a Standard of Performance

    regulations for the utilities are not available. Table 2-1 shows current tariff structure

    used in Laamu Atoll.

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    15/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 13

    Table 2-1 Maldives Energy Authority Approved Tariff for Laamu Atoll (Source MEA, 2012)

    South Central Region (Th and L)

    Bands/category Domestic Business Government

    Band A (below 100 units) 3.75 4.50 4.75

    Bands B (101 200) 4.25 5.75 5.75

    Band C (201 300) 4.50 6.50 6.70

    Band D (above 301 units) 5.50 7.50 7.75

    Fuel surcharge: Rf 0.03/kWh per each Rf 0.10 increase in the fuel price when the fuel price goes above Rf

    8.10

    hhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhh

    h

    2.3 Energy Supply

    The total installed power generation capacity of diesel generators in the country in the

    year 2012 was about 245 MW. Of the total generation capacity 105 MW is installed in

    the tourist resorts, while 120 MW is installed in the inhabited islands of the atolls. 20MW is installed in industrial islands8.

    Each outer island is electrified with its own diesel powered mini grid system.

    The power supply systems in most of the islands have been developed on an ad-

    hoc basis by the island communities.

    Similar to most communities in Maldives, the power system in Gan-Fonadhoo stretch

    has been developed and operated by the communities. Table 2-2 provide the break-up

    of installed capacity, peak load and electricity production detail for Gan-Fonadhoo

    stretch.

    It is also observed that as per the reported figures the efficiency of the overall energy

    systems in the Laamu stretch is low and there might be lot of scope on energy efficiency

    measures on supply side.

    Table 2-2 Power plants in GanFonadhoo (Energy Outlook, 2013)

    PowerhouseService

    Provider

    Daily Peak Load

    (KW)

    Installed

    Total (kW)

    Annual Billed

    units (MWh/yr)

    Annual Fuel

    Consumption (kl/yr)

    Mathimaradhoo FENAKA 400 680 1,373.63 594.00

    Maahina FENAKA 160 280 846.11 343.80Thundi FENAKA 240 380 556.61 389.52

    Mukurimagu FENAKA 160 390 592.81 252.00

    Fonadhoo FENAKA 425 1110 2,424.34 720.00

    Maandhoo PRIVATE 1800 3000 - 1900.00

    Kadhdhoo PRIVATE 65 400 - 150.00

    MNDF PRIVATE 50 210 - 109.00

    Total - 3300 6450 5,793.49 4458.32

    8 Maldives SREP Investment Plan, 2013-2017

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    16/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 14

    3 The Project

    The supply of quality electricity to the citizens of the Maldives is one of the top priorities

    of the Government of Maldives (GoM). Based on the evidence and experience from the

    CPS in Addu City, the Government of Maldives (GoM) is exploring the feasibility ofconstructing another CPS in Laamu Atoll where the islands are connected by land. Under

    the Low Emission and Climate Resilient Development (LECReD) program, the project

    focuses in constructing a single CPS for providing power to all citizens ofGan-Fonadhoo

    in Laamu Atoll.

    The objective of this feasibility study is to assess the technical, institutional, regulatory,

    economic, financial and environmental aspects of the proposed central power station

    and distribution network to feed the local LV networks and intake of energy from

    appropriate renewable energy sources.

    3.1 Project Location

    Maldives is located geographically 7635N to 04224S in Indian Ocean (Kench 2011).

    Maldivian archipelago comprises of 22 atolls with 1,192 Islands and is 1,000 km long and

    200 km wide (MEC 2004). The size of Maldives atolls varies from 1.4 to 2,800 sq. km and

    atoll basin has a depth of 30-80 m (MEE 2012). Additionally, average size of Maldives

    Islands are 0.5 to 2 sq. km (MHAHE 2001). The Islands are low-lying islands, 80% are lessthan 1m above mean sea level (MEEW 2007), with total land area of 300 sq. km (Shaig

    2006). Maldives has a tropical climate, thus it experiences two seasons due to change in

    wind directions and locally known as hulhangu (westerly monsoon) and iruvai

    (northeast monsoon).

    Lammu Atoll is geographically located between Thaa Atoll and Gaafu Alifu Atoll. Thus

    strategically located at the south of central Maldives. The atoll capital is Fonadhoo (See

    Picture 3-1). The atoll has a total population of 13,7209.The atoll is locally known as

    Hadhunamathi and the atoll comprises of 53 islands. Laamu Atoll, Gan is known as thelargest island in the Maldives. Similar to other atoll islands in the Maldives, the islands

    are surrounded or enclosed by reef structures. Out of the few regional airports, Laamu

    atoll comprises of one domestic airport on Kadhdhoo Island.

    9Population and Housing Census, Preliminary Results, 2014

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    17/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 15

    Picture 3-1 Laamu Atoll

    3.2 Methodology

    A field survey was conducted during the month of September-October 2014 to collect

    data on the existing power systems on the Gan-Fonadhoostretch. There are eight power

    systems operating in Gan-Fonadhoo stretch and five of them are run by FENAKA

    Corporation Limited. Kadhdhoo Island has two powerhouse, one is operated by

    Regional Airports for Kadhdhoo airport facilities and the other powerhouse is operated

    by Maldives National Defense Force (MNDF) for their operations. In addition, Horizon

    Fisheries operates separated powerhouse at their fish processing plant in Mandhoo

    Island.

    The technical information related to the powerhouse such as installed capacity and

    means of provision of electricity were collected through stakeholder discussion

    conducted during the field visits. Additionally, log sheets, mechanism of handing fuel,

    both used and fresh supply were collected from the powerhouse. Furthermore, heights

    of chimney, noise level inside and outside the powerhouse were noted for crosschecking

    with the Maldives Energy Authority (MEA) regulations and guidelines. Photographic

    analyses of the surrounding of powerhouse system were also undertaken.

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    18/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 16

    4 Socio-Economic Context of the Project Location

    The land mass ofGan Fonadhoo stretched to 15 kilometers in north south direction

    on eastern edge of Laamu Atoll in Maldives. Gan Fonadhoo is connected via a course

    way and shared with two other islands, Maandhoo and Kadhdhoo Island. These shortand shallow water separated by geography are linked by course ways. Land transport is

    possible and available from Gan Thundidistrict to very south ofFonadhoo Island. Gan

    Island has four districts where communities live and to the south is Maandhoo Island,

    so far the only establishment is a large fish processing factory operate and manage by

    Horizon fisheries Pvt ltd., a private company in the Maldives. And next to the south is

    Kadhdhoo Island, where a domestic Airport is operated by the Regional Airports, Govt.

    of Maldives. Fonadhoo Island is to the south ofKadhdhoo Island and where community

    scattered in the central area of the island.

    Kadhdhoo Airport Course way

    Picture 4-1 Kadhdhoo Airport and Course Way

    Basic public services are available in Gan Island and Fonadhoo Island by Government

    offices and agencies. Gan Island and Fonadhoo is managed by Elected Council members

    for each Island. Atoll Council office is established in Fonadhoo Island. School are

    established in both Islands and education is accessible for all the children. Nursery

    schools, Primary schools and Secondary schools provides ideal environment for study

    and learning. Students have access to modern facilities and they are thought by trained

    staff.

    A health Centre and the Regional Hospital is available in the Islands of Gan- Fonadhoo.

    Basic medical facilities are available in the Hospitals. In some areas specialists are

    available to diagnose and treat patients. The expansion of Regional Hospital is planned

    in year 2015. Mobile phones, Television and Radios are common in the community and

    Internet service is available from both telecom companies, Dhiraagu and Ooredoo.

    Rain water collecting arrangement is done at community houses to collect safe drinking

    water. Bottled water is also available at shops and cafes. There is a large water

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    19/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 17

    desalination plant operated by FENAKA Corporation, from where the community can

    purchase fresh water in bulk if they request. Taxi, cars, vans, trucks and crane services

    are available in the region. Motor bike and bicycle are the common mode of land

    transportation. For students a free bus service is provided by the community.

    To improve social harmony and to build closer relationship among the communities in

    suburbs and other islands, many programs have been carried out with the initiation of

    Councils and NGOs. Activities that encourages visiting other communities and meeting

    people, are held such as sports and cultural events. Preserve of heritage and culture

    needs to be up held; emphases placed on protecting and promoting awareness of such

    issues.

    Land usage plan is available for the islands, details on present urban area and area for

    housing development, areas allocated for agriculture, tourism and hotel business and

    environmentally protected as greens are also clearly indicated.

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    20/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 18

    Table 4-1 Statistics as of October 2014 (Gan-Fonadhoo, Laamu Atoll)

    Population Gan Fonadhoo Total

    Male

    Female

    Students

    Foreigners (Appx. no)

    1,836

    1,707

    1161

    400

    1,153

    1,050

    484

    100

    2,989

    2,757

    1645

    500Schools / Education Centers

    Nursery

    Primary

    Secondary

    College

    University Campus

    5

    2

    1

    1

    2

    2

    -

    1

    -

    -

    7

    2

    2

    1

    2

    Households

    Number of Houses 725 510 1235

    Health Facilities

    Health Centers

    Hospitals (Regional)

    Doctors

    -

    1

    9

    1

    -

    2

    1

    1

    11

    Businesses

    Shops ( General goods )

    Caf / Restaurants

    Hardware shops

    Workshops

    Carpentries

    91

    15

    4

    8

    3

    43

    4

    1

    3

    1

    134

    19

    5

    11

    4

    Guest Houses

    Less than 6 Rooms

    20 Rooms

    28 Rooms

    8

    2

    1

    2

    -

    -

    10

    2

    1

    Vehicles

    Motorcycle

    Cars

    Pickup

    Lorry

    Van

    168

    26

    14

    4

    8

    180

    30

    5

    5

    2

    348

    56

    19

    9

    10

    Vessels

    Fishing Boats ( Dhoni)

    Passenger Boat

    Speed Boat

    Dingis

    16

    3

    2

    8

    -

    3

    1

    14

    16

    6

    4

    22

    Fish Processing

    Fish Drying / Food products,

    etc.

    2 2 4

    Factories

    Horizon Fisheries Pvt Ltd - 1 1

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    21/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 19

    4.1 Gan Island

    Gan Island has four districts namely, Thundi, Maahinna, Mathimaradhoo and

    Mukurimagu. Population of the Gan Island as of October 2014 is 3543 living in 725

    households. Main economic activities in Gan are fishing and agricultural farming. Thereare large size 12 fishing vessels and the major income generates from fishing industry.

    Farming would generate approximately 15 percent of income for the community.

    Construction activities also generates reasonable income to their families here in the

    districts ofGan. Many administrative and technical jobs at Regional hospital, Dhiraagu

    regional office, Maldives Customs at Gan, Police Regional Headquarters and FENAKA

    Corporation regional office are being filled by the members of the Gan community. Fuel

    and other commercial products are available in the Island. Consumer products and

    clothing are available in local shops.

    Food, hardware and construction material are delivered by sea transport. The island

    operates 3 vessels to transport food, vegetables and construction material to and from

    the capital, Male.

    In Gan island construction of training resort is ongoing at north of the island aiming to

    cater students from throughout the nation and abroad. Construction of 100 units of

    housing will be done next year. Harbor extension project is planned for 2015 to cater

    for the growing demand of the boat movements. Extension of regional hospital will be

    a huge program which is planned for the coming year. Maldives National University will

    be having a large campus in this region and construction is expected to start during the

    year 2015. Construction of linked road brings so much hope for the community of this

    region, knowing that it will bring speed for transport of goods and services. Ice plants,

    workshop and other medium size business is encouraged in the commercial area in Gan

    Island. Gan community welcome investors and committed to support, to establish

    businesses for mutual benefits.

    Picture 4-2 Gan Harbor

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    22/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 20

    4.2 Fonadhoo Island

    Fonadhoo Island is the Capital of Laamu Atoll. Fonadhoo Island council office and Atoll

    council office is located in Fonadhoo Island. There are three suburbs in Fonadhoo, they

    are Barasil, Medhuavah and Kurigam. The population of the island as of October 2014is 2203 living in 510 households.

    Main income of the community is generated from local jobs. Many jobs in Kadhdhoo

    Airport is being filled by members of this community. Administrative and technical jobs

    in Maandhoo Fisheries Factory, Atoll Council office, STO outlet, Bank of Maldives, Post

    office and Police station at Fonadhoo occupies by the people from Fonadhoo Island. May

    be around 10 percent of the community incomes generates from agricultural farming in

    this community. Small scale fish drying and fish products distribution is being done by

    two local companies.

    Food, hardware and construction material are delivered by sea transport. The island

    operates 2 vessels to transport food, vegetables and construction material to and from

    the capital, Male. Fuel and other commercial products are available in the Island.

    Consumer products and clothing shops are common in the island. STO operates a large

    retail shop, where construction materials, hardware and consumer products are

    available. Fonadhoo Harbor is spacious and will cater for the growing demand of boat

    movement for the coming many years. Linked road construction brings so much hope

    and excitement for the community ofFonadhoo. The road will bring speed to deliver the

    goods and service to all corners of the region.

    In Fonadhoo island housing programs are underway, 185 house will be completed in one

    year period. Additional 160 plots have been release for the housing purpose. South of

    Fonadhoo will be released for tourism development in the coming year. Fonadhoo

    community welcomes to bring commercial scale business to the island.

    Picture 4-3 Fonadhoo Harbor

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    23/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 21

    5 Existing Power Systems

    The Gan-Fonadhoo stretch consists of Fonadhoo, Kadhdhoo, Mandhoo and Gan islands.

    The data indicates that there is a combined peak demand of 3.28 MW among all the

    islands. There are 15 generator sets below the rating of 800 kW at operation but mostof these machines are in bad condition. In addition there are 3 generator sets with rating

    of 800 kW and 1000 kW at the powerhouse of Horizon Fisheries factory. They all are

    high speed generators which requires frequent maintenance and service. Xvcvvv vvvv

    vvvvvss ssss sss

    5.1 Power System ofGan

    Gan Island has four districts namely Thundi, Maahinna, Mukurimagu and

    Mathimaradhoo. The power systems in these districts has been utilized to cater to the

    need of the individual district. However very recently Thundidistrict powerhouse has

    been decommissioned and now power system of Maahinna delivers power to the

    community ofThundi. The major consumers such as Large Guest Houses and industrial

    sites they have their own Diesel Generators due to frequent interruption and

    fluctuations in Utility power. In general the powerhouses are in bad condition due to

    lack of capacity, under size, over load and inefficiency.. vvvvvv vvvvvvv vvvvvvvvv vvv

    vvv zzzz

    5.2 Power System ofThundi

    The daily peak demand for this district is observed as 240 kW. The poor condition of the

    powerhouse in Thundihas resulted in shutting down the system in August 2014. The

    system was under capacity and there was no generator paralleling and load sharing

    facilities. The electricity is now provided to Thundidistrict from Maahinna powerhouse.

    The connectivity is established by two transformers of 11kV, 800kVA at powerhouse and

    320kVA as a distribution transformer at Thundiand via 11kV, 3 phase, 70mm2 armored

    underground cable. Only one generator set of 250kW is kept at Thundipowerhouse and

    is used on emergency basis. Picture 5-1 shows inside and outside ofThundiPowerhouse.

    Picture 5-1 Thundi Powerhouse

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    24/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 22

    5.3 Power System ofMaahinna

    Maahinna district have a daily peak demand of 160 kW. Currently three generator sets

    are used in Maahinna powerhouse to provide electricity to the population ofMaahinna

    and Thundidistrict. Two generator sets of 250 kW and one generator set of 800 kW isused together with a synchronizing control panel board.

    The powerhouse ofMaahinna consists of a small office room, panel room and generator

    room. A day tank of 1600 liters is kept inside the powerhouse to provide fuel to two

    generator sets of 250 kW and fuel for the 800 kW generator sets is provided directly

    from the bulk storage tank. It is to be noted that fuel required for operating

    Mathimaradhoo Power system is also supplied from these bulk storage tanks. Having

    small facilities for fuel storage results in frequent transport of fuel on the road vehicles

    and increase risk of accidents on handling.

    The chimney ofMahinna Powerhouse does not meet the minimum requirement set by

    the Maldives Energy Authority (MEA). The powerhouse is not equipped with noise

    abatement. Even though the community housing is far away, noise pollution, air

    pollution and ground contamination need to be addressed.

    There is no site marking and no access control to the powerhouse. Safety and security

    at the site is insufficient. There are no dyke wall for fuel storage tanks or preventive

    measures for oil spills. Also, no firefighting equipment or trained staffs available at the

    site. The powerhouse lacks in services and in maintenance record keeping.

    Power system has many weak links, the development at power system happens very

    much on emergency basis and there are many limiting factors in these power systems.

    It could be bus bar rating, breaker rating, cable rating, protection method and levels.

    The Aluminum cable network in the Maahinna district is very weak and unreliable, faults

    and leakages are very common causing additional disruption during rainy seasons.

    Picture 5-2 shows inside and outside ofMaahinna Powerhouse.

    Picture 5-2 Maahinna Powerhouse

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    25/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 23

    5.4 Power System ofMathimaradhoo

    The daily peak demand in Mathimaradhoo is 300 kW. Many large consumers in this

    district are having their own generators to cater for their facilities. Mathimaradhoo

    power system can be considered substandard and extremely low in every aspect ofengineering and operation. The powerhouse consists of a control room, fuel storage

    room and generator room. In generator room there are two generator beds, on one bed

    only parts of a generator body is kept and 250 kW generator on the second bed is also

    not functional and this has been out of service since 2013. Power interruption is

    frequent and power quality is low due to under capacity, control and network

    conditions.

    Currently Mathimaradhoo powerhouse does not have a bulk fuel storage tank and the

    fuel is supplied on a need basis from Maahinna powerhouse. Presently they have 2

    metal tanks of 4000 liters and 2 tanks of 5000 liters for handling fuel. As per the MEA

    Guideline plastic tanks cannot be used as fuel storage tanks. In addition, proper bund

    walls have to be constructed around the storage tanks.

    The only generator which provides electricity to the community is 800kW generator set

    which is installed outside the Powerhouse, a machine transferred from water company,

    MWSC. The chimney of the powerhouse is totally damaged and is lower than the height

    specified in MEA guideline. It is also observed that the generator set operated in this

    powerhouse is higher than the peak demand of 300kW. As a result the generator is not

    operating at optimum capacity, but at the same time we should note that the physical

    condition of these machines are extremely low. In all aspects the damage is high, fuel

    efficiency is low due to bad condition of the machine and not having the right size of the

    machines. The distribution system due to under size and over load results in heavy loss

    in this district.

    The powerhouse lacks many facilities and features. Safety, security, substandard

    equipment and systems increase risk for the personal as well. Measuring, indicators and

    electrical protection, lack of proper operational and maintenance procedures increase

    risk of damage, risk of fire and risk of life. As part of the emergency plan for the current

    needs the company is planning to deliver power to the community of Mathimaradhoo

    from Maahinna powerhouse. As they did for Thundi district, similarly it is planned to

    install 11kV Substations. This will demand to add capacity at Maahinna powerhouse.

    Once adopted the generator at Mathimaradhoo powerhouse will be used for stand-by

    power. But none of these current activities will provide a solution for the growing

    demand in the communities in near future. Picture 5-3 shows inside and outside of

    Mathimaradhoo Powerhouse

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    26/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 24

    Picture 5-3 Mathimaradhoo Powerhouse

    5.5 Power System ofMukurimagu

    The current peak demand ofMukurimagu is 160 kW. Two generator sets are installed in

    Mukurimagu powerhouse to provide electricity to the community. Generator setscombination of 150 kW and 125 kW are continuously in operation. The third generator

    set of 120 kW installed in the powerhouse has been out of order for several months.

    Even though the powerhouse has load sharing features, at control panel, the motorized

    breakers are out of order and the protections does not function properly.

    The exhaust pipe of the generators are facing to the adjacent neighboring house

    damaging the trees and plants and polluting the air at their homes. Noise and pollution

    is a serious issue in this powerhouse. Neighboring communities are suffering badly due

    to air pollution, noise and ground contamination.

    It is observed the machine in operation at the time of visit was leaking heavily, loss of

    fuel from the system, lack of spare parts and under capacity forced the operators run

    these machines on extreme condition. Generators, control panels, distribution network

    and auxiliaries are all in very weak condition. The facilities can be considered high risk

    due to lack of safety and security, lack of electrical safeties to protect equipment and

    personal. Picture 5-4 shows Control panels and generator room ofMukurimagu.

    Picture 5-4 Control Panels and Generator Room of Mukurimagu Powerhouse

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    27/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 25

    5.6 Power System ofFonadhoo

    Fonadhoo is the capital of Laamu Atoll and have 2203 residents in the island. The power

    system ofFonadhoo Island was developed under the support from Asian Development

    Bank. However, it took few years the electrical load surpass the available capacity of thepowerhouse. It is apparent that the load forecasting and capacity building was not

    carried out in a realistic way, the life of the powerhouse was so short.

    Currently powerhouse have one generator sets of 360 kW, one generator set of 200 kW

    and one generator set of 400 kW. However, 200 kW generator set is now out of order.

    The island have a peak demand of 530 kW, in order to meet this demand both generator

    sets are operating at peak load hours, as a result during maintenance of these machine

    power cuts are evident.

    Fuel is stored in 2 x 15000 liters steel tanks installed in a higher elevation at south side

    of the power plant but there is no dyke walls for these tanks. Generator panel has its

    limits and New Gen set in operation and immediate programs on going are only to cater

    for the current shortages and as a whole the system will not provide power security for

    the coming years. Beside the capacity issues, the power system lacks many features on

    safety and operational and maintenance practices. Picture 5-5 shows power system of

    Fonadhoo Island.

    c

    Picture 5-5 Fonadhoo Powerhouse

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    28/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 26

    5.7 Other Power Producers

    Kadhdhoo Airport operates a powerhouse at Airport compound. The current demand

    of 50 kW will increase in near future with the development programs. If the Power is

    available from CPS the Generators can be utilize for emergency purpose. Picture 5-6shows Generator Sets installed inside Kadhdhoo Airport.

    Picture 5-6 Generator Sets Installed Inside Kadhdhoo Airport

    MNDF Site at Kadhdhoo operates a powerhouse with similar load of 50 kW. According

    to the Officers, three more buildings are under construction and the completion of these

    buildings in the near future will result in a load growth forecast of 100 kW. Picture 5-7

    shows generator sets installed inside Kadhdhoo MNDF premises.

    Picture 5-7 Generator Sets installed inside Kadhdhoo MNDF Premises

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    29/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 27

    Maandhoo factory, Horizon Fisheries Pvt Ltd have a large diesel power plant equipped

    with high speed diesel generators from Cummins. The peak load recorded was 1800 kW.

    When CPS provides power for the growing demand of the factory the existing facilities

    at the powerhouse can be utilized for emergency purpose. Picture 5-8 shows

    powerhouse building of the factory.

    Picture 5-8 Powerhouse Building of Fish Factory

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    30/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 28

    6 Load Forecast and Available Capacity

    Given the high sensitivity of power development plans to demand projections, load

    forecasting represents a crucial element of electric power utility programming. The main

    purpose of any form of load forecasting is estimating the most likely future demand toserve as a basis for supply planning. This includes expansion and operation of power

    station as well as the planning of distribution facilities.

    Based on the study the existing facilities are equipped with high speed diesel engines,

    these machines and the related systems are undersize, inefficient and over loaded. With

    current situation available capacity cannot cater even for the realistic load of the Islands

    today.

    Gan-Fonadhoo stretch can be considered a very potential area for economic growth

    having land, harbors, an airport and people. The communities are vibrant. The planned

    developmental programs for next 3 years will reflect in additional energy requirement.

    As a result there will be load growth that need to be addressed. Strategic decisions need

    to be made to build energy supply security for the near future and long term.

    Load growth factors have been reviewed based on available statistics and production

    data. Analysis of current development projects and planned projects for next three

    years has been reviewed for energy requirement. Population growth, commercial

    activities, income and purchasing power of the currency have been considered in

    generating the future growth trend.

    Graph 6-1 shows the current daily load of the stretch 2014 and graph 6-2 shows the

    forecasted load for the year 2018. Graph 6-3 shows load forecast and available capacity

    of the proposed power system, Phase I and graph 6-4 shows allowable RE intake of 30%

    of the peak load on any given year.

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    31/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 29

    DAILY LOAD CURVE 2014GAN-FONADHOO (LAAMU ATOLL)

    Graph 6-1: Daily load curve 2014

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    32/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 30

    ESTIMATED DAILY LOAD CURVE 2018GAN-FONADHOO (LAAMU ATOLL)

    Graph 6-2: Estimated daily load curve 2018

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    33/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 31

    LOAD FORCAST & AVAILABLE CAPACITY (MW)GAN-FONADHOO (LAAMU ATOLL)

    Graph 6-3: Load forecast and available capacity

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    34/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 32

    ALLOWABLE RE INTAKEGAN-FONADHOO (LAAMU ATOLL)

    - 30 percent ofthe forcasted load at a given year

    Graph 6-4:AllowableRE intake

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    35/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 33

    7 Demand for Electrical Energy

    Electricity has given us the freedom to use power when we want, where we want, and

    in the form we want. But electricity has to be generated from other sources of energy

    like fossil fuel, hydro, wind, solar and nuclear. And at every moment we must generatethe same amount of electricity as we consume.

    The developing countries rely heavily on the fossil fuels in their energy production, so

    the demands for more electricity will increase the amount of fossil fuels to produce it.

    In many cases it is difficult to find alternative sources of energy either because of natural

    conditions, source are not readily available, economic situation, etc.

    The proportion of renewable energy is increasing worldwide and it is important to

    maintain the trend because of the increased demand for electricity in the developing

    countries. The solution is not to restrict the demand, but to try make the role of fossil

    fuels less dominant.

    Electricity is the very basis of our civilization. Currently we are facing a future of ever-

    increasing demand for electricity and this demand must be fulfilled, keeping in mind the

    other big issues of the future. Fortunate for us, at the moment we are equipped with

    more profound scientific knowledge and better technological capabilities than ever

    before. Both human history and the history of life on Earth in general is filled with

    examples of the importance of flexibility, and especially of consequences caused by the

    lack of it. Strive for flexibility is the key issue in the future of energy and electricity

    production.

    Electrical energy has wonderful properties for improving living conditions, for creating

    wealth and for providing widespread communication facilities. Electricity literally gives

    power to the people. That is one reason why demand for electric energy will continue

    to increase.

    7.1 Electricity Demand Pattern

    Demand for electrical energy changes continuously, depending upon the time of the

    day, day of the week and the season. After midnight, demand generally minimizes

    because of the reduced human activity. In the morning, when people wake up, they

    switch on appliances, offices open up, shops will start business and commercial

    operations increases their power demand. In Maldives electricity demand peaks during

    noon when the effect of solar irradiation reaches the maximum. Operation of Air

    conditioners and fans for cooling purpose and industrial load makes peak load early

    afternoon. On Fridays, most citizens apparently relax in the morning resulting in low

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    36/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 34

    electricity consumption and during rainy days, when temperature falls to comfort range

    the consumption of electric energy goes down due to reduction in cooling load.

    Electricity production based on wind and sunshine has characteristics that differ

    substantially from those of fuel-based generation. Weather events and the time of the

    day determine the output of these renewable sources, resulting in poor deliverability.

    Maldives being a sunny country, solar based power production would help to reduce

    demand to be covered by power station especially around noon.

    Finding new methods for producing energy, and especially finding new combinations of

    production with both fossil fuels and renewable sources of energy, is of utmost

    importance in tackling the problems related to the growing demand for electrical

    energy.

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    37/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 35

    8 Renewable Energy Options

    Maldives being a country entirely dependent on imported fossil fuel in meeting its

    energy needs have made her vulnerable to the external fuel shocks and have made

    provision of electricity expensive and unsustainable. To make the electricity servicesustainable and less expensive it is important to explore locally available energy sources

    and maximize the use of these energy sources.

    According to locally available studies and reports, Maldives is blessed with number of

    renewable energy sources namely wind, solar, ocean energies and waste-to-energy, etc.

    8.1 Wind Energy

    Wind is a form of solar energy. Wind are caused by the uneven heating of the

    atmosphere by the sun, irregularities of the earths surface and rotation of the earth.

    This wind flow or motion energy, when harvested by a modern wind turbine, can be

    used to generate electricity.

    Wind is a clean source of renewable energy that produces no air or water pollution. And

    since the wind is free, operational costs are nearly zero once a turbine is erected. Mass

    production and technology advances like creating new blade designs, more efficient

    turbines to produce economical wind energy, systems that are designed for extremelyharsh environment, will attract projects even with low-wind areas. Many times wind is

    strong in rainy days, when less sun light is available and peak operating time for wind

    and solar systems occur at different times of the day and year. Hybrid systems including

    wind are more likely to produce power when we need it.

    Department of Meteorology collects hourly data at different locations across the

    country at 10 meters height. This data is has been projected for different heights based

    on the mathematical tools and analysis suggests good wind power potential at northern

    part of the country and consider fair in south part of the Maldives, at project site.

    Development of affordable wind capacity to include as a percentage of clean energy

    resources in the electricity mix can be a part of the strategic plan. But it shall not be part

    of the Power Project, Phase 1, for Gan-Fonadhoo region due to time involves in site

    survey and wind mapping before designing the system and finding the economics of it.

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    38/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 36

    Picture 8-1 Maldives wind resource map

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    39/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 37

    8.2 Ocean Energy

    Ocean wave energy is energy that has been transferred from the wind to the ocean. As

    the wind blows over the ocean, air-sea interaction transfers some of the wind energy to

    the water, forming waves, which stores this energy as potential energy and kineticenergy.

    Tidal range are the regular and predictable change in the height of the ocean, driven by

    gravitational and rotational forces between the Earth, Moon and Sun, combined with

    centrifugal and inertial forces. Maldives experiences two high tides and two low tides

    per day. During the year, the amplitude of the tides varies depending on the respective

    position of the Earth, the Moon and the Sun.

    Tidal currents are the ocean water mass response to tidal range. Tidal currents are

    generated by horizontal movements of water, modified by seabed bathymetry,

    particularly near coasts or other constrictions like reefs and islands. Tidal current flows

    result from the rise and fall of the tide, although these flows can be slightly influenced

    by short-term weather fluctuations, their timing and magnitude are highly predictable

    and largely insensitive to climate change influences.

    Ocean thermal energy conversion: About 15 percent of the total solar input to the ocean

    is retained as thermal energy, with absorption concentrated at the top layers, declining

    exponentially with depth as the thermal conductivity of the sea water is low. Sea surface

    temperature can exceed 26oC in tropical latitudes, while temperatures 1 km below the

    surface are between 5oC and 10oC. The OTEC resource map (picture 8-2) showing annual

    average temperature differences between surface waters and the water at 1,000m

    depth shows a wide tropical area with a potential greater than 20 oC temperature

    differences.

    Picture 8-2 OTEC Resource map

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    40/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 38

    Many research and development goals remain to be accomplished, including cost

    reduction, efficiency and reliability improvements, identification of suitable sites and

    interconnection with the utility grid, better understanding of the impacts of the

    technology on marine life and the shoreline.

    Ocean energy technologies are suitable for the production of both electricity and

    potable water, whilst OTEC can also be used to provide thermal energy services.

    According to the map of Surface Ocean currents shown in picture 8-2 there are

    significant currents in the location of the Maldives. These currents generally influenced

    by different aspects, among others:

    the monsoon periods and associated winds in the region

    the specific location of the atoll and islands being considered

    its location regarding the chain of islands, specially north to south

    its location in the atoll ( central, east, west, north, south)

    Picture 8-3 Surface ocean currents

    One of the major issue regarding ocean currents is the lack of sufficient data on which a

    detailed assessment could be based. The measurements require for this purpose will

    take at least one year in order to deliver useful data and must be as site specific as

    possible.

    Picture 8-4 Study area (Laamu Atoll)

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    41/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 39

    As seen in picture 8-4 the study area seems to have potential channels that can be used

    to harness energy from ocean current. It is recommended to conduct detail assessment

    of the potential to generate energy from ocean current on these channels in near future.

    In order to explore energy generation potential in these channel we suggest to seek

    financial and technical support from relevant entities. Utilizing ocean energy to includeas a percentage of clean energy resources in the electricity mix could be part of the long

    term plan for the region.

    8.3 Waste Heat Recovery

    It is estimated that about 40 to 50 percent of industrial energy input is lost as waste heat

    in the form of hot exhaust gases, heat transfer to cooling water and heat loss from hot

    equipment surfaces and heated products. As the industrial sector continues efforts toimprove its energy efficiency, recovering waste heat losses provides an attractive

    opportunity for an emission-free and less-costly energy resource. Numerous

    technologies and combinations of technology are commercially available for waste heat

    recovery. Many industrial facilities have improved their energy productivity by installing

    these technologies.

    Several factors can be determine whether heat recovery is feasible in a given

    application. For example, small-scale operations are less likely to install heat recovery,

    since sufficient capital may not be available and because payback periods may be longer.Another concern is the ease of access to the waste heat source. In some cases, the

    physical constraints created by equipment arrangements prevent easy access to the

    heat source, or prevent the installation of any additional equipment for recovering the

    heat.

    Method for waste heat recovery include transferring heat between gases or liquid, like

    boiler feed water preheating and transferring heat to generate mechanical energy,

    electrical energy, desalination, etc. Exhaust heat from diesel power plant can be utilized

    for sea water desalination through low temperature distillation process such as MultiEffect Distillation (MED), Multi Effect Distillation with Thermal Vapour Compression

    (MED-TVC) and Multiple Effect Distillation with Mechanical Vapour Compression (MED-

    MVC). Some of the advantages of these machines are;

    very low energy consumption, produce steadily high purity distillate water,

    do not need complex pre-treatment,

    low maintenance cost,

    highly reliable,

    very high thermal efficiency.

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    42/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 40

    In formulating the Phase I of Power Project, installation of heat recovery boilers and

    desalination machines is not considered, but spacing of silences and exhaust stack will

    allow retrofit of these machines in future. Since these project requires additional capital

    and technology review and technical expertise, we recommend to implement such

    project independent from main Power Project-Phase I, at a later stage.

    8.4 Biomass

    Biomass refers to organic matter that stored energy through the process of

    photosynthesis. It exists in one form as plants and may be transferred through the food

    chain to animal bodies and their waste. It is the fuel derived from timber, agriculture

    and food processing wastes or from fuel crops that are specially grown or reserved for

    electricity generation. Biomass fuel can also include sewage sludge and animal manure.

    The major capital cost items for a biomass power system include the fuel handling

    equipment, the combustor, boiler, prime mover, generator, controls stack and

    emissions control equipment.

    Today system cost is in the range between $3000 and $4000 per kilowatt of electricity.

    Large systems require significant amounts of material, which leads to increasing haul

    distances and material costs. Small systems have higher O&M cost per unit of energy

    generated and lower efficiencies than large systems. Therefore, determining the

    optimal system size for a particular application is an iterative process.

    The most important factors in planning for a biomass energy are resource assessment

    and procurement. As part of the screening and feasibility analysis processes, it is critical

    to identify potential sources of biomass and to estimate the fuel quantities needed. To

    produce one megawatt hour electricity the fuel requirement would be approximately

    one ton of good quality wood chips per hour. The region will not be able to produce and

    deliver even one ton of biomass per day, therefore depends on the requirement the fuel

    has to be imported and deliver to the site.

    Finding a potential supplier to produce and deliver a fuel that meets the requirements

    of the biomass equipment can be a bit of an intensive process as it involves determining

    the load to be served, identifying possible equipment manufacturers or vendors,

    working with those vendors to determine a fuel specification and contacting suppliers

    to see if they can meet the specification and at what price. It is necessary to estimate

    the monthly and annual fuel requirement to help with fuel handling and fuel storage

    planning.

    Whether combusting directly or engaged in gasification, biomass resources do generateair emissions. These emissions vary depending upon the precise fuel and technology

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    43/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 41

    used. If wood is the primary biomass resources, very little SO2 comes out of the stack.

    NOx emissions vary significantly among combustion facilities depending on their design

    and controls. Some biomass power plants show a relatively high NOx emission rate per

    kilowatt hour generated if compared to other combustion technologies.

    Development of a biomass plant to include as a percentage of clean energy resources in

    the electricity mix can be part of the strategic plan. But it shall not be part of the Power

    Project, Phase 1, for Gan-Fonadhoo region due to the complex study involves in

    technical, operational and commercial aspects.

    8.5 Waste to Energy

    Waste to Energy plants burn municipal solid waste (MSW) to generate electricity or

    heat. At the plant MSW is unloaded from the collecting trucks and shredded or

    processed to ease handling. The waste is fed into a combustion chamber to be burned.

    The heat released from burning the MSW is used to produce steam, which turns a

    turbine to generate electricity.

    MSW consist of everyday items such as product packaging, paper, plastic items,

    furniture, clothing, bottles, food scraps, newspapers, appliances, paint and batteries. It

    does not include medical, commercial and industrial hazardous or radioactive wastes,

    which must be treated separately.

    Burning MSW can generate energy while reducing the volume of waste by up to 90

    percent, an environmental benefit. Ash disposal and the air pollution emissions from

    plant operations are the primary environmental impact control issues. Toxic material

    include trace metals such as lead, cadmium and mercury, and trace organics, such as

    dioxins and furans. The control of such toxics and air pollution are key features of

    environmental regulations governing MSW fueled electric generation. These plant

    produce comparatively high rates of nitrogen oxide emissions. The on-site land use

    impacts are generally equal to those of coal or oil fueled plants.

    To make sure the energy is generated cleanly, there shall be a number of high-tech

    pollution controls in place. That includes equipment to capture particulate matters,

    carbon injections to absorb heavy metals, dioxins and furans, and the addition of lime

    to neutralize acid gases, etc.

    Today in Gan-Fonadhoo stretch produces roughly 8 tons of MSW per day. In each

    community, MSW is either burn in open areas or dispose to the beach. Collecting to a

    central location will require proper methods, transport and public awareness.

    Implementing a small plant could be an option that need to be explored.

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    44/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 42

    Development of a biomass plant to include as a percentage of clean energy resources in

    the electricity mix could be an option. A separate study need to be conducted to forecast

    the near future scenario and assess the feasibility of such plant operating in the region.

    But it shall not be part of the Power Project, Phase 1, for Gan-Fonadhoo region due to

    the complex studies involve in technical, operational and commercial aspects.

    8.6 Solar Energy

    According to satellite data solar radiations and daylight hours across the country are

    reasonably good. In addition, a study was conducted by JICA in the year 2009 based on

    the data collected in 2003-04 for Male and Hulhumale Island to find out the solar PV

    potential. According to the study annual average radiation across the country ranges

    between 5.79 to 5.88 kWh/m

    2

    /day.

    Using the radiation data for Maldives for mono crystalline cells, give a Capacity

    Utilization Factor (CUF) of 19 percent, while the modules are fixed. Every m2 solar

    collector area in Maldives will results in 300 kWh/year. Similar modules with single axis

    tracking generate electricity at 24 percent CUF, which will generate 380 kWh/year/m2.

    Percentage increase in the cost is much higher than the percentage in the yield; hence

    fixed module systems provide power at a lesser cost than the tracked systems. Double

    axis tracking does not yield much as the country is located at the equator.

    The storage batteries for year round operation of solar have not been considered. The

    very basic reason for not opting the storage is that not only it increases the requirement

    of solar modules almost three times, it require huge amount of space to store the

    batteries.

    GRAPH 8-1 shows adding more renewable beyond about 30% requires investments in

    integration controls. This cost, combined with the occasional need to curtail some of the

    renewable generation, reduces the economic attractiveness of additional renewable

    generation, but still allows very substantial levels of renewable contribution, with their

    additional environmental benefits, with only modest cost impacts.

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    45/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 43

    Graph 8-1 Relation between levelized cost of energy with respective to of renewable energy penetration

    Every hour, enough of sunlight energy reaches to meet the world's energy demand for

    a whole year. Solar energy is the conversion of sunlight into electricity through a

    photovoltaic (PVs) cells. A photovoltaic cell is made from silicon alloys.

    The amount of power solar panels produce is determined by the quality of the solar

    panel, solar cells and technology used in making the solar panel.

    Mono-crystalline- efficiency is in 16% range. PV cell is made from pure mono-crystalline

    silicon with almost no defects or impurities. High purity mono cells are used to make

    computer CPU chip, relatively low purity cells are used for solar module. The most

    common size of mono-crystalline cell is 5x5 and 6x6. Mono-crystalline has a lifetime

    of 25 to 30 years under normal circumstance.

    Poly-crystalline-efficiency is in 13% range. PV cell is producing using numerous grade of

    poly-crystalline silicon. This is less expensive to manufacturing due to simpler process

    involved in production compared with mono-crystalline. The most common size of poly-

    crystalline cell is 5"x5" and 6"x6". Polycrystalline has a lifetime of 20 to 25 years under

    normal circumstance.

    Amorphous - efficiency is in 10% range. Silicon composed of silicon atoms in a thin layer

    rather than a crystal structure. It absorbs light more effectively than crystalline so cells

    can be thinner. Thin film technology can be used in rigid, flexible, curved and foldaway

    modules. They have a lower cost than crystalline cells but have a lower efficiency.

    Amorphous has lifetime of less than 10 years under normal circumstance.

    Sunlight is composed of photons, or particles of solar energy. There photons contain

    various amount of energy corresponding to the different wavelengths of the spectrum.When photons strike a photovoltaic cell, they may be reflected, pass right through, or

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    46/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 44

    be absorbed. Only the absorbed photons provide energy to generate electricity. When

    enough sunlight, energy is absorbed by the material, semiconductor, electrons are

    dislodged from the material's atoms. Special treatment of the material surface during

    manufacturing makes the front surface of the cell more receptive to free electrons, so

    the electrons naturally migrate to the surface. When the electrons leave their position,holes are formed. When many electrons, each carrying a negative charge, travel toward

    the front surface of the cells, the resulting imbalance of charge between the cell's front

    and back surfaces creates a voltage potential like the negative and positive terminals of

    the battery. When the two surfaces are connected through an external load, electricity

    flows.

    The photovoltaic cell is the basic building block of the PV system. Individual cells can

    vary in size and one cell only produces 1 or 2 watts, which isn't enough power for most

    applications. To increase power output, cells are electrically connected into a packagedweather-tight module. Modules can be further connected to form an array. The term

    array refers to the entire generation plant, whether it is made up of one or several

    thousand modules.

    When DC from photovoltaic cells is used for commercial applications or sold to electric

    utilities using the electric grid, it must be converted to alternating current, AC, using

    inverters. The performance of a photovoltaic array is dependent upon sunlight, climate

    conditions and its performance. The environmental impact of a photovoltaic system is

    minimal, requiring no water for system cooling and generating no by-products.

    Development of solar PV system to include as a percentage of clean energy resources in

    the electricity mix shall be part of the package to develop the power system at Gan-

    Fonadhoo stretch. This program shall run in parallel with the power system

    development project, phase 1.

    Pictures of the potential roofs to install Solar PV in Gan - Fonadhoo stretch are provided

    in Annex 1

  • 7/21/2019 Laamu Gan-Fonadhoo Feasibility Study & Technical Requirements Final 090315

    47/160

    Feasibility Study and Technical Requirements to Build Central Power Station, Distribution Network and Intake of Renewable Energy 45

    9 Proposed Power System for Gan Fonadhoo

    Considering the future requirement and supply of reliable and efficient power to the

    region we shall propose to have a common central power system that will deliver power

    across the land to all corners with proper characteristics and sufficient amount throughan 11 kV distribution network. The network can be shared to intake renewable energy

    from different areas of the region.

    Power Plant will be develop under the name of Power System Development Project,

    Phase I. In the proposed design for phase I, all necessary design philosophy and site

    reservation will be considered for the Phase II. It is foreseen that capacity building under

    Phase II will only be required beyond year 2028. The Power system shall consider as

    Smart Generating Plant.

    Phase I will include installation of a 16 MW medium speed diesel power plant which

    operates on marine gas oil. Engine cooling shall be done via sea water taken from inner

    lagoon. The 11 kV switch gear system will have switch gears for gen sets, auxiliary

    transformers and outgoing feeders. A bus coupler will be in cooperated to allow

    maintenance and modification on switch gear system.

    The prime mover of the power plant shall be medium speed, 4 stroke diesel engines.

    These machines can run on 45 percent fuel efficiency and maintenance interval can be

    very long compare to high speed generators. Life of these engine can be thirty plus years

    in operation.

    Generator Sets, Package substations and auxiliary systems will be monitored and

    operated with PLC / SCADA. Staff can be stationed at central control room to run and

    manage the power system.

    Properties of a smart generating plant includes fast starting, fast ramping up and down

    of load, high fuel efficiency, fuel flexibility, minimum maintenance outage time, remote

    control of outputs, black start capability, short building time, easy adaptable capacity,

    low sensitivity to ambient condition, minimum water use and low capital expenditure.

    A problem with the fuel supply or the electrical switchgear system is called a common-

    cause fault. Therefore, any element of a power plant that might be the reason of a

    common-cause fault should be of the highest possible quality. Moreover, the number

    of vulnerable elements in the common part should be as low as possible. The generating

    sets in pa


Recommended