STATEWIDE BUSINESS PROCESS PROCEDURE
Project Management Status Reporting
Draft
Office of the Chief Information Officer
Department of Administration
State Information Technology Services Division
PO Box 200113
Helena, MT 59620-0113
Tel: (406) 444-2700
FAX: (406) 444-2701
DEPARTMENT OF ADMINISTRATION
Janet R. Kelly, Director
STATE INFORMATION TECHNOLOGY SERVICES DIVISION
Richard B. Clark, Chief Information Officer
Brian Schweitzer
Governor
State of Montana
7/29/2019 Draft Status Report New
2/17
7/29/2019 Draft Status Report New
3/17
S T A T E W I D E P R O C E D U R E : P R O J E C T M A N A G E M E N T S T A T U S
R E P O R T I N G
P A G E 3
DRAFT STATEWIDE PROCEDURE:PROJECT MANAGEMENT STATUS REPORTING
EFFECTIVE DATE: APPROVED:
I. Procedure Purpose
This Statewide Procedure defines the steps that agencies shall follow to deliver status information
of an agency reported project to the State IT PMO. The information shall be presented to
enterprise funding authorities and other interested parties with the results of the project.
This Procedure implements the requirements of the State of Montana Information Technology
Project Management Policy and MCA 2-17-521(4)(c).
II. Applicability
This Procedure applies to agencies and third-parties (such as contractors or other service
providers), who provide project management services related to the planning, implementation and
closeout of IT projects.
III. Scope
This Procedure applies to IT projects funded through the Long Range IT Plan (LRITP) or as
required by the State of Montana Chief Information Officer (CIO), Office of Budget and ProgramPlanning (OBPP), or Legislative Finance Committee (LFC).
IV. Definitions
Term Definition
Status Report A report required during the course of a project which documents the
current status of the project.
Data A subset of information in an electronic format that allows it to be retrieved
or transmitted. Reference theNational Information Assurance (IA)
Glossary.Variance A quantifiable deviation, departure, or divergence away from a known
baseline or expected value. For the purpose of this procedure, Variance
shall be graphically depicted with a (triangle) or delta symbol.
Reference theGuide to the Project Management Body of Knowledge
(PMBOK Guide)-Fourth Edition.
http://www.cnss.gov/Assets/pdf/cnssi_4009.pdfhttp://www.cnss.gov/Assets/pdf/cnssi_4009.pdfhttp://www.cnss.gov/Assets/pdf/cnssi_4009.pdfhttp://www.cnss.gov/Assets/pdf/cnssi_4009.pdfhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.cnss.gov/Assets/pdf/cnssi_4009.pdfhttp://www.cnss.gov/Assets/pdf/cnssi_4009.pdf7/29/2019 Draft Status Report New
4/17
S T A T E W I D E P R O C E D U R E : P R O J E C T M A N A G E M E N T S T A T U S
R E P O R T I N G
P A G E 4
Term Definition
Variance Criteria Criteria established for measurement of Variance.
Organizational
Process Assets
Any or all process-related assets, from any or all of the organizations
involved in the project that are or can be used to influence the projects
success. These process assets include formal and informal plans, policies,
procedures, and guidelines. The process assets also include the
organizations knowledge bases such as lessons learned and historical
information.
Reference theGuide to the Project Management Body of Knowledge
(PMBOK Guide)-Fourth Edition.
Refer to the separate document, Asset Usage Handling Instructions: Confidential Information
for information-related definitions.
Refer to theStatewide Information System Policies and Standards Glossaryfor a list of local
definitions.
Refer to the Guide to the Project Management Body of Knowledge (PMBOK Guide)-Fourth
Editionand the Dictionary of Project Management Terms published by ESI International for
project management definitions. Where terminology is in conflict, the definitions within the
PMBOK Guide shall take precedence.
V. Roles and Responsibilities
The following roles and responsibilities support this procedure:
Agency Project
Manager
Project manager as defined in the agencys Project Management Plan. The
Project Manager submits the Status Report to the IT PMO.
State IT Project
Management
Office (IT PMO)
Tracks, reviews, and retains Status Reports for use in other enterprise
documents; analyzes for process improvement; and identifies potential
training needs and facilitates as appropriate.
VI. Requirements
Information contained in the Status Report delivered to the IT PMO shall be used in the
development of enterprise-required documents.
Reference the separate document, Asset Usage Handling Instructions: Confidential
Information for guidance on originating, securing, transmitting, and storing non-public
information which may be included in the deliverables identified in this procedure.
http://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://itsd.mt.gov/content/policy/policies/Administration/Statewide_Glossary_IS_Policies_and_Standards.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Statewide_Glossary_IS_Policies_and_Standards.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Statewide_Glossary_IS_Policies_and_Standards.pdfhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://itsd.mt.gov/content/policy/policies/Administration/Statewide_Glossary_IS_Policies_and_Standards.pdfhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspx7/29/2019 Draft Status Report New
5/17
S T A T E W I D E P R O C E D U R E : P R O J E C T M A N A G E M E N T S T A T U S
R E P O R T I N G
P A G E 5
A. Information Management
The information within individual Status Reports are Information Assets1, owned by individuals
within their respective agencies. Unless specified otherwise by the agency, the agency head or
equivalent executive officer is the Information Owner2.
IT PMO-operated information system usage and performance data, information, and statistics
shall be owned and maintained by IT PMO.
B. Reporting
Agencies shall develop and submit Status Reports to the IT PMO for all reported projects in
accordance with the requirements defined in Appendix A. Project status shall signify current
status of the schedule, scope and budget of the project. The Status Reportshall:
Describe the results variance (i.e., the difference) between the current status and
the last status report based on the information requirements published by the IT PMO
(See Appendix A).
1 Reference Asset Usage Handling Instructions: Confidential Information.
2 Ibid.
7/29/2019 Draft Status Report New
6/17
S T A T E W I D E P R O C E D U R E : P R O J E C T M A N A G E M E N T S T A T U S
R E P O R T I N G
P A G E 6
VII. Enterprise Review Process
The goal of Status Reporting is to provide the stakeholders with information by which the current
results of the project can be evaluated and approved, and if needed, courses of action can be
developed, recommended, and implemented. The Enterprise Review Process (Figure 1)
establishes the procedural relationship between reporting project results and review by
executives. This process is the basis for IT PMO reporting requirements and actions.
Figure 1 Enterprise Review Process
The process has six phases, four of which are addressed within this procedure:
1 - Establish Information Requirements (This procedure)
2 - Collect Information (This procedure)
3 - Analyze Information(This procedure)
4 - Distribute Finished Analysis(This procedure)
5 - Evaluate Results
6 - Deliberations
This procedure specifies the actions taken to accomplish Phases 1 through 4, above.
7/29/2019 Draft Status Report New
7/17
S T A T E W I D E P R O C E D U R E : P R O J E C T M A N A G E M E N T S T A T U S
R E P O R T I N G
P A G E 7
VIII. Procedure
A. Phase 1Information Requirements
The IT PMO shall maintain and publish a list (Appendix A) of information required within
agency Status Reports. This list shall be updated as required. The required information shall bebased upon the documentation defined within the PMBOK Guide.
Figure 2 Information Requirements Phase
State IT PMO procedural steps:
1. Develops information requirements.
2. Reviews requirements with the CIO and the PMOAG.
3. Disseminates final information requirements via email to all project managers of
record and the PMOAG.
7/29/2019 Draft Status Report New
8/17
S T A T E W I D E P R O C E D U R E : P R O J E C T M A N A G E M E N T S T A T U S
R E P O R T I N G
P A G E 8
B. Phase 2Collect Information
Figure 3 Collection Phase
The following procedure shall be used to develop and deliver an agency project Status Report. In
accordance with the requirements defined in Appendix A, the project manager on behalf of the
agency shall:
1. Classify the information within the Status Report according to the agencys
information management requirements.
2. Deliver the Status Report to the IT PMO, which meets the information requirements
published by the IT PMO as Appendix A.
3. Deliver Asset Usage Handling Instructions for any confidential information3.
4. Deliver the Status Reportvia email to the IT PMO [email protected].
Upon receipt of the Status Reportthe IT PMO shall:
1. Verify that the report meets the information requirements:
a. If it does, the report state is accepted.
b.
If it does not, the report state is not accepted.2. Acknowledge receipt of an accepted report, and the Collection Phase is complete.
3. On error, or if the report is not accepted, resolve discrepancies with the submitter.
3 Ibid.
http://c/Local_Documents/My_MT_Documents/8-Policy%20Projects/Proj_Mgmt/Closeout%20Procedure/[email protected]://c/Local_Documents/My_MT_Documents/8-Policy%20Projects/Proj_Mgmt/Closeout%20Procedure/[email protected]://c/Local_Documents/My_MT_Documents/8-Policy%20Projects/Proj_Mgmt/Closeout%20Procedure/[email protected]://c/Local_Documents/My_MT_Documents/8-Policy%20Projects/Proj_Mgmt/Closeout%20Procedure/[email protected]7/29/2019 Draft Status Report New
9/17
S T A T E W I D E P R O C E D U R E : P R O J E C T M A N A G E M E N T S T A T U S
R E P O R T I N G
P A G E 9
Upon completion of the Collection Phase, the information shall be analyzed within the Analysis
Phase.
C. Phase 3Analyze Information
Figure 4 Analysis Phase
State IT PMO procedural steps:
1. Enter report data into the database.
2. Perform trend analysis based on the criteria in Appendix B.
3. Identify (any) anomalies needing clarification from project managers.
4. Resolve any anomalies with project managers, and update database.
5. Review the database looking for items that were efficient/effective in the process of
managing the IT projects.
6. Identify areas for potential improvement.
7. Identify items for inclusion within the public Project Management Knowledge Base.
8. Periodically review the data base and Knowledge Base to identify trends:
a. Areas where efficiencies could be gained
b. Potential problems
c. Best practices
9. If an area for improvement is noted, work with the process owners and other
stakeholders to formulate recommendations for process changes.
7/29/2019 Draft Status Report New
10/17
S T A T E W I D E P R O C E D U R E : P R O J E C T M A N A G E M E N T S T A T U S
R E P O R T I N G
P A G E 1 0
D. Phase 4Distribute Finished Analysis
Figure 5 Distribution Phase
State IT PMO procedural steps:
1. Assemble finished analysis reports.
a. Provide for CIO review of report information.
b. Correct factual errors.
c. Obtain CIO approval of the finished reports.
2. Present to stakeholders.
a. Reports will be submitted to the CIO Office.
b. For LFC reportable projects, CIOs Office will submit reports to the LFC
3. Post finished analysis as required.
a. Hard copy of reports shall be archived within the IT PMO in accordance with
Records and Information Management Procedures
b. Electronic copy of reports will be parsed and presented to mature PM
practices within the state.
7/29/2019 Draft Status Report New
11/17
S T A T E W I D E P R O C E D U R E : P R O J E C T M A N A G E M E N T S T A T U S
R E P O R T I N G
P A G E 1 1
IX. Change Control and Exceptions
TheStatewide Procedure: Development of Statewide Information Technology Procedures and
Guidelines Procedureshall govern procedure changes or exceptions. Submit requests for a
review or change to this instrument by Action Request form (at
http://itsd.mt.gov/content/policy/policies/Administration/action_request.doc ). Submit requests
for exceptions by anException Request form (at
http://itsd.mt.gov/content/policy/policies/Administration/exception_request.doc ). Changes to
policies and standards will be prioritized and acted upon based on impact and need.
X. Closing
Direct questions or comments about this instrument to the State of Montana Chief Information
Officer atSITSD Service Desk(athttp://servicedesk.mt.gov/ess.do ), or:
PO Box 200113
Helena, MT 59620-0113(406) 444-2700
FAX: (406) 444-2701
XI. References
A. Legislation
Title 2, Chapter 17, Part 5, MCA, et al.
B. Policies, Directives, Regulations, Rules, Procedures,
Memoranda
DRAFT Statewide Policy: Information Technology Project Management
Statewide Policy: Establishing and Implementing Statewide Information
Technology Policies and Standards
Statewide Procedure: Development of Statewide Information TechnologyProcedures and Guidelines
Procedurehttp://itsd.mt.gov/content/policy/policies/Administration/Enabling_IT_Procedure.pdf
C. Standards, Guidelines
Guide to the Project Management Body of Knowledge (PMBOK Guide)-
Fourth Edition
http://itsd.mt.gov/content/policy/policies/Administration/Procedure_and_Guideline_Development.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Procedure_and_Guideline_Development.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Procedure_and_Guideline_Development.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Procedure_and_Guideline_Development.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/action_request.dochttp://itsd.mt.gov/content/policy/policies/Administration/action_request.dochttp://itsd.mt.gov/content/policy/policies/Administration/action_request.dochttp://itsd.mt.gov/content/policy/policies/Administration/exception_request.dochttp://itsd.mt.gov/content/policy/policies/Administration/exception_request.dochttp://itsd.mt.gov/content/policy/policies/Administration/exception_request.dochttp://itsd.mt.gov/content/policy/policies/Administration/exception_request.dochttp://servicedesk.mt.gov/ess.dohttp://servicedesk.mt.gov/ess.dohttp://servicedesk.mt.gov/ess.dohttp://servicedesk.mt.gov/ess.dohttp://servicedesk.mt.gov/ess.dohttp://servicedesk.mt.gov/ess.dohttp://data.opi.mt.gov/bills/mca_toc/2_17_5.htmhttp://data.opi.mt.gov/bills/mca_toc/2_17_5.htmhttp://itsd.mt.gov/content/policy/policies/Administration/Enabling_IT_Policy.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Enabling_IT_Policy.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Enabling_IT_Policy.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Enabling_IT_Policy.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Enabling_IT_Policy.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Procedure_and_Guideline_Development.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Procedure_and_Guideline_Development.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Procedure_and_Guideline_Development.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Procedure_and_Guideline_Development.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Procedure_and_Guideline_Development.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Enabling_IT_Procedure.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Enabling_IT_Procedure.pdfhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://itsd.mt.gov/content/policy/policies/Administration/Enabling_IT_Procedure.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Procedure_and_Guideline_Development.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Procedure_and_Guideline_Development.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Procedure_and_Guideline_Development.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Procedure_and_Guideline_Development.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Enabling_IT_Policy.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Enabling_IT_Policy.pdfhttp://data.opi.mt.gov/bills/mca_toc/2_17_5.htmhttp://servicedesk.mt.gov/ess.dohttp://servicedesk.mt.gov/ess.dohttp://itsd.mt.gov/content/policy/policies/Administration/exception_request.dochttp://itsd.mt.gov/content/policy/policies/Administration/exception_request.dochttp://itsd.mt.gov/content/policy/policies/Administration/action_request.dochttp://itsd.mt.gov/content/policy/policies/Administration/action_request.dochttp://itsd.mt.gov/content/policy/policies/Administration/Procedure_and_Guideline_Development.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Procedure_and_Guideline_Development.pdf7/29/2019 Draft Status Report New
12/17
S T A T E W I D E P R O C E D U R E : P R O J E C T M A N A G E M E N T S T A T U S
R E P O R T I N G
P A G E 1 2
XII. Administrative Use
Product ID: PROC-20101129a
Proponent: Chief Information Officer
Publisher Office of the Chief Information Officer
Published Date:
Version Date: 11/29/2010
Custodian: State of Montana Chief Information Officer
Approved Date:
Effective Date:
RIM Class: Record
Disposition Instructions: Retain for Record
Change & Review
Contact:
SITSD Service Desk(athttp://servicedesk.mt.gov/ess.do )
Review: Event Review: Any event affecting this instrument may
initiate a review. Such events may include a change in
statute, key staff changes or a request for review or change.
Scheduled Review Date:
http://servicedesk.mt.gov/ess.dohttp://servicedesk.mt.gov/ess.dohttp://servicedesk.mt.gov/ess.dohttp://servicedesk.mt.gov/ess.dohttp://servicedesk.mt.gov/ess.dohttp://servicedesk.mt.gov/ess.dohttp://servicedesk.mt.gov/ess.do7/29/2019 Draft Status Report New
13/17
S T A T E W I D E P R O C E D U R E : P R O J E C T M A N A G E M E N T S T A T U S
R E P O R T I N G
P A G E 1 3
A P P E N D I X A
These requirements are established starting MMmm DD, YYYY. All prior versions are
superseded.
Status Report Information Requirements
Each Status Report shall contain information to satisfy the following:
Project Management Process Performance
Project Baseline ()
Summary of changes from current and previous project baseline during report period
Scope Performance Variance ()
Scope variance from the last Baseline Project Management Plan.
Statement of forecasting method(s) used to derive the Variance(s)
Summary of approved project changes
Current status of high issues and risks
Schedule Performance Variance ()
Schedule variance from the last Baseline Project Management Plan.
Statement of forecasting method(s) used to derive the Variance(s)
Work completed during the period
Work to be completed next
Cost Performance Variance ()
Cost variance from the last Baseline Project Management Plan.
Statement of forecasting method(s) used to derive the Variance(s)
Costs incurred.
Performance Variance ()
Analysis of past performance,
Current status of high issues and risks
Health of the project where:
7/29/2019 Draft Status Report New
14/17
S T A T E W I D E P R O C E D U R E : P R O J E C T M A N A G E M E N T S T A T U S
R E P O R T I N G
P A G E 1 4
o Green signifies project is on track and/or minimal variance from project
management plan.
o Yellow signifies warning to stakeholders, consider corrective actions or
monitor previously determined corrective actions and/or moderate
variance from project management plan.
o Red signifies problem to stakeholders, immediate corrective action(s)
required and/or major variance from project management plan.
Include the Lessons Learned that were identified by the agency during period:
o Causes of Variance(s)
o Root Cause of issues
o Reasoning behind chosen corrective action(s)
o Information distribution/communication
Report Delivery
Project managers shall meet the following delivery requirements:
1. Reporting Deadline: Close of business the first Monday of each month.
2. Project managers shall provide the report in an electronic format readable by the state
standard application.
3. Project managers shall provide the report in an electronic format that allows for word
processor merging or cut-and-paste of discrete data items.
7/29/2019 Draft Status Report New
15/17
S T A T E W I D E P R O C E D U R E : P R O J E C T M A N A G E M E N T S T A T U S
R E P O R T I N G
P A G E 1 5
State IT Project Management Office
Report Requirements
The IT PMO shall deliver reports to meet the following reporting and analysis requirements.
Executive Process
This information is developed to meet State of Montana executive decision-maker and
stakeholder requirements.
1. Legislative Finance Committee (LFC) on a quarterly basis or as required.
a. Project Baselineb. Key Project Individuals
c. Project Phased. Healthe. Funding
2. Office of Budget and Program Planning (OBPP)
a. Key Project Metrics during the reporting period
3. State of Montana Chief Information Officer (CIO) on a monthly basis or as required.
a. Key Project Metrics during the reporting period.
b. Lessons learned during the reporting period
i. Causes of Variance(s)
ii. Root Cause of issues
iii. Reasoning behind chosen corrective action(s)
iv. Information distribution/communication
Originating-Agency Quality Process
These requirements originate with one or more agencies to support (any) agency quality
management programs, and shall be individually defined by those agencies.
1. Comparison of Agency standing vis--vis the mean/average in agency-define criteria.
2. Other, in agency-defined criteria.
7/29/2019 Draft Status Report New
16/17
S T A T E W I D E P R O C E D U R E : P R O J E C T M A N A G E M E N T S T A T U S
R E P O R T I N G
P A G E 1 6
Information Risk Management
The Project Status Report shall include;
1. On exception significant changes to the initial Statement of Impact to the overall risk
posture of the organization. These changes (if any) to the Statement of Impact shallbe used to inform the overall statewide information risk posture.
a. Included in the changes to the Statement of Impact, assurance that the
organization has adjusted the information risk management program
appropriately.
Note: A significant change in impact is a change that could reasonably be expected to be
of concern to the funding and political approvers. This information is obtained in
consultation with the agencys Information Security Manager. ReferenceSection 2-15-
114, MCA, and Statewide Policy: Information Security Programs.
http://data.opi.mt.gov/bills/mca/2/15/2-15-114.htmhttp://data.opi.mt.gov/bills/mca/2/15/2-15-114.htmhttp://data.opi.mt.gov/bills/mca/2/15/2-15-114.htmhttp://data.opi.mt.gov/bills/mca/2/15/2-15-114.htmhttp://data.opi.mt.gov/bills/mca/2/15/2-15-114.htmhttp://data.opi.mt.gov/bills/mca/2/15/2-15-114.htm7/29/2019 Draft Status Report New
17/17
S T A T E W I D E P R O C E D U R E : P R O J E C T M A N A G E M E N T S T A T U S
R E P O R T I N G
P A G E 1 7
A P P E N D I X B
Trend Analysis CriteriaLast Update: MMmm, DD, YYYY
The following represents the criteria used to analyze the project closeout reports by the IT PMO
for use in its deliverables.
1. Baseline Measures
a. Number of approved baselines during period.
2. Scope Measures
a. Number of planned deliverables during period.b. Number of deliverables delivered during period.
c. Number of scope changes during period.
3. Schedule Measures
a. Number of milestones in original schedule during period.
b. Number of baseline milestones delivered on time to baseline during period.
4. Cost Measures
a. % difference between the cost and the cost estimate during period.b. Number of approved changes to cost estimate during period.
c. Number of re-baseline budget estimates during period.
5. Performance Measures