    COMBS Consulting Group | eGov Consulting Services | TelResources, Inc. Page i

    Information Technology

    Strategic Plan

    Developed by:

    eGov Consulting Services

    Plan Years 20122016

    2012 Plan Update

    Plan Update: 31 May 2012

  • 7/30/2019 Ector County IT Strategic Plan

    2/29

    Ector County

    Information Technology Strategic Plan for 2012 2016

    2012 Plan Update

    eGov Consulting Services Page ii

    Letter from County Commissioners

    Dear Reader:

    Thank you for your interest in Ector Countys technology direction.

    The Information Technology Strategic Plan developed in 2011 has provided a technology

    roadmap that advances us towards the future. The Plan was a snapshot in time; as deployment

    has progressed the technology initiatives have been adjusted that take advantage of the

    opportunities presented by the improvements in technology options.

    The plan was approved in September 2011 and a series of projects were initiated to address

    each of the Courts objectives. We have followed an implementation process that continuouslyevaluates the projects for the optimal technology, costs and benefits. The results of this process

    have allowed us to reduce the plans Total Cost of Ownership (TCO) while positioning Ector

    County to take advantage of the emerging broadband wireless and internet based applications.

    We are committed to the successful implementation of the Plan and accomplishing the

    initiatives contained within it. These initiatives lay the foundation for the Countys future

    technology use by streamlining our processes, solidifying our infrastructure and improving the

    cohesiveness of our team.

    We are always interested in your feedback, both corrective and complementary. Please forward

    any comments you may have to Commissioner Dale Childers [email protected].

    Again, thank you for your interest.

    Regards,

    Ector Board of County Commissioners

    mailto:[email protected]:[email protected]:[email protected]:[email protected]
  • 7/30/2019 Ector County IT Strategic Plan

    3/29

    Ector County

    Information Technology Strategic Plan for 2012 2016

    2012 Plan Update

    eGov Consulting Services Page iii

    Table of Contents

    SECTION 1: EXECUTIVE SUMMARY ......................................................................................................................... 1

    1.1 INTRODUCTION .............................................................................................................. 1

    1.2 ADDRESSING THE GOALS .................................................................................................. 1

    1.3 PRIORITIZING THE INITIATIVES............................................................................................ 3

    1.4 IMPLEMENTING THE PLAN................................................................................................. 4

    SECTION 2: REALIGN IT DEPARTMENT WITH COUNTYS NEEDS 2012 GOAL UPDATE .......................................... 5

    2.1 ITPLAN OVERVIEW......................................................................................................... 5

    2.2 DEVELOP ITGOVERNANCE STRUCTURE AND PROCESS ............................................................. 5

    2.3 REORGANIZE THE ITDEPARTMENT...................................................................................... 6

    2.4 EXPAND THE ITSTAFF AND SERVICES................................................................................... 9

    2.5 DEVELOP ITPOLICIES AND PROCESSES ............................................................................... 10

    SECTION 3: SOLIDIFY AND PROTECT THE COUNTYS TECHNICAL INFRASTRUCTURE2012 GOAL UPDATE .......... 12

    3.1 ITPLAN OVERVIEW....................................................................................................... 12

    3.2 ACQUIRE AND IMPLEMENT A SERVICE DESK TOOLSET ............................................................ 12

    3.3 DEPLOY A STORAGE AREA NETWORK (SAN)/BACKUP SYSTEM.............................................. 13

    3.4 DEPLOY A NEW NETWORK.............................................................................................. 13

    3.5 BUILD-OUT NEW COMPUTER ROOMS AT THE ANNEX AND SHERIFF'S OFFICE .............................. 17

    3.6 MIGRATE DISTRIBUTED COMPUTER ROOMS TO OFF-SITE MANAGED COMPUTING CENTER ........... 18

    3.7 NEW VOICE OVER IPSYSTEM .......................................................................................... 19

    SECTION 4: IMPROVE SERVICEABILITY OF COUNTYS APPLICATIONS ENVIRONMENT2012 GOAL UPDATE ...... 20

    4.1 ITPLAN OVERVIEW....................................................................................................... 20

    4.2 DESKTOP REPLACEMENT PROGRAM .................................................................................. 22

    4.3 CONSIDER VIRTUAL DESKTOP .......................................................................................... 22

    4.4 INTEGRATE GIS INTO COUNTY APPLICATIONS...................................................................... 23

    4.5 RE-INITIATE THE DEPLOYMENT OF ODYSSEY COURT/PUBLIC SAFETY SYSTEM.............................. 23

    4.6 CONSIDER THE MIGRATION OF INCODE TO A CLOUD-BASED ENVIRONMENT ............................... 24

    SECTION 5: INVESTMENT UPDATES ..................................................................................................................... 25

    5.1 OVERVIEW .................................................................................................................. 25

    5.2 UPDATED IMPLEMENTATION SCHEDULE ............................................................................. 25

    5.3 UPDATED CALENDARED INVESTMENTS............................................................................... 26

  • 7/30/2019 Ector County IT Strategic Plan

    4/29

    Ector County

    Information Technology Strategic Plan for 2012 2016

    2012 Plan Update

    eGov Consulting Services Page 1

    Section 1: Executive Summary

    1.1 Introduction

    The IT Strategic Plan was developed through a consensus process with County Management, IT

    Departments staff and IT Departments customers. The intent was to take a holistic, corporate

    view of information technology for the County, in order to better understand how the IT

    Department could best serve the Countys needs.

    During the planning process, the Commissioners were interviewed individually to better

    understand the direction that they wanted to set for the IT Department and information

    technology in general. The Commissioners expressed their desire to see the following goals

    pursued by IT Department:

    Realign the IT Department with the Countys Needs

    Solidify and Protect the Countys Technical Infrastructure

    Improve the Serviceability of the Countys Applications Environment.

    1.2 Addressing the Goals

    A series of project initiatives were developed to support each of the Commissioners goals.

    These long terms initiatives were designed to change not only what IT Department did, but howit did it. The goals and associated initiatives are:

    Goal Initiative Description

    Realign the IT

    Department

    with the

    Countys Needs

    Develop IT

    Governance

    Structure & Process

    Establish an IT Governance Committee with authority

    to determine the ongoing technology direction for the

    County, associated charter, and processes for projects

    and IT Department performance review.

    Reorganize IT Implement the new organizational structure with job

    descriptions that detail responsibilities.

    Expand IT Staff and

    Services

    Add at least an additional four staff to the IT

    Department. Provide for ongoing technology planning

    support.

    Develop IT Policies

    and Processes

    Develop and continue to refine IT processes to address

    needs. Provide ongoing IT planning support.

    Solidify and Acquire & Acquire and implement a toolset to be used by IT

  • 7/30/2019 Ector County IT Strategic Plan

    5/29

    Ector County

    Information Technology Strategic Plan for 2012 2016

    2012 Plan Update

    eGov Consulting Services Page 2

    Goal Initiative Description

    Protect the

    CountysTechnical

    Infrastructure

    Implement a

    Service DeskToolset

    Customer Service to record incidents, track progress

    and identify trends in order to continuously improveservice desk performance.

    Deploy SAN/Backup

    System

    Deploy a storage area network (SAN) with a

    supportable system that provides de-duplication

    capabilities.

    Deploy New

    Network

    Develop a new MAN/LAN, layer 4 transport, and

    network management system Countywide.

    Build-Out new

    computer rooms at

    the Annex andSheriff's Office

    Build out new computer room capabilities, one at the

    Annex to provide core communications functions, and

    one at the Sheriff's Office to provide support for corelaw enforcement systems.

    Migrate Distributed

    Computer Rooms

    to Off-Site

    Managed

    Computing Center

    Consolidate all application servers throughout the

    County, except CAD, to a single location; provide

    managed services for backup, monitoring and alerting

    in a virtual environment. Since the County is short 5 IT

    Staff members, and users are requiring greater amount

    of analytical support, the County should migrate the

    support of the servers at County Annex, Courthouse,

    and Sheriff's Office to an off-site hardened site. The

    outsourcing would include the moving the distributedservers and new SAN to the off-site location and the

    purchase of a new Core Switch, fiber network access.

    This would allow IT to focus more on business analysis

    functions rather than infrastructure support.

    New VOIP System Network integrated Voice over IP system to replace

    aging PBX once the maintenance contract expires on

    the existing system and the County network

    infrastructure is fully deployed.

    Improve

    Serviceability of

    Applications

    Environment

    Consider migration

    of Incode to a

    Cloud-based

    environment.

    For the next four years, continue to operate

    applications environment as currently configured.

    Consider the deployment of cloud based financials once

    the fundamental infrastructure is in place and the

    applications environment fully matures.

    Desktop

    Replacement

    Program (short-

    Place all County desktop assets (desktops, laptops, in-

    car computers) on a 4-year replacement cycle.

  • 7/30/2019 Ector County IT Strategic Plan

    6/29

    Ector County

    Information Technology Strategic Plan for 2012 2016

    2012 Plan Update

    eGov Consulting Services Page 3

    Goal Initiative Description

    term)

    Virtual Desktop

    Program (long-

    term)

    Consider migrating to a virtual desktop to minimize

    desktop management requirements; purchase servers

    to support virtualized environment.

    Integrate GIS into

    County

    Applications

    Utilizing the GIS infrastructure from Odessa, integrate

    with County applications as possible.

    Re-initiate the

    Deployment of

    Odyssey Court/

    Public SafetySystem

    Initiate project management over the Odyssey project

    to get the project on course.

    1.3 Prioritizing the Initiatives

    Each of the initiatives was prioritized by the Court according to technical sequencing and

    business need as shown below.

  • 7/30/2019 Ector County IT Strategic Plan

    7/29

    Ector County

    Information Technology Strategic Plan for 2012 2016

    2012 Plan Update

    eGov Consulting Services Page 4

    1.4 Implementing the Plan

    A detailed project plan was developed that incorporated resourcing and detailed project tasks.

    The overall IT Strategic Plan Project Structure and May 2012 status is provided below.

    Task Name % Complete Duration Start Finish

    IT Strategic Plan Implementation 31% 722.25 days Tue 9/20/11 Mon 7/7/14

    Project Kickoff 100% 0.25 days Tue 9/20/11 Tue 9/20/11

    Monitoring, Planning and Management 58% 254 days Tue 10/4/11 Tue 10/2/12

    On-Site 56% 254 days Tue 10/4/11 Tue 10/2/12

    Ongoing Cutover Progress 62% 244 days Mon 10/10/11 Mon 9/24/12

    Realign IT Department with County Needs 55% 479 days Tue 9/20/11 Wed 7/31/13

    Reorganize IT 100% 21.75 days Tue 9/20/11 Wed 10/19/11

    Develop IT Policies and Processes 100% 30.5 days Wed 11/30/11 Wed 1/18/12

    Expand IT Staff and Services 62% 142.25 days Tue 10/18/11 Mon 5/14/12

    Develop IT Governance 0% 61 days Tue 5/7/13 Wed 7/31/13

    Solidify and Protect the County's

    Technical Infrastructure22% 438.25 days Tue 9/20/11 Tue 6/4/13

    Service Desk Toolset 100% 24 days Tue 9/20/11 Mon 10/24/11

    Preliminary Network Design 100% 64.75 days Tue 10/4/11 Thu 1/12/12

    Network Integrator Vendor Research 100% 14 days Thu 1/12/12 Tue 1/31/12

    Detailed Network Design 67% 92 days Wed 2/1/12 Thu 6/7/12

    IT Staff Office Requirements 0% 13 days Mon 7/16/12 Wed 8/1/12

    Implement IT Staff Office 0% 85 days Thu 8/2/12 Wed 11/28/12

    Deploy Physical Layer 0% 241.25 days Tue 9/20/11 Fri 8/31/12

    Deploy Network Layer 0% 257.25 days Fri 6/8/12 Tue 6/4/13

    Network Complete 0% 0 days Tue 5/28/13 Tue 5/28/13

    Improve the Serviceability of the County's

    Applications Environment32% 722.25 days Tue 9/20/11 Mon 7/7/14

    Re-initiate Odyssey Deployment 37% 722.25 days Tue 9/20/11 Mon 7/7/14

    Integrate GIS into County Applications 0% 154 days Tue 6/11/13 Mon 1/13/14

    The following sections provide an update to each of the commissions goals.

  • 7/30/2019 Ector County IT Strategic Plan

    8/29

    Ector County

    Information Technology Strategic Plan for 2012 2016

    2012 Plan Update

    eGov Consulting Services Page 5

    Section 2:

    Realign IT Department with Countys Needs 2012 Goal

    Update

    2.1 IT Plan Overview

    Many County IT organizations are undergoing a significant, strategic transformation to a

    customer-focused service delivery organization. This requires that governance structures and

    processes, organizational structures, sourcing methods and core policies and processes must be

    reevaluated. This is accomplished through the initiatives included in this section:

    Develop IT Governance Structure & Process Reorganize the IT Department

    Expand IT Staff and Services

    Develop IT Policies and Processes

    2.2 Develop IT Governance Structure and Process

    IT Plan Initiative

    The County should establish an IT Governance Committee with authority to determine theongoing technology direction for the County, associated charter, and processes for projects and

    IT Department performance review.

    May 2012 Update

    This initiative was postponed until the IT staff could be increased. The IT staff has been

    operating with very limited staff due to staff resignations, illness and maternity leave. The

    limited staff had capacity to only manage critical support calls. As of May 2012 the County has

    hired an additional Help Desk Technician and the IT staff members that were out for illness and

    maternity have returned. Once the core network is installed and stabilized the governance

    structure will implemented.

    Next Steps

    Postpone the Governance process until the hiring of the IT Manager in Year 3 2014.

  • 7/30/2019 Ector County IT Strategic Plan

    9/29

    Ector County

    Information Technology Strategic Plan for 2012 2016

    2012 Plan Update

    eGov Consulting Services Page 6

    2.3 Reorganize the IT Department

    IT Plan Initiative

    The County should implement the new organizational structure, shown below, with job

    descriptions that detail responsibilities. This structure serves to:

    Separate reactive functions (e.g., Customer Service) from pro-active functions (e.g.,

    Technology Planning)

    Provide a technology-oriented, systems capabilities-focused position that is responsible for

    making activity happen on-time and on-budget within IT in the form of a project manager,

    who is also a business-oriented and customer-facing

    Provides formalized major applications support with within the IT Department

    Provides professional network management and systems administration, including security,

    and Isolates the triage mindset in Customer Service from the rest of the project-oriented IT

    Department.

    This organization assumes that the IT Department has made and is utilizing the necessary

    operational improvements (e.g., Remote Control Software, Lock Down administrative rights)

    and streamline key IT processes (e.g., Service Desk Management, Incident Management) to

    allow the IT organization to operate more effectively.

    The structure of the Information Technology Department is designed to support both strategic,

    proactive activities as well as tactical, reactive activities. It will evolve over the first four years of

    the Plan:

    Beginning with a re-organization in Year 1

    Hiring of the Infrastructure Support Supervisor and Odyssey Support Analyst in Year 2

    Hiring of the IT Manager and the Applications Support Supervisor to support the new

    financial applications in Year 3

    The Year 1 staffing changes are illustrated below.

  • 7/30/2019 Ector County IT Strategic Plan

    10/29

    Ector County

    Information Technology Strategic Plan for 2012 2016

    2012 Plan Update

    eGov Consulting Services Page 7

    Customer

    Service

    Supervisor

    Technology

    Planning

    Help Desk

    Technician

    IT Manager

    Help Desk

    Technician

    Systems

    Administrator

    Infrastructure

    Support

    Supervisor

    Key

    New Hires

    Outsourced Function

    Proactive Reactive

    Contracts Management

    Project Management

    Business Analysis

    Applications

    Support

    Supervisor

    Odyssey Support

    Analyst

    Major Applications Odyssey Support

    GIS Support

    WEB-based Systems

    Interface Development

    Security Windows Server

    Network/Storage

    Colocation Site Help Desk

    Technician

    Commissioners Court

    Ector County IT Staffing

    Plan Year 1

    May 2012 Update

    The plan called for the re-organization of the department in Year 1 and hiring into the

    infrastructure area in Year 2. The re-organization was completed by moving one of the Help

    Desk Technicians to the infrastructure area as the Infrastructure Support Supervisor rather than

    the System Administrator. The technician demonstrated the ability and commitment to

    perform the position. However, during the transition all of the Help Desk Technicians were

    unavailable due to resignation, illness, and maternity leave. The existing Customer Service

    Supervisor was reassigned to support the Public Safety area. The focused support of the Public

    Safety area proved to be beneficial due to the complexity of the law enforcement technology,

    thus a Public Safety Service Supervisor position has been created to support the Sheriff and Jail

    Complex.

  • 7/30/2019 Ector County IT Strategic Plan

    11/29

    Ector County

    Information Technology Strategic Plan for 2012 2016

    2012 Plan Update

    eGov Consulting Services Page 8

    The following is the revised organizational structure implemented in Year 1.

    Customer

    Service

    Supervisor

    Technology

    Planning

    Help DeskTechnician

    IT Manager

    Help Desk

    Technician

    SystemsAdministrator

    Infrastructure

    Support

    Supervisor

    Key

    New Hires

    Outsourced Function

    Proactive Reactive

    Contracts Management

    Project Management

    Business Analysis

    Applications

    Support

    Supervisor

    Odyssey SupportAnalyst

    Major Applications

    Odyssey Support

    GIS Support

    WEB-based Systems

    Interface Development

    Security

    Windows Server

    Network/Storage

    Colocation Site

    Commissioners

    Court

    Ector County IT Staffing

    Plan Year 1

    Public Safety

    Service

    Supervisor

    Public Safety End User

    Dispatch, Jail and

    Sheriff Operation

    support

    Administrative End User

    Annex, Courthouse and

    all non-public safety

    support.

    Help Desk

    Technician

    Next Steps

    Create a permanent position for Public Safety Service Supervisor. Create a new System

    Administrator position to support the new domain, email and server infrastructure. Transfer

    one of the Help Desk Technicians to the Odyssey Support Analyst and provide them with

    Odyssey training.

    The Year 2 reorganization is shown below.

  • 7/30/2019 Ector County IT Strategic Plan

    12/29

    Ector County

    Information Technology Strategic Plan for 2012 2016

    2012 Plan Update

    eGov Consulting Services Page 9

    2.4 Expand the IT Staff and Services

    IT Plan Initiative

    The County should add at least an additional four staff to the IT Department and outsource

    ongoing technology planning support.

    May 2012 Update

    A new Help Desk Technician was hired and the other two Technicians have returned from sick

    and maternity leave. They temporarily report to the Public Safety Service Supervisor until aCustomer Service Supervisor is hired.

    Next Steps

    Complete the hiring of the Customer Service Supervisor. Re-assign one of the Help Desk

    Technicians to the Odyssey Support Analyst. Hire a Systems Administrator. Backfill the re-

    assigned Help Desk Technician and have them all report to the Customer Service Supervisor.

    Customer

    Service

    Supervisor

    Technology

    Planning

    Help Desk

    Technician

    IT Manager

    Help Desk

    Technician

    Systems

    Administrator

    Infrastructure

    Support

    Supervisor

    Key

    New Hires

    Outsourced Function

    Proactive Reactive

    Contracts Management

    Project Management

    Business Analysis

    Applications

    Support

    Supervisor

    Odyssey Support

    Analyst

    Major Applications

    Odyssey Support

    GIS Support

    WEB-based Systems

    Interface Development

    Security

    Windows Server

    Network/Storage

    Colocation Site

    Commissioners

    Court

    Ector County IT Staffing

    Plan Year 2

    Public Safety

    Service

    Supervisor

    Public Safety End User

    Dispatch, Jail and

    Sheriff Operation

    support

    Administrative End User

    Annex, Courthouse and

    all non-public safety

    support.

    Help Desk

    Technician

  • 7/30/2019 Ector County IT Strategic Plan

    13/29

    Ector County

    Information Technology Strategic Plan for 2012 2016

    2012 Plan Update

    eGov Consulting Services Page 10

    2.5 Develop IT Policies and Processes

    IT Plan Initiative

    A recent research study1 used the concepts of Total Quality Management (TQM) to develop an

    ITIL deployment roadmap that focused the key ITIL processes that most impacted customer

    service needs. Those primary processes that are linked to providing optimized service request

    fulfillment were:

    Service Desk

    Incident Management.

    Additional ITIL Processes that support the operation include:

    Network Management Security Management

    Storage Management

    The implementation of the Service Desk and Incident Management processes will have the

    greatest effect on Customer Service and should be a priority for the IT Department. The IT

    Department has very few replicable processes in place. However, due to its low turnover rate,

    many of the processes are inherently performed by the IT personnel. The organization has

    worked because the staff simply knows what to do. However, if the County has an increase in

    turnover rate or explores alternate support and staffing options such as business process

    outsourcing, it must address the lack of documentation of the process being considered for

    outsourcing.

    In a recent 2005 study2 conducted by the MIS Center for Information Systems Research (CISR)

    of 90 outsourcing deals at 84 companies, CIOs showed much greater satisfaction with

    outsourcing arrangements where the processes were well-defined and had clear business rules.

    Nine out of 10 IT executives in the study reported success with their transaction outsourcing.

    If the County chooses to outsource any functions, then the vendor chosen should be advanced

    in their development and practice of ITIL processes. The County should be careful to choose a

    vendor that has a mature process (i.e., documented process with available metrics on processperformance) in place.

    1ITIL implementation roadmap based on process governance Dorota Nicewicz-Modrzewska, Przemysaw Stolarski,

    Adam Mickiewicz University Computer Centre, ul. Umultowska 89a, Poznan, Poland,

    2Simple Successful Outsourcing by Stephanie Overby, October 1, 2005 CIO Magazine

  • 7/30/2019 Ector County IT Strategic Plan

    14/29

    Ector County

    Information Technology Strategic Plan for 2012 2016

    2012 Plan Update

    eGov Consulting Services Page 11

    May 2012 Update

    With the deployment of the Service Desk software, the Service Desk and Incident Management

    Process were codified and training was provided to the IT Staff and End-Users. In addition, asuper user and subject matter experts group was created to assist the Customer Service group

    by distributing the problem resolution process. With the temporary vacancies of the IT Help

    Desk Technicians and the lack of direct Customer Service Supervision performance statistics

    have not been adequately maintained.

    Next Steps

    With the expected completion of the Local and Wide Area Network, the Network, Security and

    Storage management processes will have to be developed in conjunction with the

    Infrastructure Supervisor. Also once the Customer Service Supervisor is hired they will be ableto adequately track the support statistics, and manage the incident process with the super

    users and SMEs.

  • 7/30/2019 Ector County IT Strategic Plan

    15/29

    Ector County

    Information Technology Strategic Plan for 2012 2016

    2012 Plan Update

    eGov Consulting Services Page 12

    Section 3:

    Solidify and Protect the Countys Technical

    Infrastructure 2012 Goal Update

    3.1 IT Plan Overview

    To best meet the rising demands of its customers and address the complexities of connectivity

    required by the Countys enterprise applications, the County must solidify and protect its

    technical infrastructure. This is accomplished through the initiatives included in this section:

    Acquire and Implement a Service Desk Toolset

    Deploy Storage Area Network (SAN) / Backup System

    Deploy a New Network

    Build-Out New Computer rooms at the Annex and Sheriff's Office

    Migrate Distributed Computer Rooms to Off-Site Managed Computing Center

    New VOIP System

    3.2 Acquire and Implement a Service Desk Toolset

    IT Plan Update

    The County should acquire and implement a toolset to

    be used by the IT Departments Customer Service to

    record incidents, track progress and identify trends in

    order to continuously improve service desk

    performance.

    May 2012 Update

    Completed

  • 7/30/2019 Ector County IT Strategic Plan

    16/29

    Ector County

    Information Technology Strategic Plan for 2012 2016

    2012 Plan Update

    eGov Consulting Services Page 13

    3.3 Deploy a Storage Area Network (SAN) / Backup System

    IT Plan Initiative

    The County should deploy a storage area network (SAN) with a supportable system that

    provides for the safe and recoverable storage of the core applications (i.e. Odyssey and Incode)

    May 2012 Update

    The County has explored the use of Region SAN as a disaster recovery backup. However, the

    County has also begun to explore the outsourcing of the core Tyler applications (i.e. Odyssey

    and Incode) to a Tyler hosting facility. This would mitigate the need for an extensive SAN and

    would delay the deployment to a limited outsourced SAN in Year 3 2014.

    Next Steps

    Pursue an Outsourcing contract with Tyler for the Odyssey system after completion of the new

    network and of the Odyssey civil applications. This process could be initiated in Year 2 2013

    and completed in Year 3 2014.

    3.4 Deploy a New Network

    IT Plan Initiative

    The County should develop a new metropolitan area network (MAN) / local area network(LAN), layer 4 transport, and network management system Countywide.

    This would include:

    A Countywide MAN inter-connecting all major County facilities to the Annex (Network Core)

    Standardizing and simplifying the network architecture and systems management by

    initially integrating access switching, core switching, and eventually providing for server

    virtualization, telephony services and building wireless access so that systems management

    and security can be managed end to end.

    Centralizing the network core on fault tolerant network switches Installing a new Data network at each County Facility supporting 10/100/1000 switched

    Ethernet, supporting QoS.

    The diagram below illustrates the conceptual design for the new network.

  • 7/30/2019 Ector County IT Strategic Plan

    17/29

  • 7/30/2019 Ector County IT Strategic Plan

    18/29

    Ector County

    Information Technology Strategic Plan for 2012 2016

    2012 Plan Update

    eGov Consulting Services Page 15

    The design called for the reuse of as much of the existing tower assets within Ector County,

    including the use of City of Odessa towers. However, the City Odessa expressed concerns

    regarding the loading stress on their towers. The County has had to build an extra tower in

    order to obtain the appropriate line of site network connection.

    The backhaul microwave network is shown below:

  • 7/30/2019 Ector County IT Strategic Plan

    19/29

    Ector County

    Information Technology Strategic Plan for 2012 2016

    2012 Plan Update

    eGov Consulting Services Page 16

    Next Steps

    Finalize network IP subnetting and switching design. Deployment is expected to be completed

    in Year 1 by the fall of 2012.

    A review of the legacy LMR radio infrastructure should be performed in Year 2 2013 in order

    to verify integrity of the LMR system.

  • 7/30/2019 Ector County IT Strategic Plan

    20/29

    Ector County

    Information Technology Strategic Plan for 2012 2016

    2012 Plan Update

    eGov Consulting Services Page 17

    3.5 Build-Out New Computer rooms at the Annex and Sheriff's Office

    IT Plan Initiative

    The County should build out new computer room capabilities, one at the Annex to provide core

    communications functions, and one at the Sheriff's Office to provide support for core law

    enforcement systems. This would include:

    Upgrading the Annex computer room to house the network core and potentially the virtual

    desktop servers. Although these items could be externally hosted, due to the fundamental

    importance of the network and desktop management, the network core and the virtual

    desktop environment (if implemented) should be internally hosted and managed at the

    Annex.

    Creating a single domain structure for all County users. Implementing a SAN and modernizing server platforms to blade systems at the Annex for

    the core Odyssey applications. This will leave the existing distributed servers at the remote

    locations until they are either migrated to the external computing center or consolidated in

    the Annex computer room if an adequate external data center is not available.

    May 2012 Update

    The main computer room is being centralized at the Annex. This room was further evaluated

    for adequacy of space to house the core switching and internet connection. New racks are

    being deployed by JTS to house the new switching and wireless backbone interconnects.

    The Sheriff Office was further reviewed for adequate computer room space. After reviewing

    the existing computer room and the 911 room, the 911 room was selected due to space

    availability, ease of interconnection to the critical servers, and reduced cost of installation.

    The courthouse computer room, although inadequate from a wire management perspective,

    will be continued to be used in the short term since the court does not want to make

    substantial infrastructure investments in the Courthouse. The computer room houses the

    Odyssey servers and switching. However, once the Odyssey servers are remotely hosted the

    need for this room will be reduced.

    Next Steps

    Continue deployment of the new racks at each of the County facilities, verify cabling adequacy

    replacing any bad cabling. This is expected to be completed in Year 1, second quarter of 2012.

  • 7/30/2019 Ector County IT Strategic Plan

    21/29

    Ector County

    Information Technology Strategic Plan for 2012 2016

    2012 Plan Update

    eGov Consulting Services Page 18

    3.6 Migrate Distributed Computer Rooms to Off-Site ManagedComputing Center

    IT Plan Initiative

    The County should consolidate all application servers throughout the County, except CAD, to a

    single location; provide managed services for backup, monitoring and alerting in a virtual

    environment. Since the County is short IT staff members, and users are requiring greater

    amount of analytical support.

    In order to provide improve the level of systems management and overall support the County

    could migrate the support of the servers to an off-site hardened managed data center site. The

    migration would include:

    Moving (or replacing as required) the remaining distributed servers throughout the county.

    In considering the move of the servers to a potentially virtualized outsourced data

    center, a server test bed would have to be created to verify with the applications

    vendors those that could operate in a virtualized environment.

    Purchasing, deploying and integrating a new core switch with the existing County network.

    Deploying a new secondary storage area network (SAN).

    Deploying a fiber network link from the Annex to the managed data center.

    The outsourcing of these systems to an external site could then allow the IT Department to

    focus more on business analysis functions rather than infrastructure support and provide the

    County with disaster recovery site.

    May 2012 Update

    The outsourcing of these systems has been explored with Region 18. Region 18 will be

    providing the core switching and fiber trunking between the Annex and their data center for

    Internet access and offsite storage. This migration will allow Ector County to save the cost of

    deploying a long haul fiber link and SAN storage. It will allow for the outsourcing of the

    Odyssey and Incode applications to the Tyler hosting facility.

    Next Steps

    An overall migration of all of the Ector County servers will be reconsidered in Year 3 once the

    WAN and Internet is deployed and the Infrastructure support staff is fully engaged to support

    the existing systems. The County will also consider using Region 18 as an external SAN storage

    host.

  • 7/30/2019 Ector County IT Strategic Plan

    22/29

    Ector County

    Information Technology Strategic Plan for 2012 2016

    2012 Plan Update

    eGov Consulting Services Page 19

    3.7 New Voice Over IP System

    IT Plan Initiative

    The County should deploy a new network integrated Voice over IP system to replace aging PBX

    once the maintenance contract expires.

    May 2012 Update

    This was planned for Year 5.

    Next Steps

    Continue with original plan strategy.

  • 7/30/2019 Ector County IT Strategic Plan

    23/29

    Ector County

    Information Technology Strategic Plan for 2012 2016

    2012 Plan Update

    eGov Consulting Services Page 20

    Section 4:

    Improve Serviceability of Countys

    Applications Environment 2012 Goal Update

    4.1 IT Plan Overview

    Ector County has traditionally had a siloed approach to its applications architecture, with

    disparate applications used for most County functions and little integration between them.

    Historically, systems were originally acquired based upon their ability to support departmental

    needs; the systems acquisition process did not require the development of detailedspecifications against which all vendors would be evaluated, nor did it consider the wider

    technology environment in which applications would be deployed and supported.

    Two relatively recent acquisitions by the County have challenged the siloed approach: Incode

    and Odyssey. These are state-of-the-art applications recently introduced to the marketplace

    have the ability to integrate or interface to other systems; in fact, these fully integrated systems

    are available that handle end-to-end functionality for key functional areas, such as County

    operations and public safety. In addition, these applications have the inherent ability to

    (a) leverage key data, such as GIS, that could be used to link disparate systems together, and (b)

    streamline operational workflows for improved process efficiency when done in conjunction

    with process re-engineering.

    The future state of Ector Countys applications and their various interacts are illustrated below.

  • 7/30/2019 Ector County IT Strategic Plan

    24/29

  • 7/30/2019 Ector County IT Strategic Plan

    25/29

    Ector County

    Information Technology Strategic Plan for 2012 2016

    2012 Plan Update

    eGov Consulting Services Page 22

    4.2 Desktop Replacement Program

    IT Plan Initiative

    The County should consider investing in a multi-year budgeted desktop equipment replacement

    plan, which, in the short term, would bring all the computers up to a capability that would

    support Windows 7.

    May 2012 Update

    This project was postponed to Year 2 due to limited staff and lack of network connectivity to

    deploy new software.

    Next Steps

    Deploy new workstations with Windows 7/Office connected to MS Exchange once the network

    is completed.

    4.3 Consider Virtual Desktop

    IT Plan Initiative

    The County should consider the deployment of a Virtual Desktop Infrastructure, which would

    allow it to leverage the limited IT staff it has available for upgrades of hardware and software.

    However this should be considered once the Countys network infrastructure is mature, the IT

    staff is prepared to support the higher level of complexity, and the economics of the virtual

    desktop environment is more favorable than the replacement of legacy desktop units.

    May 2012 Update

    The project was not planned until Year 4. With the delay of the desktop deployment this

    project can be delayed to Year 5.

    Next Steps

    Continue with plan strategy for Year 5 implementation.

  • 7/30/2019 Ector County IT Strategic Plan

    26/29

    Ector County

    Information Technology Strategic Plan for 2012 2016

    2012 Plan Update

    eGov Consulting Services Page 23

    4.4 Integrate GIS into County Applications

    IT Plan Initiative

    The County should begin development of its GIS capabilities in cooperation with entities in the

    area that share similar geo-codes (e.g., City of Odessa). To do this, the County must acquire

    industry standard GIS software, i.e., ESRI and integrate it with the Odessa GIS Server.

    May 2012 Update

    This project has been postponed to Year 3 due to lack of network connectivity an effective

    Odyssey implementation.

    Next Steps

    Deploy in Year 3.

    4.5 Re-Initiate the Deployment of Odyssey Court/Public Safety System

    IT Plan Initiative

    The County should re-evaluate the Odyssey deployment, including:

    Reviewing functional requirements and acceptance criteria to determine original functional

    needs.

    Reviewing Tyler deliverables to date and how they met the acceptance criteria. Reviewing the project management and governance methodology to determine functional

    decision making process and progress to date and path forward.

    May 2012 Update

    All of the plan initiatives were completed. The next steps were further reviewed with the

    Council of Urban Counties (CUC) in order to determine the cost estimate for resolving the

    existing deployment issues. In addition, the Ector County court staff was engaged and trained

    on the use of the Odyssey system. As of this update the Court Staff is coordinating with IT to

    schedule a business workflow review of the civil processes. As of this update a date has not

    been agreed by the Court staff.

    Next Steps

    Finalize date with court staff to perform business workflow review. Obtain detailed cost from

    Tyler to resolve deployment constraints. Implement required changes to the civil systems in

    Year 2 2013 and the Criminal Systems in Year 3 2014.

  • 7/30/2019 Ector County IT Strategic Plan

    27/29

    Ector County

    Information Technology Strategic Plan for 2012 2016

    2012 Plan Update

    eGov Consulting Services Page 24

    4.6 Consider the Migration of Incode to a Cloud-based Environment

    IT Plan Initiative

    Continue to operate with the existing version of Incode. Consider the migration of Incode to a

    Cloud-based Environment as the application and County network infrastructure matures.

    May 2012 Update

    The Incode migration to the Tyler hosting site was explored and the feasibility verified.

    Next Steps

    Complete network/internet deployment as well as Odyssey migration to the Tyler hosting site.

    Continue with the original plan for deployment in Year 4.

  • 7/30/2019 Ector County IT Strategic Plan

    28/29

    Ector County

    Information Technology Strategic Plan for 2012 2016

    2012 Plan Update

    eGov Consulting Services Page 25

    Section 5:

    Investment Updates

    5.1 Overview

    This section details the calendarized investments for the implementation, both one-time and

    recurring, and the related implementation schedule for the initiatives described in the plan.

    5.2 Updated Implementation Schedule

    The following reflects the timeline updates to the Strategic Plan.

    Year 1

    Q1 Q2 Q3 Q4

    Year 2

    Q1 Q2 Q3 Q4

    Year 3

    Q1 Q2 Q3 Q4

    Year 4

    Q1 Q2 Q3 Q4

    Year 5

    Q1 Q2 Q3 Q4

    Develop IT Governance

    Goal 1: Realign IT Department with County Needs

    Reorganize IT

    Expand IT Staff and Services

    Develop IT Policies/Processes

    Goal 2: Solidify and Protect the Countys Technical Infrastructure

    Service Desk Toolset

    Deploy San/Backup System

    Deploy New Network

    New Data Centers

    Migrate Computer Rooms

    New VOIP System

    Goal 3: Improve the Serviceability of the Countys Applications Environment

    Migrate Incode to Cloud

    Desktop Replacement Program

    Virtual Desktop Program

    Initiate GIS

    Re-Initiate Odyssey Deployment

  • 7/30/2019 Ector County IT Strategic Plan

    29/29

    Ector County

    Information Technology Strategic Plan for 2012 2016

    2012 Plan Update

    5.3 Updated Calendared Investments

    The 2012 updated calendared investments, both one-time and recurring, are shown in the

    diagram below. The original plan forecast is also shown for comparison.

    2012 Calendared Investments

    Original 2011 Plan Calendared Investments

    $0

    $200,000

    $400,000

    $600,000

    $800,000

    $1,000,000

    $1,200,000

    $1,400,000

    1 2 3 4 5

    Years

    One-time

    Recurring

    Year 1 Year 2 Year 3 Year 4 Year 5 TotalOne-Time $1,384,445 $1,308,376 $482,938 $135,100 $1,000,100 $4,310,959

    Recurring $18,767 $585,328 $1,176,660 $1,250,460 $1,300,460 $4,331,675

    TOTALS $1,403,211 $1,893,704 $1,659,598 $1,385,560 $2,300,560 $8,642,633

    Calendari zed Investment

    Year 1 Year 2 Year 3 Year 4 Year 5 Total

    One-Time $1,811,500 $365,235 $2,390,000 $340,000 $725,000 $5,631,735

    Recurr ing $49,000 $628,905 $859,105 $710,105 $903,855 $3,150,970

    TOTALS $1,860,500 $994,140 $3,249,105 $1,050,105 $1,628,855 $8,782,705

    Calendari zed Investment


Recommended